Professional Documents
Culture Documents
Kececioglu, Dimitri B. - Maintainability, Availability, & Operational Readiness Engineering Handbook, Volume 1-DeStech Publications (2003)
Kececioglu, Dimitri B. - Maintainability, Availability, & Operational Readiness Engineering Handbook, Volume 1-DeStech Publications (2003)
Availability, &
Operational
Readiness
Engineering
Handbook
VOLUME 1
DE Stech Publications
Maintainability, Availability & Operational Readiness Engineering
Handbook, Volume 1
DEStech Publications, Inc.
1148 Elizabeth Avenue #2
Lancaster, Pennsylvania 17601 U.S.A.
ISBN NO.1-932078-05-3
PREFACE
including the use of the Markov chains approach with constant and
nonconstant failure and repair rates.
The combination of reliability, which may be quantified if the mean
time between failures ( M T B F )is known, and of maintainability, which
may be quantified if the mean time to restore the equipment to success-
ful function (MTTR) is known, yields the steady state availability of
any equipment. The availability of equipment is a very important mea-
sure, because it determines the percent of their uptime; consequently,
the percent of their operational time the equipment is available to give
the desired level of output or production. The overhead for equipment
being essentially fixed, the more available the equipment is to deliver
the required output or to manufacture a product, the lower will be the
overhead cost per unit of output or per unit of manufactured product.
The intrinsic, inherent, or instantaneous, as well as a great variety of
steady state availabilities, are quantified in these handbooks and their
applications are illustrated by numerous worked-out examples.
In addition to assuming that the equipment is available to provide
the desired function after the start of its operation, it has to be ready
to start to operate at a desired point in time, or when the call for it
to start to operate arrives. The concept that quantifies the probability
that the equipment will be ready to start its function, when called upon
to do so, needs to be developed and quantified. This is accomplished by
the concept of operational readiness, which is covered extensively
in these handbooks.
An all-encompassing concept which quantitatively combines op-
erat ional readiness, mission reliability and design adequacy is
system effectiveness. This concept needs to be developed to assure
that not only the equipment starts its operation when needed, it also
completes its mission, or function, satisfactorily and performs all of its
designed-to functions as specified. Methods for quantifying system
effectiveness are developed and illustrated in these handbooks for
quick implementation thereof.
After the equipment is designed and built, its designed-in maintain-
ability needs to be demonstrated. MIL-STD-471 gives many methods
of achieving this. These methods are covered in detail, and all demon-
stration models are derived and illustrated by many examples in these
handbooks.
To assure that the equipment will meet their maintainability goals,
methodologies need to be developed to predict their maintainabil-
PREFACE xxxi
PA 17601 - 4359, Vol. 1, 720 pp. and Vol. 2, 568 pp., and “Reliability
& Life Testing Handbook” by Dr. Kececioglu, published by DEStech
Publications, Inc., 1148 Elizabeth Ave. #2, Lancaster, PA 17601 -
4359, Vol. 1, 950 pp., 2002 and Vol. 2, 900 pp., 2002.
Each chapter has numerous practical examples, completely worked
out and necessary computer programs given. Problems to be worked
out by students and practitioners are given at the end of each chapter,
as well as complete references. It is recommended that those who teach
reliability engineering courses start by teaching out of the two-volume
“Reliability Engineering Handbook,” follow it by teaching out of the
two-volume “Reliability & Life Testing Handbook,” and then follow it
by teaching out of this, the two-volume “Maintainability, Availability
and Operational Readiness Handbook.”
Chapter 1 of Volume 1, of this two-volume handbook establishes
the objectives of this handbook, the overall benefits of an integrated
reliability and maintainability engineering program implemented in in-
dustry and government, and covers 22 case histories documenting the
actual benefits derived from the implementation of reliability and main-
tainability engineering.
Chapter 2 defines and quantifies system effectiveness, and gives
the relationship between reliability and system effectiveness. It also
defines reliability and maintainability comprehensively and provides
46 practical benefits of implementing reliability and maintainability
engineering.
Chapter 3 defines maintenance, preventive maintenance, cor-
rective maintenance;identifies and defines all types of corrective and
preventive maintenance downtimes and their relationship to all other
times associated with the life of equipment. It also covers maintenance
personnel factors and costs; maintenance personnel safety factors; and
maintenance support facilities and equipment.
Chapter 4 discusses 15 maintainability design criteria which mini-
mize equipment downtime, increase accessibility to critical, high failure
rate parts in equipment, provide better packaging; identify the correct
placement of labels which contain operating and maintenance instruc-
tions so that they can be seen easily, and the correct choice of fastener
design; provide for the correct identification of equipment check points,
numbering of parts, marking of connectors so that they are connected
to the correct receptacle, etc.
Chapter 5 covers downtime distributions, and maintainability en-
PREFACE xxxiii
MAINTAINABILITY,
AVAILABILITY AND
OPERATIONAL READINESS
ENGINEERING
1
2 M AIN TAINABILIT Y ENGINEERING
10. UnreIiability hits the Navy supply business in two principal ar-
eas: aircraft unavailability and high supply costs. In addition,
the dollars required for supply are in direct competition with
dollars required for new ships and aircraft. The aviation spares
inventory aboard a large attack carrier has a value of approxi-
mately $4,000,000, while in an industrial air station the inventory
represents approximately $300,000,000. The Aviation Supply Of-
fice is currently buying spares for the entire Navy at a rate of
$500,000,000 per year. Better reliability and maintainability can
be a significant factor in reducing these costs [6, p. 811.
11. Rear Admiral J.M.Lyle (SC), USN, past commanding officer,
Naval Aviation Supply Office, said “In addition to costs in readi-
ness or time, unreliability costs us in dollars. The major direct
added cost, of course, is the additional stocks of parts to meet
the higher usage rate and to supply more frequent repairs. There
is also the cost of added transportation to meet emergency sit-
uations. And, of course, there are the intangible and indirect
costs stemming out of unreliability. What is the dollar cost of
grounding an A3D Aircraft for lack of parts? Though not readily
measured, it is nevertheless real and important.” [6]. “A Horizon
Stabilizer Actuator for one of our attack aircraft is an example of
unreliability, evidenced by failure or wear rate far exceeding that
expected. The replacement rate which finally developed was 60%
as contrasted with an expectation of 8%. Interpreted into dol-
lars, this usage increase cost us $400,000 additional in stock level
buys. Moreover, this usage increase multiplied our repair and
transportation costs seven times.” “Or take a fuel control having
current fighter application. The item cost us over $5,000. There
have been 27 modifications to this control. Just bits and pieces
to effect these modifications have cost us a total of $2,500,000.
The delays, and other direct and indirect costs, are on top of
that.”
12. GM reported that its 1961 appliances required 9% less service
than the 1960 models and 33% less than 1957 models.
13. ”There is no question at Tapco that reliability is a profitable
venture,” said R.R. Lwders, past Chief of Reliability, Tapco Di-
vision, Thompson Ram0 Woolridge, Inc. The profit contribution
shows up in many forms:
14. The Air Force placed an order with Hoffman Electronic Cor-
poration of Los Angeles, California, to undertake a major pro-
duction contract for AN/ARN 21-C TACAN equipment, which
is the airborne portion of a ground-linked, short-range, naviga-
tional aid system [7] with a strict requirement of implementing
a complete reliability and maintainability engineering program.
The economic advantages of these “build-it-right-the-first-time”
procurement actions taken by the Air Force and Hoffmann can
be summarized as follows and in Table 1.2 :
14.1 Price savings of $445 per set times 10,000 sets on order or
$4,450,000.
14.2 Service life estimates of 3,000 hr.
12 MAINTAINABILITY ENGINEERTNG
14.3 8.5 times more reliable; i.e., 17.5 hr versus 150 hr MTBF.
14.4 Maintenance costs per failure of $140.
14.5 In one year on 10,000 sets of navigational systems $70,650,000
was saved.
25 -
Unit B
-020-
4
d
Cost savings ;
of $6,821,000 8
I
I I
I I
OO 300 600 900 1,200 1,500 1,800
MTBE hr
Fig. 1.1 - Plot comparing cost and MTDIZ for airborne indicator panels from two different
suppliers.
14 MAINTAINABILITY ENGINEERING
16. Table 1.4 illustrates the benefits of trade-off studies which can-
not be conducted without reliability and maintainability inputs.
The problem resolved in Table 1.4 is whether to throw away or
repair a failed module from the overall cost point of view. Un-
der “Total cost of spares,” 60 repairable modules per ten years
are estimated to be needed, yielding $20 x 60 = $1,200, and 50
throwaway modules yielding $150 x 50 = $7,500. This informa-
tion is derived from reliability engineering studies. Under “Cost
of repair - active repair time,” the M T T R of two hours is needed
yielding 60 repairs/lO years x 2 hr/repair x $15/hr = $1,800.
This M T T R can only be obtained from Maintainability Engi-
neering studies. Finally, it is found that the “repair case” will
cost $14,796 versus $8,680 for the “discard case”; consequently,
the “discard case” wins out at great savings.
19. The F/A-18 was developed under the Navy's "new look" weapons
procurement program in an effort to improve reliability and main-
tainability and thus, reduce life-cycle cost [lo]. During the four-
year period after entering service, the F/A-18 was three times
more reliable than the two aircraft it replaces, the F-4J and the
A-7E. The F/A-18 has an average of 2.2 mean flight hours be-
tween failures ( M F H B F ) compared with its closest competi-
tor the F-4J averaging 0.8 M F H B F . The F/A-18 required
26.0 M M H / F H which was a great improvement over the 46.1
MMIFI/FH necessary for the A-7E.
21. Pump failures cost an average of $4,000 per repair in the petro-
chemical industry. The M T B F for typical pumps is 18 months
and because of the number of them at large refineries main-
tenance costs for pump repairs alone may exceed $3,000,000.
Exxon has introduced a pump failure reduction program which
has yielded significant results and led to 29% less failures after
the first year of implementation [12].
PROBLEMS
1-1. What is maintainability?
1-2. What is maintainability engineering?
1-3. What in today’s advanced society dictates the acquisition and
the application of the maintainability engineering principles?
1-4. Name three complex products of today which should be de-
signed by and their performance monitored through main-
tainability engineering.
1-5. Name three current space and defense projects which have
been designed by and whose performance is being monitored
through maintainability engineering.
1-6. Which specific phases of existence of a product or system
does maintainability deal with?
1-7. List five of the most important applications of and benefits
derived from maintainability engineering in your opinion.
1-8. Illustrate by two numerical examples why product or sys-
tem complexity dictates the acquisition and application of
the knowledge of maintainability engineering.
1-9. Why is today’s worldwide industrial competition a challenge
t o maintainability engineering?
1-10. How do you think maintainability specifications are set?
REFERENCES
1. Billit, A.B., “Control of Maintainability in Aerospace Fluid Power Sys-
tems,” Aerospace Reliability and Maintainability Conference Proceed-
ings, Washington, D.C., pp. 340-349, June 1964.
2. Harter, W.W., “Results of an Airplane Reliability Program,” Aerospace
Reliability and Maintainability Conference Proceedings, Washington,
D.C., pp. 65-70, June 1964.
3. Powell, H.R., “The Minuteman Approach to System Reliability,” Aero-
space and Maintainability Conference Proceedings, Washington, D.C.,
pp. 51-58, June 1964.
4. Camarata, J., “Product Reliability - The Concept of Integrated Relia-
bility and Quality Assurance,” Aerospace Reliability and Maintainabil-
ity Conference, Washington, D.C., pp. 172-178, May 1963.
REFERENCES 19
2.1.1 WSEIAC
The concept of System Effectiveness as developed by the Weapons Sys-
tem Effectiveness Industry Advisory Committee (WSEIAC), involved
the totality of the requirements associated with the system’s avail-
ability, dependability and capability, as well as reliability. It must be
pointed out that reliabilitp is directly a component of availability and
of dependability. Furthermore, reliability has t o be designed into a
system. It affects its design and in turn its performance or capability.
WSEIAC task groups prepared and published six reports in eleven vol-
umes. Their titles and Defense Technical Information Center numbers
are as follows:
21
22 SYSTEM EFFECTIVENESS
2.1.2 ARINC
Another set of System Effectiveness concepts have been developed by
ARINC Research Corporation, 2552 Riva Rd., Annapolis, MD 21401.
A summary of these concepts is presented in Fig. 2.1. The definitions
of the System Effectiveness concepts are given in Table 2.1 and the
time categories involved are given in Table 2.2.
These efforts help t o properly place reliability engineering in the
overall picture and in the concept of System Effectiveness. They point
out more vividly the importance of reliability engineering as an overall
concept encompassing reliability, maintainability, availability, opera-
tional readiness, dependability, design adequacy and capability.
RELIABILITY E N G I N E E R " CONCEPT 23
I -
I
I
I
Storage
time
Free
time
Availability -
t
I
- - Active Repair lime
Serviceability . (Repairability)
therefore,
NFW
reliability estimate = 1 - -
NT(t) '
where
and
+
A ( t ) B ( t ) = 1. (2.6)
where
NAC = number of systems that have accomplished all
designed-to mission objectives when called upon
to do so, at a point in time,
and
NT = total number of systems on hand at the start of
the mission.
Operational readiness is the probability that the system is either
available at the beginning of the mission or can be brought to an oper-
ationally ready state by the beginning of the mission. The probability
that having started the mission successfully, the system will complete
28 SYSTEM EFFECTIVENESS
(2.10)
where
NAV = number of systems that are available to start
their mission successfully.
A quantitative definition of mission reliability, R M ,is
(2.11)
where
NCM = number of systems that, having started their mis-
sion successfully, complete their mission success-
fully.
Design adequacy is a difficult concept to conceive because it is dif-
ficult to quantify. It can be illustrated by examples, however. Let
us assume one wants to take six people t o work, there is only one
car available, and the car’s capacity is only four passengers. The de-
sign adequacy of this car for this mission is 416, or 67%. In terms
of intercontinental ballistic missiles, the probability that the required
number of missiles have been checked out and are ready to be launched
at the designated time is operational readiness. The probability that
each missile is successfully launched, reaches the target and explodes
successfully is mission reliability. The probability that the missile de-
stroys the specified target to the extent intended is design adequacy.
If the number specified to destroy the whole target were launched suc-
cessfully, and an inspection revealed that only 90% of the target was
destroyed, then the design adequacy of these missiles is 90%.
A quantitative definition of design adequacy, D A , is
(2.12)
RELIABILITY ENGINEERlNG CONCEPT 29
which yields
NAV = NT X OR = 119 x 0.98 = 116 systems.
30 SYSTEM EFFECTIVENESS
or
or
REFERENCES
1. Kececioglu, Dimitri B., Reliability Engineering Handbook, DEStech Pub-
lications, 1148 Elizabeth Ave., #2, Lancaster, PA 17601-4359, Vol.1,
720 pp. 2002.
2. Kececioglu, Dimitri B., Reliability Engineering Handbook, DEStech Pub-
lications, 1148 Elizabeth Ave., #2, Lancaster, PA 17601-4359, V01.2,
568 pp., 2002.
3. Kececioglu, Dimitri B., Reliability 8 Life Testing Handbook, DEStech
Publications, 1148 Elizabeth Ave., #2, Lancaster, PA 17601-4359,
Vol.1, 960 pp., 2002.
4. Kececioglu, Dimitri B., Reliability t3 Life Testing Handbook, DEStech
Publications, 1148 Elizabeth Ave., #2, Lancaster, PA 17601-4359,
v01.2, 900 pp., 2002.
Chapter 3
MAINTENANCE
37
CORRECTIVE
UNRELl ABI LlTY MAINTENANCE
ACTIONS k2
1 1 Y Y 1 #
I b
2 2 L
‘FACILITIES n P I
*COST
t
PREVENTIVE
MAINTENANCE
c ACTIONS
1
PREVENTIVE conucriw
MAINTENANCE MAINTENANCE sunny DUAY TIME
TIME
*
I
- I I I I I I I 1 4
Fig. 3.2 - Preventive and corrective maintenance times and their relationships to all other
times associated with the life of equipment.
40 MAINTENANCE
even though design provisions for minimizing such delays can some-
times be made.
Most maintainability predictions are based on the distribution of
the active maintenance time and on the evaluated mean active main-
tenance time of the equipment.
All of the above maintenance times can to a lesser or greater ex-
tent be minimized or even eliminated by designing the right reliability,
maintainability, and safety into equipment and systems. Consequently,
desired reliability, maintainability and safety levels should be designed
into all equipment and systems.
12. Checkout time is the time required to test and observe the oper-
ating characteristics and outputs of the equipment to determine
whether it can be put back t o service again and function satis-
factorily or within the specification requirements.
13. Clean up time is the time required to tidy up and clean up the
equipment and its immediate surroundings.
14. Logging the wstomtion action time is a necessary time that should
be devoted to documenting the whole active maintenance and
restorative action t o insure that all reliability and maintainabil-
ity data is properly documented for subsequent reduction to re-
liability and maintainability parameters, for analysis, for design
reviews and for feedback to the disciplines responsible for the fail-
ures and malfunctions. The objective is to improve the reliability
and maintainability of equipment and systems.
6. Work stands.
7. Consumable supplies (spares, lubricants, etc.).
8. Equipment for jacking or hoisting heavy units.
9. Transportation equipment.
10. Shop facilities.
11. Test facilities.
12. Supply facilities.
13. Storage facilities.
14. Convenient and adequate changing, washing and rest areas.
15. Technical data.
16. Operating manuals.
17. Maintenance manuals.
Equipment and systems should be so designed as t o minimize the
requirements for support facilities and equipment, and to use standard
(not special) support items wherever possible.
PROBLEMS
MAINTAINABILITY DESIGN
CRITERIA
49
50 MAINTAINABILITY DESIGN CRlTERIA
(a) Prefered completely automatic built-in test (I)) Alternate auxiliary general purpose test
(test time - 5 minutes). (test time - 45 minutes).
Fig. 4.1 - Preferred and alternate diagnostic aids for rapid and positive fault identification.
aE +-
0
r
&
!i
s
c,
R
n
D
W
a
e
lr
e
E
a
n
rd
W
I
2
53
54 MAINTAINABILITY DESIGN CRITERIA
-
Sbrm rtnlnrr you I-
trking the govrrv
Fig. 4.4(b) - Minimum working space required for using common hand tools to provide
adequate accessibility.
r-------- 1
m
1
L
I I i
i
3
r
I
I
NI
n I
I
0 L
0
CS
I d
I .-.
th
“-to---- to-’ Er
57
T A
0
0
cs
I
0
B V
m
58
n S
ua
mk
Y
c
59
HERE (ON TOP)
(LUGS)
GOOD BAD
c II
This
4-7.Where and how would you locate your car transmission’s oil dip-
stick for ease of preventive maintenance thereof? Document your
suggestions with appropriate drawings.
4-8. Where and how would you locate your car engine’s spark plugs
for ease of maintenance thereof? What special tools if any, would
you use? Document your suggestions with appropriate drawings.
4-9. Come up with a better example than that given in Fig. 4.1 of
this chapter to decrease the diagnostic time of failed equipment.
Document your suggestions with appropriate drawings.
4-10. Come up with a better example than that given in Fig. 4.2
illustrating easier accessibility. Document your suggestions with
appropriate drawings.
Chapter 5
DOWNTIME DISTRIBUTIONS
AND MAINTAINABILITY
ENGINEERING FUNCTIONS
67
68 DOWNTIME DISTRIBUTIONS
-1 -- -r5= l t;
/
(rj.1)
N
for ungrouped data, where t' = log, t , and from
(5.2)
N= 1 nj, (5.3)
j=1
( 5.4 )
L J
70 DOWNTIME DISTRIBUTIONS
N'=29
C nj = 46 = N ,
j=1
N'
C n j t S = 30.30439,
j=1
and
N'
C nj(t;)2 = 75.84371.
j=1
- 46(0.65879)2
or
Ut'
.
=
[
75.84371
46-1 1.'
01' = 1.11435.
Consequently, the lognormal pdf, representing the data in Table
DOWNTIME DISTRIBUTIONS 71
5.1, is
or
1 L( l'-0.65879
e-2 1.11435
2
,
g ( t ) = (1.11435)t 6
where t' = log, t .
The plot of this pdf is given in Fig. 5.1 in terms of the straight
times in hours. See Table 5.3 for the g ( t ) values used.
The pdf of the log, t which is that of a normal distribution, or of
the t' values, is
(5.10)
or
1 e-6(
t'-0.65870
1.11435
2
.
g(t') = (1.11435)&
This pdf is that of a normal distribution and is shown plotted in
Fig. 5.2. See Table 5.3 for the g(t') values used.
2. The mean time to restore the system when this part fails, 5, is
obtained from
or
'i = 3.595 hr,
z
This compares with a mean of = 3.609 hr, which would be
obtained using the straight t's and averaging them. The differ-
ence is due to the fact that the former value assumes all data
are exactly lognormally distributed which is not the case, and
the latter gives only one estimate of a statistic, the arithmetic
mean, of the times to restore which would be an estimate of one
of the parameters, the mean of a normal distribution were the
data normally distributed. However, if it is known that the t's
come from a lognormally distributed population the T = 3.595 hr
is the value closest to the true mean.
0.4
T
0.3
0.2
0.1
0 I
I A
I
A'
1 .
I
. I .. I
O
c. Mode
tl t2 Median
3
I
-t =Mean
4 5 6 7 8
'At the mode, t'= 0.5582 hr, g ( i ) = 0.34470 and g(?) = 0.19247.
4 t the median. i = 1.932 hr, g ( i ) = 0.18530 and g(5) = 0.35800.
0.4 -
>
n 0.3 - -
Y
0
-3
v)
c
0)
-0 0.2 - -
_-
E
-
.-
n
la
o
E
n 0.1 - -
0 4
76 D 0 WNTIME DISTRIB U TIONS
or
f = 1.932 hr.
This means that in a large sample of t's, half of the t ' s will have
values smaller than i, and the other half will have values greater
than i.
4. The time by which one-half of the restorations of such systems
will be completed is the median, or
i = 1.932 hr.
5. The most frequently occurring, or observed, time to restore such
systems is the mode of the pdf of the t ' s , f, and is given by
-
f = etf-o:f -i e-":f (5.13)
f = e0.65879- (1.11435)'.
t
consequently,
t' = 0.5582 hr.
6. The standard deviation of the times to restore such systems is
given by
(5.14)
1
Qt = 3.59549 [e(1*11435)2 - 135 ,
or
ut = 5.641 hr.
This compares with the standard deviation of the straight t's of
the raw data, assuming they are normally distributed, or
ut = 4.945 hr.
The difference between these two values is due to the skewness
of the data which favors the lognormal distribution.
ANALOGOUS ENGIIVEERJNG FUNCTIONS 77
EXAMPLE 5-2
Prove that
M ( t ) = 1- e - p t , (5.15)
if the restoration, or repair, rate is constant with time.
*-r is the location parameter of the respective distribution involved; i.e., that of f ( T ) or g ( i ) .
TABLE 5.4 - Continued.
Item f ability engineering Maintainability engineering
number Item bctionn Item bctiona
4
(0
Q(T1) = I - e
- fT1 A( T)dT
M(t1) = 1 - e- J:' p ( t ) dr
MTBF = -y + 1 m
R ( T ) dT MTTR = -y +
OD
11 - M ( t ) ] dt
--
80 ANALOGOUS ENGINEERING FUNCTIONS
= -1 t
eu d v ,
or
M ( t ) = 1 - e- &*4 4 dt.
where
0 I 2 3 4 5 6 7 8 9 I0
lime to restore, t, hr
Fig. 5.3 - Plot of the repair rate function of the data of Example 5-1 when
the times to repair are lognormally distributed, for Example 5-3.
82 ANALOGOUS ENGINEERING FUNCTIONS
Repair rate,
t, Maintainability, density,
-hr 1’ 4t’) O(2) =M(t) g(t) -
1 M(t)
N I
rP/hr
0.2 -1.60944 -2.03552 0.0210 0.22552 0.9790 0.23035
0.4 -0.91629 -1.41357 0.0788 0.32961 0.9212 0.35780
0.6 -0.5 1083 -1.04965 0.1469 0.34397 0.8531 0.40320
0.8 -0.22314 -0.79141 0.2144 0.32718 0.7856 0.41646
1.o 0.00000 -0.59121 0.2772 0.30061 0.7228 0.49590
1.2 0.18232 -0.42768 0.3345 0.27227 0.6655 0.40911
1.4 0.33647 -0.28929 0.3862 0.24524 0.6138 0.39954
1.6 0.47000 -0.16944 0.4327 0.22057 0.5673 0.38882
1.8 0.58779 -0.06373 0.4746 0.19849 0.5254 0.37780
2.0 0.69315 0.03083 0.5123 0.17892 0.4877 0.36689
2.2 0.78846 0.11636 0.5463 0.16163 0.4537 0.35629
2.4 0.87547 0.19444 0.5771 0.14638 0.4229 0.34611
2.6 0.95551 0.26627 0.6064 0.13290 0.3936 0.33765
3.0 1.09861 0.39469 0.6534 0.11039 0.3466 0.31854
3.6 1.28093 0.55830 0.7117 0.08510 0.2883 0.29517
4.0 1.38629 0.65285 0.7431 0.07232 0.2569 0.28 154
4.6 1.52606 0.77827 0.7817 0.05749 0.2182 0.26348
5.0 1.60944 0.85310 0.8032 0.04976 0.1968 0.25281
5.6 1.72277 0.95480 0.8301 0.04053 0.1699 0.23860
6.0 1.79176 1.01671 0.8430 0.03559 0.1570 0.22666
7.0 1.94591 1.15504 0.8760 0.02625 0.1240 0.21161
8.0 2.07944 1.27487 0.8988 0,01986 0.1012 0.19625
9.0 2.19722 1.38057 0.9163 0.01534 0.0837 0.18322
-
10.0 2.30259 1.47512 0.9299 0.01206 0.0701 Q.17205
ANALOGOUS ENGINEERTNG FUNCTIONS 83
and
The plot of p ( t ) for various values oft is given in Fig. 5.3 based on
the calculated results given in Table 5.5.
A sample calculation follows:
For t = 2 hr,
g(t’ = log, t ) = g(t’ = 0.69315)’
-
- 4[z(t‘ = 0.69513)]
Qt’
’
--
0.69315-0.65879
1.11435 )
1.11435 ’
- 4(0.03083)
1.11435 ’
or
0.3988
g(t‘ = log, 2 hr) = = 0.35784.
1.11435
Therefore,
or
g(t = 2 hr) = 0.17892,
The maintainability for t = 2 hr is
s(t’=0.69315)
M ( t = 2 hr) = J_- 4(4 dz,
-
- L 0.03083
4(4 dz,
or
M ( t = 2 hr) = 0.5123.
84 DOWNTIME DISTRTBUTIONS
Consequently,
g(t = 2 hr)
p(t = 2 hr) =
1 - M ( t = 2 hr)’
-- 0.17892
1 - 0.5123’
or
PROBLEMS
Do the following:
(1) Write down the maintainability function for this equipment.
(2) Calculate the maintainability of this equipment for an al-
lowable time to restore of 5 hr.
(3) Calculate the mean time to restore this equipment.
(4) Calculate the 50% confidence level time t o restore.
( 5 ) Calculate the time to restore for a maintainability of 95%.
5-6. An equipment which requires restoration t o satisfactory function
when its components fail has a lognormal pdf with the following
parameters:
-
t' = 5 and = 0.5.
Do the following:
(1) Determine the probability density function of the times to
restore the equipment and plot it.
(2) Determine the maintainability function and plot it.
(3) Determine the repair rate function and plot it.
(4) Calculate the 50% confidence level time to restore the equip-
ment.
( 5 ) Calculate the time to restore for a maintainability of 95%.
5-7. Given is the following times t o restore distribution of an equip-
ment which requires restoration t o satisfactory function when its
components fail:
Do the following:
(1) Write down the maintainability function for this equipment.
(2) Calculate the maintainability of this equipment for an al-
lowable time to restore of 5 hr.
PROBLEMS 89
Do the following:
(1) Write down the maintainability function for this equipment.
(2) Calculate the maintainability of this equipment for an al-
lowable time to restore of 4 hr.
(3) Calculate the mean time to restore this equipment.
(4) Calculate the 50% confidence level time to restore.
(5) Calculate the time to restore for a maintainability of 95%.
5-9. Given is the following time-to-restore distribution of an equip-
ment which requires restoration to satisfactory function when its
components fail:
Do the following:
(1) Write down the maintainability function for this equipment.
(2) Calculate the maintainability of this equipment for an al-
lowable time to restore of 5 hr.
(3) Calculate the mean time to restore this equipment.
(4) Calculate the 50% confidence level time to restore.
(5) Calculate the time to restore for a maintainability of 95%.
5-10. An exponential equipment has a repair rate of 5 repairs per hour.
Do the following:
(1) Write the time-to-restore distribution equation in terms of
the repair rate.
(2) Write the time-to-restore distribution equation in terms of
the MTTR and plot it.
90 DOWNTIME DISTRIBUTIONS
91
8
c
rd
c
Q,
Y
c
'7
a
Y
r,
0
- 0
92
EXPONENTIAL CASE 93
that part, in time tl, when that part fails or has to be replaced
preventively.
4. Maintainability comprises those characteristics (both qualitative
and quantitative) of materials, design and installations which
make it possible t o meet operational objectives with a minimum
expenditure of maintenance effort (in terms of manpower, skill
levels, test equipment, technical data, operating and maintenance
manuals, maintenance support organization and facilities) under
operational environmental conditions in which scheduled and un-
scheduled maintenance is performed.
