Professional Documents
Culture Documents
Method Statement For Earthworks (Rev 00)
Method Statement For Earthworks (Rev 00)
METHOD STATEMENT
FOR EARTHWORKS (REV 00)
REKA IKHTIAR SDN BHD.
1.0 GENERAL
The purpose of this Method Statement is to outline the role and responsibility of
surveyor and the importance of setting out works for construction purpose.
The following scope of works define the activities which will be carried out for the
implementation of Earthwork according to the prescribe drawing:
o Preparation of Work
o Roadway Excavation
o Embankment Filling
3.0 MANPOWER
Manpower Nos.
Supervisor/Foremen/Site Agent 1
Excavator Operator 3
Drivers 10
Skilled Worker 3
Surveyor 1
Safety Officer 1
REKA IKHTIAR SDN BHD.
b) The entire width of the road reserve from left side to right side boundary shall be
cleared of all trees, stumps, shrubs, vegetation and debris. All rubbish and
cleared off materials shall be removed from the working area and must be placed
at designated area within the limits of works.
e) Survey setting will be carried out to determine the original ground level according
to actual site condition.
a) After setting up the road centerline, the surveyor will determine the positions and
elevation of side. Slope pegs will be provided to guide the earthwork team to
start road excavation.
c) Carting away of earth materials will be by the use of excavators and ten (10)
wheeler dumping trucks. Location of dumping areas within the road reserve areas
must be submitted to the SOR for further verification and approval. In case of an
adjacent dumping site nearby the working area, bulldozers may be used.
REKA IKHTIAR SDN BHD.
d) Suitable materials shall be hauled to fill areas or dumped at designated dump site
within the road reserve area. In case of excessive material, an external dumping
ground must be defined and must be agreed by the landowner. All location of
dumping site outside the road boundaries must be submitted to the SO/SOR.
f) Cutting slopes shall be cleared of all loose rock fragments (if any) and cut slope
shall be 1V:1H, as stated in the drawings, unless otherwise specified or directed
by S.O. The surface of slopes shall be trimmed to an even profile.
g) Surface drains such as interceptor drains, bench drains, slope drains, cascading
drains shall constructed on all surface, as specified in construction drawings, to
discharge water run-off to avoid future erosion or slope failure.
h) The level of the bottom surface of a cutting shall be maintained above formation
level where movement of constructional plant is required. This is to prevent
damage to the subgrade.
i) For cut area supporting R.C. structure base or embankment, the top 300 mm of
the subgrade shall be scarified and recompacted to not less than 95% of the
maximum dry density, or otherwise directed by S.O. / S.O.R
j) Where hard material will be present, ripping method will be implemented with the
use of bulldozer
REKA IKHTIAR SDN BHD.
b) Side slopes shall be maintained according to the drawing. Cut slope will be
2V:1H as specified in the drawings.
d) Ripping off hard material will be by the use of two (2) steel teeth attached at the
rear section of the bulldozer.
f) Where ripping method is not possible, the hard material will be classified as rock
material.
a) Expose all rock material by clearing up and hauling out ripped and loose
materials.
b) Rock material will be classified with the presence of SO/SOR using ripping
method. Ripping of rock material must follow the standard procedure on how to
classify rock. ( Rock blasting method of statement )
c) Once the area is identified as rock, topographic survey will be conducted with the
presence of SOR to assess the volume of rock to be removed.
REKA IKHTIAR SDN BHD.
e) Surveyors will set out slope pegs and limits of blasting all in accordance with the
construction drawings to ensure that no over-blasting will take place.
f) Blasted material will be carried away using excavators and lorries. Location of
dumping grounds will be determined and must be submitted for SO’s approval.
g) The level of the bottom surface of a cutting shall be maintained above formation
level where movement of constructional plant is required. This is to prevent
damage to the subgrade.
h) All drainage structures shall be constructed according to the figure required in the
construction drawing. In areas where rock is present, blasting will be controlled to
define the formation of drains. The use of pneumatic or hydraulic breakers may
be used in areas where controlled blasting is not possible.
a) Identified unsuitable materials shall include running silt, peat, logs, stumps,
perishable material, slurry, mud or any material of the following nature:-
b) Either one of the two methods below or both will be used to load and haul:
REKA IKHTIAR SDN BHD.
