Professional Documents
Culture Documents
2 5 E Ition
2 5 E Ition
2 5 E ITION
ontents
P GE P GE
1
r
I
P GE P GE
P GE P GE
22C.2 Employer to effe t Contractors 29 Nominated Sub Contractors and
All Risks Insurance of the Works Nominated Suppliers 57
22C.3 Remedy if Employer fails to insure
29 1 Nomination of a sub-contractor or a
23 Possession, commencement and supplier
completion 45 29.2 Contractor s right of reasonable
objection
23 1 Posse:;sion of Site 29.3 Sub-con tractor and supplier w2:1Tanty
23.2 Commencement and completion to Employer
23.3 Postponement or suspension 29.4 Contractor s tender for work provided
for by a Prime Cost Sum
24 Damages f o r non completion 45 29.5 Nomination using the standard
conditions
24 1 Architect to certify Contractor s failure 29.6 Contractor s responsibility for
to complete on time Nominated Sub-Contra ctors and
24.2 Liquidated and ascertained damages Nominated Suppliers
24.3 Refund if Completion Date revised 29.7 Quantity Surveyor s notification of
interim payments
? ) Extension of time 46 29.8 Direct payment of Nominated Sub-
Contractors and Nominated Suppliers
25 1 Contractor s first notice of delay 29.9 Extension of time for completion
25.2 Contractor s second no tice of Nominated Sub-Contract works or
25.3 Fixing new Completion Date delivery of Nominated Supply
25.4 Contractor s default involved in the Contract goods
delay 29.10 Substantial completion of Nominated
25.5 Rate of progress Sub-Contra ct works
25.6 Nominated Sub-Contractors and 29.11 Architect to certify Nominated Sub-
Suppliers to be kept informed Contractor s failure to complete on
time
26 Delay recovery measures 51 29.12 Early final payment to Nominated
Sub-Contractor or Nominated
26 1 Delay recovery measures Supplier
26.2 Delay recovery proposals 29.13 Re-nomination
26.3 Contractor to carry out delay recovery 29.14 Architect s consent
me sures 29.15 Employer not liable to a Nominated
26.4 Extension of time to cover shortfall in Sub-Contractor or Nominated
recovering delay Supplier
26.5 Contractor to be reimbursed for the
cost of preparing the proposal if delay 3 Persons engaged by Employer 63
recovery not instructed
30 1 Persons for whom the Employer is
27 Direct loss and/or expense 53 responsible
30.2 Access to Site and permission to
27 1 Contractor s not ice of claim for carry out work
additional payment 30.3 Contractor to fulfil his obligations to
27.2 Quantity Surveyor s ascertainment of persons engaged by the Employer
Contractor s claim
27.3 Contractor s defaul t involved in the 31 Facilities for statutory undertakers
delay or disruption and utility companies 64
27.4 Nominated Sub -Contractor s claim
for additional payment Access to Site and facilities to canry
out work
28 Notice of claims for additional
payment 55 32 Certificates and payments 64
P GE P GE
32.4 Calculation of Retention 37.4 Quantity Surveyor to prepare final
32.5 Retention Rules account
32.6 Quantity Surveyor to prepare final 37.5 The final settlement
account 37.6 Architect to notify sub-contractors
32.7 Adjustment of the Contract Sum and suppliers
32.8 Issue of Final Certificate
32.9 Effect of Final Certificate 38 Fluctuations 84
32.10 Proceedings comme nced before
Final Certificate 38 1 Fluctuation provisions only appli cable
32 11 Proceedings commence d after Final if expressly stated to be
Certificate 38.2 Adjustment fluctuations occurri ng
32.12 Effect of Architect s certificates after the Completion Date
32.13 Late payment
39 Notices certificates and other
Surety Bond 73 communications 85
4
~ f u : ~
> ??
r
;,
rticles of greement
This greement is made on the ................................ day of ................................ 20 ..... .
l
t
between
of ......................................................................................................................................................
r ····················································································································································
( the Contractor )
I
Whereas the Employer wishes to have work carried out comprising:
( the Works )
at ......................................................................................................................................................
showing and describing the work to be carried out prepared by or under the direction of or at
therequest of the Architect;
and where s the Contractor has, based on the Tender Documents made in the Form of
Tender his calculation of the sum that he will require for carrying out the Works by pricing the
bills of quantities;
5
Governing law
11 The Contract shall be governed by and construed according to the laws for the time
being in force in Hong Kong.