5. Maintainability is the rapidity with which failures and malfunc-
tions are diagnosed and corrected, or preventive maintenance is
completed and the equipment is successfully checked out. It is a
function of interacting variables including those of the design con-
figuration of the equipment, of accessibility of frequently failing
or malfunctioning parts, or of parts scheduled for more frequent
preventive maintenance on the one hand and available facilities
and appropriate manpower on the other.
where
p = equipment corrective repair, replacement or restora-
tion rate, in restorations per unit time; e.g., restora-
tions per hour,
and
1
MTTR = -.
P
The maintainability function for the exponential time to restore dis-
tribution case, from Eq. (6.1), is
or
M ( t 1 ) = 1 - e-btl = 1- e -&h, (6.5)
where
M ( t 1 ) = probability that repair will be successfully com-
pleted in time tl when it starts at t l = 0,
and
tl = the repair, replacement, or restoration time for
which M(t1) is to be determined.
Once the MTTR is given, M ( t 1 ) can be calculated for any specific
value of t l . Figure 6.2 illustrates two such maintainability functions,
M ( t ) : One for an equipment with an MTTR of 0.5 hr and the other
for an equipment with an MTTR of 1 hr.
An equipment with an exponential times-to-restore pdf has a 63.2%
probability of being restored satisfactorily in a time t which equals
its MTTR, a probability of 40% for t = 0.5108 x MTTR, a prob-
ability of 22% for t = 0.2485 x MTTR, a probability of 90% for
t = 2.3026 x MTTR and a probability of 95% for t = 2.9957 x MTTR.
Finally, there is a 50% probability of accomplishing restorations in
t = 0.69315 x MTTR, which is called the median time to restore. See
Table 6.1 for these and other values.
Of specific interest in maintainability specifications are the 90% and
95% probabilities. It is often desirable to specify a maximum repair,
maintenance, or restoration time, tMMAx,which should possibly not be
exceeded, or exceeded only with a small probability. Such constraints
on maximum maintenance times are usually associated with the 90th
or 95th percentile; i.e., the probability of accomplishing maintenance
in a specified time tMMAXshould be 0.90 or 0.95, according to what
the specification demands. In the case of an exponential distribution
of restoration times, M ( t ) = 0.90 for tMMAX= 2.3026 X i"TR and
M ( t ) = 0.95 for tMMAx= 2.9957 x MTTR. The explanation of such a
0.900 0-91
0.777
I /
n
e
s
0.632 1
/ Y(t)=l-e
1.o I:5 2
ERT = 0.347 hr ERT = 0.693 hr
Restoration time, t, hr
Fig. 6.2 - Two exponential maintainability functions.
96 MAINTAINABILITY AND ITS QUANTIFICATION
consequently,
and
tMMAX= - M T T R X IOge
EXAMPLE 6-1
It is specified that with probability M ( t ) = 1 - cr = 0.90,or with
cy = 0.10, the maintenance time for a specific equipment must not
exceed one hour; i.e., tMMAX=i 1 hr. Determine the MTTR that has
to be designed into this equipment.
REPAIR RATE 97
= 0.434 hr,
M T T R = (-2.302)
or about 26 minutes.
'
I
(6.10)
= MTTR'
Since the M T T R is a fixed number, the repair rate, p, is constant for
the exponential distribution. When this is the case, the probability of
completing a repair in a short period of dt when repair started t time
units ago; i.e., p dt is always constant, regardless of how long a repair
action has been in progress. For all other distributions, the repair rate
is nonconstant. It usually increases as a function of the progressing
maintenance time, t.
But if the predicted failure rates are not correct, the measured MTTR
may deviate significantly from the predicted value, even though the
individual repair times initially were well estimated. When designing
an equipment for maintainability, prediction techniques such as those
in MIL-HDBK-472are used. An MTTR estimate of an exponentially
failing equipment is obtained from
N
CXi
(6.11)
where
N = total number of replaceable or repairable components,
and
-
ti = mean equipment repair time when the ith component
fails.
Equation (6.11) applies when the average time to restore the equip-
ment is desired when all components fail eventually. Equation (6.11) is
a practical design tool for maintainability. When the predicted failure
rates are available, the maintainability engineer evaluates the expected
repair times, c. They are estimated by maintenance time analysis
methods based on previous field data or expert engineering judgment
which consider fault verification, fault localization, fault isolation, dis-
assembly, replacement, reassembly, adjustment, servicing and check-
out. Each of these actions takes a certain time to perform, but these
times can well be estimated from the design, testability, and packaging
concept for the equipment. Trade-off techniques are used to change
design and packaging characteristics, as well as test capabilities, to
c,
achieve the desired failure rates, Xi, and mean repair times, for the
various types of failures and thus to comply with the MTTR require-
ment. The maintainability engineer can trade-off these X i and to
achieve the MTTR goal by good design for reliability (Xi) and main-
tainability (c). As to the measured MTTR, this is determined from
CORRECTWE MAINTENANCE TIME 99
EXAMPLE 6-2
A system consists of three replaceable units which have the follow-
ing MTBF's and replacement times:
Subassembly 1 : MTBF1 = 1,000 hr, = 1.0 hr,
MTTR =
X I q t A2 G + A3 7i
A1 + +
A2 A3
7 (6.13)
MTTR =
+
(0.001)(1) (0.002)(0.5) (0.002)(1) +
0.001 f 0.002 0.002 +9
or
0.004
MTTR = -= 0.8 hr, or 48 min.
0.005
(6.15)
where
M = total number of different active preventive main-
tenance actions undertaken,
fj = frequency with which the jth preventive mainte-
nance task is performed, preventive maintenance
tasks per unit time,
and
-
tMpj = system’s mean active preventive maintenance
time when the j t h preventive maintenance task
is performed.
If the frequencies f j are given in -
maintenance tasks completed sat-
isfactorily per hour, the downtimes t M p , should be given in hours.
(6.16)
(6.21)
(6.22)
or
-
i = et'.
where
MTTR = 2 hr.
Therefore,
where
1
or
’= MTTR = repair rate,
1
p = - = 0.5 repair/hr.
2
Therefore,
e-o.5 i
g ( t ) = 0.5
104 MAINTAINABILITY A N D ITS QUANTIFICATION
,
I,,
,
0 1 2 3 4 5 / r 6 7 0 9 10 11 12 13 14
1 9 4 1 5.99 9 1
lime to restore, t, hr
Fig. 6.3 - Plot of the maintainability function for the times to restore of Example 6-3.
106 MAINTMNABILITY A N D ITS QUANTIFICATION
rn
1 1 1 2 I
50 1.38629
90 4.60517
95 5.99146
99 9.21034
or
3
MTTR = -
Zoge( 1 - 0.95) = 1.00142 hr.
where LN stands for lognormal,N for normal, and 4 for the standard
normal distribution,
t’ = log, t , (6.27)
-
t; - t‘
z(t’l) = -, (6.28)
Qt’
LOGNORMAL CASE 107
and 7 and q t , are given by Eqs. (5.1) and (5.2), and (5.3) and (5.4),
respectively. Entering the standard normal distribution probability
tables with % ( t i )yields M(t1) quantitatively.
It is also desirable to determine the maintenance time by which
a specific percentage of the maintenance actions will be completed
satisfactorily. This is also the time tl-, for which the maintainability
is 1 - a,or
(6.30)
and
(6.31)
or
EXAMPLE 6 4
Given the times-to-restore data of Example 5-1, do the following:
1. Determine the maintainability function and plot it.
2. Determine the maintainability for this part if the maintenance
action needs t o be completed within 5 hr.
3. Determine the maintainability for a 20 hr completion time.
4. Determine the time within which 90% of the maintenance actions
for such parts will be completed.
108 MAINTAINABILITY AND ITS QUANTIFICATION
1-a 4t;-a 1
0.80 0.8416
1.036
1.282
1.645
2.326
1. The maintainability function for the system, when this part fails,
M ( t ) , from Eq. (6.26), is
J-03
where
-
%(t')= -,
- t'
2'
Qt'
t' = log, t ,
-
t' = 0.65879,
and
01' = 1.11435.
The quantified M ( t ) values are shown plotted in Fig. 6.4.
2. The maintainability for this system, for a maintenance time of
5 hr is
4(4 dz.
1.o
0.8
0.6
0.4
0.2
0
0 1 2 3 4 5 6 7 0 9 10
Time to restore, t, hr
Fig. 6.4 - Plot of the maintainability function for the times to repair of Example 6-4.
110 MAINTAINABILITY A N D ITS QUANTIFICATION
With
t = 5 hr, t' = log, 5 = 1.6094,
and
%(loge5) =
-
1.6094 0.65879
= 0.85310,
1.11435
or
M(5 hr) = 0.8032, or 80.32%.
This means that there is about an 80% chance that the mainte-
nance action on these systems, when this part fails, will last 5 hr
or less, or the probability of completing the maintenance action
satisfactorily within 5 hr is about 80%.
3. The maintainability for this system when this part fails, for a
maintenance time of 20 hr, is
or
M(20 hr) = 0.9820, or 98.20%.
(6.35)
where
g(t) = time-to-restore distribution.
The Weibull times-to-restore distribution is
(6.36)
EXAMPLE 6-5
Given is the following Weibull times-to-restore pdf of equipment
which requires restoration to satisfactory function when its components
fail:
where t is in hours.
Do the following:
1. Write down the maintainability function for this equipment.
2. Calculate the maintainability of this equipment for an allowable
time-to-restore period of 5 hr.
3. Calculate the mean time t o restore this equipment.
4. Calculate the median time t o restore this equipment.
5, Calculate the time t o restore for a maintainability of 95%.
SOLUTIONS TO EXAMPLE 6-5
1. The maintainability function for the equipment is given by
M(l) = 1 - C-0.25 3.5
.
2. The maintainability of this equipment for an allowable time-to-
restore period of 5 hr is
5-0.23 3 5
M ( t = 5 hr) = 1 - ~-(-4Tii-) '
or
M(l = 5 hr) = 0.83875, or 83.875%.
3. The mean time to restore this equipment is given by
Therefore,
M T T R = 0.25 + 4.0 (0.8998),
or
M T T R = 3.84920 hr.
where
g ( t ) = time-to-restore distribution, which needs to
be known ahead of time,
and
11 = restoration period for which the maintainability
is to be predicted.
PROBLEMS 115
where
N(t 5 tl) = number of maintenance actions which were com-
pleted successfully in time tl or less; or the num-
ber of maintenance actions that required t l or
less time to complete successfully, or were clocked
to have been completed successfully in time tl or
less,
and
EXAMPLE 6-6
Failures were simulated in identical equipment operating in identi-
cal environments, and the same maintenance crew restored this equip-
ment to satisfactory function. Out of the 120 restoration times that
were clocked, 115 lasted 35 minutes or less.
Determine the a posteriori maintainability of this equipment for a
required restoration time of 35 minutes.
SOLUTION TO EXAMPLE 6-6
The a posteriori maintainability is given by
-
h
115
M ( t l = 35 min) = - = 0.958,
120
or
-
h
M ( t 1 = 35 min) = 95.8%.
Consequently, the average maintainability that has been demonstrated
is 95.8010, and that on the average 95.8% of the restorative or mainte-
nance actions lasted 35 minutes or less.
PROBLEMS
6-1. Given is the times-to-repair data of Table 6.5 for a specific part
in a system. Do the following:
116 MAINTAINABILITY A N D ITS QUANTIFICATION
Do the following:
118 MAINTAINABILITY AND ITS QUANTIFICATION
Do the following:
(1) Write down the maintainability function for this equipment.
(2) Calculate the maintainability of this equipment for an al-
lowable time to restore of 5 hr.
PROBLEMS 121
123
124 MEAN TIME TO ACTIVELY RESTORE AN EQUIPMENT
or
where
-
t~ = mean time t o correctively restore the downed equip-
ment t o successful function for t hours of operation,
and
N
i=l
This 5
time should be minimized to reduce the downtime per op-
erating hour, to reduce the cost of corrective maintenance, to increase
the availability of equipment, t o increase the production per hour and
to reduce the unit cost of production.
If the failed units must be repaired elsewhere and brought to the
equipment for installation, or repaired on the spot, and the mean time
RESTORATION EFFICIENCY AND CONSISTENCY 125
consumed for this effort is & for Unit 1, & for Unit 2, etc..., then Eq.
(7.1) becomes
where
-
tf = mean time to replace a failed unit with a fresh
one.
0
Restoration time, t
C T ~= 1 - u1 / CT,= 1 - u2 / G, u; < c.
and
The crew with the larger CT should be preferred. Figure 7.1 shows
the relative values of u1 and u2. Again, it is desirable t o conduct sta-
tistical tests of comparison t o determine the confidence level at which
C T ~is greater than C T ~if, CT, > C T ~were the case.
EXAMPLE 7-1
It has been established that an equipment’s intrinsic mean restora-
tion time clocked for a select, skilled crew is 36 minutes. Two other
crews of the equipment manufacturer’s Service Department are selected
to restore the equipment shipped to a key customer. The times t o re-
store this equipment by each crew are determined with the following
results:
Crew 1: = 42 min and u1 = 4 min.
Crew 2: = 48 min and 62 = 8 min.
128 MEAN TIME TO ACTIVELY RESTORE A N EQUIPMENT
3. Which crew would you select from the restoration time efficiency
point of view?
4. Which crew would you select from the restoration time consis-
tency point of view?
or
(7.10)
If each unit has a constant failure rate, then the mean maintenance
man-hours for t cumulative operating hours is given by
N
(7.11)
i=l
also known as
-
D;i = M M H / O H , (7.13)
(7.14)
(7.15)
This value may be used to calculate the average labor cost, CL,for
repairing and replacing failed equipment on the spot and/or in a repair
shop for t cumulative hours of operation of the equipment from
7
CL = D R R - C L , (7.16)
where
CL = average labor cost to repair and replace, $, for t
operating hours of the equipment,
and
CL = averagelabor cost per hour, or the average hourly
labor rate.
EXAMPLE 7-2
A subsystem consists of three units, which are reliabilitywise in
series. Their useful life failure rates and wear-out pdf parameters are
given in Table 7.1.
MEAN MAINTENANCE MAN-HOURS 131
%
with i = 1,2 a.nd 3. Ta.ke = 0.25 and % = 0.75.
The average replacement times, F,
and the required number of ser-
vice men, n;, as well as the werage repair times, z,
and the required
number of repairmen, ri, are given in Table i.2.
0.75 2
1.00 3
0.50 2
1. What is the mean time t o replace these three units, per subsys-
tem operating hour?
2. Wha,t is the mean time t o repair these three units, per subsystem
operating hour?
3. What is the mean time to repair and replace these three units,
per subsystem operating hour?
4. Same as Case I h u t for operating liours equal to the stabilized
M T B F of this subsystem with units reliabilitywise in series,
given by
132 MEAN MAINTENANCE MAN-HOURS
1
Subsystem MTBF = rnss = 7.
MTBF~G
=
I” Rss(T)dT,
1. The mean time to replace these three units, per subsystem oper-
ating hour, is determined from
For Unit 1
ml = L m R 1 ( T )dT
= Jrn
(0.25 e-0*0003
0
* + 0.75 e-[5551 ) d T ,
T 9.5
ml = 0.25 0.0003
1
-+ 0.75 [Tl+ o1 r (+ i, 1)]
ml = -0.25
0.0003
+ 0.75 [o + 300 r (A+ 1)],
where
Therefore,
0.25
ml =
0.0003
+ 0.75 [(300)(0.88726)] = 1,032.96683 hr.
Similarly,
m2 =
- /m
0
(0.25 e-o*ooo6 * + 0.75 T 3.5
) dT,
m2 = -0.25
0.0006
+ 0.75 [o + 500 r (A+ 1)] ,
134 MEAN MAINTENANCE MAN-HOURS
where
therefore,
0.25
m2 = -+ 0.75 [(500)(0.89975)]= 754.07292 hr;
0.0006
m3 =
0.25
0.00045
+0.75 [o + 400 r (f+ i)] ,
where
Therefore,
0.25
m3 = -+ 0.75 [(400)(0.91257)]= 829.32656 hr.
0.00045
Substituting these values into the equation for F, yields
-
'* = i= 1
-
(z) 0.50 0.80
= 1,032.96683+ 754.07292
2. The mean time to repair these three units, per subsystem oper-
5 (z),
ating hour when all units require repair, is determined from
-
d* =
r=l
-
- 0.75 1.00 0.50
1,032.96683 754.07292 + 829.32656'
or
-
d* = 0.002655094 hr/subsystem operating hr.
MEAN MAINTENANCE MAN-HOURS 135
3. The mean time to repair and replace these three units, per sub-
system operating hour, is given by
-- (0.75 t 0.50) +
(1.00 0.80) (0.50 t 0.25)
1,032.96683 754.07292 -t 829.32656 ’
or
-
d& = 0.004501492 hr/subsystem operating hr.
4. The mean time to replace these three units for operating hours
equal to the stabilized M T B F of this subsystem
-
2 = ma, tL,
-
where
1
m,, = subsystem M T B F = 7,
x*
i=l
1
m88 = 1 1 1 ’
1,032.96683 + 754.07292 + 829.323656
or
mss = 285.71309 hr.
Therefore,
-
2 = (285.71309)(0.001846397),
or
-
1 = 0.527539796 hr.
5. The mean time to repair these three units for operating hours
equal to the stabilized M T B F of this subsystem is given by
- -
d = mss-dC,
= (285.71309)(0.002655094),
or
-
d = 0.758595111 hr.
136 MEAN MAINTENANCE MAN-HOURS
6. The mean time to repair and replace these three units for oper-
ating hours equal to the stabilized MTBF of this subsystem is
given by
- -
d m = ma, d h ,
*
= (285.71309)(0.004501492),
or
-
dRR = 1.286135189 hr.
7. The mean time to replace these three units for operating hours
equal to the regular, statistical M T B F of this subsystem is
-T = MTBFREG.F,
where
MTBF-G =
/," Raa(T)dT,
= J,- &(T) Rz(T) R3(T) dT,
9. The mean time t o repair and replace these three units for oper-
ating hours equal t o the regular, statistical MTBF of this sub-
system is
- -
dm = M T B F ~ G * dm,
= (260)(0.004501492),
or
-
dm = 1.170387920 hr.
-
where Dj, is the total mean man-hours to repair and replace
the failed units in the subsystem per one operating hour, then
-
D;1R =
(0.75)(2) t (0.50)(1) + (1.00)(3) t (0.80)(3)
1,032.96683 754.07292
(0.50)(2) t (0.25)(2)
829.32656 '
or
-
D;iR = 0.010905978 MMHlsubsystem operating hr.
-
11. The Dizp of Case 10, if Units 1 and 3 can be repaired and re-
placed simultaneously, but by the two separate crews, is the same
since the replacing and repairing man-hours are independent of
simultaneity, as long as these two crews are putting in their time
anyway. Thus, even though the repair and replacement of Units
1 and 3 occur simultaneously, the mean man-hours per operating
hour remain unchanged.
12. The mean time to repair and replace these three units, per sub-
system operating hour, for Case 11 is given by
138 MEAN TIME FOR MAINTENANCE
however, since Units 1 and 3 are being repaired and replaced si-
+
multaneously, we use the larger of ( d l q)/rnland (&+ g)/m3.
Thus, for Unit 1
-
dl + +
-- - 0.75 0.50
= 0.001210107,
ml 1,032.96683
and for Unit 3
+ +
Since (& q ) / m l > (% g ) / m 3 the MTTR of the subsystem
per operating hour is
- +
0.75 0.50 1.00 0.80 +
diiR = 1,032.96683 754.07292 '
or
-
dhR = 0.002387037 hr/subsystem operating hr.
(7.17)
where
A,; = mean corrective failure rate for the ith unit
while the equipment undergoes preventive main-
tenance, also in corrective failures per hour,
which is also the number of corrective restorative
actions required per equipment operating hour,
MEAN TIME FOR MAINTENANCE 139
where
N
~ ( X G + Xpi G)= (289 X (0.55) + (310 x (0.75)
i=l
t (179 x (0.33)
+(6.667 x (0.25)
+(2.273 x (0.35)
t (3.333 x 10'~) (o.i5),
= 0.003413,
and
N
C(Xk+ Xpi) = (289 X + 310 X t 179 X
i=l
+6.667 x 1 0 ' ~t 2.273 x 1 0 ' ~t 3.333 x
= 0.013051.
Then, the MTTR is given by
0.003413
MTTR =
0.013051 '
or
MTTR = 0.261513 hr.
PROBLEMS
t; = 0.50 hr,
$ = 0.80 hr,
and
= 0.25.
Furthermore, the required number of service men, ni, are
the following:
n1 = 1,
n2 = 3,
and
n3 = 2.
and
cis = 0.50.
The number of required repairmen, ~ i are, as follows:
T i = 2,
T2 = 3 ,
and
T 3 = 2.
142 MEAN TIME FOR MAINTENANCE
=
MTBF~G 1 A,, dT,
00
where R,, is the reliability function for the configuration and the
types of units comprising the configuration.
7-2.A system consists of three units which are reliabilitywise in series.
Their useful life failure rates and wear-out probability density
function parameters are given in Table 7.5.
TABLE 7.5 - Useful life and wear-out data associated
with the three units of the subsystem
for Problem 7-2.
and
f: = 0.33.
Assume the stabilized MTBF of each unit is given by
1
MTBFi =
A,. + 1
1. What is the mean time to replace these three units per system
operating hour if the average replacement times, q,
are as
follows:
= 0.55 hr,
t'; = 0.75 hr,
and
= 0.33.
Furthermore, the required number of service men, ni, are
the following:
n1 = 1,
n2 = 3,
and
n3 = 2.
2. Same as Case 1but for operating hours equal to the stabilized
MTBF of the units.
3. What is the average total maintenance-man hours to repair
and replace per system operating hour, if the failed units
are not disposable but require repair in a workshop before
PROBLEMS 145
they are replaced and the average repair times, d;, are as
follows:
d1 = 1.5,
d; = 2.0
and
23 = 1.0.
The number of required repairmen, ri, are as follows:
T i = 2,
r2 = 3,
and
T3 = 2.
= 0.55 hr,
= 0.75 hr,
and
< = 0.33.
Assume the stabilized MTBF of each unit is given by
1
MTBFi =
Li+&
2. What is the average total maintenance man-hours t o repair
and replace per system operating hour, if the failed units
are not disposable but require repair in a workshop before
they are replaced? The required number of service men, ni,
are as follows:
nl = 1,
n2 = 3,
and
n3 =2
The average repair times, d;, are as follows:
d; = 1.5 hr,
d; = 2.0 hr,
and
& = 1.0 hr.
The number of required repairmen, r i , are as follows:
= 2,
T2 = 3,
and
T3 = 2.
Chapter 8
MAINTAINABILITY
ENGINEERING
SPECIFICATIONS AND THEIR
APPLICATIONS
147
148 MAINTAINABILITY ENGINEERING SPECIFICATIONS
8.2 -
MIL STD 470 -
This standard provides requirements for establishing a maintainabil-
ity program and guidelines for the preparation of a Maintainability
Program Plan.
The following tasks are required t o be incorporated into the Main-
tainability Program:
1. Prepare a maintainability program plan.
8.3 -
MIL STD 471 -
This standard provides procedures and test methods for verification,
demonstration, and evaluation of qualitative and quantitative main-
tainability requirements. It also provides for qualitative assessment of
various Integrated Logistic Support factors related to, and impacting,
the achievement of maintainability parameters and item downtimes,
such as technical manuals, personnel, tools and test equipment, main-
tenance concepts and provisioning.
MIL - STD - 471 149
8.3.1 REQUIREMENTS
Maintainability verification, demonstration, and evaluation are required
to be performed in accordance with the maintainability, M, test plan
prepared by the contractor and approved by the procuring activity.
The M test plan shall be totally responsive to the qualitative and
quantitative requirements and supplemental information contained in
the procurement documents and the M program plan required by MIL
- STD - 470. The plan shall embody three phases at the system level:
1. Phase I - Verification.
2. Phase I1 - Demonstration.
and
Plan A, which assumes a lognormal g(t),
or
Plan B, for which selection of a g(t) is not necessary.
- as they relate to the mean-
Figure 8.1 illustrates these parameters
time-to-restore distribution, g(t);and Fig. 8.2 as they relate to
the Operating Characteristic (OC) Curve.
2. Calculate the demonstration sample size, It, for Test Plan A ,
from
TABLE 8.1 - Stratification procedure.
Eguipmena ~ Radar X Y Z
152 MAINTAINABILITY ENGINEERING SPECIFICATIONS
P
0
1 --
n = ( y ) ,
where
p = consumer’s risk,
cr = producer’s risk,
or
-
P(P L Po = tL1) L a’
and
d^ = standard deviation of the maintenance times.
1 2 3 4 5
Relative
frequency of Cumulative
Maintenance FdUn occurrence, range,
t d mode Effect percent percent
Receiver 1. Component 1. Noise 20 -
O.Oo0 0.199
remove/ out of
replace tolerance
2. Component 2. Receiver 35 -
0.200 0.549
shorted/open inoperative
otherwise reject.
For Test B
Accept if
otherwise reject.
Here
and
EXAMPLE 8-1
The maximum acceptable mean maintenance time is
-
p1 = tul = 55 minutes,
TEST METHOD 1 155
P(F 2 7 m ) 5 p = 10%.
The desirable, design-to, mean maintenance time is
-
PO = tL1 = 35 minutes,
with a producer's risk, a,of 5%, such that
h
n=
+
(1.65 x 35 1.28 x 55)2
(eoa6 - 1) = 33.67,
(55 - 35)2
or
n = 34,
with
Z,: = 0.6, a prior estimate.
Then,
( )
2
1.65 t 1.28
n= = 30.99,
or
n = 31.
EXAMPLE 8-2
If? = 40 minutes and Ct = 30 minutes, determine if the equipment
passes its maintainability demonstration test according to Plan A, and
according to Plan B.
SOLUTIONS TO EXAMPLE 8-2
Plan A
or
n 30
2 5 35 t 1.65-
a= 43.49.
Since
40 5 43.49,
the equipment passes the test.
Plan B
or
30
40 5 35 + 1.65-
m = 43.89.
Since
40 5 43.89,
the equipment passes the test.
TEST METHOD 1 157
2q*
or
-t f = log, =t - -1O- 2t / .
h
2
or
-t f = 3.255.
A
4. /3 = consumer’s risk.
5. a = producer’s risk.
The two times-to-restore distributions for the same chosen, fixed
maintainability are shown in Fig. 8.3. The corresponding OC curve is
shown in Fig. 8.4.
0
tL t
Maintenance time, t, for a fixed maintainability
L J
The decision criterion is
Accept if
n
-I
2 -I-Z(1-M) 6 5 2'**
TEST METHOD 2 161
Reject otherwise.
EXAMPLE 8-3
It is specified that for a maintainability of 95% the desired mainte-
nance time of the equipment be 35 minutes, and the 95% maintenance
time is not to exceed 55 minutes.
The consumer's risk is specified as lo%, and the producer's risk a6
5%.
Determine the maintenance actions that have to be demonstrated,
assuming = 1.2.
SOLUTION TO EXAMPLE 8-3
G'iven are
a = 0.05, /3 = 0.10,
M = 95%, 100%- M = 5%,
t L = 35 minutes,
tu = 55 minutes.
2
, = z0.05, zp = t O . 1 0 ,
t, = 1 . 6 5 , =
~ ~1.28,
t'u = log,55 = 4.00733,
and
t'L = log, 35 = 3.55535.
Then,
+ (1.65)?
or
= [ 2
2 ] 1*65t 1'28 ) ? = 142.88,
(1'2)2 (4.00733 - 3.55535
n = 143.
EXAMPLE 8 4
The maintenance actions of Example 8-3 are demonstrated with
the following results:
A
nnew = -
2'25 (142.88)= 223.25,
1.44
or
nnew = 224.
Therefore, n = 143 is not adequate and the additional maintenance
tasks that have to be demonstrated are
nadd = 224 - 143 = 81.
EXAMPLE 8-5
At the conclusion of the total required maintenance tasks the fol-
lowing updated results are obtained:
A
t'* = log, 35
[
+- (1.65)(1.49) 4-
:2
+ 2(224 - 1)
tt8 = 3.55535 + 0.25274 = 3.808,
or
ti* = 3.81,
and
TEST METHOD 3 163
Since
5.36 p 3.81,
the equipment has not met the tL = 35 minutes requirement.
0 T
t
and
[B]= zQIMu(l - Mu)]'/2f z p [ M ~ ( l -ML)]'/~.
Use next lower integer value. Also
Po = 1- Mu,
and
and
Table 8.3 provides sampling plans for various CY and P risks and
ratios of
~-ML
k = Pi/Po = when M u > 0.80.
1-Mv
k I p-0.05
C D
1.5 a6 54.100
2.0 a2 15.700
2.5 13 8.400
3.0 9 5.430 7 3.980 0 3.290 7 4.000 5 3.150 4 2.430 4 3.090 3 2.500 2 1.540
4.0 0 3.290 5 2.010 4 1.970 4 2.430 3 1.750 2 1.100 3 2.300 2 1.540 1 0.824
5.0 4 1.970 3 1.370 3 1.370 3 1.750 2 1.100 2 1.100 2 1.540 1 0.824 1 0.824
10.0 2 0.018 2 0.818 1 0.353 1 0.532 1 0.532 1 0.532 1 0.824 1 0.824 0 0.227
To Bnd the rarnplc h e , b r given po.pI ,a and , divide the appropriate D vdae by p~ and use the greatest
integer less than the qnotient. Example: pD = 0.05yp1 E 0.10, a E 0.10, p f 0.05 and L = = 4.
Then n = & = ## = 40. The acceptance number ir c = 4.
168 MAINTAINABILITY ENGINEERING SPECIFICATIONS
1. Mu = 0.90, then
Po = 1 - M u = 1 - 0.90 = 0.10.
Since Po < 0.20, Table 8.3 is used to find c and n as follows:
Q = 0.05, ,B = 0.10,
and
1 - ML
PI
k=-=
Po 1 - Mu
- 11 -- 0.70
0.90
0.3
= - = 3.
