BOQ-COMPOUND WALL OF 2,456' LENGTH & 7' HEIGHT

FOR HRC

ITEM CEMENT BLOCK MASONRY WALL


DESCRIPTION OF ITEMS UNIT
No. Qty RATE Rs/- AMOUNT
A CIVIL WORKS
1.0 EARTH WORKS
1.1 Earth work in excavation by Mechanical means / Manual Means (
Hydraulic Excavator) in All types of soils (excluding soft & hard rock)
as defined by IS-1200 in both dry and wet conditions including
shoring strutting de-watering sub- soil and rain water to keep the
excavation dry, leveling and dressing the bottom of Excavation to
correct level and shifting the excavated material for a lead up to 50
m as directed by the Engineer-in-charge, to a depth not more than
1.50M.
CRS walls (2'-6" depth) Cu. Mt 1383.00

1.2 Filling in trenches and basement with excavated earth, boulders are
to be broken rolled and well consolidated in layers not exceeding
20mm thick each layer sufficiently watered and thoroughly
compacted by
CRS walls (2'-6" depth) Cu. Mt 277.00

2.0 PLAIN CEMENT CONCRETE BED


Plain Cement Concrete in (1:4:8) proportion nominal mix for Under
flooring bed using 40mm size (SS5) hard Granite or Trap metal from
approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water, etc., to site, including cost of
seignior age charges and all other taxes on all materials and
including all labour charges for machine mixing, laying concrete,
ramming, finishing top surface to the required level, curing , etc.,
complete for finished item of work as directed by the Engineer-in-
charge.
PCC bed under CRS walls Cu. Mt 117.78
PCC bed under Pits Cu. Mt 1.59

3.0 MASONRY WORKS:


3.1 CRS MASONRY
Providing and laying C.R.S Masonry 2nd sort as specified in CM (1:8)
including fair cutting, waste bonding, Plumb lining, leveling,
scaffolding, and curing below ground level and up to plinth, all
materials and labour etc. complete. Cu. Mt 299.07

3.2
Providing and laying Solid Cement Blocks Masonry with 200 mm
thick Solid Cement Blocks in super structure above plinth level in
cement mortar 1:4 (1 cement : 4 coarse sand), including cost and
conveyance of all materials like cement, sand, blocks, water etc., to
site, including seignior age charges, sales & other taxes on all
materials and all operational, incidental and labour charges such as
mixing cement mortar, scaffolding charges, constructing masonry,
lift charges, curing, etc., complete for finished item of work. (Net 5'
Height)
Cu. Mt 321.62
4.0 DAMP PROOF COURSE (D.P.C):

Page 1 of 3
BOQ-COMPOUND WALL OF 2,456' LENGTH & 7' HEIGHT
FOR HRC

ITEM CEMENT BLOCK MASONRY WALL


DESCRIPTION OF ITEMS UNIT
No. Qty RATE Rs/- AMOUNT

Providing and laying damp-proof course 40mm thick with cement


concrete 1:2:4 & waterproofing material on top surface of CRS
Masonry, including cost of all materials, necessary shuttering,
machine mixing, concrete laying, ramming in layers, finishing top
surface to the required level, curing and etc., complete, as directed
by the Engineer-in-charge for finished item of work.
Sq. Mt 150.65

5.0 PLASTERING:
5.1 Plastering 12mm thick in one coats in CM (1:6) with sponge
finishing mixed with integral Waterproofing compound of" Fosroc"
or equivalent make with prior approval from the Engineer in Charge,
mixed in the proportion recommended by the Manufacturer,
including cost and conveyance of all materials like cement, sand,
water etc., to site, cost of seignior age charges and all other taxes on
all materials, and operational, incidental charges and all labour
charges for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves etc. as directed by Engineer-in-charge,
complete for finished item of work for external uneven faces of
walls. Sq. Mt 3423.80

6.0 PAINTING:
6.1
Providing and applying White wash in two or more coats, Including
cleaning all surfaces of dirt, dust loose scales etc. before painting
and including all materials, labour and scaffolding at all heights for
All Internal walls, external walls & ceiling.
Sq. Mt 3423.80

7.0 R.C.C. WORKS

Supply and Placing of Concrete as per IS-4926:2003 of specified


Grades with minimum Cement content as per IS-456:2000 and
standard mix Design as per IS-10262:1982 with coarse aggregate of
nominal size of 20mm and fine aggregate ( River Sand) of Zone II as
per the Mix design approved by the consultants from standard
suppliers as L & T, Birla, ACC or Equivalent , including cost and
conveyance through transit Mixers, Pumping, Leveling, grading,
spreading, Vibrating & Curing etc., complete, including the cost of
mixing super plasticizer Sika " Sikament 600", Fosroc or equivalent
with prior approval of the Engineer in charge to enhance the
workability of concrete, including the cost of all materials , labour
but excluding the cost of Reinforcement steel & Shuttering/
Formwork

For RCC Foundations,PEDESTALS,COLUMNS & TIE BEAMS


M 20 grade( Cement content 320kg/Cum) Cu. Mt 5.87

8.0 FORM WORKS


Providing Centering, shuttering and scaffolding with props and steel
plate shuttering as required forPCC, foundations, pedestals,
columns & tie beams Sq. Mt 59.22

Page 2 of 3
BOQ-COMPOUND WALL OF 2,456' LENGTH & 7' HEIGHT
FOR HRC

ITEM CEMENT BLOCK MASONRY WALL


DESCRIPTION OF ITEMS UNIT
No. Qty RATE Rs/- AMOUNT
9.0 REINFORCEMENT STEEL

Providing High Yield Strength Deformed steel bars (Fe 500 grade as
per IS 1786-1979 of different diameters including labour charges for
cutting, bending to required sizes and shapes
MT 0.47

Note: Supply of steel & cement under Client scope. GRAND TOTAL -

Page 3 of 3