Definitions
16 The following words and phrases in the Articles of Agreement the Conditions and the
Appendix shall have the meanings given belo w unless the context in which they appear
requires otherwise or the Articles the Conditions or an item or entry in the Appendix
provides otherwise:
Architect: the person named as the Architect in Article 3 or any successor appointed
under Article 5.
Articles or Articles o f Agreement: the Articles of Agreement to which the Conditions are
annexed.
Commencement Date: the date stated in the Appendix for the commencement of the
Works.
Completion Date: the date stated in the Appendi x by which the Works or a Section are
to be completed or such later date to be fixed by the Architect under clause 25.
9
Contract: the Articles of Agreement, the Appendix, the Form of Tender submitted by
t ~ Contractor, the Employer s letter of acceptance of the Contractor s ten oer and any
correspondence between the parties expressed to form part of the Contract, the Special
Conditions, if any, the Conditions, the Contract Drawings, the Specification and the
Contra ct Bills.
Contract Bills the priced bills of quantities referred to in the recitals of the Articles and
submitted by the Contractor with his tender, or a certified true copy of those bills of
quantities.
:I Contract Drawings the drawings referred to in the first and fourth recitals of the Articles
and enumerated as such in the Contra ct Bills or the Specification.
Contract Sum: the sum stated in Article 2, or such other sum that becomes payable in
accordance with the Contract.
Contractors All Risks Insurance o f the Works insurance which provides cover against
physical loss of or damage to the Works, temporary works and materials and goods, as
described in clause 22.
Date for Possession o f the Site the date or dates for the possession of the whole or
parts of the Site stated in the Appendix under the reference to clause 23.1.
Date o f Substantial Completion the date stated in the Substantial Completion Certificate
for the Works or a Section, issued by the Architect under clauses 17 1 and 17.2.
day a calendar day and includes Sundays and other days which are general holidays
by virtue of the General Holidays Ordinance (Chapter 149, Laws of Hong Kong).
Defects Liabilit y Period the period stated in the Appendix under the reference to clause
17.3, commencing on the da y after the Date of Substantial Completion o f the Works or
a Section or the d ay after the Relevant Date of Substantial Completion of a Relevant
Part.
Defects Rectification Certificate a certificate issued by the Architect to the effect that
all defects, shrinkages and other faults have been rectified in accordance with the
Contract, as described in clauses 17.4 and 17.5.
direct /ass a n d / o r expense the monetary consequences that flow naturally without
other intervening cause and independently of special circumstances because of the
direct consequences of a qualifying event and which are not otherwise reimbursed to
the Contractor.
1
Engineer: a person engaged as a member of the Employer s design team for the design
and supervision of one or more of the geotechnical, civil, structural or building services
elements of the Works, as referred to in clause 1. 7.
Excepted Risks: a) Any consequence o f war (whether war be declared or not) in which
Hong Kong is actively engaged, the invasion of Hong Kong, acts of terrorists in Hong
Kong, civil war, rebellion, revolution or military or usurped power in Hong Kong, riot,
commotion or disorder in Hong Kong other than amongst the employees of the
Contractor or any person for whom the Contractor is responsible;
b) the Architect s design of the Works insofar as damage, loss or
injury is the direct conseq uence of the design;
c) a cause due to any neglect or default of the Architect, the Employer
or any person for whom the Architect or the Employer is responsible;
d) ionizing radiation or contamination by radioactivity from any nuclear
fuel or from any nuclear waste from the combustion of nuclear fuel, radioactive toxic
explosive or other hazardous properties of any explosive nuclear assembly or nuclear
component thereof;
and e) pressure waves caused by aircraft or other aerial devices travelling
at sonic or supersonic speeds.