0.1
Then, from Table 8.3
D = 3.98;
consequently,
n=-=
D D - 3.98
Po 1-Mu 1-0.90,
or
ri = 39.8.
Use the greater integer value less than the quotient, then n = 39.
Therefore, 39 maintenance actions have to be demonstrated.
2. From Table 8.3 with a = 0.05, p = 0.10, and k = 3,
c = 7.
3. Accept if r 5 c. Here,
r = 5<c=7;
consequently, the equipment should be accepted as having demon-
<
straked a maintainability of at least M = 70% with p lo%, for
a critical, desired maintenance time of T = 20 minutes.
TEST METHOD 4 169
4. In this case
T = (0.25) n,
or
T = (0.25)(39) = 9.75, or T = 10.
Since, in this case,
T = 10 > c = 7.
the equipment should be rejected.
log,,, M T T R c =
5 (log,,
i=l
tci 1 -
= t" = log,, i,
n C
and
s = tlp =
2(log,,
i=l
tCd2 - nc(log1, MTTRc)*
nc - 1 (8.3)
where log,, t = t", and MTTRc is the measured geometric mean time
to repair, or ic.
170 MAINTAINABILITY ENGINEERING SPECIFICATIONS
8.7.4 DISCUSSION
The value of the equipment repair time, E R T , t o be specified in the
detailed equipment specification should be determined from:
ERT(specified) = 0.37 ERTmaS, (8.5)
where ERTma, is the maximum value of E R T that should be accepted
no more than 10% of the time, and 0.37 is a value resulting from the
application of the “Student’s t” operating characteristics that assures
a 95% probability that an equipment having an acceptable ERT will
not be rejected as a result of the maintainability test when the sample
size is 20, and assuming a population standard deviation u p of 0.55.
EXAMPLE 8-7
A specific equipment’s median repair time, E RT, requirement is
2.50 hours. Twenty (20) corrective maintenance tasks are performed,
in accordance with the procedure outlined in Appendix A of MIL-STD-
471, or Table 8.1, and their duration is recorded. Using these times to
repair, the following are calculated:
logl0MTTRG = 0.65,
where -
logl0MTTRG = t”.
Also
- = log,oi,
tl‘
as
TEST METHOD 5 171
It may be seen that MTTRG is the median time to restore the equip-
ment t o satisfactory function. The standard deviation of the twenty
(20) corrective maintenance actions is calculated t o be u p = S = 0.85.
Determine if the equipment is meeting its repair time, E R T , require-
ment.
SOLUTION TO EXAMPLE 8-7
Accept the equipment as having met its ERT requirement if
+
loglo MTTRG 5 loglo ERT 0.3970t8#,
+
0.65 5 log10 2.50 0.397(0.85),
+
0.65 5 0.3979 0.3375,
or
0.65 5 0.7354;
therefore, this equipment is meeting its ERT requirement.
EXAMPLE 8-8
An aircraft has a required operational readiness of 75%, with an
average daily usage of 2 hours per day and an average flight length of 4
hours per flight. The nonchargeable maintenance downtime per flight
is 0.2 hours per flight and the delay downtime is 1 hour er flight. Find
the chargeable maintenance downtime per flight, -m. C M J
2
I \ I \ - I
- 0.2 - 1,
CMDT
= 48 - 36 - 0.2 - 1
NOF
or
CMDT
= 10.8 hours per flight.
NOF
174 MAINTAINABILITY ENGINEERING SPECIFICATIONS
where
and
and
Xa -c11 = -q.
of fi
Then, the test sample size can be shown to be
n=
+
(1.28 1.28)* = -6.57
-
o.09 - 72.8,
(0.3f 1)2
or
n = 73.
or
(8.10)
Reject if
EXAMPLE 8-10
A prototype aircraft has completed a demonstration test period of 8
flights. The chargeable maintenance time for each flight is given in the
next table. If the required mean chargeable maintenance downtime is 5
hours per flight, has the aircraft met its C M D T requirement? Assume
0 = 0.10.
Flight CMDT,
number hr
1 3.0
2 12.0
3 1.5
4 5.0
5 3.0
6 6.0
7 8.5
8 2.0
TEST METHOD 5 177
3 + 12 + 1.5 + 5 + 3 + 6 + 8.5 + 2
= -41
8'
or
-
X = 5.13 hours.
By Eq. (8.10),
s=
\(NOF
1 -l) [ c Xf-
NOF
._
I- 1
(NOF) 4,
where
a
X X f = (3)2 + (12)2+ (1.5)2+ (5)2 + (3)2
i=l
+
+(6)2 (8.5)2 (2)2, +
+ +
= 9 + 144 2.25 + 25 9 + 36 + 72.25 + 4.
= 301.5.
Then, Eq.(8.10) becomes
or
s = 3.6130 hours.
Since a = 0.10, q, = 1.28, and the test for the decision procedure
is
%a s (1.28) (3.6130)
jQ+-=5+
drn J8 7
+
= 5 1.6351,
= 6.6351, or 6.64hr/ f light.
178 MAINTAINABILITY ENGINEERING SPECIFICATIONS
Then, since
-
X = 5.13 < 6.64,
the aircraft system has met its target CA4DT requirement.
EXAMPLE 8-11
During testing of a new aircraft system, a. total of 1,500 flight hours
are accuniula.ted. Also, 7,560 hours of chargeable maintenance down-
time a.re incurred during the testing. If the required maintenance iiian-
hours for the syst.em is 5 man-hours per flight hour. with a 4 h 4 R of
lo%, has the aircra,ft met the man-hour rate requirement?
TEST METHOD 7 179
C M M = 7,560 hours,
D F H = 1,500 hours,
and
M H & = 5 man-hours/flight hour.
Calculate A M R by
A M R = 0.10. M H R Q ,
= 0.10-5,
or
A M R = 0.50 man-hours/flight hour.
Calculate M B R by Eq.(8.11):
CMM
MHR= -
DFH '
--7,560
-
1,500'
or
M H R = 5.04 man-hours/flight hour.
Since, by Eq. (8.12),
M H R 5 MHRo+ AMR.
5.04 5 +
5 0.50,
5.04 5 5.50,
(8.14)
where
X,. = man-hours for corrective maintenance Task i,
n = number of corrective maintenance tasks sampled,
which shall not be less than 30,
M T B F = MTBF of the unit = ~ / X T , where AT is the value
in Table 8.1, Column 9,
(PS)= estimated total man-hours required for
preventive maintenance during a period of
operating time equal to n (MTBF)hours,
and
T = total operating time = n ( M T B F )
x,- i-15 x c i
-
n
and
are calculated.
Table 8.1 is used to determine the total equipment failure rate, AT,
and the MTBF from ~ / X T .
The specified preventive maintenance tasks that will be required to
be performed in operating time,
T = n .(MTBF)
TEST METHOD 7 181
2
qfc= (5). 2
variance = -
Consequently,
Rearranging yields
182 MAINTAINABILITY ENGINEERING SPECIFICATIONS
EXAMPLE 8-12
In a specific equipment with a designed-in M T B F of 200 hours, 30
corrective maintenance actions, sampled per Table 8.1, are simulated.
The corrective maintenance man-hours expended for each action are
recorded. The average man-hours per corrective maintenance task is
calculated to be
30
- c xci
X, = -
i=l
= 2.5 man-hours,
30
and the standard deviation of the man-hours expended for the correc-
tive maintenance tasks is calculated to be
h
d = 0.55 man-hours.
It is estimated that in a time period of
- -
T = n ( M T B F ) = 30 (200),
or
T = 6,000 hours,
the average total man-hours that will be required for all preventive
(scheduled) maintenance tasks would be
PS = 85 man-hours.
The producer’s risk is chosen to be CY = 5%.
Determine if this equipment has met its man-hour rate, M H R ,
requirement of M H R = 0.050 man-hours per operating hour.
SOLUTION TO EXAMPLE 8-12
The decision criterion for Test Method 7 is the following:
If
- PS 2
X , 5 M H R . ( M T B F ) - - n t &-$,
accept the equipment.
TEST METHOD 8 183
In this case
85 0.55
2.5 5 0.050(200) - -
30
+ 1.645-
rn’
2.5 5 10 - 2.833 + 0.1652,
or
2.5 _< 7.332.
Consequently, the equipment is accepted because it has met its M H R
requirement.
(2)the mean time to restore the equipment, 3, or the MTTR and the
maximum time to restore for a maintainability of 95% (tMmoz =
95%) are specified.
It may be seen that through this test a duality of requirements are
met simultaneously, as it is required that for an accept decision an
accept decision has to be reached on both 2 and tMm,,.
The method is based on a maximum possible consumer’s and pro-
ducer’s risk of 16%.
The test constraints are the following:
< 100 minutes.
*
I. 10 minutes 5 ?specified
2. 5 3.
It is asserted that most maintainability demonstrations comply with
these restrictions.
1. If the test plan is that of and tMmnz = 90%, then Table 8.4
(Plan A l ) is used in conjunction with Table 8.5 (Plan B1).
2. If the test plan is that of 7 and t ~ , . , , ~=
, 95%, then Table 8.4
(Plan A l ) is used in conjunction with Table 8.6 (Plan Bz).
184 MAINTAINABILITY ENGINEERING SPECIFICATIONS
Here
and
Nc = number of corrective maintenance tasks performed in the
test.
PLAN B1
Reject region
C-L
00
00
/
wept
I I II
0 5 20 40 60 80 100
Y 3 - 3
bo
(0
2 - 2
1 - 1
0
0 20 40 60 80 100
Number of maintenance tasks to be performed
Fig. 8.8- Plans B1 and Bz, Test Method 8.
190 MAINTAINABILITY ENGINEERING SPECIFICATIONS
PLAN B2
Here
Choose the sample tasks by preparing Table 8.1 and basing Column
12 on a total sample size of 100. Choose variable sampling in conjunc-
tion with a random number table uniformly distributed between 0 and
1, as per procedure of Column 13. Total up the maintenance tasks with
a duration exceeding the required values of 5 and tMm,, . Compare these
totals with those given in Tables 8.4, 8.5 and 8.6, as applicable t o the
two maintenance time requirements, for an accept or reject decision.
EXAMPLE 8-13
It is specified that the maintainability of the equipment be demon-
strated on the following dual requirement basis:
1. A mean time to restore o f ? = 30 minutes.
2. A time for a 95% maintainability or for a tMmos = 45 minutes.
Determine the following:
1. If 25 maintenance tasks were demonstrated, what is the maxi-
mum number of tasks that should exceed 30 minutes in duration
for an accept decision?
2. Same as Case 1, but for a reject decision.
TEST METHOD 9 191
- c 5 tci
(a) c = x c -
is1
nc 9
where
t& = corrective maintenance times,
and
n, = number of corrective maintenance tasks
demonst rated.
where
TEST METHOD 9 193
where
f, = number of expected corrective maintenance
tasks occurring during a representative
operating time T,
fp = number of expected preventive maintenance tasks
tasks occurring during the same
operating time T,
and
f, = ACTand f p = APT.
Also the following may be used:
where the t& and tpj are determined for the same represen-
tative time.
where
t; = log, t,.
h
Accept if 7; (specified) 2 tz p z .
Otherwise reject.
194 MAINTAINABILITY ENGINEERlNG SPECIFICATIONS
-
8.12.2.2 TEST FOR fp
h
Accept if f; (specified) 2 +z p g.
Otherwise reject.
Otherwise reject.
EXAMPLE 8-14
For a special, maintainabilitywise vital equipment the following are
specified:
-*
t , = 5.250 hr,
-*
t, = 1.500 hr,
p = 0.05 for lcand lp,
-1
tcIp = 3.000 hr,
and
tkmar, = 12.50 hr, for M,,,, = 95%.
In a series of maintainability demonstration tests the following are
determined:
nc = 46,Zc = 3.595 hr, and sc= 5.641 hr,
A
= 20 and
fp = 40,
and
t0.95 = 12.08 hr, for M,,,,,, = 95%.
Determine if the specified requirements have been met by these
maintainability demonstration results.
TEST METHOD 9 195
1. Test f o r t c .
.. 6
-
tc + zp- = 3.595 t 1.645-
5.641
= 4.963 hr.
6 a
Since
Sy = 5.250 hr > 4.963 hr,
we accept the equipment as having met the mean corrective main-
tenance time requirement.
2. Test f o r t p .
- 6- 0.375
t p + z P - p = 1.356 t 1.645 -= 1.436 hr.
A
6 m
Since
S i = 1.500 hr > 1.436 hr,
we accept the equipment as having met the mean preventive
maintenance time requirement.
3. Test for T c / p .
+
= 2.350 + 1.645
= 2.809 hr.
[ 46 x 60(20 + 40)2 I’
60(20 x 5.641)2 46(40 x 0.375)2 ‘ I 2
Since
tclp= 3.000 > 2.809,
1
Acceptance level
L2-l
Acceptance level
is less than or equal to that shown in Table 8.7 and/or Table 8.8,
corresponding t o each index for the specified confidence level.
EXAMPLE 8-15
The following are specified for a specific equipment:
1. Median value of the corrective maintenance times =
ic = 2.75 hours.
2. Median value of the preventive maintenance times =
ip= 1.35 hours.
3. 95th percentile of the corrective maintenance times =
tMmoSc = tQ,95= 3.45 hours.
t , = p,(actual) - k 9
C
i=l fpi
where
fpi -frequency of occurrence of the ith task in the
referenced period,
Ic = number of different preventive maintenance tasks
performed,
fpi = total number of preventive maintenance tasks
200 MAINTAINABILITY EN GINEElUNG SPECIFICATIONS
performed,
XPi = midpoint of the time intervals in which the
different maintenance tasks were performed,
p,(actual) = actual mean preventive maintenance time
-
calculated using this formula = t,.
Accept if T,(p,) required l-Zp(pp)actual.
Reject if Z,(pp) required < tp(p,) actual.
i=l
fpi = 28
k =6
C fpi
i=l
.X p i = 960
202 MAINTAINABILITY ENGINEERING SPECIFICATIONS
where
fpi = frequency of occurrence of the ith task in the
referenced period,
k = number of different preventive maintenance
tasks performed,
C j p i = total number of preventive maintenance tasks
performed,
Xpi = midpoint of the time interval in which the dif-
ferent maintenance tasks were performed,
pp(actual) = actual mean preventive maintenance time
calculated using this formula.
The 27th ranked value is 55 minutes and the 28th ranked value
is 57 minutes. Consequently, the duration of the 27.55th obser-
vation, or of the preventive maintenance task time, is
55 + (27.55 - 27.00)(57 - 55) = 56.10 min.
Since
tMrnlSZ, (required) = 58 min. > tMmo+p(actud)
= 56.10 min.
we accept the equipment.
204 MAINTAINABILITY ENGINEERING SPECIFICATIONS
PROBLEMS
where
Z = mean time to restore the equipment,
and
ut = standard deviation of the times to restore.
where
-
2 = mean time to restore the equipment,
and
at = standard deviation of the times to restore.
and
206 MAINTAINABILITY ENGINEERING SPECIFICATIONS
t' = log, t .
Determine the additional maintenance tasks that have to be
demonstrated.
3. If at the conclusion of the required maintenance tasks the
following updated results are obtained:
? = 2.9 log, minutes,
and
ott = 1.19 lo& minutes,
Determine if the equipment has met the desired mainte-
nance time requirement of 60 minutes.
4. Same as in Case 3 but for the maximum allowable mainte-
nance time of 75 minutes.
t' = log, t .
Determine the additional maintenance tasks that have to be
demonstrated.
3. At the conclusion of the required maintenance tasks the
following updated results are obtained:
5' = 3.1 lo& minutes,
and
at#= l.Olog,minutes.
Determine if the equipment has met the desired mainte-
nance time requirement of 50 minutes.
-
h
np = 55, 3, = 1.980 hr, and sp
= 0.275 hr,
tcIp = 1.050 hr, and cfGp= 4.005 hr, withf, = 19 and f p = 45,
and
t0.95 = 13 hr, for MmcrOc
= 95%.
Determine if the specified requirements have been met by these
maintainability demonstration results.
8-17. The following are specified for a specific equipment:
1. Median value of the corrective maintenance times =
ic = 4.25 hours.
2. Median value of the preventive maintenance times =
ip= 2.85 hours.
3. 95th percentile of the corrective maintenance time =
tMm,,, - tQ.95= 4.95 hours.
(8A.3)
(8A.4)
216 MAINTAINABILITY ENGINEERING SPECIFICATIONS
(8A.5)
(8A.9)
E ( X )= e p + 0 2 / 2 (8A.10)
and
2
ax = p(e' - I)'/,~, (8A. 11)
where p and Q denote the mean and standard deviation of log X .
For E ( X ) = PO, from Eq. (8A.11)
do = p0(eu2 - (8A.12)
and for E(X)= p l ,
d1 = p l ( e u 2 - l)'/*. (8A.13)
Substitution of Eqs. (8A.12) and (8A.13) into Eq. (8A.9) yields
(8A.14)
APPENDICES 217
Test Plan B
For Test Plan B
d l = do = d^ ( 8 A .15)
where $is the prior estimate of the standard deviation of the mainte-
nance time. Substitution of ;for do and d l in Eq. (8A.9) yields
(8A.16)
(8B.4)
(8B.5)
and
(8B.7)
(8B.8)
where p and o is the mean and standard deviation of log,X, respec-
tively, and zp is the (1 - p)th percentile of the normal distribution.
Then
log, x p =p + zp 0, (8B.9)
and the MLE of log, Xp is
A
l0geXp = Y
-
where
. n
APPENDICES 219
In Eq. (8A.11)
E(Y)= P9 (8B.12)
and if n is large
E(S)2 Q 11, pp. 137-1391, (8B.13)
and
Therefore
E(log, X,)
h
p + zpu. (8B.15)
(8B.16)
and
n-1
-n
2 1.0. (8B. 18)
(8B.19)
(8B.20)
220 MAINTAINABILITY ENGINEERING SPECIFICATIONS
(8B.21)
(8 B .22)
(8B.23)
(8B.24)
(8B.25)
and
(8B.26)
Equating the right hand side of Eqs. (8B.25) and (8B.26) yields
(8B.27)
(8B.28)
REFERENCE
1. Duncan, Acheson J . , Quality Control and Industrial Statisiics, Richard
D. Irwin, Inc.,'992 pp., 1974:
APPENDIX 8C - TEST METHOD 3
If X I , XJ,.. .,X , is a random sample indicating a series of main-
tenance actions,
0, if the maintenance action is completed before
the specified maintenance time, T*,
1 , otherwise,
APPENDICES 221
(
P ( x = Ic) = ;)p*(l -p y , (8C.3)
and
Var(X) = n p (1 - P). (8C.5)
The test hypothesis is
El0 : T = X p , ,
and
HI : T = Xp, > ( P I > PO).
It is equal to the hypothesis
Ho :p = PO = Mu,
and
H1: p = p l = ML.
Considering the second hy othesis, the test problem chan es to
K
finding the sample size n and t e acceptance value c which satis y the B
(8C.6)
and
(8C.7)
= 1-0, (SC.8)
222 MAINTAINABILITY ENGINEERTN G SPECIFICATION S
-
1
e'@ j 2 dt ,
6
= P, (8C.9)
that is
c-npo
dn Po (1- P o ) = zu, (8C.10)
and
(8C.11)
and (8C.11)
Rearranging Eqs. (8C.10) yield
c = n Pl - -Zm/n Pl (1 - P l ) . (8C.13)
from Eq. (8C.13)
Subtracting Eq. (8C.12) yields
(8C.15)
where Q;= 1-pi ( i = 0,l). Dividing both sides by ( p l -PO) and then
squaring both sides yields
= ( z a m + z p r n
(8C.16)
Pl -Po )2-
c = n [ zp P o r n t f a P l r n
am t z p m
(8C.17)
APPENDICES 223
(8C.18)
r=O
..
and
(8C.19)
Solving Eqs. (8C.18) and (8C.19) yields the sample size n and the
acceptance critical value c.
APPENDIX 8D - TEST METHOD 4
If the underlying distribution of the corrective maintenance task
time, X , is lognormal, and XI, X 2 , . +,
Xn, is a random sample from
X, then Y = lo X is normally distributed and = logX1,yz =
-
log X2, . .,ync =qog Xnc is a random sample from p.
Define
nc ;=I
1
loglo X;= -
nc ;=I
c
nc -
y; = Y , (8D.1)
and
(80.2)
Assume
1' = loglo x N N ( p , 2), (80.3)
then
-
- N - N(O,l), (80.4)
.I&
224 MAINTAINABILITY ENGINE ERTN G SPE CIFICATI0NS
(80.5)
and
-
Y-p ncS2
-
U l f i and -are independent.
U2
Consequently,
(80.6)
is Student’s t distributed.
(80.7)
therefore
loglo MTTRG - log10 ERT
T=
S
&= i - 1).
N t(nc (80.8)
A=
Uptime - T O T - Downtime =I-- DT
-
(8E.2)
TOT TOT TOT *
But since
DT = C M D T + N C M D T + DDT, (8E.3)
C M D T + N C M D T + DDT
A=l- (8E.4)
TOT
226 MAINTAINABILITY ENGINEERING SPECIFICATIONS
then
T O T (D U R )
NOF = (8E.9)
24(AFL) *
Substitution of Eq. (8E.9)into Eq. (8E.6) yields
(8E .12)
where
. n
n = sample size
and
X , = acceptance critical value.
Considering the alternative forms of Eqs. (8E.11) and (8E.12):
(8E.13)
and
( 8 E .14)
(8E. 15)
and
(8E.16)
(SE.19j
228 MAINTAINABILITY ENGINEERING SPECIFICATIONS
and
(8E.20)
Subtracting Eq. (8E.19)from Eq. (8E.20)yields
M i - MO = ( +
~ n ZP)-
U
fi'
(8E.21)
Then, the test sample size, from Eq. (8E.21),becomes
(8E .22)
T
t (PS)- ;=I
-
n (MTBF)
1
- MTBF [x+ 3.
(8F.2)
APPENDICES 229
(8F.3)
and
(8F.4)
Furthermore assume that ph is the required man-hour rate. The pro-
ducer's risk is a,and the acceptance critical value is ph, then
yields
(8F.6)
Since
(8F.7)
(8F.8)
230 MAINTAINABILITY ENGINEERING SPECIFICATIONS
(8F.10)
where pk = M H R.
APPENDIX 8G - TEST METHOD 8
Test Method 8 is a constant probability ratio sequential test, n
items are under test, and X is a random variable such that
X = 1,if the item failed t o pass the test,
and
X = 0,if the item passed the test.
Assume that
P(X = 1) = p , (8G.1 )
P(X = 0) = 1 - p , (8G.2)
then
n
N, =EX;
i=l
is the total number of items which failed to pass the test, where X;
has a value of either 0 or 1.
The test hypothesis is
Ho : P = Po,
HI : P = PI.
APPENDICES 23 1
(8G.8)
(8G.9)
(8G.10)
A = - 1, - P (8G.11)
(21
and
B=-. P (8G.12)
1-a
If cn+dl is a negative number, no acceptance value exists. ( c n + d l )
+
takes on the next smaller integer value and ( c n d2) takes on the next
larger integer.
232 MAINTAINABILITY ENGINEERING SPECIFICATIONS
1 - FOR PLAN A1
Producer’s risk: a = 0.06 at k 5 0.22. Consumer’s risk: ,f3 = 0.06
at k 2 0.39.
Here
Accept if
N,, 5 0.305 n - 3.35. (8G.13)
Reject if
N,, 2 0.305 n + 3.35. (,8G.14)
APPENDICES 233
Continue test if
0.305 n - 3.35 < n < 0.305 n + 3.35. (8G.15)
2 - FOR PLAN B1 AND PLAN B2
For Plan B1
0 = 0.10, Po = 0.02,
p = 0.10,PI = 0.10,
therefore
0.90
log, A = log, -
0.10
= 2-20?
0.10
log, B = log, - - -2.20,
0.90
1-0.02
loge 1-0.10 0.085
= log 0.10~1-0.02f= -1.69 = 0.050,
e 0.02 1-0.10
-2.20
d 1 ---- - -1.30,
1.69
and
2.20
d2 = - = 1.30.
1.69
The acce t a me test criteria are the following:
Accept i P
N,, 5 0.050n - 1.30. (8G.16)
Reject if
+
N , 2 0.050n 1.30. (8G.17)
Continue test if
0.050n - 1.30 < n < 0.050n + 1.30. (8G.18)
For Plan B 2
cr = O . l O , P O = 0.01,
p = 0.10, Pi = 0.05,
therefore
log,A = 2.20,
loge B = -2.20,
1-0.01
loge 1-0.05 0.041
= log 0.05[1-0.01] - 1.651 - 0.025,
e 0.01 1-0.05
-2.20
dl = -= -1.33,
1.651
234 MAINTAINABILITY ENGINEERING SPECIFICATIONS
and
2.20
&=--1.651 - 1'33'
The acceptance test criteria are the following:
Accept if
Nn 5 0.025n - 1.33. (8G.19)
Reject if
Nn 2 0.025n -I-1.33. (8G.20)
Continue test if
0.025n - 1.33 < n < 0.025n 4-1.33. (8G.21)
(8H.1)
If n is large
-
- N (8H.2)
P(X s Xalp = ~ s =
) P, (8H .3)
APPENDICES 235
where
Xa = acceptance critical value.
Subtracting pa from both sides of the inequality in Eq. (8G.10) and
dividing both sides by d l f i yields
(8H.4)
(8H.5)
-
where zp is the corresponding value for 1 a = P found in Table 6.4.
Consequently, the critical value, X,, is
Xa = ps - 20 dlfi, (8H.6)
(8H.7)
Xa = ps - ZP Z/fi. (8H.8)
Then, the accept and reject criteria become the following:
Accept if
pc(specified) 2 X c + -
*'
'ZP dc
(SH.ll)
236 MAINTAINABILITY ENGINEENNG SPECIFICATIONS
Reject if
(8H.
13)
(8H.14)
(8H.15)
where fc and fpm are the number of corrective and preventive mainte-
nance actions, respectively. Then
-
xp/c =
f c x c t fpmxpm
(8H.16)
fc + fpm 9
and
(8H.17)
(8H.18)
Accept if
(8H.20)
Reject if
(8H.22)
(8H.24)
U
Since
then
loge tMmaz - CL - 2,. ( 8 H- 2 6 )
U
or
tMmar = antilog, ( p + k,Q) = u). (88.28)
Equation (811.28) says that if X, has a distribution as defihed by
Eq. (8H.22), then its ( 1 - a ) t h percentile is equal to antilog ( p + 2,~).
Estimating p and u by
(8H.29)
and
(8H.30)
( 8H.31)
The test hypothesis is
tMmal 5 (specified) 9
and the acceptance criteria are the following:
Accept if
(specified) 2
tLrnas
( 8H.32)
APPENDICES 239
(8H.33)
1, if t; > t,,
xj = 0 , if tj < t,,
i = 172,...,n. (81.1)
If the hypothesis
Ho : t , = t , , (81.2)
is true, where t, is the percentile value of the maintenance distribution,
then P(X; = 1) = 0.50 for the test for the median if the t, stands for
the 50th percentile, or P(X; = 1) = 0.05 for the test for the 95th
percentile if the t, stands for the 95th percentile.
So, the test for the median and the 95th percentile is changed to
test the hypothesis
Ho : P = Po, (81.3)
where the value of Po is e ual to 0.50 for the test for the median, or is
7
equal to 0.05 for the test or the 95th percentile.
If hypothesis (81.3) is true considering
n
Y = Cxj7 (a1.4)
i=l
240 MAINTAINABILITY ENGINEEHNG SPECIFICATIONS
r
P E X i 5 C1IP = PO) = 0.25,
i=l
and for the 90% confidence level
(81.5)
/ n \
(81.6)
(81.7)
(81.14)
'SO
..
(81.15)
I .
r=O
Confidence level
Acceptance level
tzrd
Chapter 9
PREVENTIVE MAINTENANCE
AND ITS QUANTIFIED
ADVANTAGES
243
244 P R E V E N T N E MAINTENANCE
0 TP TP
t' q- TP -p- 7
2.
Or
I
0
Y
t,+TP
TP
t,+2 T, - Age of
equipment
I Failures reduced
0
I tl Age. T. hr
NF(t1) = N A, =
i’ 0
N(t) h(t) dt.
246 PREVENTIVE MAINTENANCE
-
Fig. 9.2 Effect of poor preventive maintenance on the r e
liability bathtub curve of equipment.
AGE REPLACEMENT POLICY 247
MT, = I* RTp(t)dt,
01
or
J”
al
MT,= x [ R ( T p ) ] J R ( T )d r . (9.3)
j=O 0
Recalling that
- -1 - Ed for z < 1,
1- j=o
if we take
then,
or
-
The equations for &,(t) and MT, apply for any component, or
equipment, as long as the R(Tp)and consequently R(r) can be formu-
lated. It applies for example to equipment with parallel or standby
redundancy when preventive maintenance may be exercised every Tp
hours without aborting the mission.
EXAMPLE 9-1
Consider an equipment consisting of two parallel, constant-failure-
rate units. Find (1) its RT, and ( 2 ) its MT,.
AGE REPLACEMENT POLICY 249
%,=lo hr(t) = [2 e-
(0.01)( 10) - e- (0.02)( lo)] j
50 hr
or
For
Tp --t 00 ; MT, = 150 hr = 1.5 m,
Tp = 150 ; MT, = 179 hr,
Tp = 10 ; MT, = 1,097 hr,
and for
Tp = 0 ; MT, = 00.
These MT, values for various Tpperiods have been plotted in Fig.
9.4.
