Professional Documents
Culture Documents
Example 7.1 Sizing For Building
Example 7.1 Sizing For Building
Example 7.1 Sizing For Building
Design suitable beam and column arrangement for a floor to cover an area 9mx 9m.
For this illustrative example, we will omit stairs or lift shafts to keep things as simple as
possible.
Structures E2 1
Option 1
Primary Beam
Primary Beam
9m
Structures E2 2
9m
Secondary Beam
Option 2:
3m
Secondary Beam
Primary Beam
Primary Beam
A slab span of 9m is (in my opinion) too large, so I
3m
will use a series of primary and secondary beams.
Secondary Beam
3m
3m centres supported on primary beams. Secondary Beam
Comments: IN MY OPINION (and it’s MY design) a 3m slab span is too small Of course.
We could add more columns, but I do not want to do.
Structures E2 3
Option 3: 9m
Secondary Beam
It consists to provide secondary beams at 4.5m
centres supported on primary beams.
4.5 m
Primary Beam
Primary Beam
Secondary Beam
Comments: IN MY OPINION this is better solution
4.5 m
(But you may disagree)
Secondary Beam
Structures E2 4
9m
Secondary Beam
4.5 m
Primary Beam
Primary Beam
Design parameters (general)
Secondary Beam
Reinforcement yield strength fy =500 N/mm2
4.5 m
(reminder fd =fy/1.15 =0.87fy =435 N/mm2
Secondary Beam
Concrete strength C 30/35 fck =30 N/mm2
ONCE DECIDED UPON, THESE PARAMETERS MUST BE USED BY THE WHOLE GROUP
Structures E2 5
9m
Secondary Beam
4.5 m
Primary Beam
Primary Beam
There are then other parameters for the slab and
beams: Secondary Beam
4.5 m
Slab c over 20mm
Beam cover 40mm Secondary Beam
These calculations are to ESTIMATE member sizes, so the above values will be used
throughout the design AT THIS STAGE
Structures E2 6
9m
Secondary Beam
4.5 m
In order to establish the loads, we need to estimate
Primary Beam
Primary Beam
a suitable slab thickness. Secondary Beam
For this we use span to depth (L/d) ratios.
4.5 m
For a continuous slab L/d=30
In this case: Secondary Beam
L/d = 4500/d = 30 → d=4500/30 = 150mm
Strictly speaking this is the ‘effective depth’ of the slab, giving an overall depth:
In order to do this, I have no alternative but to calculate the loads on the slab:
Characteristic Loads:
=5.0 kN/m2
Imposed Load:
Structures E2 8
Ultimate load
4.5 m
Beam Loads using SIMPLE Slab Analysis apportioning
Centre Secondary Beam
load according to width of slab carried : carries 4.5/2 + 4.5/2 = 4.5m
width of slab
4.5 m
Load on outer secondary beam
=16.3 x 2.25 = 36.7 kN/m Outer Secondary Beam
carries 4.5/2 = 2.25 m width
of slab
Load on inner secondary beam
=16.3 x 4.5 = 73.4 kN/m
Structures E2 10
Method 2:
At this stage (before we have dealt with indeterminate beams in the analysis course) we
need to use computer software to analyse the beams.
All we are interested in at this stage is the shear force diagram. (which gives us
the load applied to the supporting beams)
Structures E2 11
w kN/m
5wL/8
2
wL /8 hogging
3wL/8
3wL/8
4.5 m
From the shear force diagram :
Centre Secondary Beam
Load on outer secondary beam carries 4.5/2 + 4.5/2 = 4.5m
width of slab
4.5 m
=3WL/8 = 3 x 16.3 x 4.5/8 =27.5 kN/m
Load on inner secondary beam Outer Secondary Beam
carries 4.5/2 = 2.25 m width
=2 x 5WL/8 =2 x 5 x 16.3 x 4.5/8 =91.7 kN/m of slab
Note that both methods give the same TOTAL load on all
beams:
27.5 +91 7 +27.5 =146.7 kN/m
36.7 +73.4 +36.7 = 146.8 kN/m Structures E2 13
I will use the Method 1 (simpler) method. Beam 1
Beam 1
Load on outer secondary beam
Beam 3
Beam 3
Beam 2
=16.3 x 2.25 =36.7 kN/m
Beam 2 Beam 1
9.0m
Load on inner secondary beam
=16.3 x 4.5 =73.4 kN/m
Structures E2 14
(Secondary) Beam 1: simply supported
Beam 1
Beam 3
Beam 3
Beam 2
Structures E2 15
𝑀 372 𝑥 106
𝑏≥ = = 470 𝑚𝑚
(0.167 𝑥 𝑑 2 𝑥 𝑓𝑐 ) 0.167 𝑥 397.52 𝑥 30
Structures E2 16
(Secondary) Beam 2 Beam 1
Beam 3
Beam 3
M max =WL2/8 =73.4 x 92/8 =744 kNm Beam 2
Beam 1
Decide upon a beam size: 9.0m
𝑀 744 𝑥 106
𝑏≥ = = 600 𝑚𝑚 Use beam size 550dp x 600w
(0.167 𝑥 𝑑 2 𝑥 𝑓𝑐 ) 0.167 𝑥 497.52 𝑥 30
Structures E2 17
Secondary beams dimension:
(in this case the result is obvious – we double the load, therefore double the moment
and hence double the required width.
If we had used a different depth to Beam 1, the result would need to be calculated)
Structures E2 18
P = 300 kN
reaction from
Beam 2
(Primary) Beam 3
Lm
In this case the beam 3 analysis is again very simple.
In this case it is a simply supported beam with a
central point load applie:
EQUILIBRIUM!!
Structures E2 20
THIS COMPLETES THE BEAM DESIGN
Structures E2 21