Final Certificate: the certifica te issued by the Architect stating the Final Con tract Sum
and the total of the amounts of Interim Certificates to be set off against that sum, as
described in clause 32.8.
Final ontract Sum: the sum resulting from the adjustment of the Contract Sum in
accordance with the Contract.
Form o f Tender: the form of tend er referred to in the first recital of the Articles as being
part of the Tender Documents.
Interim Certificate: a certificate issued by the Architect stating the amount of an interim
payment due to the Contractor, as described in clause 32.1.
Limit o fRetention: the amount stated in the ppendix under the reference to clause
32.4 as the limit to the amount of Retention to be held by the Employer on the payment
for the Contr actor s work in progress.
Nominated Sub Contract: the sub-co ntrac t between the Contractor and a Nominated
Sub-Contractor.
11
2) The Contractor shall assign to the Employer (so far as he is lawfully able to do so)
the benefits of all suppliers and sub-contractors warranties, guarantees or other ancillary
agreements fo r materials, goods or work insofar as they are required by the Contract,
Nominated Sub-Contracts or Nominated Supply Contracts, other than the direct
warranties to the Employer required under the Nominated Sub-Contracts and Nominated
Supply Contracts, within 60 days after the issue of the Substantial Completion Certificate
for the whole of the Works.
2) Where the drawings referred to under clauses 5.3, 5.4, 5.5 and 5.6 have been
issued electronically, th e Contractor shall, if so required by the Architect, provide the
as-built drawings electronically.
2) Neither the Employer, the A rchitect nor the Quantity Surveyor shall divulge any of
the rates or prices in the Contract Bills or use them except for the purposes of the
Contract and any proceedings relating to the Contract.
3
6 Statutory obligations
Statutory Requirements
6.1 The Contractor shall comply with and give the notices required by any Ordinance,
regulation, rule, order or by-law applicable to the Works ('the Statutory Requirements')
which are to be complied with by the Contractor.
2) If the Archi tect agrees with the Contractor, he shall issue an instruction to resolve
•
1
the infringement as soon as practicable afte r receipt of the notice and the instruction
shall, if appropriate, require a Variation.
Fees o r charges
6.3 1) The Contractor shall pay all fees or charges legally demandable under the Statutory
Requirements.
2) The net amount of those fees or charges paid by the Contractor shall be added to F
the Contract Sum unless they: l
l
a) are fees or charges that the Contractor is liable to pay under the Statutory
Requirements, and the liability was known prior to the date for submission of tenders
f
r
I and has not been increased;
2) The Contractor shall all ow those persons reasonable access to the Site, per mit
them to carry out their work and provide them with the facilities referred to in clause 31.
4
2) The Contracto r shall be responsible for accurately setting out the Works and shall
correct any error arising from inaccurate setting out at his own cost unless the Architect
accepts the error without correction subject to a reasonable reductio n in the Contract
I
Sum having regard to the Employer s loss of value of the Works and any expenses that
he may incur arising from the inaccurate setting out.
2) Where the Con tractor is responsible for the selection of the materials and goo ds in
accordance with a performance specification or otherwise, the materials and goods
must be fit for the purpo se stated in the Contract.
3) If any of the specified materials or goods are not procurable, then the Contractor
shall sub mit alternative proposals for materials or goods of similar type and standard
and of comparable quality and price to the Architect for his approval; and
a) if the proposed alternative materials or good s are of similar type and standard and
of comparabl e quality and price to those specified, and the Architect approves
them, the substitution of the alternative materials or goods for those specified
shall be made with no adju stment to the Contract Sum; or
b) if the proposed alternative materials or goods are not of similar type and standard
or comparable quality or price to those specified, and the Architect approves them,
he shall instruct a Variation to adjust the type, standard, quality or price.