252 PREVENTIVE MAINTENANCE
u)
1100 --
a
2 1000--
900 --
I 800.-
s
r(
* 400-
300--
150 hours
200 --
+--- -- - ---- .--- --.- - ------
100 --
I
%p+ m
1
0 so 100 1so 200
~ ( t=)e-’ (9.12)
with no maintenance, and with preventive maintenance every Tp hours
RT,(t) = [R(Tp)]j R(T), (9.13)
where
t=jTp+r.
Then, from Eq. (9.12)
R T , ( ~=) (e-’ T p ) j e-’ ‘9
(9.13‘)
254 PREVENTIVE MAINTENANCE
therefore,
RTp(t)= e-’ = R(t)! (9.14)
In other words the reliability of the unit with preventive mainte-
nance every Tphours is not any different than that with no preventive
maintenance, if the unit has a constant failure rate!
If the single unit has an increasing failure rate there will be an
-
improvement in its reliability with preventive maintenance, because
then,
RTp(t)= [R(TP)li R(r) > \
R(j T p + r ) . (9.15)
7 d
For a Weibullian unit, with p > 1, for example, its reliability for a
mission of t duration with preventive maintenance every Tp hours is
given by
(9.16)
(9.18)
SINGLE EXPONENTIAL UNIT CASE 255
- 1
(9.19)
(9.20)
(9.21)
It is this A, that should be used in the MTTR expression for equip-
ment subjected t o both corrective and preventive maintenance. A good
estimate of the reliability of a unit or equipment undergoing such pre-
ventive maintenance ispbtained by using Eq. (9.20) to calculate its
corrective failure rate, AT,, and then Eq. (9.21) t o calculate its relia-
bility, R*,(t), for a mission of t duration.
EXAMPLE 0-2
A bearing is operating in an equipment. It has a Weibull times-to-
failure distribution with the following parameters:
/3 = 2.0, q = 2,000 hr, and 7 = 0 hr.
1. Find the reliability of this bearing with no preventive mainte-
nance for 10, 100, 500, or 1,000 hr of operation.
2. Find the reliability of this bearing with preventive maintenance,
assuming that the bearing is replaced preventively every 10, 100,
or 500 hr.
3. Find the mean life of this bearing with no preventive mainte-
nance.
256 PRE V E N T W E MAINTENANCE
with PO /
Age, T, hr
R(T)= e - ( h ) ’ * O .
For T = 10 hr
10
R(T = 10 hr) = e-(-)’” = 0.999975,
for T = 100 hr
q . 0
R(T = 100 hr) = e-(llooo = 0.997503,
for T = 500 hr
500 2.0
R(T = 500 hr) = e - ( m ) = 0.939413,
and for T = 1,000 hr
1000 2.0
R(T = 1,000 hr) = e-(*) = 0.7788007.
2. The reliability of this bearing, with preventive maintenance is
&,(t) = [R(Tp)lJR W ,
where
t=jTP+r,
e
258 PREVENTIVE MAINTENANCE
For Tp = 10 hr
These R ~ , = l o ( t values
) are given in Table 9.1 for 0 < T 5 10 and
j = 0,1,2 and 3, and are plotted in Fig. 9.6.
For Tp = 100 hr
These R~,=5w(t) values are given in Table 9.3 for 0 < T 5 500
and j = 0, 1,2, and 3, and are plotted in Fig. 9.8.
These RT ( t ) values for Tp = 10,100 and 500 hr are shown plot-
ted togetger in Fig. 9.9. A study of Tables 9.1, 9.2 and 9.3, and
of Figs. 9.6 through 9.9 indicates the substantial improvement in
the mission reliability of these bearings with preventive mainte-
nance, or replacement, every Tp= 10,100 or 500 hr. The smaller
the Tp the greater the reliability improvement.
Table 9.4 gives the reliability of these bearings with no preven-
tive replacement in Column 4, with preventive replacement every
Tp = 100 hr in Column 5 , and using the approximate Eq. (9.21)
in Column 6. A comparison of the results in Columns 4 and 5
brings out the great improvement of bearing reliability with pre-
ventive replacement. A comparison of the results in Columns 5
and 6 brings out the fact that after about the third preventive re-
placement of these bearings their reliability is well approximated
by Eq. (9.21) with at least a three-decimal-place accuracy. Fig-
ure 9.10 illustrates the difference in the bearing’s reliability as
calculated from Eqs. (9.21) and (9.16). It may be seen that
the two equations give essentially the same reliability value, with
five-decimal-place accuracy, at mission times that are a multiple
of T p ,The values deviate from each other at other mission times
with a maximum deviation of 0.000616 for t 2 3 Tp.
SINGLE EXPONENTIAL UNIT CASE 259
RT+ .oo(t)
f j=O j=l j=2 j=3
0 1.00000000 0.99750312 0.99501236 0.99252796
15 0.99994378 0.99744692 0.99495653 ' 0.99247225
30 0.99977502 0.99727859 0.99478855 1 0.99230476
45 0.99949388 0.99699814 0.99450880 0.99202571
60 0.99910040 0.99660565 0.99411729 0.99163518
75 0.99859474 0.99610125 0.99361415 0.99113323
90 0.99797705 0.99548510 0.99299954 0.99052021
100 0.99750312 0.99501236 0.99252796 0.99004983
260 PREVENTIVE MAINTENANCE
I
I I I
0 10 20 50 10
Fig. 9.6 - Reliability versus mission time plot for the bear-
ing in Example 9-2 maintained preventively ev-
ery Tp = 10 hr.
SINGLE EXPONENTIAL UNIT CASE 26 1
1.000
0.999
0.998
0.997
0.996
0.995
0.994
0.993
0.992
0.991
0.990
I ! I I
Fig. 9.7 - Reliability versus mission time plot for the bear-
ing in Example 9-2 maintained preventively ev-
ery Tp = 100 hr.
262 PREVENTIVE MAINTENANCE
Fig. 9.8 - Reliability versus mission time plot for the bear-
ing in Example 9-2 maintained preventively ev-
ery'T, = 500 hr.
1.00 ~
/
1
-
-
,I 0 hours
0.98 -
It.% -
-
a4
h
0.94-
#i*
; 0.92
., 0.88
c 1 I I I I 1 1 m I
Ma
-
0 100 200 300 400 So0 600 700 mlpoo
Mlsslon t i n . t J 1
, i. hours
Fig. 9.9 - Reliabilityversus mission time plot for the bearing in Example 9-2 maintained
''2 = 10, 100, 500 or 00 (nonmaintained) hr.
preventively every
264 PRE V E N T N E MAINTENANCE
1.000
0.999
0.998
0.997
'\
0.9%
0.995
0.994
0.993
R(t)
0.992
0.991
0.990
0.989
0.988
0.987
0 1
Fig. 9.10 - Reliability versus mission time plot for the bear-
ing in Example 9-2 maintained preventively ev-
ery Tp = 100 hr.
SINGLE EXPONENTIAL UNIT CASE 265
~~~ ~
1 2 3 4 5 6
Mission
duration
t = T,
hr
j 7,
hr
& ( T ) = e-(:Ib nT,,(t)= [ R ( T , ) ~ ~ I Z ~( . (~ t)2) e -*
0 0 0 1.oooooo 1.000000 1.000000
50 0 50 0.999375 0.999375 0.998751
Kl
100 0+1 100 0.997503 0.997503 0.997504
a,
a, 150 1 50 0.994391 0.996880 0.996259
200 1-2 I00 0.990050 0.995012 0.995015
250 2 50 0.984496 0.994390 0.993772
300 2-3 100 0.977751 0.992528 0.992531
350 3 50 0.969839 0.991908 0.991292
400 3-4 100 0.960789 0.990050 0.990054
450 4 50 0.950G35 0.989431 0.988818
500 4-5 100 O.!J394 13 0.987567 0.987584
700 6-7 100 0.884700 0.982652 0.982560
1,000- 9+io ioo 0.778801 0.975309 0.975320
SINGLE EXPONENTIAL UNIT CASE 267
For Tp= 10 hr it is
- 99.91672914
M T ~ = l Ohr
O - 1- 0.99750312'
or
MTp=iwhr = 40,017hr.
Finally, for Tp = 500 hr
- 489.775803
MT~=500hr - 1 - 0.93941306'
or
M ~ p hr==~8,084
~ hr.
These and additional values are shown plotted in Fig. 9.11, to-
gether with the mean bearing life with no preventive mainte-
nance. It may be seen that the mean life of the bearing increases
substantially with preventive maintenance, as Tp decreases, over
that with no preventive maintenance when Tp = 00. Hence, the
great benefits that result through preventive maintenance at reg-
ular prechosen periods of operation of units which have an in-
creasing failure rate characteristic with increasing operating time,
like that exhibited by this bearing with p = 2.0 > 1.
268 PREVENTIVE MAIlVTENANCE
160,000-
150,000-
140, O O P
130,000- %P'
hours
120,000-
399.998
25 160,004
n 110,000-
50 80.008
8
.
.a
100,000-
100
300
40,017
13,383
8 500 8,084
u; 90,000
-
L
80,000
[
1 - 11,000 4,171
1,773 1
P
8 60,000
4
CI
; 50,000
Maan time between failures when the
bearing i s subjected t o preventive
40,000 naintmance every Tp hours.
10,000
I I I 1 I I I I I I I
0 100 200 300 400 SO0 600 700 800 900 1000
1” R(r) d r
gives the mean time between both preventive replacements and correc-
tive failures. The total replacement rate, AT, is therefore given by
1
AT = = A, -I-A,. (9.22)
J? R(r) dr
Also
since
(9.23)
consequently, since
(9.24)
then,
(9.25)
where
and
EXAMPLE 0-3
Given is the system of Fig. 9.12 which is subjected to preventive
maintenance every 1,000 hr according to Policy I. Its various failure
rates are given thereupon.
R(t) =
or
R(t) =
2. The mean time between failures can be obtained from Eq. (9.5),
or,
272 PREVENTIVE MAINTENANCE
-
-24.9975 e-o*oo201 ’ (1 e o * m ) dr,
= 967.46 - 584.80 e-0-00171 Tp
t 12,436.57e-0*00201 TP
J,” R ( r )d r = 1 1,cJocJ
R ( r ) dr = 704.20445,
From Case 2,
R(Tp) = R(1,OOO)= 1 - [I - R(l,OOO)]
= 1 - 0.6120199 = 0.3879801,
and
1,000
R ( r ) dr = 704.20445,
CORRECTIVE AND PREVENTIVE REPLACEMENT RATE 273
therefore,
= 0.000551 rpfhr,
” = 0‘3879801
704.20445
or
A, = 551 */lo6 hr.
A, = 0*6120199= 0.000869fr/hr,
704.20445
or
A, = 869 fr/106 hr.
NSP = N S P - c t NSP-P,
where
or
(9.29)
j=O J‘
(9.30)
where
(9.31)
If the reliability goal is not met, then Tpshould be adjusted to the left,
or to a lower value, to obtain a A, which satisfies the requirement of
Eq. (9.32). This is usually possible without altering the CG-zvery
significantly, because the CT-Iversus Tp curve usually has a shallow
bottom in the minimum cost region, whereby a change in Tp does not
change the CT-Ivalue significantly, as may be seen in Fig. 9-13in the
region of Ti.
0 TP
where the X'S are failures.
This policy is used when maintenance schedules are based on equip-
ment operating time rather than unit, component or part operating
0 Tr’ Tr, hours
A, =
1
- -1 -- Tp- J2[1- Q ( T ) ]dr (9.35)
J? R ( r )dr TP TpJ? R(7) dr
Simplifying Eq. (9.35)yields
(9.36)
- -
S?'Q(r) dr
TpJ? R ( r )d r
A, lower bound
for Policy I1
5 XCZI <
A,
Q(Tp)
J? R ( r ) dr
for Policy
I and upper
(9.37)
(9.38)
and
d 3 =
~ 0.33 hr,
and if the mean preventive replacement times, pip, of the units
are as follows:
Flp = 0.25 hr,
tT*p= 0.35 hr,
and
-
t*3p = 0.15 hr ?
1. The stabilized average corrective failure rate of each unit €or Pol-
icy I1 is given by Eq. (9.35), or
1 1
J,"' R(t) d t = / 0
150
[0.25e-O.OOo3 ' + 0.75 e-(A)2's]d t ,
Tpl 0.25
R ( t ) dt = -(1 - 0.9559975) + 0.75 (142.799),
A50
0.0003
where
1 150
e-(A)2's
dt = 142.799,
LTP'
=IS0
and
0.25
R ( t ) dt = -(1 - 0.9559975)+ 0.75 (142.799)= 143.768,
0.0003
/," R(t)dt = / 0
440
[0.25 e-O*OOo6 * + 0.75 e - ( h ) 3 ' 5 ] dt,
Tm =440
R ( t ) dt = -0.25
0.0006
(1- 0.76797) t 0.75 (387.25),
where
e-(&)3'5 dt = 387.25,
using Simpson's Rule with 16 intervals. Then,
Tm =440
R(t)d t = -0 25
0.0006
(1-0.76797)+0.75(387.25) = 387.115,
and
1
A,, = -- - = 0.000310 fr/hr.
387.115 440
For Unit No. 3
LTp3=3w
where
0.25
R(t) d t = -(1- 0.873716)
0.00045
+ 0.75 (286.1135),
1 300
e - ( h ) 4 * 5 d t= 286.1135,
using Simpson's Rule with 16 intervals. Then,
R(t) dt = - 0.25
0.00045
(1 - 0.873716) + 0.75 (286.1135) = 284.743.
and
A,, = - 1
284.743
--
300
= 0.000179 fr/hr.
BLOCK REPLACEMENT POLICY 281
xpi = -.1
iP'
For Unit No. 1,
1 1
XPI = TpI - - = 0.006667 preventive replacements/hr,
150
for Unit No. 2,
1 1
=-
A,, =- = 0.002273preventive replacements/hr,
Tpz 440
and for Unit No. 3,
Xp, = - 1 =- 1
= 0.003333 preventive replacements/hr.
Tp3 300
3. The subsystem's stabilized M T T R for Policy I1 is given by
N
C (A,, & t X p i F ~ P )
MTTR = '=' N 9
C ('ci + 'Pi)
i=l
where, from previous results,
N=3
C
i=l
q'( &R + Xpi T i p ) +
= [(0.000289) (0.55) (0.006667) (0.25)
I
t (0.000310) (0.75)+ (0.002273)(0.35)
[ I
+ [(0.000179)(0.33)+ (0.003333)(0.15) ,
= 0.003413,
I
and
N=3
(Aci+ xpi) = (0.000289)+ (0.006667)+ (0.000310)
i=l
+ (0.002273)+ (0.000179)+ (0.003333)
= 0.013051.
282 PREVENTIVE MAINTENANCE
Therefore,
0.003413
MTTR = = 0.261513 hr.
0.013051
4. The stabilized M T B F of the subsystem with corrective and pre-
ventive maintenance for Policy I1 is given by
1
MTBF = N - ’
C ’ci
i=l
1
I
MTBF =
(0.000289) + (0.000310) + (0.000179)’
or
M T B F = 1,285.35 hr.
Then,
R(t = 10 hr) = 0.992250, or 99.2250%.
or
R(t = 10 hr) = 0.996484, or 99.6484%.
BLOCK REPLACEMENT POLICY 283
-
- R(500 t 10)
R(500) '
or
R(510 hr)
R(T, 2) =
R( 500 hr) '
Using Eq. (9.39),
R(T + t = 510 hr) = 0.024194,
and
R ( T = 500 hr) = 0.027045.
Therefore,
0.024 194
R ( T = 500 hr,t = 10 hr) =
0.027045'
where
CD
mh = Rh(t) d t ,
or the regular MTBF of parts h,
or
or
k
(9.41)
using Policy 11. A similar equation can be written for Policy I also. The
optimum TPl and TP2 can be obtained now by piecewise optimization,
or by plotting the terms C and C separately, versus CT-ZZfor various
i j
values of Tpand separately finding TP; and TP2,as shown in Fig. 9.15.
Usually, further savings would be obtained by making Tp2 an integer
multiple of Tpl. Tpl may then become a minor overhaul and Tp2 a
major overhaul, preventively. Again, it should be checked to see that
the equipment’s reliability goal is being met with these TPl and T;2
preventive maintenance schedules.
If all components in the equipment are reliabilitywise in series, then
N
REQ(T,2) = n R i ( T i ,t ) ,
i=l
but the ages of all components in the equipment at the beginning of
every mission need to be known to be able t o evaluate the equipment’s
REPLACING GROUPS OF PARTS 287
Components of Croup 2
L
I
0 T* 'T
Pi P2
T = 2T
P2 PI
Preventive maintenance schedule, Tp, hr
7-77
1
Corrective
maintenance
cost,
c, - $
75.00
Preventive
maintenance
cost,
cp- $
10.00
2 145.00 35.00
3 80.00 12.00
where
and
For Unit 1
1
CT-II = (10.00) -
TPl
For Unit 2
For Unit 3
+ + (0.75) e-(&)4'5
[(0.25) e-(0*00045)T
3 dT
The costs associated with the various preventive replacement pe-
riods, Tpi, are shown in Table 9.6 and are plotted in Fig. 9.lG
from which it is found that Til = 132 hr, Ti2 = 285 hr and
Ti3 = 213 hr.
2. To achieve further savings, T;2 and /or T;3 can be made an in-
teger multiple of Til. Since
-Tp;
= - - 28.5 hr - 2.1591,
Tpl 132 hr
and
-Ti3
= - - 213 hr - l.Gl3G.
TP; 132 hr
P r e v e n t i v e maintenance s c h e d u l e . T lir
D'
Fig. 9.16 - The total cost of corrective plus preventive maintenance as a function of preventive
maintenance schedule, Tp,for each unit in Example 9-5.
REPLACING GROUPS OF PARTS 291
are close to two, further savings are possible if we take Ti2 and
T;3 to be
and
TP3 = 2 TP;.
Making TP; and T& integer multiples of TP; will minimize the
number of times the equipment must be down for preventive
maintenance.
3. To check to see whether or not the reliability goal of the sub-
system is being met with these minimum-cost preventive main-
tenance schedules, calculate the equipment’s reliability from
(9.42)
EXAMPLE 9-6
Work out Example 7-2 again, as follows:
4. Repeat Case 2 for the case when the T' and Tp'3are made integer
p2.
multiples of TP;.Make sure that the rehability goal of R = 0.980
is still met when the adjustments in the TG are made.
5 . Determine the total downtime, plus the corrective, plus the pre-
ventive maintenance costs for Policy Il for 3,000cumulative hours
of operation, using the downtimes given in Table 9.7 for each unit
with an overall cost of downtime of $10,000 per hour of subsystem
downtime, and the minimum cost TG.
6. Repeat Case 5 using the adjusted T; found in Case 4, the correc-
tive and preventive downtimes given in Table 9.7, the preventive
downtimes and costs given in Table 9.8, with the same overall
downtime cost of 510,000 per hour of subsystem downtime, for
3,000 cumulative hours of operation.
7. Discuss comparatively the results found in Cases 5 and 6.
SOLUTIONS TO E X A M P L E 9-6
1. Using the data of Example 7-2 the reliability model for each unit
is
R l ( T ) = 0.25 e-(O.OOo3) + 0.75 e-(soo
2 ) l . S
,
& ( T ) = 0.25 ,-(O.ooos) * + 0.75 e-(&)'",
(9.44)
294 PREVENTIVE MAINTENANCE
1
When Units 2 and 3
are maintained
preventively
simultaneously. 0.35 41.50
When Units 1, 2,
and 3 are maintained
preventively
simultaneously. 1 0.50 51.50
REPLACING GROUPS OF PARTS 295
and
Rs(TpX33) = 0.933958,
where
Tpl = 132 hr,
TP; = 285 hr,
and
T;3 = 213 hr.
Then, from Eq. (9.45)
1 - 0.899067 1 - 0.863154 1 - 0.933958
XEQ =
128.3045
+
’272.8430
+
= (7.86671 5.01556 3.16203)
208.8540 ’
+
(9.46)
or
XEQ = 0.00160443 fr/hr.
The subsystem’s reliability for 8 hr of continuous operation, using
the minimum cost preventive maintenance schedules, is
Rss = e-’EQ t,
or
R s s ( t = 8 hr) = 0.9872466.
296 P R E V E N T N E MAINTENANCE
Since,
Rss(t = 8 hr) > &GOAL,
that is
0.9872466 > 0.980,
then the subsystem is meeting its reliability god using the up-
per bound of the corrective failure rate and the minimum cost
preventive maintenance schedules.
2. The expected number of corrective maintenance actions for 3,000
hr of cumulative operation for Policy I1 using the upper bound
of the corrective failure rate is given by
Nc;= A& t.
Therefore,
and
and
N d = (0.000316203)(3,000)= 0.9486.
3. The expected number of preventive maintenance actions that will
be required for each unit for Policy I1 for 3,000 cumulative hours
of operation, using the optimum TPi,is
t
Npi = Xpi t=-
Ti:.
Npl = 132- 22.7273,
37000
3,000
Np2-
- 285 -
- 10.5263,
REPLACING GROUPS OF PARTS 297
and
3,000
4 3 = 213 = 14,0845.
T;2/T’l,
4. The ratio of and T$/TP; is found t o be approximately 2
from Example 9-5. Since Til = 132 hr, let 2’; = T;3 = 2 TP;=
2 (132) = 264, therefore the Ad may be calculated from
c3
i=l
Nd t; = 2.73979 hr.
c3
i=l
Np; t i = 11.47871 hr.
6. Solution 1 - Method 1
The preventive maintenance schedules for Units 2 and 3, Tp*2and
TP’, can be taken as multiples of TPl. Consequently, take
T;2 = Ti3 = 2 T’; = 2 (132) = 264.
The total corrective, preventive, and downtime costs for Policy
I1 for 3,000 cumulative hours of operation can be found by using
r 3 1
CT =
where
CT = cost of corrective t cost of preventive actions
on Unit 1 when maintained alone t cost of pre-
ventive actions on Units 1 , 2 and 3 when main-
tained simultaneously,
N1 = number of preventive maintenance actions on
Unit 1 alone during the operating time of 3,000
hr ,
N1,2,3 = number of preventive maintenance actions on
Units 1, 2 and 3 simultaneously during the op-
erating time of 3,000 hr.,
A,; = rate of corrective actions for Unit i,
t d & = downtime for corrective actions for Unit i,
c d = downtime cost, $/hr,
Cc; = corrective maintenance cost for Unit i,
C1, = preventive maintenance cost for Unit 1 alone,
Cp1,2,3= cost per preventive maintenance action for
Units 1, 2 and 3 simultaneously, $/hr,
t d l = downtime when only Unit 1 is preventively
maintained,
and
unit 3 0 0 0 0 0 0 0 0 0 0 0 0
1 i ~ i i l 1m 1 t t ~ 1 1 1 m . 1 r n m ~ l
Fig. 8.17 - Preventive maintenance times for Units 1,2 and 3. Unit 1 gets replaced 11 times,
and Units 1,2 and 3 together also 11 times.
REPLACING GROUPS OF PARTS 301
{ +
CT = 0.000786671 [(0.55) (10,000) 75.001
+ 0.000411743 [(0.75)(10,000)+ 145.001
+ 0.00053542 [(0.33) (10,000)+ 80.00)
+
{ 11 ([lo 4-(0.25)(10,OOO)]
1
+
or
{ 11 [51.50i- (0.50) (10,000)]
CT = $111,206.06.
Solution 1 - Method 2
Another way of calculating the total corrective and preventive
maintenance, and the downtime cost would be as follows: The
expected number of preventive maintenance actions for each unit
are:
3 000
For Unit 1, Npl = 132 = 22.7273 actions.
3000 -
For Unit 2, Np2 = 264 - 11.3636 actions.
3000
For Unit 3, Np3 = 264 = 11.3636 actions.
The preventive actions taken for the whole system will be 11.3636
actions for Unit 1 only, and 11.3636 actions for Units 1, 2 and
3 together. The preventive maintenance can be determined in a.
tabular form as given in Table 9.9.
Total preventive maintenance cost = $698.87 + $85,227
= $85,925.87.
The total corrective maintenance cost for the system is given by
cc =
l3
i=l
Xci ( t d c i
or
1
4-0.00053542 I(0.33) (10,000) t 80.001 (3,000),
C, = $28,029.56.
Then,
Total cost = Total preventive maintenance cost +
Total corrective maintenance cost,
or
Total cost = $85,925.87 t $28,029.56 = $113,955.43.
Solution 2 - Method 1
Other combinations of TP;, TP2 and Tp2 can be used t o calculate
the total cost for preventive and corrective maintenance actions;
e4.9
TPl = 132 hr, TP; = 3 TP;= 3 (132) = 396 hr,
and
T& = 2 TPl = 2 (132) = 264 hr.
The mean corrective maintenance rate for each unit can be cal-
culated using
or
AEQ = 0.0024166875.
Then
Rss(T = 8 hr) = e-’EQ @),
Rss(T = 8 hr) = e-0.0024166875 (8)
9
or
Rss(T = 8 hr) = 0.98085219 > 0.980.
The total cost can be calculated using the equation
CT = [k
i=l
Xci (tdci cd + cci)
1 ++ t N 1 (cp1 + cd)
id1
{
CT = 0.0007866710 [(0.55) (10,000) + 75)
+ 0.0010945965 [(0.75) (10,000) t 1451
+ 0.00053542 [(0.33) (10,000) + 801 (3,000)
+ 7 [ l o t (0.25) (10,000)]
1
+ 8 [16.50 t (0.30) (10,000)]
+ 4 [40 t (0.40) (10,000)]
+ 3 [51.50 + (0.50) (10, OOO)],
or
CT = $116,707.30.
Solution 2 - Method 2
Another way of calculating the total maintenance and downtime
cost would be as follows: The expected number of preventive
maintenance actions taken for each unit:
hit 2 4- + + + + + + +
w
0 0 0 0 0 0 0 0 0 0 0 0 0
cn Unit 3
I ” I ” I ” l ” I ‘ ” ’ ~ ’ ’ ~ ’ ~
0 132 264 396 792 1.188 1,584 1,980 2,376 2,772 3,168
Preventive maintenance times, hours I
3 , m
Fig. 9.18 - Preventive maintenance times for Units 1, 2 and 3. Unit 1 gets replaced 7 times,
Units 1 and 2,4 times, Units 1 and 3, 8 times and Units 1, 2 and 3, 3 times for
Example 9-6, Case 6 and Solution 2, Method 1.
306 PREVENTIVE MAINTENANCE
Np3 =
3000 = 11.3636.
264
Unit 3
The preventive actions taken for the whole system will be 3.7879
actions for Units 1, 2, and 3 together, 3.7879 actions for Units
1 and 2 together, 7.5758 actions for Units 1 and 3 together, and
7.5758 actions for Unit 1 only. The preventive maintenance cost
can be determined in tabular form as given in Table 9.10.
From Table 9.10 the total preventive maintenance cost = $547.36$
$75,759= $76,306.36. The total corrective maintenance cost for
the system can be found by
C, = { +
0.00078667l [(0.55) (10,000) 751
+ 0.00010945965 [(0.75) (10,000)+ 1451
+ 0.00053542 [(0.33) (10,000)+ 80)
or
C, = $43,690.80.
Then
Total cost = Total preventive maintenance cost +
total corrective maintenance cost,
or
Total cost = $76,306.36 + $43,690.80 = $119,997.16.
The comparison of the maintenance costs for the two different
preventive maintenance schedules is given in Table 9.11. The
comparison shows that Solution 2 schedules have lower preventive
maintenance but higher corrective maintenance costs than for
Solution 1 schedules. The overall cost for Solution 2 schedules is
about 5% higher. Other combinations can be tried in a similar
way to find the one with the least cost.
TABLE 9.10 - Cost of preventive maintenance for the system for 3,000 operating hours
for Case 6, Solution 2, Method 2.
1 2 3 4 5 6 7
Units involved in Expected Cost per I
Preventive Downtime per Expected Preventive
the maintenance number of action, maintenance cost, action, downtime, downtime cost,
0
0
action actions $ t hr hr $
4
1,233 3.7879 51.50 I 195.08 I 0.50 1.8940 18,940
1,2 3.7879 40.00 151.52 I 0.40 1.5152 15,152
1, 3 7.5758 16.50 125.00 0.30 2.2727 22,727
I
1 7.5758 10.00 75.76 0.25 1.8940 18,940
I 1 I
75,759
308 PREVENTIVE MAINTENANCE
Solution 1 Solution 2
shedules: shedules:
T’i = 132 hr, Tp’r= 132 hr,
T2 = Tp3 = 264 hr. Tp’2= 396 hr,
T& = 264 hr.
maintenance cost
for 3,000 hr,
Method 2 S 85,925.87 S 76,306.36
Total corrective
maintenance cost
for 3,000 hr,
Method 2 S 28,029.56 S 43,690.80
Total cost for
3,000 hr,
Method 2 S 113,995.43 S 119,997.16
Total cost for
Method 1 $ 111,206.06 $ 116,707.30
Reliability 98.62% 98.09%
REPLACING GROUPS OF PARTS 309
7. Tlie total cost in Case 5 is higher than the one in Case 6, com-
paratively, as follows:
In Case 5 it is $ 143,320.93.
SE
sw
h,,, = 30 fr/106hr
1 hWQ = 50 fr/106hr
? h,, = 200 fr/ 1o6cycles
SE
sw
Lo=
10 fr/106hr
1 LwQ = SO fr/106hr
kWE= 1 0 0 fr/ 1 o6cycles
L
SE
*
sw
Lo= 10 fr/106hr
1 LswQ= 50 fr/106hr
A, = 100 fi/106 cycles
9-5. Solve the bearing problem of Example 9-2 when the parameters
of these bearings’ probability density function are the following:
7 = 0.0 hr,
,O = 3.0 hr.
and
q = 3,000 hr.
