IV Blisters Elimination Actions - Lipsko1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Area Possible Main aspects Actions Who When Status

reason of
problem
Process Proper Observed not equad laminator temperature in Modify system of SŚ w.44(new target w.51 after stop
laminator whole cross section of laminator ( entrance heating to achive production)
temperature and center is ok but right side edge present proper range on whole
lower temperature) laminator surface.

1) In action: point discussed with Kazimierz Odwald, plan to implement solutions from Balex (technical drawings of Balex solution prepared by Kazimierz):
1st stage (w.52 2020)
a) additional flashing in laminator to stop losing hot air from area of plates heating
2) 2nd stage (Feb 2021)
a) add bariers inside lamiator with insulation
b) Cover plates on beginning and end of laminator
c) Add air mixers
3) cover exit of laminator by additional PVC belts ( done)
4) test transfer of hot air in laminator with synthetic smoke to observe where we loosing heat (w52 or w.1/2021 and FEB 2021)
Hot air

1a) Installation of flashing to avoid heat loosing

Balex solution

Lipsko solution

Laminator movement direction


1
Area Possible Main aspects Actions Who When Status
reason of
problem
Process Proper Observed not equad laminator temperature in Modify system of SŚ w.44(new target w.51 after stop
laminator whole cross section of laminator ( entrance heating to acchive production)
temperature and center is ok but right side edge present proper range on whole
lower temperature) laminator surface.

2a and 2b) Installation of additional bariers ( insulation) inside laminator to stop loosing hot air / pulling cold air on the end of laminator

Current sittuation Expected solution

2
Area Possible Main aspects Actions Who When Status
reason of
problem
Process Proper Observed not equad laminator temperature in Modify system of SŚ w.44(new target w.51 after stop
laminator whole cross section of laminator ( entrance heating to acchive production)
temperature and center is ok but right side edge present proper range on whole
lower temperature) laminator surface.

2c) Installation of additional mixers to create hot air flow more turbullent – it must be last stage when whole laminator is properly covered

3) Cover edges of plates in exit of laminator area to avoid additional cooling by air – done

3
Blisters meeting: 12.03.2021

Laminator heating – implemented actions


during yearly maintenance

Verification planned for week 12 and 13/2021