4) The Contractor shall provide the Architect, upon his request, with vouchers, test
certificates or othe r evidence to satisfy the Architect that the materials and goo ds comply
with the Contract.
5
6) All work must be carried out in a proper and workmanlike manner in accordance
with the Contract or, in the absence of any specific performance requirements, to the
Architect s satisfaction.
Inspection nd tests
8 2 1) The Contra ctor shalf carry out or, if so required by the Contract, arrange for a third
party to carry out, the tests specified in the Contract in compliance with the specified
testing procedures.
2) In addition to the tests specified in the Contract, the Architect may instruct the
Contractor open up for inspection any work covered up and carry out, or arrange
for a third party to carry out, tests of materials and goods {whether or not already
incorporated in the Works) and work which has been carried out.
3) The cost of the testing, the opening up for inspection and any consequential making
good shalf be added t o the Contr act Sum unless:
b) the inspection or test shows that the materials, goods, workmanship or work are
not in accordance with clause 8;
d) the work was carried out without the inspection notice required by the Contract.
a) the removal from the Site and the replacement of materials and goods that are not
in accordance with clause 8;
d) a Variation for alternative remedial work to sorne or all of the materials, goods or
work as is reasonably necessary in consequence of them not being in accordance
with clause 8, with no extension of time or addition to the Contract Sum.
6
Rectifying defects
8 4
The Architect may instruct the Contractor to rectify defects which appear before the
commencement of the Defects Liability Period.
2) The Contractor shall indemnify the Employer from and against all claims,
proceedings, damages, costs and expense arising from the Contractor or any sub-
contractor or supplier infringing or being held to have infringed any of the intellectual
property rights referred to in clause 9.3 1 ).
7
Construction manager
10.2 1) The team shall be headed by an experienced and compet ent construction manager
approved by the Architect.
3) The Architect may instruct the Contractor to replace the construction manager or
a member of the team for incompetence or misconduct.
4) The Contractor shall not remove or replace the construction manager or any member
of the team unless requested by or agreed to b y the Architect.
12 Architect s representative
Archite ct s representative
12.1 The Arch itec t and/or the Employer may appoint an architect, engineer, clerk of works
or other person as the Architec t's representative to be resident on the Site and actin g
under the direction of the Architect.
c) check that the types, standards and quality of the materials and goods, t he standard
and quality of the Contrac tor s workmanship and the quality of his work are in
accordance with the requirements of the Contract;
d) check, amend as necessary, and where appropriate sign the records submitted to
him by the C ontra ctor for approval; and
e) carry out the duties and exercise the powers delegated to him by the Architect
under clause 12.2,
8
(b) under clause 13.2(a) for the remeasurement of Provisional Quantities and Provisional
Items in any bills of quantities included in the sub-contra ct or supply contract; and
14 Contract Bills
33
15 Contract Sum
2) Subject to clause 14.3 the parties are deemed to have ac cepted any error whether
of arithmetic or not in the calculation of the Contract Sum stated in Article 2.
2) Materials and goods delivered to or adjacent to the Site shall not be removed
without the consent of the Architect. If they have become the property of the Employer
the Contractor shall remain responsible for loss or damage to them except to the extent
that the loss or damage is due to an act or neglect o f the Employer or any person for
whom the Employer is responsible.
3) The Contractor shall indemnify the Employer against loss or damage to materials
and goods stored off site that have become the property of the Employer shall be
responsible for the cost of their storage handling and insurance and shall not remove
them from where they are being stored e xcep t for use upon the Works.
Separate Defects Liability Period for each Section and Relevant Part
17.2 1) If sectional completion of the Works is provided for in the Contract or the Employer
takes possession of a Relevant Part each Section or Relevant Part shall have its own
separate Defects Liability Period.