Plot the reliability function for Tp = 10 hr, Tp = 100 hr, Tp = 500
hr and Tp= 1,000 hr. Then, tabulate your results in the format
given in Example 9-2. Discuss the reliability function’s behavior
in detail.
9-6. Solve the bearing problem of Example 9-2 when the parameters
of these bearings’ probability density function are the following:
7 = 100.0 hr,
/? = 2.0 hr.
and
q = 2,000 hr.
Plot the reliability function for Tp = 10 hr, Tp = 100 hr and
Tp = 500 hr. Then, tabulate your results in the format given
in Example 9-2. Discuss the reliability function’s behavior in
detail.
9-7. Given is the system of Problem 7-1, wherein each unit is replaced
preventively. Do the following:
(1) If Unit 1 is replaced preventively every 50 hr, Unit 2 every
200 hr and Unit 3 every 100 hr what is the stabilized average
corrective failure rate of each unit for Policy I?
.
(2) Same as in Case 1 but for Policy 11.
(3) What is the stabilized average preventive replacement rate
of each unit Policy I?
(4) Same as in Case 3 but for Policy 11.
( 5 ) What is the system stabilized M T T R (Mean Time to Re-
-pair) if the mean corrective repair times of the subsystem,
d;R, when the ith unit fails, are as follows:
-
-d l =~ 0.55 hr;
2 R = 0.75 hr;
-dd3R = 0.33 hr;
PROBLEMS 315
and
-
t"3p = 0.15 hr?
(6) Same as in Case 5 but for Policy I1 and for both bounds of
A,.
(7) What is the stabilized M T B F of the subsystem with cor-
rective and preventive maintenance for Policy I?
(8) Same as in Case 7 but for Policy I1 and for the lower bound
of A,.
(9) What is the stabilized reliability of the subsystem with cor-
rective and preventive maintenance for a 10-hour mission
for Policy I?
(10) Same as in Case 9 but for Policy I1 and for the lower bound
of A,.
(11) What is the reliability of the subsystem without any main-
tenance for a mission of 10 hr?
(12) What is the M T B F of the subsystem without any mainte-
nance?
9-9. Given is the subsystem of Problem 7-3 wherein each unit is re-
placed preventively. Determine the following:
(1) If Unit 1 is replaced preventively every 225 hr, Unit 2 ev-
ery 450 hr, and Unit 3 every 450 hr, what is the stabilized
average corrective failure rate of each unit for Policy I?
(2) Same as in Case 1 but for Policy 11.
(3) What is the stabilized average preventive replacement rate
of each unit for Policy I?
(4) Same as in Case 3 but for Policy 11.
(5) What is the subsystem stabilized M T T R for Policy I if the
mean corrective repair times of the subsystem, ZiR, when
the ith unit fails, are as follows:
-
-dd l R2 ==~ 0.55 hr,
0.75 hr,
and
-
d3R = 0.33 hr,
and if the mean preventive replacement times, F i p , of the
units are as follows:
-
t * p = 0.25 hr,
-
t f 2 p = 0.35 hr,
PROBLEMS 317
and
-
t*3p = 0.15 hr?
and
-
t*3p = 0.15 hr?
(3) How would you check to see whether or not the operational
reliability, or the reliability goal, of the subsystem is be-
ing met with these minimum-cost preventive maintenance
periods?
9-13. Given is the subsystem of Problem 7-1. Determine the following:
The minimum cost, preventive maintenance period for each
one of the three units using Policy 11. The corrective and
preventive maintenance costs are given in Table 9.13. Plot
the total cost of corrective and preventive maintenance for
each unit versus their preventive replacement period, Tp.
Show how it is possible to achieve further savings by making
Tpz and/or Tp3 an integer of Tpl.
How would you check to see whether or not the operational
reliability, or the reliability goal, of the subsystem is be-
ing met with these minimum-cost preventive maintenance
periods?
9-14. Work out Problem 9-13 again using the lower bound of the cor-
rective failure rate for Policy 11, and the data given in Tables
9.13 and 9.14 and do the following:
cost, c, cost, c,
$ $
1 75.00 10.00
2 145.00 35.00
3 80.00 12.00
9-17. Work out Problem 9-16 again using the upper bound of the
corrective failure rate for Policy 11, and the data given in Tables
9.13 and 9.14 and do the following:
If an average, stabilized reliability goal of R = 0.980 is spec-
ified for 8 hr of continuous operation, determine whether or
not this subsystem meets this requirement using the upper
bound of the corrective failure rate.
Determine the expected number of corrective (unscheduled)
maintenance actions that will be required for each unit for
Policy I1 using the upper bound of the corrective failure
rate and the optimum Tpi for 3,000 cumulative hours of
operation.
Determine the expected number of preventive (scheduled)
maintenance actions that will be required for each unit for
Policy I1 for 3,000 cumulative hours of operation.
Repeat Case 2 for the case when the T p and~ Tp3 are made
integer multiples of Tpl. Make sure that the reliability g o d
of R = 0.980 is met when adjustments in Tpi are made.
Determine the total corrective, preventive, and downtime
costs for Policy I1 using the upper bound of the corrective
failure rate, for 3,000 cumulative hours of operation, using
the datagiven in Tables 9.13 and 9.14, and overall downtime
cost of $10,000 per hour of subsystem downtime, and using
the optimum Tpi found in Problem 9.16.
Repeat Case 5 using the adjusted Tpi found in Case 4, the
corrective and preventive maintenance costs and downtimes
given in Table 9.17 and overall downtime cost of $10,000 per
hour of subsystem downtime, for 3,000 cumulative hours of
operation.
Discuss comparatively the results found in Cases 5 and 6.
9-18. Do the following:
(1) Summarize the results obtained by each unit for each case
of Problem 9-17.
(2) Comparatively discuss the summarized results for each case.
(3) Which top three preventive maintenance schedules would
you recommend and why? List the following:
(3.1) Preventive maintenance schedule for each one of the
three units.
(3.2) Number of corrective maintenance actions.
324 PREVENTIVE MAINTENANCE
9-20. Work out Problem 9-19 again using the upper bound of the
corrective failure rate for Policy I, and the data given in Tables
9.13 and 9.14 and do the following:
If an average, stabilized reliability goal of R = 0.980 is spec-
ified for 8 hr of continuous operation, determine whether or
not this subsystem meets this requirement.
Determine the expected number of corrective (unscheduled)
maintenance actions that will be required for each unit for
Policy I using the optimum Tpj for 3,000 cumulative hours
of operation.
Determine the expected number of preventive (scheduled)
maintenance actions that will be required for each unit for
Policy I for 3,000 cumulative hours of operation.
Repeat Case 2 for the case when the Tp2 and Tp3 are made
integer multiples of Tpl. Make sure that the reliability goal
of R = 0.980 is met when adjustments in Tpi are made.
Determine the total corrective, preventive, and downtime
costs for Policy I for 3,000 cumulative hours of operation,
using the data given in Tables 9.13 and 9.14, and overall
downtime cost of $10,000 per hour of subsystem downtime,
and using the optimum Tpi found in Problem 9.19.
Repeat Case 5 using the adjusted Tp;found in Case 4, the
corrective and preventive maintenance costs and downtimes
given in Table 9.17 and overall downtime cost of $10,000 per
hour of subsystem downtime, for 3,000 cumulative hours of
operation.
Discuss comparatively the results found in Cases 5 and 6.
Redo Cases 2 through 7 for 20,000 cumulative hours of op-
eration of the subsystem.
9-21. Do the following:
(1) Summarize the results obtained by each unit for each case
of Problem 9-20.
(2) Comparatively discuss the summarized results for each case.
(3) Which top three preventive maintenance schedules would
you recommend and why? List the following:
(3.1) Preventive maintenance schedule for each one of the
three units.
(3.2) Number of corrective maintenance actions.
(3.3) Number of preventive maintenance actions.
PROBLEMS 327
-
Nci
= 0.10,
Ni
and
-
NWi
= 0.90.
Ni
and
-
t*Sp = 0.15 hr?
Corrective Preventive
maintenance maintenance
cost, c, cost, c,
$ $
75.00 10.00
145.00 35.00
80.00 12.00
T
Unit Corrective Preventive
maintenance maintenance
cost, c, cost, cp
8 $
75.00 10.00
145.00 35.00
80.00 12.00
maintenance maintenance
cost, c, c,
cost,
$ 16
1 75.00 10.00
2 145.00 35.00
3 80.00 12.00
-
Nci
= 0.20,
Na
and
-
N w-i
- 0.80.
Ni
(3) How would you check to see whether or not the operational
reliability, or the reliability goal, of the subsystem is be-
ing met with these minimum-cost preventive maintenance
periods?
9-28. Work out Problem 9-27 again using the upper bound of the
corrective failure rate for Policy 11, and the data given in Tables
9.13 and 9.14 and do the following:
If an average, stabilized reliability goal of R = 0.980 is spec-
ified for 8 hr of continuous operation, determine whether or
not this subsystem meets this requirement using the upper
bound of the corrective failure rate.
Determine the expected number of corrective (unscheduled)
maintenance actions that will be required for each unit for
Policy I1 using the upper bound of the corrective failure
rate and the optimum Tpi for 32,000 cumulative hours of
operation.
Determine the expected number of preventive (scheduled)
maintenance actions that will be required for each unit for
Policy I1 for 32,000 cumulative hours of operation.
Repeat Case 2 for the case when the Tpz and Tp3 are made
integer multiples of Tpl. Make sure that the reliability goal
of R = 0.980 is met when adjustments in Tpi are made.
Determine the total corrective, preventive, and downtime
costs for Policy I1 using the upper bound of the corrective
failure rate, for 32,000 cumulative hours of operation, using
the data given in Tables 9.13 and 9.14,and overall downtime
cost of $10,000per hour of subsystem downtime, and using
the optimum Tpi found in Problem 9.27.
Repeat Case 5 using the adjusted Tpi found in Case 4, the
corrective and preventive maintenance costs and downtimes
given in Table 9.17 and overall downtime cost of $10,000 per
hour of subsystem downtime, for 32,000 cumulative hours
of operation.
Discuss comparatively the results found in Cases 5 and 6.
9-29. Given is the subsystem of Problem 7-1. Determine the following:
(1) The minimum cost, preventive maintenance period for each
one of the three units using Policy I. The corrective and
preventive maintenance costs are given in Table 9.22. Plot
the total cost of corrective and preventive maintenance for
each unit versus their preventive replacement period, Tp.
PROBLEMS 333
I I Corrective
maintenance
Preventive
maintenance
cost, cp
I I O
, S: cc I $ I
23.00 15.00
12.00
REFERENCES
1. Bazovsky, I., N. R. MacFarlane, R.L. Wunderman, Study of Main-
tenance Cost Optimization and Reliability of Shipboard Machin-
ery, United Control Corporation, Seattle, Washington, DDC No.
AD 283428, June 1962.
2. Cox, D. R., Renewal Theory, Methuen, London, 135 pp., 1962.
Chapter 10
PERIODIC REPLACEMENT
POLICIES
(10.1)
where
335
336 PERIODIC REPLACEMENT POLICY
and
E[N(T,)] = expected number of failures followed
by minimal repair actions in an interval Tp.
The expected number of failures in a Tpinterval, per unit, is determined
from
where
X(T) = instantaneous failure rate function, given by
(10.3)
and
R ( T ) = reliability function of a unit.
Then, the total cost per unit, per unit operating time, is given by
EXAMPLE 10-1
A unit with a Weibull times-to-failure pdf is preventively main-
tained under the Ordinary Periodic Replacement Policy. The parame-
ters of the Weibull pdf are y = 0, p = 2 and 77 = 30 hr. The cost of the
planned preventive replacement is $5 and the cost of minimal repair is
$30. Find (1) the optimum preventive replacement time, and (2) the
minimal total preventive maintenance cost per unit time of operation.
(10.5)
ORDINARY PERIODIC REPLACEMENT POLICY 337
or
(10.6)
1” X(T) dT = /,”T-
: dT= (?) 2
. (10.9)
Substitution of Eq. (10.9) into Eq. (10.4), yields the total cost
per unit operating time, per unit, for the OPRP, or
(10.10)
The minimal total cost per unit time, C+7111,and the optimum
replacement time T; can be found by finding the first derivative
of the cost function, given by Eq. ( l O . l O ) , with respect to the
replacement interval, Tp,setting it equal to zero, and solving it
for Tp. Then,
(10.11)
G-IZI =
5 +3 01224745
( ~2 )
12.24745 ’
or
= $0.8165 /hr.
0 T O To + L
@> V p T y l .
0 T
virtual time
+
to failure
Cr Jm f ( T )
TO
dT+Ce /" f(T)
0
dT = Cr R(To)+Ce Q(To),
(10.13)
where
To = ordering time,
C, = expedited order cost per cycle,
and
R(To)= probability that a unit will not fail up t o time To.
It is assumed that Ce > Cr.
Minimal repairs are made whenever a unit fails. The total expected
number of failures consists of the expected number of failures if the unit
MODIFIED PERIODIC REPLACEMENT POLICY 34 1
CT-IV-mr
I = Cmr [lTITIL A ( x ) f ( T )d x dT
or
(10.14)
where
Cmr = cost of a minimal repair action.
It is assumed that C, < C m r . Note that in the first term of Eq.(10.14)
the integrand, A(x), of the inner integral after integration becomes a
function of the variable of integration of the outer integral, T . The
limits of integration of the inner integral are ( T ,T + L ) , where T varies
between 0 and To which are the limits of integration of the outer inte-
gral. This may be seen in Fig. lO.l(b).
The expected salvage value per cycle [4, p. 2541 is the expected
+
remaining life value of the unit which is replaced at time (To L ) , but
is still able to operate. It is determined for the period from the time
of replacement t o the virtual time of failure, as shown in Fig. lO.l(c).
Then, the expected salvage value per cycle is given by
roo
= -c,
Lo+,[T - (To+ L ) ] dR(T),
roo
(10.15)
342 PERIODIC REPLACEMENT POLICY
where
C, = salvage value per unit time of operation,
and
f ( T )dT = -dR(T).
Using Eqs. (10.13), (10.14), (10.15), and adding the cost of pre-
ventive replacement, C p , the total cost per cycle, per unit, is given
by
(10.16)
=L + I T o T f ( T )dT + To R(T,),
Note that this last equation is the integration by parts of the second
term of
Tcy = L + 1 To
R ( T ) dT. (10.17)
The total expected cost per unit time of operation, per unit, for an
infinite time span can now be determined as
CT-ZV = -,
q/ (10.18)
TEy
MODIFIED PERIODIC REPLACEMENT POLICY 343
(10.19)
the failure rate function is
2T
X(T) = -
r12 ’
(10.20)
LT’LX(x) dx =
2 Td T
T+L 7
r7
( T ) ~ - (5) .
= T+L
2
(10.22)
Substituting Eq. (10.22) into Eq. (10.16), the total expected cost
per cycle becomes
roo
R(T)dT.
- csL + L
The integral
/6” T
[(T)2 +L - (3’1 f(T)
344 PERIODIC R E P L A C E M E N T POLICY
or
(10.23)
Substituting Eqs. (10.19) and (10.21) into Eq. (10.23), yields the total
expected cost per cycle, or
(10.24)
MODIFIED PERIODIC REPLACEMENT POLICY 345
(10.25)
C$-V = c1 + c2 + c3 ? (10.27)
where
C1 = scheduled replacement cost,
346 PERIODIC REPLACEMENT POLICY
1 ,28)
(10.29)
I' r7'1
To' ICA m I U
w w I V
L,
I Tp
or
(10.31)
Then, the total cost model for maintenance Policy V, per unit time
of operation , or the total cost rate, assuming an infinite time span, a
constant €ailure rate for spares, and that at least one failure occurs in
(To,T p ) ,is given by
s2R ( T )
R(TcJ)
"1 j- l}}. (10.32)
It should be noticed that one in the last term of Eq. (10.32) comes
from the assumption t1ia.t a t least one failure occurs in the interval
(To,T p ) .If the expected number of units failing in that interval is very
small adding one failure assures that at least one failure is accounted
for, conservatively.
348 PERIODIC REPLACEMENT POLICY
EXAMPLE 10-3
Units with a gamma times-to-failure pdf are preventively main-
tained under the MPRP, using Policy V. The parameters of the gamma
pdf are ,8 = 2 and 7 = 200 hr. The scheduled replacement cost is
$15. The minimal repair cost at failure is $70. The spare replace-
ment cost at failure is $10 and the constant failure rate of the spares is
A' = 0.05 fr/hr. Find the minimum total preventive and corrective cost
per unit time of operation, C$-v,the optimum planned replacement
time, Tp*-v, and the optimum switchover time T,'.
SOLUTION TO EXAMPLE 10-3
Theoretically the optimum cost occurs when $$ and are
equated to zero, and T,' and T i are found by solving these two equa-
tions simultaneously when the other parameters are known. To solve
for the optimum switchover time T,', TJ is obtained first using the
OPRP of Policy 111, which is a one-parameter policy. Then, substitut-
ing T; in Eq. (10.32)with the same /3, C1 and C2, T,*will be found as
the value which minimizes further the total cost rate, CT-V.
To find the T; from the OPRP of Policy 111, the gamma times-to-
failure pdf
(10.33)
(10.35)
or
(10.36)
Substituting Eq. (10.36) into Eq (lO.l), the total cost per unit time of
operation, per unit,.for the OPRP, or Policy 111, is given by
(10.38)
A computer iteration with the given values of C1, Cz and 7 for Policy
111, yields
(10.39)
The expected residual life, p') is evaluated from Eq. (10.29) after Tois
determined, or from
p' = s2 R ( T )dT 9
R(T0)
where
350 pmuomc REPLACEMENT POLICY
which is obtained by dividing Eq. (10.34) by Eq. (10.35). Therefore,
(10.40)
T9-TO
+
-
p' = 9 9 To [ T . + 2 9 - e (Tp+2q)]. (10.41)
Substituting Eq. (10.41) into Eq. (10.31) yields the expected number
of spares, or
(10.42)
Finally, substituting the Eqs. (10.39) and (10.42) into Eq. (10.32) and
dividing by Tp.yields the total preventive and corrective maintenance
cost per unit tune of operation, or
-To-- 9
9+To
+ c3). (10.43)
Comparing the minimum cost obtained for OPRP of Policy I11 with
Policy V, it may be seen that C+-v = 0.1488 < C+-rII = 0.1553.
Therefore, a saving is achieved using Policy V.
MODIFIED PERJODIC REPLACEMENT POLICY 35 1
where C1 and C2 are as given in Eq. (10.27), and C{ is the cost rate
of idle time.
, average residual life at To,p',
To find an expression for E [ r ] the
is used again. Then,
E ( r )= E[Tp - (To + +)I, (10.45)
352 PERIODIC REPLACEMENT POLICY
(10.47)
1.6
1.4 !\
minimum total cost per unit time of operation and the ordering
schedule.
10-5. Units that have a Weibull times-to-failure pdf are preventively
maintained under the Modified Periodic Replacement Policy-
Policy N with a constant lead time. The parameters of the
Weibull pdf are y = 0 and P = 2. q varies from 300 to 500
hr. Cp = $5, Ce = $40, C m r = $30, Cr = $20, L = 10 hr and
c8 = $O.OOl/hr. Find the minimum total cost per unit time of
operation, the ordering schedule and the expected cycle duration.
10-6. Units that have a Weibull times-to-failure pdf are preventively
maintained under the Modified Periodic Replacement Policy-
Policy N with constant lead time. The parameters of the Weibull
pdf are 7 = 0, /3 = 2 and q = 400 hr. Cp = $ 5 , Ce = $40,
C, = $20, L = 10 hr and c8 = $0.001/hr. Do a sensitivity anal-
ysis of the total cost per unit time of operation if the cost of a
minimal repair, C,,,,, varies from $30 to $50.
1.O-7.Units with a gamma times-to-failure pdf are preventively main-
tained under the Modified Periodic Replacement Policy-Policy
V. The parameters of the gamma pdf are P = 2 and 7 = 200 hr.
The scheduled replacement cost is $10. The minimal repair cost
at failure is $50. The spare replacement cost at failure is $40 and
the constant failure rate of the spares is A' = 0.05 fr/hr. The
planned replacement time is Tp = 140 hr. Find the minimum
total preventive and corrective maintenance cost per unit time
of operation, C$,v,and the optimum switchover time T,'.
10-8. Units with a gamma times-to-failure pdf are preventively main-
tained under the Modified Periodic Replacement Policy-Policy
V. The parameters of the gamma pdf are p = 2 and q = 200 hr.
The scheduled replacement cost is $10. The minimal repair cost
at failure is $50. The spare replacement cost at failure is $40 and
the constant failure rate of the spares is A' = 0.05 fr/hr. The
planned replacement time is Tp = 350 hr. Find the minimum
total preventive and corrective maintenance cost per unit time
of operation, C$-v,and the optimum switchover time T,'.
10-9. Units with a gamma times-to-failure pdf are preventively main-
tained under the Modified Periodic Replacement Policy-Policy
VI. The parameters of the gamma pdf are P = 2 and 7 = 100
hr. The scheduled replacement cost is $10. The minimal repair
cost at failure is $30. The idle time cost is $2 per hour of idle
time. Find the minimum preventive and corrective maintenance
REFERENCES 357
REFERENCES
1. Barlow, R. E. and Proschan, F., Mathematical Theory of Reliability,
John Wiley & Sons, Inc., New York, 256 pp., 1965.
2. Kaio, N. and Osaki, S., “Optimal Planned Policies with Minimal Re-
pair,” Microelectronics & Reliability, Vol. 28, No. 2, pp. 287-293,
1988.
3. Eraclides, S. T.,
“A Survey and Applications of Alternative Cost Saving
Preventive Maintenance Policies,” Master’s Research Report submitted
to Dr. Dimitri B. Kececioglu at The University of Arizona, 113 pp.,
1984.
4. Ross, S.M., Applied Probability Models with Optimization Applications,
Holden-Day, San Francisco, 234 pp., 1970.
5. Crk, V., “Optimal Preventive Maintenance Schedule and Spare Provi-
sioning Policies,” Master’s Research Report submitted to Dr. Dimitri
B. Kececioglu at The University of Arizona, 147 pp., 1991.
6. Cox, D. R., Renewal Theory, Methuen, London, 135 pp., 1962.
Chapter 11
MODIFIED BLOCK
REPLACEMENT POLICIES
(11.3)
359
360 MODIFIED BLOCK REPLACEMENT POLICIES
and
f(s) = L [ f ( T ) ]= Laplace transform of f ( T ) . (11.4)
f ( T ) is the times-to-failure pdf of the unit. Assuming an infinite time
span, or life, of the equipment, the average cost per unit time of oper-
ation is given by
(11.5)
EXAMPLE 11-1
A unit has a gamma times-to-failure pdf with /3 = 2 and q = 200
hr. The unit is preventively maintained under the ordinary block re-
placement policy. The planned replacement cost is $10. The corrective
replacement cost is $50. Find the minimum total preventive cost per
unit time of operation for the OBRP and the optimum replacement
time.
SOLUTION TO EXAMPLE 11-1
With p = 2, the gamma pdf becomes
(11.6)
or
1
(11.8)
=q s* (7 s + 2)'
and its inverse is
(11.9)
MODIFIED BLOCK REPLACEMENT POLICY 361
(11.10)
The total preventive plus corrective maintenance cost per unit time of
operation, CT , assuming an infinite time span for OBRP, and using
Eqs. (11.1) and (ll.lO), is given by
1
CT-VZZ = -{Cp
TP
+ cc Ro(Tp)) (11.11)
or
cT-VII
1
=-
TP
{cP+ C, (8+ 4 -* % -A)}.
e
4
(11.12)
The optimum T; time and the minimal total cost C$-vzz can be ob-
tained by taking the partial derivative of CT-VII with respect to T p ,
%, setting it equal to zero and solving for T;. Due to the complexity
of the CT-VII expression, the use of computer optimization will yield
the sought values for T; and C;-vIz. The results are
C+-vIz = $0.11874 /hr and Tp*= 300 hr.
(11.13)
and variance
o2 = N Var[Ho(Tp)]. (11.15)
MODIFIED BLOCK REPLACEMENT POLICY 363
where
L g(z) dz = 1 - a, (11.16)
r n [ q = L a . (11.17)
(11.20)
and the holding cost of the average level of spares per unit time of
operation for N units is given by
(11.21)
where
c h = holding cost per unit time of operation per one unit.
364 BLOCK REPLACEMENT POLICY
(11.22)
where
Cb = shortage, or backorder, cost per unit time of operation
per one unit.
If the expected order cost per cycle, Co, is independent of the num-
ber of spares ordered; then, the expected ordering cost per unit time
is given by
Co
(11.24)
if•
p
The total cost per unit time is the sum of the costs given by
Eqs. (11.13), (11.21), (11.22), (11.23) and (11.24), or
+ ch foscs- x) g(x) dx
foo Co
+ cb Js (X - S) g( X) dx + T, '
= N [ Cp + C~PHo(T,) l
+ NT~h foTp[H 0 (T,)- H(T)] dT
roo
or
366 BLOCK REPLACEMENT POLICY
(11.25)
(11.30)
MODIFIED BLOCK REPLACEMENT POLICY 36 7
where j = 1,2, -,k . Then, the holding cost of the average number of
units in kTp period is
(11.31)
The holding cost of the excess stock and the backorder cost per unit
time are determined by substituting Eq. (11.29) into Eq. (11.22) and
(11.23), or
(11.32)
and
(1 1.33)
Since the order for spares is made once in kT, intervals, the ordering
cost per unit time is given by
co
- (11.34)
k Tp’
The total cost per unit time is the sum of the costs given by Eqs.
(11.13), (11.31), (11.32), (11.33) and (11.34), or
+-liCOTp‘ ( 11.35)
+ (cb+ ch)/-
Sk
2 g(2) dz + -.kCOTP (11.36)
EXAMPLE 11-2
100 units with gamma times-to-failure pdf's are put into operation
a t time T = 0. They are replaced according to the OBRP on failure and
at a predetermined time interval Tp. The parameters for the gamma
pdf are ,f3 = 2 and q = 100 hr. The preventive replacement cost is
C, = $5. The corrective replacement cost is C, = $80. The shortage
cost per unit time of operation per one unit, is cb = 20 $/hr per unit.
The holding cost per unit time of operation per one unit is Ch = $1
/hr. The ordering cost is C, = $100 /order. It is assumed that the
desired assurance level is 95%. (1) If the order for spares is made every
Tp hr, find the minimal total cost per unit time of operation and the
optimum preventive replacement schedule. (2) Repeat Case 1 when
the order for spares is made every 3T, hr.
SOLUTION TO EXAMPLE 11-2
From Example 11-1 the expected number of replacements in a T,
interval is given by Eq. (ll.lO), or
( 11.37)
The mean of the spares demand distribution, g(z), for the multi-period
model, for N units is
(11.38)
(11.39)
Substituting H(T, - u) and h(u) into the integral of Eq. (,11.28) yields
MODIFIED BLOCK REPLACEMENT POLICY 369
or
Ti
I=---
Tp 3
+---e
3 - 2 9
- -Tp e-2 % (11.40)
8 q2 4 q 16 16 877
Substituting Eq. (11.40) into Eq. (11.28), yields the variance of the
spares demand distribution, g(z), or
(11.41)
The holding cost per unit time of operat,an for the mu +period
model can be determined using Eqs. (11.31) and (11.37), or
(11.42)
Finally, substituting Eqs. (11.37) and (11.42)into Eq. (11.36), the total
cost model per unit time of operation for N units, and the multi-period
model, is
370 BLOCK REPLA CEMENT POLICY
where
E[N1] = expected number of failures of new components,
E[N2] = expected number of failures of reconditioned
components.
C1 = planned preventive replacement cost,
Cz = failure replacement cost with a new component,
and
C3 = failure replacement cost with a used component.
+ + J," h,(T,
g ( V T ) = f ( T o r') - u ) f(u+ r') du, (11.46)
where
f ( T ot 7') = failure time distribution of the new
components,
372 BLOCK REPLACEMENT POLICY
(11.47)
and
L-'{ho(s)} = ho(r)in the r time domain.
Another way of defining the ordinary renewal density (ORD), h o ( s ) ,
is noting that Eq. (11.47)can be written as
ho(4 = f ( 4+ h o w f ( 4 9 ( 11.48)
and using the fact the Laplace transform of a convolution is the product
of the separate Laplace transforms; then, Eq.(11.48)can be converted
to obtain
rT
(1 1.49)
x Denote mnewrls.
Fig. 11.2- (a) Forward recurrence time, VT, for Policy IX;
(b) Parameters and variables used in the deriva-
tion of the pdf of VT for Policy IX.
(11.50)
where
+ lTo -
ho(To v) f(u + 7') d v ] dr'}
11. (11.53)
EXAMPLE 11-3
New units have a gamma times-to-failure pdf with p = 2 and
77 = 200 hr. The units are preventively maintained under MBRP with
Policy IX.The planned replacement cost is C1 = $10. The failure
replacement cost with a new component is Cz = $50. The failure re-
placement cost with a used component is C3 = $10. The constant
failure rate of the reconditioned units is A' = 0.002 fr/hr. Find the
minimum total preventive and corrective cost per unit time of oper-
ation, the optimum planned replacement time, TP, and the optimum
switchover time T,*.
SOLUTION TO EXAMPLE 11-3
If the new units have a gamma times-to-failure pdf with p = 2,
then
(11.54)
Therefore,
MODIFIED BLOCK REPLACEMENT POLICY 375
or
1
hO(4 = (11.56)
rls(rls+2)’
Then,
1
s )- (1 - e-2:),
h,(r) = ~ ~ - ‘ h , ( = (11.57)
277
and
1
ho(To- u ) = - 11 - e - 2 -1. (11.58)
277
Also, if we substitute T = u + T, we get
1
f(.+?> 772 ( u + r ) e-?.