Hydraulic excavator loaded into waiting dump trucks and haul to fill areas or
dump area.
Hauling of materials from cuttings to embankments or other areas of fill shall only
be undertaken where sufficient spreading and compaction plant are operating at
the place of deposition to ensure compliance with the compaction requirement.
c) Where unsuitable material has to be removed below the natural ground level or
below the formation level in cuttings as directed by S.O. / S.O.R., the resultant
excavation shall be backfilled with suitable material, deposited and compacted
as specified for embankment or filled area construction
The material for the top 300 mm of the subgrade shall have the following
minimum properties:-
b) Samples of soil from cut area with different nature shall be taken for laboratory
tests to determine the suitability of the soil as fill materials. Sampling location
shall be recorded. All laboratory tests shall follow the approved specification and
quality assurance stated in the QA/QC plan. The frequency of the test shall be at
every change of source.
REKA IKHTIAR SDN BHD.
c) Fill materials for use in areas of fill and embankment construction shall be
suitable or approved materials obtained from excavation in cuttings or
designated borrow pits. No filling / backfilling works shall be carried out until
inspected and approved by S.O / S.O.R. The fill material for the top 1m below
the formation level shall have CBR value not less than 5%. For the top 300 mm
below the formation level, the material shall meet the requirements
d) Spreading and leveling of the hauled materials will be done using bulldozers
and/or backpushers to the specified loose thickness determined from trial
compaction done prior to the actual commencement of bulk earthwork.
f) For landfill, the frequency of Plasticity Index Test, Field Density Test and
Compaction Test shall be 3000 mm2 per layer. For Road subgrade, the
frequency of Field Density Test shall be 500 mm2 per layer, but Plasticity Index
Test, Compaction test per layer.
g) Earth fill shall be compacted in layers not exceeding 300 mm loose thickness,
unless otherwise directed by S.O/S.O.R. or as determined from trial compaction.
Field compaction trials shall be carried out as directed by S.O./S.O.R. for each
main type of fill materials prior to any subsequent filling works to determine the
number of roller passes in relation to the loose depth of materials and type of
compaction plant used to achieve the desired compaction as determined by
Field Density Test. Each main type of fill materials shall have been tested with
Compaction Test and CBR test before any field compaction trials.
h) The degree of compaction for fill below the top 300 mm of subgrade shall be not
less than 95% of maximum dry density. Throughout the top 300 mm of
subgrade, the material shall be compacted to not less than 95% of the maximum
dry density. The top 300 mm shall be compacted in two layers at 150 mm each.
REKA IKHTIAR SDN BHD.
i) The materials for each layer of earth fill shall be added with water or aerated and
dried, as necessary, to bring its moisture content to a uniform level and optimal
for compaction.
j) The formation of fill area shall be finished fair, free of potholes, gullies and
depressions. The finished levels of fill shall nowhere be lower than those shown
in drawings. For road works, the top surface of subgrade shall be finished to the
required shape, super elevation, levels and grades according to the construction
drawing and specification.
k) Each layer shall extend over the full width of the filled area and shall be
compacted with 12-15 tons working capacity vibrating roller as soon as
practicable after being placed and spread.
m) Where the embankment surface for constructional traffic is necessary, the area
shall be brought up to a level above formation level by minimum 300 mm thick.
n) When it is necessary to trim off the formation to its final level, the excess material
over the carriageway shall be removed in a single operation. Thereafter no
constructional plant shall be permitted over the finished embankment other than
machines used for the final trimming operation until the commencement of the
pavement construction works.
c) The slopes shall thereafter be properly watered, fertilized and maintained until an
adequate carpet of vegetation develops along the slope sides.
d) All earthwork surfaces shall be kept well drained throughout the course of the
earthwork operation by providing temporary water course, earth drains to ensure
surface dry and well maintain.
e) Temporary drainage systems, silt trap and washing bay shall be provided. Any
silt deposited in the existing drains shall be cleared.
b) Dumping away lorries must be provided with a spotter or flagman during hauling
and dumping.
No. Work Activity Hazards Effects Current Risk Control (L) (S) Risk Rating Recommended Measures
Poor access and Slip, trip & fall - Toolbox 2 2 4 Low - To provide proper
egress into trench ladder as safe access
and egress for trench
REKA IKHTIAR SDN BHD.