34
3) The requirements for the issue of a Substantial Completion Certificate under clause
17.2(2) shall be the same as those under clause 17.1.
defe ts
17 3 1) The Contractor shall rectify all defects, shrinkages or other faults which are identified
during the Defects Liability Period of the Works, a Section or a Relevant Part stated in
the Appendix, and are caused either by materials, goods or workmansh ip which are not
in accordance with the Contract, by natural causes or as a result of a Specifie d Peril
occurring during the construction period prior to Substantial Completion.
2) The Architect shall list the defects to be rectified in schedules of defects which he
shall issue to the Contractor as Architect s instructions from time to time during the
Defects Liability Period. The final schedule of defects shall be issued not later than 14
days after expiry of the Defects Liability Period.
3) The Con tractor shall rectify the defects specified in the schedules of defects to the
Architect s satisfaction within a reasonable time after receipt o f those schedules.
4) If the ontractor does not comply with the Architect s instruction to rectify the
defects listed in a schedule of defects within a reasonable time the provisions of clauses
4.3(3) and 4.3(4) shall apply.
5) The Archi tect may instruct the Contract or not to rectify some or all of the defects
specified in the schedules of defects, in which case a reasonable reduction to the
Contract Sum shall be made for the defects not rectified.
b) the Contra ctor has satisfactorily completed all the uncompleted items of work on
the list issued with the Substantial Completion Certificate; and
c) all defects required to be rectified under clause 17.3 have been satisfactorily rectified.
2) Upon the completion of rectifying defects to the last Section or Relevant Part in
accordance with clause 17.4 the Architect shall issue a Defects Rectification Certificate
for the Works and the completion of rectifying defects for the whole of the Works shall
be deemed to have taken place on the date stated in the certificate.
5
2) The insurance cover shall be against the liabilities referred to in clause 21.2(1)
sustained during the period from the Commencement Date until the Defects Rectification
Certificate for the whole of the Works has been issued and the Con tracto r has finally
left the Site.
a) a cross l iability clause to the effect that the insurances shall cover the Employer,
the Contractor, his sub-contractors and their sub-contractors of all tiers as separate
insured, and
b) a waiver of any right of subrogation which the insurers may have against any of the
insured.
4) The third party liability insurances against injury or death to any person and injury
or damage to real or personal property under clause 21.2(1) shall each be effected with
the limit of indemnity stated in the ppendix for any one occurrence or series of
occurrences arising out of one event but unlimited in the aggregate amount for the
period of the insurance.
2) The cover shall be in terms approved by the Architect but in any case cannot be
beyond the best terms currently available.
Policies to be produced
21.4 The party responsible for effecting the insurances under clause 21.2 shall pro vide
evidence of cover to the other party prior to the Commencement Date and shall produce
the policies of insurance and the premium receipts for inspection and approval by the
other party as soon as practicab le afterwards.
4
a) costs and expenses in respect of shoring and prepping up, testing, dismantling or
demolishing part of the Works, existing constr uctions on the Site or temporary
works, removing and disposing of debris and damaged materials or goods and
protecting the Works, existing constructions on the Site, temporary works and
materials or goods;
incurred in the repair, reinstatement, redesign and supervision fol lowing damage to
the Works, existing constructions on the Site, temporary works or materials or goods
from any cause excluding:
e) the cost of repairing or replacing proper ty which is defective solely due to natural
wear and tear resulting from ordinary use or deterioration, rusting or corrosion;
g) loss or damage solely due to the total suspension of carrying out the Works where
the insured failed to take reasonable precautions to protect the property insured
and to avoid or reduce the a mount of loss or damage;
i) loss or damage to materials, goods or work directly resulting from its own defect in
materials, goods or workmanship or fault, defect, error or omission in design, plan
or specification but not excluding resultant damage to any other materials, go ods
or work which are lost or damaged as a consequence of those defective materials,
goods or work;
Q loss or damage to property during the period between 14 days after Substantial
Completion and the date of issue of the Defects Rectification Certificate other than
loss or damage arising from a cause occurring prior to the commencement of that
period or caused in the course of remedying defects or the testing and
commissioning of building services or other installations;
41