=- ( 11.59)
(11.60)
or
(11.61)
(11.62)
Subsequently, substituting g(vT) into Eq. (11.51) yields
E[VTl = 1Tp-To
+
r’[f(r’ To) + Q] dT’, (11.63)
376 BLOCK REPLACEMENT POLICY
Finally,
(11.65)
Substituting Eq. (11.65) into Eq. (11.50), the mean number of recon-
ditioned unit failures in (To,Tp)can be found from
Finally, substituting Eqs. (11.66) and (11.45) into Eq. (11.44), the
total expected maintenance cost per operating period Tpcan obtained,
.$fODIFZED BLOCK REPLACEMENT POLICY 377
or
- ( T p s- T o )
-e 2 [9 [(Tp -9 To) 4.1)
(1 1.67)
2. Find the optimum switchover time, and the minimum total pre-
ventive and corrective maintenance cost per unit time of opera-
tion, and obtain
where
ri = idle time, and (Tp- To)1 T i .
MODIFIED BLOCK REPLACEMENT POLICY 379
+
Note that from time k Tp to ( k Tp To)ordinary renewal process
takes place, similar t o the one discussed in Section 11.2.2, since at
failure a new unit of zero age is substituted which is identical t o the
failed one. The expected number of failures E I N p T o ] ] can be found
using Eq. (11.45),or
E "[0,To] 1 = H~( 1, (11.69)
where Ho(To)is the renewal function already defined in Eq. (11.2).
To obtain the expected idle time, E [ t i ] ,note that it corresponds to
the mean left over time from the first failure in (To,Tp)to Tp,or
E[T;]= E[Tp- 7'1, (11.70)
as illustrated in Fig. 11.4.
r' was named the forward recurrence time, or residual life of the
component at To,or VT in Policy IX;then,
E[T;]= E[Tp - T' - To],
= Tp- To - E[T'I,
or
E[T;]= Tp- To - E [ V T ] . (11.71)
E [ V T ] was derived in Section 11.2.2 and given by Eq. (11.51) as
+
*f(u r') du ] d7'. (1 1.72)
Thus, the expected idle time per period Tp is given by
and the total-cost model per unit time of operation, CT, assuming an
infinite time span, is given by
EXAMPLE 11-4
Work out the same problem as in Example 11-3, but when the
units are preventively maintained under MBRP with Policy X, and (1)
the idle time cost is $5 per hour, and also when (2) the idle time cost
is $50 per hour.
SOLUTION TO EXAMPLE 1 1 4
Following the same procedure as in Example 11-3, the total pre-
ventive and corrective maintenance cost per unit time of operation, for
an equipment with infinite life time of operation, is
(11.75)
The T; and the C$,,II using the OBRP, as was done in the Ex-
ample 11-1, are
The optimum switchover time, T,*, and the minimum total preven-
tive and corrective maintenance cost per unit time of operation are the
following:
(1) Cs = $5 per hour, C+-x = $0.10926 /hr and T,' = 293.75 hr.
(2) C, = $50 per hour, C;-x = $0.11874 /hr and T,*= 300 hr.
Comparing the minimum cost obtained from the OBRP with that
from Policy X (with the idle time cost $5 per hour), we find that
C;-vrr = 0.11874 > C+-x = 0.10926. So a saving is achieved when
using Policy X. It must be pointed out that there may be no such
savings if the cost of idle time, per hour of idle time, is substantially
large and To<< Tp. It can be seen that when the idle time cost is $50
per hour the switchover time is equal to the planned replacement time.
That means Policy X can't apply. Therefore the units are actually
maintained under the OBRP.
PROBLEMS
made every Tp hours, find the minimal total cost per unit time
of operation and the optimum preventive replacement schedule.
(2) Repeat Case 1 when the order for spares is made every 4 Tp
hours.
11-4. Work out Problem 11-3 again but for q = 200, q = 100 hr and
7 = 50 hr. (1) Find the optimal number of replacement intervals
which minimizes the total cost per unit time of operation. (2) For
each solution of Case 1 determine the number of required spares,
Sk, in stock at the beginning of each interval.
11-5. 100 units with gamma times-to-failure pdf’s are put into opera-
tion at time T = 0. They are replaced according to the Ordinary
Block Replacement Policy on failure and at a predetermined time
interval Tp. The parameters for the gamma pdf are p = 2 and
7) = 100 hr. The preventive replacement cost is C p = $5. The
corrective replacement cost is C, = $80. The shortage cost per
unit time of operation per one unit, is cb = $20 /hr per unit. The
holding cost per unit time of operation per one unit is Ch = $1
/hr. The ordering cost is Co = $100 /order. It is assumed that
the desired assurance level is 95%. (1) If the order for spares is
made every Tp hours, find the minimal total cost per unit time
of operation and the optimum preventive replacement schedule.
(2) Repeat Case 1 when the order for spares is made every 5 Tp
hours.
11-6. Work out Problem 11-5 again for the desired assurance levels of
90% and 99%. (1) Find the optimal number of replacement in-
tervals which minimizes the total cost per unit time of operation.
(2) For each solution of Case 1 determine the number of required
spares, Sk, in stock at the beginning of each interval.
11-7. New units have a gamma times-to-failure pa’j with /3 = 2 and q =
200 hr. The units are preventively maintained under Modified
Block Replacement Policy-Policy IX. The planned replacement
cost is C1= $10. The failed unit’s replacement cost with a new
component is Cz = $50. The failed unit’s replacement cost with
an used component is Cs = $20. The constant failure rate of
the reconditioned units is A‘ = 0.05 fr/hr. Find the minimum
total preventive and corrective maintenance cost per unit time of
operation, the optimum planned replacement time, Tp’, and the
optimum switchover time T,*.
11-8. New units have a gamma times-to-failure pdf with /3 = 2 and q =
100 hr. The units are preventively maintained under the Modified
Block Replacement Policy-Policy IX. The planned replacement
REFERENCES 383
ADDITIONAL MAINTENANCE
POLICIES
385
386 ADDITIONAL MAINTENANCE POLICES
where
mean total cost in one renewal cycle
= mean total corrective replacement cost before T,-xz is reached
+mean total preventive and corrective replacement cost
after Tp-xz is reached,
or
mean total cost in one renewal cycle
+
= N - c, [(1 - 21 I) c, t 11 ’ I ’ C,],
and
mean length of one renewal cycle
= mean time to the preventive replacement age
+mean time the component remains above the
preventive replacement age,
or
mean length of one renewal cycle
= L+l,
and
C, = preventive replacement cost,
C, = corrective replacement cost,
T,-xl = prescribed threshold age, or preventive replacement
age,
N = mean number of failures before the preventive
replacement age, T P - x ~is, reached,
or
(12.1)
or
(12.3)
and
u e l = (mean number of preventive replacements above TP-xz) ,
5 l(at most 1).
Then, the mean total replacement cost per unit time of operation,
C(T,,xz), is given by
+
C(T,-XZ) = "* c, (1- u * 1)Cc+ u * 1 * CP]/(L
4-1 ) . (12.4)
Equation (12.1) can be derived as follows:
The number of trials t o reach the specified preventive replace-
ment age Tp-xz is a geometric process with the success probability
of R(Tp-xz) and the failure probability of 1- R ( T p - x ~for
) each trial.
Note that the last trial is always a success trial preceeded by several
failure trials. Each one of these preceeding failure trials consists of a
failure event occurring prior to age Tp followed by replacing the failed
unit by a fresh one. The success trial always ends up with a unit still
surviving at age Tp. The mean number of failures before a specified
age Tp-xz is reached, N, is given by
00
N = k { [l - R(Tp-xr)lkR(Tp-xr)) 7
k=O
00
OPTIONAL REPLACEMENT POLICY 391
or
N = 1 - R(Tp-xz)
W p - X I ) *
or
L= [JP-”’ T f ( T ) ,571
R(Tp-xz)
+ Tp-XI.
The term for the mean conditional life is actually the mean life of the
truncated time-to-failure distribution or f ( T )truncated at TP-x1. But
J,
TP--x~
T f ( T )dT = -Tp-xz - R(Tp-xz) +1 T‘-xI
R ( T ) dT.
where e-“ is used for the residual (conditional) life reliability of the
opportunity, since the exponential distribution is assumed for the time-
to-opportunity arrival.
OPTIONAL REPLACEMENT POLICY 393
Therefore, the mean time the component remains above the pre-
ventive replacement age, 1, is given by
or
or
-U1 = p 77 = 10 7.
2. Determine the effect of different replacement opportunities 011
the best preventive replacement age.
3. Discuss the results.
394 ADDITIONAL MAINTENANCE POLICES
I I
0 0.25 0.5 0.75 1.0 1.25
1. Figure 12.2 shows the average cost rate for an Optional Replace-
ment Policy expressed as a ratio of the cost of implementing an
Optional Replacement Policy to that with no planned replace-
ments at all (pure corrective replacements). Separate lines have
been drawn for various ratios of Cp/Cc. Examination of Fig. 12.2
shows that for some combinations of costs and the preventive re-
placement age, the performance of the best optional replacement
policy is considerably cheaper than either the Block policy (which
corresponds to a preventive replacement age of zero), or a policy
with no preventive replacement at all (which corresponds to a
preventive replacement age of infinity).
2. The effect of different frequencies of replacement opportunities
on the best preventive replacement age is shown in Table 12.1.
The top row of the table applies when the replacement opportu-
nities are rare compared with the frequency of failures, and the
bottom row when the replacement opportunities are relatively
OPTIONAL REPLACEMENT POLICY 395
frequent. In each row block there are three figures for each cost
ratio. The center figure gives the best value of the preventive
replacement age, and the upper and lower values give the preven-
tive replacement ages resulting in costs in excess of the optimum
by 5%. At the bottom of the table for comparison purposes is
the best preventive replacement age for an age replacement pol-
icy which is the limiting case of the optional policy with “very
frequent replacement opportunities.”
3. The following can be concluded from the results in Table 12.1:
(a) The most important factor in determining the best preven-
tive replacement age is the cost mtio, Cp/Cc.
(b) The best preventive replacement age increases as replace-
ment opportunities become more frequent, because the in-
crease in Tp,xz results in more frequent corrective replace-
ments at the age lower than T,-xz and less frequent preven-
tive replacements plus corrective replacements above TP-xx,
due to more frequent opportunities.
396 ADDITIONAL MAINTENANCE POLICES
(12.5)
where
H(TroITo)= expected number of failures in interval Tro, with
immediate replacement, starting with a
component of age TO.H(T,,ITo) can be
generated by the following recurrence
relationship:
(12.6)
and
PT,,(Y(To)= probability of a component having an age of Y
at the end of an interval of length T,, given
that it had an age TOinitially. PT,,(YITo) can
be generated from the following recurrence
relationship :
OPTIONAL REPLACEMENT POLICY 397
1, if Y = TO,
0 , otherwise.
(12.7)
1. Figure 12.3 shows, as Fig. 12.2, the average cost rate for an Op-
tional Replacement Policy expressed as the ratio of the cost of
implementing the optional replacement policy to that with no
planned replacements at all (pure corrective replacements). A
major feature of Fig. 12.3 is the step at a preventive replacement
age ratio of 1.00. This occurs because consecutive replacements
are prevented when the preventive replacement age exceeds the
int erval bet ween planned replacements.
Comparing Fig. 12.3 with Fig. 12.2 yields the following conclu-
sions:
(a) The costs are lower when the replacement opportunities are
regular and the same preventive replacement age is in force.
( b ) The best preventive replacement age for a n y cost ratio when
the replacement opportunities are regular is lower than that
for the case when replacement opportunities are exponen-
tially distributed.
2. The effect of different frequencies of replacement opportunities on
the best preventive replacement age is shown in Table 12.2. The
format is exactly the same as that for Table 12.1 in Example
12-1. The table was not extended to cover the more frequent
replacement opportunities since the same pattern is obtained as
in Table 12.1 of Example 12-1. The general conclusions about
the factors which aflect the best pmuentive replacement age are
unchanged. Perhaps the most striking aspect of the comparison
is that the results are so similar.
Ratio of cost of implementing
the Optional Replacement Policy
to that of no planned replacements
w
09
c)
8
P -. - 0
N
UI h
s 'tl
0
h
OPTIONAL REPLACEMENT POLICY 399
CPICC
Ratio CR+ 0.5 0.3 0.2 0.1 0.05 0.01
0.25 - 0.90 0.70 0.60 0.50
0.40 0.20 0.10 0.05 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
1.00 0.96 0.58 0.42 0.25 0.21 0.17
0.46 0.25 0.17 0.06 0.02 0.00
0.05 0.03 0.00 0.00 0.00 0.00
(12.8)
(12.10)
and
-
I N T ( t u) = integer part of ( t . u) rounded
to the next lower integer value.
-
(b) If TP-x- > l / u , let k = INT(Tp-xz u) and
{
K = kk ,+ 1, ifif Tp-xz - ( l / u ) INT(Tp-xz - u) = 0,
TP-xz - ( l / u ) INT(Tp-xz - u) > 0.
a
Then,
R(t) 2 [R(K/u)]’R(r), (12.12)
where
j = INT{t/(K/u)),
and
T =t - (K/u)j.
2. When Trois constant:
(12.13)
402 ADDITIONAL MAINTENANCE POLICES
1). New items (not burned-in yet) are used to replace those that fail
in the test-bed (Stage l), while the in-service failures (Stage 2) are
replaced by items already operating in the test-bed (Stage 1). The
Two-stage Replacement Policy can be applied to such a system. This
process has been generalized to “multi-stage burn-in” where more test-
beds each with a certain number of items are used. The stage order
number for each test-bed is assigned according to its burn-in length; i.e,
the test-bed with the shortest burn-in length is Stage 1, the test-bed
--
with second shortest burn-in length is Stage 2, -,the test-bed with
the longest burn-in length is the last stage, say Stage n. New items
always go to the vacancies caused by the failures in Stage 1. Service
failures are always replaced by surviving items from Stage n. Failures
at Stage i (1 < i 5 n) are always replaced by surviving items from
Stage (i- 1).
If the failure rate of the items increases with age, that is, the older
the item becomes, the more likely it is to fail, and Cj, > C f 2 because
failures among the first group items incur extra costs by causing dam-
age to other parts of the system, then it seems reasonable to suppose
that the following strategy would reduce the o v e r d replacement costs.
Replace all failures in the second group (hereafter called Stage 2) by
items already operating in the first group (Stage 1). Fill all the vacan-
cies in Stage 1 by new items, whether the vacancy is caused by failure
or by transfer t o Stage 1. It is clear that such a strategy cannot agect
the ovemll failure rate, or the failure rate of the whole system. It will,
however, decrease the failure rate in Stage 1, where replacement of fail-
ures is relatively expensive, at the price of increasing the failure rate
in Stage 2 where replacement is cheaper. If we assume that the cost of
transferring an item from Stage 1 to Stage 2 is small compared with
Cjl, such a policy will result in a net saving over simple replacement.
A strategy of this kind will be described as “two-stage replacement.”
It may be represented diagrammatically by Fig. 12.4.
404 ADDITIONAL MAINTENANCE POLICES
STAGE 1
Failures
New
components
* Nl
in Stage 1
b
cfl
components
I I STAGE2 I I Failures
N2
cfl
Fig. 1 2 . 4 Two-stage replacement policy.
-t in Stage 2
Cj1 > Cj2 > -.. > Cj,. Then the replacements are performed as
follows:
All failures in Stage ( i + 1) are replaced by components already
operating in Stage i where 1 5 i 5 n - 1. All vacancies in Stage i,
caused by failures and transfers of components into Stage ( i 1) are +
replaced by components operating in Stage ( i - 1). This process is
continued until Stage 1 is reached, where all vacancies resulting from
transfers and failures are replaced by new components. In Stage n all
failures are replaced by transferring components from Stage (n - 1);
there is no transfer of components from this stage. In this strategy,
new components enter only into Stage 1. The policy cannot change
the overall failure rate, but it certainly can decrease the failure rate in
Stage i at the expense of increasing the failure rate in Stage (i 1). +
The transfers can be made according to one of the following two rules:
1. Transfer by age - the oldest working component in Stage i is
MULTISTAGE REPLACEMENT POLICY 405
where
Pi,i+l= transfer rate, or transfers/(component). (hr),
or expected number of transfers from Stage i to
+
Stage (i l),per component, per unit time of
operation,
Ci, j + 1 = cost of transferring one component from Stage i
+
t o Stage (i l),
m = mean life of a component,
or
m= lo R(T)dT,
rm
(12.16)
406 ADDITIONAL MAINTENANCE PO LICES
and
C, = capital cost of a component.
The tmnsfer mte, P;, i + l , depends on the transfer rule and the
life distribution of the components considered, and is determined as
follows:
1. If transfer is made by age; i.e., the oldest component in Stage i
+
is transferred t o Stage (i l), then Pj, i + l can be obtained by
eliminating T; between the following two equations:
5 Nj
[
where P1(
Ti
j=i+l
pi, i+l = X r
n
= R-1( j$iN>)
, (12.18)
EXAMPLE 12-3
Assume N components have an exponential life distribution with
failure rate A. Find the transfer rate PI,2 for the Two-stage Replace-
ment Policy with N l and Nz components at Stage 1 and Stage 2,
respectively, if
hf ULTISTAGE REPLACEMENT POLICY 407
or
N2
P1,2 = - A, transfers/(component). (hr).
N1
2. If transfer is at random, then from Eq.(12.19)
or
1
= - Nl
A t P1,2 A N ’
Then, since N = N1 Nz,+
EXAMPLE 12-4
There are ten (10) interchangeable, non-screened, line-replaceable
units (LRU’s) in a complex electronic system. According to their
failure replacement cost, they can be divided into the following two
groups:
408 ADDITIONAL MAINTENANCE POLICES
SOLUTIONS TO EXAMPLE 1 2 4
Since this is a two-stage case, then n = 2. For the mixed-exponential
life distribution, the reliability function is
R(T)= Pl e -Xi T
+(1- p 1 ) e-'2 '.
os
or
(12.21)
Rearranging yields
(S,2l2 +K S , 2 + G = 0,
where
and
N
G = A1 A2 --
N1 m
[PI A2 + (1- p 1 ) A,].
Solving Eq. (12.21) for 4 , 2 yields
- K + m
p1,2 = (12.22)
2
2. Since this is a two-stage replacement case, substituting n = 2
into Eq. (12.15) yields
c 2 = " N / m - N1 4 , s ) Cjl + 0 + Nl P1,2 C j 2 ]
+ N 1 p1,2 c 1 , 2 + ( W m ) c,,
or
N
C 2 =-
m ( C j l i -C c ) + NI PI,^ (Cj2 + C1,2 - Cj,). (12.23)
(12.24)
410 ADDITIONAL MAINTENANCE POLZCES
co = -
1,000
[4 (250) t 6 (600)t 10 (200)] = $6.600/hr.(12.25)
and
c
2 =-
lo (250 t 200) t 4 (1.5 x (600 t 25 - 2501,
1,000
or
C2 = $6.750/hr. (12.26)
where
10
Ii' = 0.01 + 0.000909 - = 0.0084,
4 (1,000)
and
lo
G = 0.01 (0.000909) -
4 (1,000)
[0.1 (0.000909) + 0.9 (O.Ol)],
or
G = -1.364 x lom5,
and
and
(12.31)
respectively, where
(12.34)
OPPORTUNISTIC REPLACEMENT POLICY 413
(12.35)
12.2.7 COMMENTS
The a.pplication of the Multistage Replacement Policy requires the ex-
changeability among the components in the parent system and a gra-
dient i n their replacement costs.
Backward direction
4
1 1 , 0 0 0 I+.
0
A = T/n, (12.36)
where
Sk = age of component L at stage k, L = 1,2,. m.
a , ,
(12.37)
where
dSk = decision made on the system at stage k,
t5k = undetermined events which may occur
under d s k and S s k with their own
feasible range & and mass function
p k ( e ‘ k ) , and causes the
next state to be stochastic,
t k ( . ) = state transition function at Stage k ,
-
S s k - 1 = system state at Stage k - 1 which is
a random variable,
fk(dsk,SSk,Zk) = decision cost at Stage b which is a
function of the system’s current state
s s k , decision d s k and the random
events Zk under s s k and dsk,
s. t . = abbreviation of “subject to,”
416 ADDITIONAL MAINTENANCE POLICES
and
Dk = feasible decision sets for the system
a t Stage k.
Under the opportunistic replacement policy, the feasible decision sets
at any stage of the system are
replacing Component 1 preventively,
replacing Component 2 preventively,
I
replacing Component rn preventively, J
C& in all,
1
replacing Components 1, 2 and 3 preventively,
replacing Components 1, 2 and 4 preventively,
C$ in all,
(12.38)
where
CL = combination value of m choosing i.
The state transitions of any component L , L = 1,2, * , m, in the
system with an age of Sk a t Stage k under different decisions are shown
in Fig. 12.6, where k = n - 3 and Sk = S,k, = 3. If component L is
replaced preventively at Stage k, then an identical new component will
start its mission immediately at Stage R with an initial age of zero. If
the decision is t o “keep it in service,” then there will be two possible
out comes:
0PPO RT UNISTIC REPLACEMENT POLICY 417
0
w
- _ _q.,_ _s,"_+_ _ _ _
d
PI
*a -r
a
E
= 1=J
.-
C st =3
m-------
8
U
rd
--
- --
0 . I t
I I I
= MIN
(P1q
+(1 -
OPPORTUNISTIC REPLACEMENT POLICY 419
and
+
CplZ...(m-l)mPC12...(m-l)m= joint corrective replacement
cost of all m components.
By the conditional probability law
(12.41)
where
p = shape parameter,
and
77 = scale parameter,
420 ADDITIONAL MAINTENANCE POLICES
then
or
s: E [O,T&,] , L = l , 2 , . * . , m , (12.42)
OPPORT UArlSTIC REPLACEMENT POLICY 421
in unit of hours, or
in unit of A, where
Tkgg = T(R(T)=o.oI
= 7 (1% 100)l'p- (12.44)
(12.45)
Let bl and b, be the lower and upper bounds for the subscripts of array
B . Then, the total number of elements in arrays A and B should be
equal; i.e.,
[ 12.4G)
Next Page
-
When array A(u1, u2, * -,am) is stored rowwise into array B(b), their
subscripts have the following relationship:
where
(12.48)
and
w, = 1. (12.49)
Conversely when array B(b)is stored rowwise into array A(u1, u 2 , . - .,urn),
their subscripts have the following relationship:
where
I N T ( X ) = integer part of X.
Using Eq. (12.47), we can store the elements of an m-dimensional ar-
ray, A(u1,up, -
u m ) , into their corresponding locations in an one-
e e ,
OVERHAUL POLICIES
13.1 OVERHAUL
Overhaul is a maintenance activity undertaken at scheduled time in-
tervals whose primary purpose is to reduce the number of failures and
prevent equipment from reaching the age at which frequent failures
cause substantial loss of performance. In comparison with the preven-
tive maintenance policies, given in Chapters 9, 10, 11 and 12 by which
a component, an equipment or a system is restored to “as good as new”
condition after replacement or repair, an overhaul action is considered
as a restorative action which does not return an equipment to “as good
as new” condition but improves its performance. Figure 13.1 illustrates
the effect of overhaul and repair on the equipment’s condition. It may
be Seen that there is gradual deterioration of the equipment’s perfor-
mance over time which ends eventually in the replacement of the whole
equipment.
In contrast to preventive maintenance policies where the criteria
are most often to determine the optimum replacement or repair sched-
ule so that the total cost per unit of operating time is minimized, an
overhaul strategy is based on making decisions whether, and when, to
overhaul, as well as the level of overhaul to which equipment is to be
repaired. Overhaul versus replacement and repair is a decision most
often based on minimization of future cost, maximization of future
benefits or reducing the failure rate to acceptable levels. The decision
is usually made at regular time intervals so that the loss of production
due to downtime is minimized. For example, overhaul/replacement de-
cision is made once a week, once a month or once a year. To optimize
the overhaul/repair/replacement activities over a sequence of regular
intervals, information about overhaul, repair and replacement costs is
required. Since overhaul may consist of different maintenance activi-
461
462 OVERHAUL
T = calendar time,
Td = total downtime (overhaul time),
and
(13.1)
If the time between two overhauls of an equipment or a system is
fixed and equal to a mission or required operating time (To = Topt),
then from Q. (13.1), it is obvious that, depending on the M T B F
464 OVERHAUL DEFINED
Early failure
period
- Chance failures
- t -
-start of
wear-out
or
-
T = rn Q(To). (13.3)
Therefore, in general, equals the mean time between failures
multiplied by the unreliability for the overhaul period.
EXAMPLE 13-1
100 units with the mean time to failure, rn = 5,000 hr, are to
be overhauled at regularly scheduled time intervals, To, equal to 500
hours. Determine the following:
or
R(500) = e-*,
- e-O.l 9
or
R(500) = 0.904837.
with the overhaul schedule, To,so chosen that the occurrence of wear-
out failures is reduced to a minimum. The Weibull pdf is given by
(13.4)
(13.5)
where
Pc = shape parameter for chance failures ( p = l),
pw = shape parameter for wear-out failures (P > l),
qc = scale parameter for chance failures (qc = rn, = x),
1
N
= subpopulation undergoing wear-out failures.
The reliability of the system for a new mission of duration of t hours,
starting the mission at age To(overhaul interval), or after having al-
ready operated a total of To hours, is obtained from
(13.6)
or
3e-(-)@" vc + +e-(T~~~'Ly)pw
Rc,w(To,t ) =
+ +e - ( T o ~ ~ ~ ) P w
Pc
LL
N e-(Tv.
or
Equation (13.8) can be solved numerically to find the mean time be-
tween scheduled and unscheduled overhauls.
The expected number of overhauls that will be performed in calen-
dar time, T,which is the operating time plus total downtime, is given
bY
(13.9)
where
Nwh = number of overhauls,
T = calendar time,
TD = total overhaul time or total downtime,
and
EXAMPLE 13-2
A mixed sample of exponential and Weibullian parts is used in
an equipment. Ninety percent of the parts are exponential with the
following parameters:
pc = 1.0; qc = 5,000 hr and yc = 0 hr.
Ten percent of the parts are Weibullian with the following parameters:
& = 2.5; qw = 1,000 hr and -yw = 0 hr.
If the reliability goal is &OAL = 0.985, determine the following:
1. The interval between overhauls, To, so that the reliability for a
mission duration of 50 hr satisfies the reliability god.
2. The mean time between both scheduled and unscheduled over-
hauls, MTBO.
3. If 100 such equipment are in operation, determine the number of
those that will fail prior to the overhaul time, To.
SOLUTIONS TO EXAMPLE 13-2
1. Using Eq. (13.6) and the given parameters, the reliability of
an equipment for a mission duration of 50 hr, given that the
equipment is overhauled every To hours, is given by
MTBO =
5*000 +
- 4,500 (1 - e -1pe i7" 0.1 e - ( m )
T 25
' dT,
= 0.782422 + 0.066367,
or
R,,w(700) = 0.848789.
If 100 such equipment are in operation, then the number of those
that will fail prior to To = 700 hr, is given by
N j = N Qc,w(TO),
= N [1 - & ( ~ o ) ] ,
= 100 [l - 0.8487891,
= 15.1211,
or
Nj = 16 units.
where
p = mean wear life,
T = age, or accumulated operating time since new,
and
0 = standard deviation of the life times.
Here the case when only one failure mode can occur is considered;
i.e., only chance failures can occur or only wear-out failures can occur
and not both simultaneously.
OVERHAUL POLICIES 471
and so on.
To reduce the number of failures which are caused by wear-out the
overhaul interval, To = T,, or
T ~ = ~ - z u , (13.13)
should be so chosen that the probability of wear-out failures is small.
For single components the replacement or overhaul time must be
kept at ( p - 4 a) or ( p - 5 a) or in between, to prevent wear-out from
appreciably increasing the failure rate. If large numbers of components
are in a system, this replacement or overhaul time must be further
reduced to ( p - 5 a),or even ( p - 6 a),according to the reliability
requirements.
By a proper choice of the replacement, or overhaul, time To = ( p -
t a ) ,wear-out failures can be substantially reduced, or even eliminated.
Then, only chance failures would occur and the probability that the
equipment would fail in operation is drastically reduced.
When only chance failures occur between regular overhauls, the
number of parts of the same kind which will have to be replaced because
of failing prior to regular overhaul time Toamounts, on the average, to
(13.14)
When Q(To)is small and only chance failures occur [2, p. 2001,
then
m
N j = N - 1. 0 ( 13.15)
m
472 OVERHAUL DEFINED
EXAMPLE 13-3
An equipment has a mean time to failure of m = 4,000 hr, a mean
wear-out life of p = 1,200 hr and a standard deviation of Q = 100
hr. To prevent the wear-out failure from occurring prior to scheduled
overhauls the interval between overhauls, To, should be determined
from To = p - 4 Q. Determine the following:
1. The interval between overhauls, To, and the reliability of an
equipment for a mission duration of T = To assuming that only
chance failures occur.
2. The probability of wear-out failures occurring prior to To.
3. The probability of chance failures occurring prior to To.
4. Compare the results of Cases 2 and 3.
5. If 100 such equipment are in operation how many will fail due to
chance failures prior to To?
6. If the interval between overhauls is extended to To = 1,000 hr,
what is the probability of wear-out failures occurring prior to To?
Compare this result to the result of Case 2.
7. Determine the reliability of an equipment for a mission duration
of T = To = 1,000 hr and compare this result with the result of
Case 1.
8. If 100 such equipment are in operation, how many will fail due
to chance failures prior to To = 1,000 hr?
9. What should be the mean wear-out designed-in life if there is
a requirement that not more than 1% fail due to wear-out, as-
suming that a good approximation of the standard deviation is
,
0 = #.
or
R(800) = 0.81873.
Then
z=- P - To
U
- 1,200 - 1,000
-
100 '
or
z = 2.
From the standard normal cumulative distribution tables and for
z = 2 the probability of wear-out failures is
Qw(l,000) = 0.02275.
Comparing the results of Cases 2 and 6 it can be seen that when
the overhaul interval, To, is extended from 800 hr to 1,000 hr
the probability of wear-out failures increases from 0.0000317 to
0.02275.
7. The reliability of an equipment for a mission duration of T =
To = 1,000 is given by
~ ( 1 , 0 0 0 )= e - s ,
- e-0.25 9
or
R(1,000) = 0.7788.
Comparing the results of Cases 1 and 7 it can be seen that when
the overhaul interval, To,is extended from 800 hr to 1,000 hr the
reliability of an equipment for a mission duration of To = 1,000
hr decreases from 0.81873 to 0.7788.
8. If there are N = 100 units at the start of an overhaul interval
of To = 1,000 hr, then the number of those that will fail due to
chance failures is given by
Nf = N Q(l,000),
= N [l - R(TO)]
= 100 [l -0.77881,
= 22.12,
OVERHAUL POLICIES 475
or
N j = 23.
or
To = p (1 - 6). (13.16)
- 1. ooo
2.326 7
1 - T
or
p = 1,303.1 hr.
( 13.17)
which is the ratio of the expected, or average time, ?ire, between sched-
uled and unscheduled overhauls to the fraction of overhauls caused by
the actual failure of the system. From Eq. (13.17)
( 13.18)
or
mT,, = m.
It is known that for a nonmaintained system its mean life is given by
00
m= R(t) dt.
(13.19)
Equation (13.17) for mT,,and (13.19) for Aavg are valid regardless of
the failure distribution of the components. For example, if a component
fails only because of wear-out and is not preventively replaced after ?"re
hours of operation, it will fail with a mean time between failures equal
to its mean wear-out life, m.
OVERHAUL POLICIES 477
(13.20)
where
(13.21)
where
p d ( i , j ) = probability that the system will go from state i
to state j in one period of time if decision d is
made,
and
S,,(G) = min
i
C O ( G ,GI PO(G,G ) + cO (G , F ) PO(G,F)
+PO(G,G ) s n - m +PO@, F ) % - l V ) ,
or
C % ( G , G ) p&(G,G) + C R p ( G , F )pRp(G,F)
+ P W , G)Sn-dG) + P Y G , F ) %-l(F). I
(13.25)
The first two lines are for the case where the decision is to overhaul.
The first two terms represent the cost of overhaul if the system is ini-
tially good and after one period of time it is still in good condition,
480 OPTIMAL OVERHA UL/REPAIR/REPLACE POLICY
Co(G,G), times the probability that the system is still in good con-
dition after one period of time if it was initially good, po(G,G), plus
the cost of overhaul if the system is initially good and after one period
of time it is in a failed state, Co(G, F),times the probability that the
system is in a failed state after one period of time if it was initially
good, po(G,F). The next two terms represent the total expected fu-
ture cost with (n - 1) remaining intervals if the system is in a good
condition after one period of time, S,,-l(G), times the probability that
the system is still in good condition after one period of time if it was
initially good, po(G, G ) plus the total expected future cost with (n- 1)
remaining intervals if the system is in a failed state after one period
of time, Sn-l(F), times the probability that the system is in a failed
state after one period of time if it was initially good, po(G, F).
The next two lines are for the case if the decision is to replace.
The first two terms represent the cost of replacement if the system is
initially good and after one period of time it is still in good condi-
tion, C%(G,G), times the probability that the system is still in good
condition after one period of time if it was initially good, p b ( G ,G ) ,
and the system is replaced, plus the cost of replacement if the system
is initially good and after one period of time it is in a failed state,
CRp(G,F),times the probability that the system is in a failed state
after one period of time if it was initially good, pRp(G,F), and the
system is replaced. The next two terms represent the total expected
future cost with ( n - 1) remaining intervals if the system is in a good
condition after one period of time, Sn-l(G), times the probability that
the system is still in good condition after one period of time if it was
initially good, p&(G, G ) ,and the system is replaced, plus the total ex-
pected future cost with ( n - 1) remaining intervals if the system is in
a failed state after one period of time, Sn-l(F), times the probability
that the system is in a failed state after one period of time if it was
initially good, pRp(G,F),and the system is replaced.
The minimum of the two values on the right side of Eq. (13.25)
determines the best decision, and the minimum total expected future
cost if the system is initially in a good state.
Similarly, if the system is initially in a failed state, i = F ; then,
the possible decisions are either repair or replace. Making a repair de-
cision the probabilities of going from state i to j in one period of time
are pr(F,G ) and pr(F,F ) . Making a replacement decision, the proba-
bilities of going from state i to j in one period of time are p b ( F ,Gj
and p h ( F , F ) . Figure 13.3 shows possible decisions and the associ-
ated probabilities of going from state i to state j . Using Eq. (13.24)
OVERHAUL POLICIES 481
*
n Time n-1
Sn(F)= min
i
' (F,G)P'(F, G) + (F,F )P'(F, F)
C
+P'(F, G ) Sn-l(G) + P V ,F) Sn-dF),
or
+
C&(F,G) p%(F,G) CRp(F,F)pRp(F,F)
+pRp(F,G) Sn-l(G) + P & ( F , F ) Sn-l(F)+ ,I (13.26)
The minimum of the two values on the right side of Eq. (13.26) de-
termines the best first decision, and the minimum total expected fu-
ture cost with n remaining periods of time to operate if the system
is initially in a failed state. In both EQ. (13.25) and (13.26) the o p
timum future cost, Sn-l(j), is not known and to find the minimum
total expected future cost, Sn(i),these two equations should be solved
recursively by starting from the stage where the value of Sn-l(j) is
known. Usually So(i),or the optimum future cost with zero remaining
intervals to operate, is known. Now, using a s . (13.25) and (13.26)
the minimum total expected future cost with one remaining interval to
operate, Sl(i), can be determined. This value is used again to calculate
&(i) and going backwards, repeating the same procedure, the values
of Sn(i),or the minimum total expected future costs with n remaining
intervals to operate, are determined.
EXAMPLE 13-4 [3, p. 1291
A complex system is put into operation. It is decided that the
system is inspected at regular one-year intervals and, depending on the
condition of the system, replacement, repair or overhaul is undertaken.
The transition probabilities from State i to State j are given in Table
13.1. Costs of the system's operation for a one-year interval, depending
on the system's condition at the start and at the end of an interval,
OVERHAUL POLICIES 483
&(i) = 0.
Then, using Eq. (13.24), the total expected future cost with one re-
maining year of operation, n = 1, is given by
r N 1
(13.27)
& ( G ) = min [ C C o ( G , j )p 0 ( G , j )
c C Y G , j ) P Y W replace, ]
overhaul,
C O ( G ,G ) PO(G,G ) + C O ( G ,F)P 0 ( G F)
= min
@( G, G ) pRp(G,G)+ C b ( G ,F )p%(G, F)
+ (1,200)
1 '
or
= min
(200) (0.75)
(500)(0.95) + (1,500)
(0.25)
(0.05) 1'
450
S l ( G ) = m i n [ 550 ] overhaul,
replace, (13.28)
and
repair,
&(F) = min N
c C R P ( F , jP) Y F , j )
j=1 replace,
= min
= min
or
s~(F)
= min [ 500
550
3 repair,
replace.
(13.29)
From Eqs. (13.28) and (13.29) the following decisions can be made:
If the system is in good condition at the decision point, where one
year of operation remains, then the minimum total expected future
cost is achieved if the system is overhauled; i.e., & ( G ) = $450.
If the system is in a failed state at the decision point, with one
year of operation to go, then the minimum total expected future cost
is achieved if the system is repaired; i.e., S1(F) = $500.
To go one step backward consider two intervals or two remaining
years of operation, n = 2, of the system. Using Eqs. (13.24) and (13.27)
yields
S2(i)= min
d
j=1 J
OVERHAUL POLICLES 485
- C O ( G , G )PO(G,G)+ cO (G , F ) PO(G,F) -
+PO(G, G ) Sl (GI+ P O (G, F) Si(F) overhaul,
& ( G ) = min (13.31)
C%(G,G) p G ( G , G )+ C G ( G , F ) pRp(G,F)
~ +p%(G, G ) + pRp(G,F)Si(F) replace.
follows:
&(G) = rnin
+
(200)(0.75) (1,200)(0.25)+ (0.75)(450)+ (0.25)(500)
,
+ +
(500)(0.95) (1,500)(0.05)+ (0.95)(450) (0.05)(500)
450 + 300 + 337.5 + 125
or
= min
475+ 75+427.5+ 25 ' I
s ~ ( G=) min [ 1002.5
912.5
] overhaul,
replace.
(13.32)
1 1
' (4G ) P' (4G ) + C'V, F)P'V, F)
C
+P'(F, G ) Sl ( G ) + P'P, F ) s1(F) repair,
&(F) = min (1 3.33)
+
CRp(F,G)pRp(F, G) C b ( F ,F)p&(F, F )
+ P Y F , G ) Sl(G) + P R V , F ) s1(F) replace.
Substituting the transition probabilities given in Table 13.1, the o p
eration costs given in Table 13.2 and the minimum values from Eqs.
(13.28)and (13.29) into Eq. (13.33)the minimum total expected fu-
ture cost with two remaining years of operation can be obtained as
follows:
[ + + +
s~(F> = min
(100)(0.60) (1,100)(0.40) (0.60)(450) (0.40)(500)
+ +
60 440 270.0 + 200
+ +
(500)(0.95) (1,500)(0.05)+ (0.95)(450) (0.05)(500) 1
or
= min
475+ 75+427.5+ 25 ' 1
(13.34)
486 OPTIMAL OVERHA UL/REPAIR/R.EPLACE POLICY
system at start
of interval i G F G F
Decision to be
made at start
of interval Overhaul Repair Overhaul Repair
Expected
future cost,
Sn(i), $ 1,841.60 1,900.30 1,376.90 1,435.50
488 OPTIMAL OVERHAUL/REPAIR/REPLACE POLICY
the system of age i, or the net aquisition cost of the system; i.e.,
A ( i ) = 30 - Cs(i), (13.36)
where the price of the new system is given in thousands of dollars.
Table 13.5 gives the values of c(i), A ( i ) and S(i,S), where S(i,6) is the
optimum value function after the fifth year of system operation; i.e., it
is the negative of the salvage value for the system of age i, or
S(i,6) = -Cs(i). (13.37)
Using the recurrence relation of Eq. (13.22) and Eqs. (13.35) and
(13.36),the total expected future cost is given by
S(i,j)= min
+ + +
c ( i ) S(i 1,j 1)
(13.38)
+ +
A ( i ) S(1,j 1) replace,
where the top line of Eq. (13.38)refers to the overhaul option and the
bottom line corresponds to the replacement option. If the decision is
to overhaul, then the total expected future cost consists of the cost of
OVERHAUL PoLrcrm 489
the overhaul and the annual cost increase, c ( i ) ,plus the optimum value
function after one year of operation, S(i+l,j+l),where the age of the
system now is (i+l) and the Order Number of a decision point is (j+l).
If the decision is to replace, then the total expected future cost consists
of the total acquisition cost, A(i), plus the optimum value function
+
after one year of operation, S(1,j l ) , where the age of the system
now is i = 1, since the system was replaced and the Order Number
of a decision point is j +
1. As in Example 13-1, to determine the
minimum total expected future cost of the system, initially of age two
years subjected to the given overhaul/replacement policy, Eq. (13.38)
should be solved recursively starting from the decision point where
S(i,j) is known. Since the values of S(i,6) are known, determine the
values of S ( i ,5 ) as follows: Using Eq. (13.38), the values given in Table
13.5 and assuming that the system’s age at the start of the fifth year
is one year, i = 1, yields
or
or
-3 overhaul,
S(2,5) = min { -6} replace.
490 OPTIMAL OVERHAVL/REPAIR/REPLACE POLICY
or
~ ( 3 , s=
) min { I:} overhaul,
replace.
Hence, the minimum future cost is
S(3,5) = 4 3 , 0 0 0 , (13.41)
and the best decision to be made at the start of the fifth year, if the
system’s age is three years, is to replace. The next stage the system
will be in is (1,6).
If the system’s age at start of the fifth year is four years, i = 4,
then,
15- 8
or
Now, consider the fourth decision point or the decision point at the
start of the fourth year, (i,4). If the system’s age at the start of the
fourth year is one year, i = 1, then,
S(1,4) = min {l E } ,
or
overhaul,
S(1,4) = min { I:} replace.
(13.43)
Since there is a tie, the best decision at the start of the fourth year, if
the system’s age is one year, can be either repair or replacement. The
next stage the system will be in is (2,5) if the decision is to repair or
(1,5) if the decision is to replace.
If the system’s age at the start of the fourth year is two years, i = 2,
then,
or
If the system’s age at the start of the third year is one year, i = 1,
then,
or
{
8 overhaul,
S(1,3) = min 9 }
replace.
Hence, the minimum future cost is
S(1,3) = $8,000, (13.45)
and the best decision to be made at the start of the third year, if the
system’s age is one year, is to overhaul. The next stage the system will
be in is (2,4).
If the system’s age at the start of the third year is two years, i = 2,
then,
or
or
18 overhaul,
{
s(l’ 2, = min 18} replace.
Hence, the minimum future cost is
S ( l , 2) = $18,000, (13.47)
and either an overhaul or a replace decision can be made with the same
minimum total expected future cost.
If the system’s age at the start of the second year is three years;
i.e., a = 3, then,
or
28 overhaul,
{
s(3’ 2, = min 25) replace.
Hence, the minimum future cost is
S(3,2) = $25,000, (13.48)
and the best decision to be made at the start of the second year, if the
system’s age is three years, is to replace.
The next stage the system will be in is (1,3). What is left is to
consider the initial stage, or the first decision point where the system’s
age at the start of the first year is two years; i.e., i = 2. Then,
or
Minimum future
C o s t , in $1,000,
W,j> Decision
-11 0
-6 RP
-3 RP
0 RP
4 RP
-1 or 0
3 RP
6 RP
11 RP
8 0
13 RP
19 RP
18 or 0
25 RP
32 Rp
and the best decision to be made at the start of the first year of o p
eration is to replace. Since the annual cost increase, which is the
difference between the cost in a particular year and the first year of
operation, is used throughout these calculations instead of the actual
annual cost, then the total future cost of $32,000 is the additional cost
for a five-year operation and failure costs determined on the cost of
the first year. Table 13.6 gives all stages necessary to determine the
minimum total expected future cost and the sequence of decisions for
the next five years of operation. To determine the sequence of best
decisions, which results in the minimum total expected future cost,
consider Table 13.6. Start from the initial stage where the system’s
age is two years, or (2,l). The best decision that minimizes the total
future cost, which is that of all future stages, is to replace and the next
stage is (1,2). At stage (1,2) either overhaul or replacement can be
chosen with the same future cost and the next stage is either (1,3) if
replacement, or (2,3) if overhaul is chosen. If overhaul is chosen the
OVERHAUL POLICIES 495
next stage is (1,3). The minimum future cost at stage (1,3)is obtained
if the overhaul decision is made and the next stage is (2,4). At stage
(2,4)the replacement decision minimizes the future cost and leads to
the stage (1,5). The hal decision at the start of the fifth year is over-
haul and after the fifth year of operation the system's function ends.
Since at stages (1,2)and (1,4)both replacement and overhaul deci-
sions are possible, then there are three possible sequences of decisions
which have the same minimum total expected future cost; i.e.,
1. replace, replace, overhaul, replace, overhaul, dispose,
or
2. replace, overhaul, replace, replace, overhaul, dispose,
or
3. replace, overhaul, replace, overhaul, replace, dispose.
Each of these decisions is made at the beginning of a decision interval
and after the fifth year of operation the system is disposed.
or
N
Since C p d ( i , j ) = 1, then,
j=1
or
1
N
g + v ( i )= 9{ j N= 1 Cd(i,j) p d ( i , j ) + jCpd(i,j)
=1
v(j) . (13.53)
(13.54)
EXAMPLE 13-6
The system of Example 13-4 is to be maintained over "a long"
period of time. The transition probabilities are given in Table 13.1 and
the operation costs in Table 13.2. Determine the best overhaul/repair/
replace decisions or the optimum maintenance policy and the steady
state average cost per unit time of operation.
SOLUTION T O EXAMPLE 13-6
To determine the optimum decisions depending on the state of the
system at start of one-year interval use the Howard's algorithm as
follows:
Step 1
Assume the following decisions at the start of an interval:
1. If the system is in good condition, G, then replace it.
Step 2
Since the variable i can be only'in N = 2 states; i.e., i = G or F,
then using Step 2 of the Howard's algorithm yields
v ( F ) = 0. ( 13.55)
Step 3
Using the data given in Tables 13.1 and 13.2 and the decisions
defined in Step 1, solve Eq. (13.53) for the steady state average cost
per interval, g, and the transient cost, v ( i ) ,or for i = G and for j = G
and F,
I 5 C o ( G , j )p 0 ( G , j )+ C p 0 ( G , j )
11
N
~ ( j ) overhaul,
j=1
min
5 C R p ( G , j )p R p ( G , j+) C p R P ( G , jv(j)
j=l
j=l
N
j=1
) replace,
or
450
min[ 550 1 overhaul,
replace.
Hence, the minimum of Eq. (13.54)is obtained if the decision is to
overhaul.
If the system is initially in a failed state, or i = F, using Tables
13.1 and 13.2,Eq. (13.54)and j = G and F ,yields
min [ i?
j=1
5
j=l
~ " ~ 7 p'(~,j)
j )
+ j=l
C % ( F , j ) p"(F,j)
F p ' ( ~ , j )v(j)
+ j=l
N
c p R p ( F , j ) 4 j ) replace, 1 repair,
Step 5 + Go to Step 3
Using the decisions obtained in Step 4, solve simultaneously Eq.
(13.53) for the steady state average cost per interval, g, and the tran-
sient cost, v ( G ) ,or for i = G and j = G and F,Eq. (13.53) yields
Using data from Tables 13.1 and 13.2, and Eqs. (13.55) and (13.62)
yields
g + v(G) = (200)(0.75) + (1,200)(0.25)
+(0.75) v(G)+ (0.25)(0),
and Eqs. (13.55) and (13.63) yield
g = (100)(0.60) + (1,100)(0.40)
+(0.60) v(G) + (0.40)(0),
or
g + v(G) = 150 + 300 + (0.75) v(G), (13.64)
and
g = 500 + (0.60) v(G). (13.65)
The solution to the system of Eqs. (13.64) and (13.65) is
v(G) = -58.82 (13.66)
and
g = 464.71. (13.67)
min
or
min
. (475 + 75) + (0.95)(-58.82) ’ I
OVERHA UL POLICIES 501
where
Li = overhaul cost limit for an equipment of age i.
The expected cost of overhaul and inspection per interval is given by
(13.70)
where
Cn(i,j) = expected cost of the first decision for an equipment of
age i and with n remaining time intervals of operation,
and
Sn-l(j)= minimum expected future cost for ( n - 1) remaining
time intervals of operation.
The expected cost of the first decision, Cn(i,j), is the sum of the
expected cost of overhaul times the probability that the overhaul cost
is less than the overhaul cost limit, Li, and the cost of a replacement,
A*, times the probability that the overhaul cost exceeds the overhaul
cost limit, Li. Using Eqs. (13.69)and (13.70) the expected cost of the
first decision is given by
-
+
C n ( i , j )= Li Pi(Li) A* [l - Pi(Li)]. (13.72)
OVERHAUL POLICIES 503
Then,
or
-
The minimal expected future cost for the (n 1) remaining time in-
tervals of operation, S,,-l(j), is the sum of the minimum future cost,
S,,-l(i+ l ) , if the equipment is overhauled at the start of the nth inter-
val times the probability that the estimated cost is less than the over-
haul cost limit, Pi(Li), and the minimal expected future cost, Sn-l(l),
if the equipment is replaced at the start of the nth interval times the
probability that the estimated cost exceeds the overhaul cost limit.
Then, the minimum expected future cost is given by
+
Sn-l(j) = Sn-l(i 1) E ( L i ) + Sn-l(l)
[I - Pi(Li)]. (13.74)
Substituting Eqs. (13.72) and (13.74) into Eq. (13.71), the total ex-
pected future cost is given by
s n ( i ) = min {Cn(i,j) + S n - l ( j ) } 7
Li
or
) min (z pi(^,) + A* [I - p i ( ~ i ) l
~ , , ( i=
Li
+Sn-l(i + 1) Pi(Li)+ Sn-1(1) [l - f i ( L i ) ] } . (13.75)
Apparently, the starting condition, or the minimum expected future
cost for n = 0 remaining time intervals of operation, is
So(i)= 0 for all i. (13.76)
The optimum overhaul cost limits are so determined that the total ex-
pected future cost given by Eq. (13.75) is minimized. The iteration
process starts from the terminating stage; i.e., n = 0, where the total
expected future cost is known, and going backwards the minimum ex-
pected future costs, Sl(i), S2(i),-..,are determined for possible equip
ment ages, i.
Alternatively, the optimum overhaul cost limits can be determined
as follows: Assume that the equipment is in state n, with the optimum
value function Sn(i), and the overhaul cost is $2. If the equipment is
overhauled, the total cost is given by
5 + Sn-l(i + l ) , (13.77)
504 OPTIMAL OVERHAUL COST LIMITS
or
-
Sl(i)= Li pi(&) + A*[1- Pi(Li)].
For the three-year-old unit and one remaining year of unit operation,
replacement is compulsory, or
&(3) = $150. (13.81)
For the two-year-old unit and one remaining year of unit operation,
since the overhaul cost is uniformly distributed over the range (0; $150)
and the cost of a new unit is A* = $150,overhaul should be always
done. Consequently, P’(L2) = 1, because overhaul is a certainty. The
overhaul cost pdf at the end of the second year of a unit’s operation is
Sl(2) = L2,
or
Sl(2) = $75. (13.83)
For the one-year-old unit with one remaining year of operation, since
the overhaul is uniformly distributed over the range (0,$100) and the
cost of a new unit is A* = $150, the overhaul is always cheaper, and
the decision is always to overhaul. The overhaul cost pdf at the end of
the first year of the unit’s operation is given by
or
&(3) = $200. (13.86)
For the tweyear-old unit and two remaining years of operation, the
probability that the overhaul cost does not exceed the overhaul cost
limit is found from Eq. (13.69), or
or
(13.87)
(13.88)
C2(2)= -
300
+ 150 (1 - 4)
. (13.89)
Using Eqs. (13.75) and (13.89),the total expected future cost for the
unit of age two years, and two remaining years of operation, is given
OVERHAUL POLICIES 507
= mL2i n ( 300
Z+l50 ( 1 - 3150
)
or
(13.90)
To find the optimum overhaul cost limit, L2,which minimizes the total
expected future cost given by Eq. (13.90), find the first derivative of
&(2) with respect to L2,equate it to zero and solve for L2. Then,
dS2(2) 2 L2 200
-=---
dL2 300 150
+ 1,
or
-dSz(2)
=--- L2 50
dL2 150 150'
Now,
and
L2 = $50. (13.91)
Substituting Eq. (13.91) into Eq. (13.90) the minimum total expected
future cost is
502
&(2) = -
300
+ 200
2,500
=-
300
+ 200-100
150
+ 50,
or
&(2) = $191.67. (13.92)
508 OPTIMAL OVERHAUL COST LIMITS
Hence, if the estimated overhaul cost is less than $50, then the decision
is to overhaul, otherwise replace the unit. The minimum total expected
future cost for the unit of two years of age, and for two remaining years
of operation, is $191.67.
For a one-year-old unit and two remaining years of operation, the
probability that the overhaul cost is less than the overhaul cost limit,
is given by
(13.93)
The expected overhaul cost is given by
or
-
L1 = -
L1 (13.94)
2'
Using Eqs. (13.75), (13.93) and (13.94) the total expected future cost
for the unit of one year of age and two remaining years of operation is
given by
= rnin(Z1
s~(I)
L1
PI(L~) + A* [I - R ( L ~ ) ]
+S1(2) W L 1 ) + Sl(1)[1 - pl(L1)I) 9
(13.95)
Substituting the values of Sl(2) and Sl(1) from Eqs. (13.83) and
(13.85), respectively, into Eq. (13.95) yields
100
OVERHAUL POLICIES 509
or
S2(1) = n
I: {g + 200 (1 - k)
+ 75$} . (13.96)
- -1 x’2
2(100) 0
100
+75,
= 50 75, +
or
& ( l ) = $125. (13.98)
Hence, the optimum total expected future cost for the unit of an age
of one year and for two remaining years of operation is S2(1) = $125,
and the decision should be to overhaul regardless of the overhaul cost
estimate.
Stage 3, n = 3
Since the unit is initially new at this stage, when three years of
unit operation remain, the system can not be three years of age.
510 OPTIMAL OVERHAUL COST LIMITS
Therefore, the minimum total expected future cost, S3(3), should not
be considered.
Consider a unit of two years of age, or i = 2, and three remaining
years of unit operation, or n = 3. Using Eqs. (13.75), (13.86), (13.87),
(13.88) and (13.98) the total expected future cost is given by
~ ~ ( =2 min
) { ~ s2( L ~ ) + A * 11- PZ(L~)]
L2
+W)WL2) + Wl) [ I - P2(L2)1) ,
or
(13.99)
&(2) = - 752
300
+275 1 -- ( :5”o)
+ f 75,
or
S3(2) = $256.25. (13.102)
Consider a unit of one year of age, i = 1, and three remaining years
of operation, or n = 3. Using Eqs. (13.75), (13.93), (13.94), (13.92)
and (13.98) yields
s ~ ( I )= min(Z1
L1
PI(L~) + A* [ I - p1(~1)1
+S2(2) W L 1 ) + S2(1) (1- Pl(L1)I) ,
OVERHAUL POLICIES 511
or
S3(l)= min
L1
{2 + 275 (1 E)+
- L1 (1.9167)L I } . (13.103)
L1 = $134.03. ( 13.108)
512 OPTIMAL OVERHAUL COST LIMITS
Since the overhaul limit is greater than the maximum ovei..aul cost
for the unit of age of one year, then the unit should be overhauled
regardless of the cost estimate. From Eq. (13.75) the minimum total
expected future cost for the unit with an age of one year, and four
years of operation remaining, is given by
S4(1)=
-L1+ S3(2),
= 50 + 256.25,
or
S4(l)= $306.25. (13.109)
Table 13.7 gives the summary of the optimal overhaul cost limits for
all possible stages and unit ages. In the table “overhaul” means that
there is no cost limit and the unit should be overhauled regardless of
the estimated overhaul cost. Figure 13.4 gives the optimal paths for
the unit, which is initially new and is maintained over the five-year
period. The minimum total expected future cost over the five years of
system operation is $306.25 which corresponds to the state &(l) since
the initial acquisition cost is not included.
EXAMPLE 13-8
A system, initially one year of age, is to be in operation for the next
four years. At regular one-year intervals the system is inspected and
the overhaul cost estimated. If this estimate is less than the overhaul
cost limit the system is overhauled, otherwise it is replaced. The over-
haul cost is uniformly distributed. The ranges of the overhaul cost,
(a,@,for different system ages, along with the system salvage values
are given in Table 13.8. The cost of a new system is A* = $10,000.
OVERHAUL POLICIES 513
k 0 0
System age, i
1 2 3 4 5
Overhaul cost range,
(a,P ) (1,2) (2,4) (3,6) (5,W
Salvage value,
S(i) 3 2 0 0 0
514 OPTIMAL OWRHAUL COST LIMITS
Determine the optimum overhaul cost limits so that the total expected
future cost is minimized.
SOLUTION TO EXAMPLE 13-8
The system is to be in operation for four more years, therefore
the variable n, number of remaining years of operation, has the values
n = 0,1,... ,4. Since the overhaul/replace policy is to be applied at
a time when the system’s age is one y e a , the system’s age, i, has
the values i = 1,2, ,5. To determine the optimum overhaul cost
a
( 13.110)
or
- Li+a
Li = -. (13.111)
2
OVERHAUL POLICIES 515
Then,
0 for Li 5 CY,
- {9
~i = for (Y < ~i < p,
for ~i 2 p.
(13.1 12)
Stage 1, n = 1, i = 1,2,3,4
Using Eq. (13.80) the optimum overhaul cost limit for a system
age varying from i = 1 to 4 years yields
+
Li = A* - S ( i ) Sn-l(l)- Sn-l(i l ) , +
+
L1 = A* - S(1) So(1) - So(2),
= 10-3-3+2,
or
L1 = 6. (13.113)
L2 = A* - S(2) + - s0(3),
= 10-2+3-0,
or
L2 = 5. (13.114)
L3 +
= A* - S(3) So(1)- s0(4),
= 10-0-3-0,
or
L3 = 7, (1 3.115)
and
+
L4 = A* - S(4) So(1) - s0(5),
= 10-0-3-0,
or
L4 = 7. (13.116)
If i = 1, then the overhaul cost is uniformly distributed in the range
) (1,2). Since the optimum overhaul limit is L1 = 6, then the
( c Y , ~=
estimated overhaul cost is always less than L1 and an overhaul decision
516 OPTIMAL OVERHAUL COST LlMITS
or
P4(L4)= 0.75, (1 3.120)
and
-
L4 = -
7+4
2 ’
11
=-
2’
or
-
Lq = 5.5. (13.1211
OVERHAUL POLICIES 517
or
Sl(2)= 3. (13.123)
or
SI(3) = 4.5, (1 3.124)
and
-
&(4) = L4 p4(L4)+ [A* - s(4)] [I - p4(L4)]
+ So(5) P4(L4)+ So(1)[I - P4(L4)],
= (5.5)(0.75)+ (10 - 0)(1 - 0.75)
+(0)(0.75) - (3)(1 - 0.75),
= 4.125 + 2.5 - 0.75,
or
Si(4) = 5.875. (13.125)
Table 13.9 gives the summary of the calculaticjns for Stage 1.
518 OPTIMAL OVERHAUL COST LIMITS
Lj = A* - ~ ( +
i )Sn-1(1)- Sn-l(i + I),
L1 = A* - ~ ( 1 )+ Sl(1)- S1(2),
= 10 - 3 - 0.5 - 3,
or
L1 = 3.5. (13.126)
L2 +
= A* - ~ ( 2 ) Sl(1)- S1(3),
= 10 - 2 - 0.5 - 4.5,
or
L2 =3, ( 13.127)
and
L3 +
= A* - ~ ( 3 ) Sl(1)- s1(4),
= 10 - 0 - 0.5 - 5.875,
or
L3 = 3.625. (13.128)
OVERHAUL POLICIES 519
= -3 - 2
4-2'
or
(13.130)
and
-
L2 = -
3+2
2 3
or
-L2 = 2.5.
(13.131)
P) = (3,6)and L3 = 3.625, then
For i = 3, (a,
- 3.625 - 3
6-3 '
or
P3(L3) = 0.21, (13.132)
and
-L3 = -
L3+ff
2 '
- 3.625 +3
, 2 '
or
-
L3 = 3.313. (13.133)
520 OPTXMAL OVERHAUL COST LLMXTS
The minimum total expected future cost, Sz(i), for n = 2 and i = 1,2,3
is determined using Eq. (13.75) and appropriate values of Pj(Lj) and
the Zi calculated previously. Then,
&(l) = El Pl(L1) + [A* - S(l)l[l - S(L1)1
+ -
Sl(2) Pl(L1) + Sl(l)[l PdLl)],
+
= (1.5)(1) (10 - 3)(0)
+ +
(3)(1) (-0.5)(0),
or
S2(1) = 4.5. (13.134)
or
&(2) = 7.25, (13.135)
and
or
S2(3)= 9.434. (13.136)
Table 13.10 gives the summary of the calculations for n = 2 and i = 1,2
and 3.
Stage 3, n = 3, i = 1 , 2
Using Eq. (13.80) the optimum overhaul cost limit for the system
of ages i = 1 and 2 years, yields
+
Li = A' - S ( i ) Sn-l(l) - Sn-l(i + l),
+
L1 = A' - S(1) &(1) - S2(2),
+
= 10 - 3 4.5 - 7.25,
OVERHAUL POLICIES 521
or
L1 = 4.25, (13.137)
and
L2 = A* - S(2) + & ( I ) - &(3),
= 10 - 2 + 4.5 - 9.434,
or
L2 = 3.066. (13.138)
If i = 1, (cr,p) = (1,2)and L1 = 4.25, then,
Pl(L1) = 1, (13.139)
and
- a+p
L1 = -
2 ’
=- 2
1 +
2 ’
or
-
L1 = 1.5. (13.140)
If i = 2, (a,P) = (2,4)and L2 = 3.066, then,
- 3.066 - 2
4-2 ’
522 OPTIMAL OVERHAUL COST LIMITS
or
&(L2) = 0.533, (13.141)
and
-
L2 = -
L2+a
2 '
- 3.066 2 +
- 2 '
or
-L2 = 2.533. (13.142)
The minimum total expected future cost for n = 3 and i = 1,2 is
determined using Eq. (13.75) and appropriate values of Pi(Li) and
calculated previously. Then,
&(I) = zi pi(L1)4- [A* - s(l)][l- Pi(Li)]
+ S2(2) S(L1)+ s2(1)[1 - Pl(L1)1,
+
= (1.5)(1) (10- 3)(0)
+ +
(7.25)(1) (4.5)(0),
or
S3(l)= 8.725, (13.143)
and
or
S3(2) = 12.216. (13.144)
Table 13.11 gives the summary of calculations for n = 3, and i = 1
and 2.
Stage 4, n = 4, i = 1
Using Eq. (13.80) the optimum overhaul cost limit for the system
of age i = 1 year, yields
L1 = A* - S(l)+ &(l) - S3(2),
= 10 - 3 + 8.725 - 12.216,
OVERHAUL POLICIES 523
or
L1 = 3.509. (13.145)
Since the overhaul cost limit is greater than the maximum overhaul cost
for a system of one year of age, then the overhaul should be undertaken
regardless of the overhaul cost estimate. Then, PI(&)= 1 and
- a+P
L1 = -
2 ’
=- 2
1 +
2 ’
or
-
L1 = 1.5, (13.146)
and
or
S4(l)= 13.716. (13.147)
Hence the total expected future cost for the system of an age of one
year and four remaining years of operation is $13,716, which may be
achieved using the optimal overhaul cost limits given in Table 13.12.
The word “overhaul” means that the overhaul decision should be made
regardless of the overhaul cost estimate since it is always less than the
overhaul cost limit. Figure 13.5 gives the optimal paths for this system
which is initially one year old, and is to be maintained over the four-
year period with the optimal overhaul cost limits given in Table 13.12.
524 OPTIMAL OVERHAUL COST LIMITS
System
PROBLEMS
13-1. 1,000 units with the mean time to failure of rn = 1,000 hr, are
to be overhauled at regularly scheduled time intervals, To,equal
to 1,000 hours. Determine the following:
Ten percent of the parts are Weibullian with the following pa-
rameters:
P, = 1.5, ~7~ = 2,000 hr and 7, = 0 hr.
SE
sw *
h,,, = 10 fr/106 hr
1 hswQ = 50 fr/106 hr
. 6
h, = 100 fr/lO cycles
Fig. 13.6 - Standby system with one active and one standby
unit for Problem 13-4.
528 OVERHAUL POLICIES
= 0
hsw,
1 hWQ= 0 6
> = 50 fr/lO cycles
hswE
Fig. 13.7 - Standby system with one active and one standby
unit for Problem 13-5.
REFERENCES
SPARES PROVISIONING
(14.1)
where
- T I ) = estimate of the expected number of failures
NF(T~
for a life period (T2 - T I ) ,per part,
X(T) = failure rate function for a life period (2'2 - T l )
for that part,
and
(2'2 - 2'1) = part life period for which the spare parts pro-
visioning is to be determined.
Equation (14.1) applies to any type of reliability bathtub curve (RBTC),
with or without preventive and/or corrective maintenance, provided
the RBTC is representative of the situation for which the number of
spare parts is determined, the appropriate X(T) is used, and the total
number of identical parts in use remains essentially constant. Then,
the total number of expected spare parts is given by
NFT(T2 - = NT NF(T2 - (14.2)
533
534 SPARES PRO VISIONING
where
Nm(T2 - 2'1) = total number of expected spare parts in life
period (2'2 - T I ) ,
and
NT = total number of identical parts in use during life period
(T2 - Tl).
If NT varies with T, then
(14.3)
where
N = ( T ) = functional relationship for the total number of identical
parts in use during part life period (2'2 - TI).
N F T ( T-~2'1) can be determined only when, in addition t o X(T) which
is obt&ned from the RBTC, NT(T) is also known. N T ( T ) may be
determined either by monitoring such parts, or by the theory of main-
tainability and the preventive and corrective maintenance policy and
schedule used, as it will be presented in the next sections. If NT and
X(T) are both constant for life period (Tz- TI), then X(T) = X and a
good estimate of the spare parts is given by
N F ~ - (- ~ = NT x X x
T 2'1) (2'2 - Ti). (14.4)
To determine the number of spares at the desired confidence level use
the assumption that if the times to occurrence of an event are expo-
nentially distributed, having rate A, then the number of events in any
interval of length t is Poisson distributed with mean X t. The Poisson
distribution can be obtained from the following identity
e-= ez = 1
Expanding the term ex into the Taylor series expansion yields
Then,
2
e-x -t ie-x
X2
+ -e-z + . . . + 2" + . . . = 1.
2 n!
SPARES PROVISIONING 535
Each term represents a probability, and the sum of all these prob-
abilities is equal to 1. Hence, each term is a term of a p d f , and in this
case of the Poisson p d f .
The interpretation of this distribution is as follows: If x is taken to
be the expected, or average, number of occurrences of an event, then
e-= = probability that that event will not occur if x remains
constant,
xe-“ = probability that that event will occur exactly once,
X2
-e’” = probability that that event will occur exactly twice,
2!
and so on.
In reliability, the event of concern is failure, and the average number
of failures in time t is given by x = A t , when A is constant. Conse-
quently, e‘” = e - X * , which is R ( t ) for a single system having a constant
failure rate, A, gives the probability that no failure will occur in time
t. ze-” = Ate’” is the probability of exactly one failure occurring
in time t , [ x 2 / 2 ! ] e - ” = [ ( X t ) 2 / 2 ! ] e - x t is the probability of exactly two
failures occurring in time t , and so on.
Therefore, the probability of exactly k failures occurring in t is
given by
Rs = 0.98511.
2. The probability that one failure occurs during this mission is
given by
f(1) = Ate-",
f(1 ) = (150)( 100)e-(150)( lo-')( 100)9
f(1) = (0.015)(0.9851),
or
f (1) = 0.01477.
3. The probability that two failures occur during this mission is
given by
- A t 0 2
f(2) = e 2! '
-0.015 (0-015)2
f(2) = e 2 '
0.000225
f(2) = (0.9851) ,
or
f(2) = 0.00011,
a much lower probability than for one failure.
SPARES PROVISIONING 537
EXAMPLE 14-2
In a system there exists a very critical unit which requires spares
to attain a specified unit reliability of 99%,for a period of 250 hr. The
unit has an M T B F of 1,250 hr and exhibits a constant failure rate
characteristic.
How many spares would be required if the unit is easily accessible
and can be replaced almost immediately, by successfully plugging in an
identical spare when the functioning unit fails, to increase its reliability
from 81.87% to 99%?
SOLUTION TO EXAMPLE 14-2
The solution may be found by using the Poisson distribution and
answering the question, “HOWmany failures, equal to the number of
spares,.can be tolerated to attain the reliability of 99%?” or the ques-
tion, “How many standby (spare) units are required to attain the
reliability of 99%?” Therefore,
and
1
= (MTBF) (t) = (E)1
(250) = 0.2.
Consequently,
(0.2)2 + . . . + -
2 k!
538 SPARES PROVISIONING
This equation should be solved for the nearest integer, k, which satisfies
the equality; then the required number of spares is found t o be
k = 2.
With two spare units, the actual reliability is
Rs = F(2) = 0.99885,
whereas with one spare it would be
Rs = F( 1) = 0.98248.
Consequently, k = 2 is the right answer.
EXAMPLE 14-3
A battery has an expected failure rate of 0.01 fr/hr and is used 24
hr per day.
1. How many spares will be required for a three-calendar-month
period (assume 30 days per month) for a 95% probability (ad-
equacy, assurance, or confidence) that there will be a sufficient
number of spares?
2. What would the battery reliability be for a 24-hr period?
3. If a battery adequacy of 95% is required for a 24-hr period, how
many spares would be required for a three-calendar-month pe-
riod, assuming the replacement of the failed batteries is immedi-
ate?
4. Compare and discuss the results obtained in Cases 1 and 3.
and
X = 0.01 fr/hr.
Then,
-
N s p = (0.01)(2,160),
or
-
N s p = 21.6 failures.
For a 95% assurance of having sufficient spares
or
R ( t ) = 0.7866.
j=O J'
For N s = 1,
0.95 5 e-0.24(l t 0.24),
0.95 < 0.9754;
therefore, one spare will be required for a 24-hr operating period.
Extending this to a three-calendar-month period, or to 90 days,
yields
Ns = (1)(90) = 90 spares.
540 SPARES PROVISIONING
EXAMPLE 14-4
There are N = 100 identical units operating in the field, or in a
production facility. Each unit has a mean time t o failure, M T T F , of
500 hr. For a period of 6 months, during which each unit operates
cumulatively to = 600 hr, determine the following:
1. The average number of spare units required.
2. The number of spare units required at the 80%, 90%, 95% and
99% confidence levels.
SOLUTIONS TO EXAMPLE 1 4 4
or
-
N s = 120 spares.
(14.5)
L J
Actual
Confidence Number confidence
level, of level,
% spares %
80 129 80.8
90 134 90.5
95 138 95.2
99 146 99.1
or
(14.6)
The number of units that will fail, N F , and need to be spared would
be given by
NF = NT Q ( t ) = NT [l - R(t)]. (14.7)
The conditional reliability function, R ( T , t ) , may be used t o find
the number of units which should start the new mission, starting at
the age T , N s ( T ) , to end up with the desired number at the end of the
new mission o f t duration, Ns(T+t),and the number that should start
at age zero, Ns(O), to end up with desired number at the end of the
+
new mission, Ns(T t ) , and vice versa. By definition the conditional
reliability is given by
(14.8)
Also
(14.9)
From Eq.(14.9)the number of units which should start the new mission
at age T , N s ( T ), is given by
(14.10)
SPARES PRO VISIONING 545
Also, by definition,
Therefore, the number of units that should start at age zero, Ns(O),is
given by
(14.11)
EXAMPLE 14-5
The times-to-failure distribution of identical units is represented
well by the normal distribution with mean 9; = 43,679hr and a stan-
dard deviation of UT = 562 hr. Do the following:
1. Find the number of units which should start the new mission
of 300-hr duration, each unit having already accumulated 42,850
hr, t o end up with 100 such units at the end of the mission.
2. Find the number of units which should start at age zero to end
up with 100 such units at the end of the new mission.
where
Ns(T + t ) = 100 units.
From Eq. (14.8)
546 SPARES PROVISIONING
or
0.8267
R(T,t) = 0.9299 = 0.8890. (14.12)
+
Substitution of Ns(T t ) = 100 and R(T 4- t ) = 0.8267, found
in Case 1, gives the number of units needed at age zero t o end
up with 100 units at the end of the new mission; then,
100
Ns(0)= -
0.8267'
or
N s ( 0 ) = 121 units.
Consequently, not 100 but 121 units need t o be provided, or
so to speak 21 additional spares should have been on hand to
accommodate this situation.
(14.16)
+
Consequently, the total number of such units that will fail by (TI T )
hours of operation, under the condition that those that fail by TI hours
are replaced, is given by the sum of Eqs. (14.13),(14.14)and (14.16),
or
EXAMPLE 14-6
Identical types of bearings have a Weibull times-to-failure distribu-
tion with the following parameters:
,O = 2, 7 = 2,000 hr, and 7 = 0 hr.
Do the following:
1. If 100 of such bearings are operating in identical equipment at
the same application and operation stress level, how many will
survive if each operates Ti = 1,300hr at 675 rpm, and how many
will fail?
2. If the failed bearings are replaced by new ones and all of them
operate for T = 700 hr thereafter, how many of the fresh ones
will fail?
3. Of those that survived Tl hours, how many will fail during the
additional T hours of operation?
+
4. What is the total number of bearings that will fail by (TI 7')
hours of operation, given that 100 start at age zero and that
those that fail by Ti hours are replaced by fresh ones?
5. What is the total number of bearings that survive after (TI+ T )
hours when we follow the policy of replacing the failed ones by
Tlhours?
SPARES PROVISIONING 549
R ( T ~=) ~-[(TI-T)/~I’
1300 2
R(1,300 hr) = e-(m),
or
R( 1,300 hr) = 0.655406.
The number of bearings that will survive is
Ns(2’1) = Ns(l,300 hr) = NoR(T1) = 100 x 0.655406,
= 65.5406,
or
Ns(l,300 hr) % 65.
The number of such bearings that will fail is
NF-R(TI)= No Q(T1)= No [1 - R(Tl)],
= 100 X (1 - 0.655406),
= 34.4594,
or
N F - R ( ~ ,300 hr) % 35.
2. From Eq. (14.14)
NF-R(T) = No [I - R(T1)][1- & ( T ) ] ,
where
700 )2
R(T)=e-(T;ooo ,
or
R(700 hr) = 0.884706.
Then,
NF-R(T = 700 hr) = l O O ( 1 - 0.655406)(1- 0.884706),
= 100 (0.344594)(0.115294) = 3.97,
or
N ~ - ~ ( 7 0hr)0 2 4.
Therefore, four out of the fresh bearings will fail while operating
700 hr after replacement.
550 SPARES PROVISIONING
Then
0.367879
NF-NR( 1,300hr; 700 hr) = 65 (1 -
0.655406]'
= 65 x 0.438701,
or
or
N ~ - 7 - ( 2 , 0 0 0hr) = 35 + 4 + 29 = 68.
SPARES PROVISIONING 55 1
+
NS-R(2,000 hr) = 100[(0.344594)(0.884706) (0.367879)],
or
Ns-~(2,000hr) = 100 x 0.672743 = 67.27 S 67.
Therefore, a total of 67 of these bearings will survive.
The same answer can be obtained from
gives the mean time between both preventive replacements and cor-
rective failures, the total replacement rate, AT, is given by Eq. (9.22),
or
1
AT = = A, + A,.
J P R ( r )dr
As defined in Section 9.5 the total average number of spares over a
long period of operation of the equipment, say t hours, is given by
= (14.22)
ASP
JFR ( r ) dr’
The total number of spares at the confidence level, CL = 1 - a , is
obtained from Eq. (9.29) by solving for N s p which is the actual number
of spares, or
(14.23)
EXAMPLE 14-7
Consider Example 9-3 and the system of Fig. 9.12. Determine
the total average number of spares for a period of 10,000 hr and the
number of spares at a 95% confidence level.
SOLUTIONS TO EXAMPLE 14-7
A, = Q(Tp) - Q(1,OOO)
J ~ R ( Tdr) so 1,000
R(7) d ~ ’
or
A, = 0.000871 fr/hr.
SPARES PROVISIONING 553
j=o J.
N s p = 20 spares.
The normal distribution with mean of Fsp and standard devi-
ation of 6may be used to approximate the Poisson distri-
bution if the mean of the Poisson distribution is large enough,
say 10 or more. Since the Poisson distribution is discrete and
the normal distribution is continuous, the continuity correction
should be used as follows:
where
P ( X 5 b ) = !I)
(b + 0.5) - Fsp (14.24)
554 SPARES PROVISIONING
In this example
I- -
or
0.95 = @
+
( N S P 0.5) - 14.2
2, = 20.95 = 1.645 =
+
( N S P 0.5) - 14.2
3.768
Solving for N s p yields
Nsp = 19.898,
or
Nsp = 20 spares,
at the 95% confidence level.
where
and
f(s) = L [ f ( T ) ]= Laplace transform of f ( T ) .
For any given time period
where
(14.26)
and
r = t - j T;,
= 10,000 - (33)(300),
or
r = 100 hr.
Using Eq. (11.10) the expected nuniber of replacements in a T;
interval is given by
1 m
- 300 + -e-2,oo - -1
- (2)(200) 4 4’
or
H(T; = 300 hr) = 0.512 spares per T; = 300-hr interval.
Also
1
100 + -e-2,,,
H ( T = 100 hr) =
100
- -1
(2)(200) 4 4’
or
H(100) = 0.092 spares.
The total average number of spares for t = 10,000 hr is given by
-
N s p = 33 [l + 0.5121 + 0.092,
-
N s p = 49.988,
or
-
N s p = 50 spares.
SPARES PROVISIONING 557
CL = 95%
2. The number of total spares at the confidence level of
is obtained by using the normal approximation to the Poisson
distribution, then
+ 0.5) - 49.988
0.95 = @
1
(Nsp
l/m 1 9
or
1.645 =
(Nsp + 0.5) - 49.988
7.07
The value of N s p which represents the number of total spares is
then found by solving for N s p , and it yields
N s p = 61.12,
or
n-(kSs)
h= 1
where
HB(Tps),Hk(Tpk) = expected number of failures in inter-
vals (O,?',) and (O,Tpk)for s and k
groups of parts, respectively.
C,, Cc = preventive replacement cost per unit
and corrective replacement cost per
unit, respectively.
558 SPARES PROVISIONING
The spares requirement model for any given operating time period t ,
or the total expected number of spares for the ith part in Group s is
given by
-4
+
N s p s = ICs [I H;(T',)] t Ad(r),
i = 1,2,...,s,
where
j = 1,2,-*.,k,
where
and
= t - l < k T&.
rk
The expected number of spares for each Group h part is given by
--m
NSPh =K(t),
m = 1,2,-..,h.
The actual number of spares for the ith unit in Group s, for example, at
the confidence level CL = 1-cu can be determined by using Eq.(14.23),
or
i = 1,2,*.*,s.
Similarly, the equations for the actual number of spares for the units in
Group k and Group h can be obtained by using appropriate subscripts
and superscripts.
SPARES PROVISIONING 559
(14.29)
(14.30)
(14.31)
where
roo
560 SPARES PRO VISIONING
and
A TO
Tw = L i- R(T)dT. (14.32)
EXAMPLE 14-9
Given the units of Example 10-2 with a Weibull times-to-failure
p d f , determine the expected number of spares, or the expected number
of spare orders to be made in a period t = 1,000 hr of operation.
SOLUTION TO EXAMPLE 14-9
In Example 10-2 the total cost per unit time of operation given by
Eq. (14.31) is minimized and the optimum ordering schedule is found
to be T,* = 23.5 hr. Using Eq. (14.32) the expected cycle length is
found to be T,, = 29.463 hr. Then, the expected number of spares, or
the expected number of single-unit orders, in time period t = 1,000 hr
is
-
N s p = INT [-]
1,000
29.463 ’
or
-
N s p = 34 spares, or orders for spares.
where
(14.35)
(14.36)
is the expected number of less reliable spares for the units failing in
the intervd (T6,Tp).8 ( r ' )is the expected residual life of a unit having
age T6 up t o time Tpand is given by
(14.37)
(14.38)
EXAMPLE 14-10
Given the units with the gamma times-to-failure pdf of Example
10-3, determine the following:
1. The expected number of minimal repairs during t = 10,000 hr of
operation.
2. The expected number of spares during t = 10,000 hr of operation
and the total number of spares at a 95% confidence level.
Then,
or
j = 144, 10,000
= INT [F] 9
or
j = 47.
Then,
T = 1 - j T; = 10,000- (47)(210) = 130 hr.
The expected number of total minimal repairs in 10,000 hr of
operation is given by
Since
or
E INl[,-,,130j] = 0.149 repairs,
then, the expected number of total minimal repairs is given by
-
N , , = (47)(0.271) t 0.149,
or
-
ATrp = 12.886 repairs.
SPARES P R 0VISIONING 563
2. The expected residual life, E ( T ' ) ,in a cycle for the gamma pdf
is given by Eq. (10.41),or
With A' = 0.05 fr/hr, the expected number of spares per cycle
becomes
pi] = 0.05
E [N~[T,',
200+2oo185.5 [185.5
+2 (200)- e-210;01085.5 (210+ 2 (~oo)]]},
= 0.05 [24.5- (0.5188)(585.5- 539.67)],
= 0.05 (24.5- 23-78),
or
E "2[185.5, 21011 = 0.036.
Then, the expected number of spares during t = 10,000 hr of
operation is
-
NSP = i { E [NZ[T& t 1)*;]I 9
= 47 (0.036t l),
or
-
N s p = 48.692 spares.
To determine the total number of spares at a 95% confidence
level, the normal approximation t o the Poisson distribution yields
0.95 = @
+
( N S P 0.5) - 48.692
Then,
( N s p t 0.5) - 48.692
=
~0.95 1.645 =
G.978
564 SPARES PROVISIONING
-t /"
0
/&,(To- u ) f(. +- r') du
1 dr'.
SPARES PROVISIONING 565
+AT' h,(T,'
1 1.
- u ) f(u t r') du dr' (14.41)
EXAMPLE 14-11
Given the units with the gamma times-to-failure pdf of Example
11-3, determine the following:
1. The expected number of spares for the original units during t =
10,000hr of operation.
2. The total number of spares at a 95% confidence level.
3. The expected number of "less reliable" spares during t = 10,000
hr of operation.
4. The total number of spares at a 95% confidence level.
H,(T,') =
T,' + -2
- 1 T*
-R - -1
211 4 4'
With 7 = 200, hr it yields
or
H,(T,* = 40 hr) = 0.01758 spares per cycle.
566 SPARES PRO VISIONING
or
j = 33.
Then,
j=O J'
and for N S P = 2
0.95 5 e-0*598 (I t-
0.598 + -)
0.5982 = 0.977.
I! 2!
Hence,
N s p = 2 spares.
SPARES PROVISIONING 567
3. For the gamma pdf the mean number of "less reliable" spares
during the interval (T:, T,) may be found from Eq. (11.66),or
= 0.002
E[N~[T;,T;I]
- - e - E [3002 - (300)(40)
200
+200 [2 (300)- 40 t 2 (200)]]
200
or
1.645 =
+ -
( N s p ~ 0.5) 36.663
6.055
Solving for N s p yields
~
N s p =
~ 46.123,
or
N s p=
~ 47 spares.
(14.43)
( 14.44)
1is the mean time the system remains above the preventive replacement
age, or
(14.45)
(14.46)
EXAMPLE 14-12
Given is a component with the gamma times-to-failure pdf of Ex-
ample 12-1, with parameters
p = 2.5 and q = 40 hr.
The cost of a corrective replacement is C, = $100 and the cost of a
preventive replacement is Cp= $20. If the replacement opportunities
are exponentially distributed at the rate of u = 0.01 op/hr determine
the following:
1. The expected number of spares in t = 100 hr for the qqtimum
replacement age, T;, and the minimum total cost per unit time,
CT -
2. The total number of spares at a 95% confidence level.
3. Repeat Case 1 for the opportunity rate of u = 0.04 op/hr.
570 SPARES PRO VISIONING
1. For given C, = $100 and C, = $20 the ratio C,/C, = 0.2. Also,
for u = 0.01 op/hr, /3 = 2.5 and 9 = 40 hr the ratio, CR,of the
mean time to failure to the mean interval between replacement
opportunities is
Then, from Table 12.1 for C,/Cc = 0.2 and CR = 1, the optimum
replacement age is 2’; = 0.25 m hr, where m = ,6.q = (2.5)(40) =
100 hr. Consequently, 2’; = 25 hr. Using Eq. (14.43)the mean
number of failures, before the preventive replacement age, T;,is
reached, is given by
where R(T,*)
is given by
(14.47)
-- Ji5
R ( t ) dt
0.939991 ’
SPARES PROVISIONING 571
or
L = 26.092599 hr.
Using Eq. (14.45)the mean time the system remains above the
preventive replacement age, 1, is given by
I=
JrR(t + Tp) e-u dt
9
R(T,’)
-
- JF R(t t 25) e’’.’ dt
7
0.939991
or
1 = 48.015763 hr.
Then, the average number of spares for an operating period of
2 = 100 hr is given by Eq. (14.46),or
100
-
26.092599+ 48.015763
+
(0.063840 1) ,
or
-
N s p = 1.436 spares.
NSP - (T.P)j
c
j=O
e-Nsp ;I
J.
> 0.95,
-
j=O
CR = Q
- =p 7) = (2.5)(40)(0.04),
21
572 SPARES PRO VISIONING
or
Then, for the cost ratio Cp/Cc= 0.2 and CR = 4, from Table
12.1, the optimum replacement age is
T; = 0.37 m = (0.37) (100) = 37 hr.
Using Eq. (14.47) the reliability for the mission duration of T;
hours is
P-l T
R(37 hr) = Jrn 1 (2)
37 77 r(P> 77
e-T dT = 0.869486.
1=
JrR(t + 37) e-Oao4 * dt 3
R(37)
- JrR(t t 37)
- e-Oao4 * dt
9
0.869486
or
1 = 19.907018 hr.
Then, the average number of spares for an operating period of
t = 100 hr is given by Eq. (14.46), or
100
-
+
40.717859 19.907018
(0.150105 + l),
or
-
N s p = 1.897 spares.
SPARES PROVISIONING 573
NSP
c
j = O e-1*897
(1’897)3’ 2 0.95.
j!
- MTBF = 4,100 hr
hours is achieved at
175,OOO hours of
100 I I I I I
1 10 100 1,OOO 10,Ooo 100,Ooo 1,000,Ooo
Cumulative operating hours
Fig. 14.1 - Component M T B F growth projection for Example 14-13.
576 SPARES PROVISIONING
and
b = cumulative MTBF at T, = 1.0 [l, Vol. 2, pp.
438, 4431.
The values of a and b may be determined as follows:
Take the logarithm of Eq, (14.48), or
log[mi(T,)] = log b' + logT,. (14.49j
It may be seen that cr is the slope of the line represented by
Eq. (14.49) on log-log scales. Pick two arbitrary points on Fig.
14.1; for example,
mil(T41 = 1 hr) = 100 hr,
and
V L ; ~ (=
T ,175,000
~ hr) = 4,100 hr.
Then, the slope, a,is
log [mi2(Ta2= 175, OOO)] - log [Wl(Ta1 = I)]. (14.50)
cr=
log Ta2 - log Ta1
Substituting the previous values,into Eq. (14.50) yields
10g4,lOO - IOg 100
a= = 0.3076.
log 175,000 - log 1
SPARES PROVISIONING 577
(14.54)
or
(14.55)
where
X;(Ta)= instantaneous failure rate function.
The average number of spares from time zero t o the time of
175,000 accumulated hours of operation, when these components
reach maturity, or an M T B F of 4,100 hr, using Eqs. (14.51) and
(14.54), is give11 by
-
Nsp(0; 175,000 hr) = 1 175,000
1
1
loo T;0*3076d T a 3
~:1-0.30,6)1 175,000 ,
-
(1 - 0.3076)( 100) 0
1
- - (175, 000)(0.6924),
69.24
578 SPARES PROVISIONING
or
-
N s p ( 0 ; 175,000 hr) = 61.649.
According to the M T B F growth curve, the MTBF after 175,000
accumulated hours of operation should be 4,100 hr. So the av-
erage number of spares during the time interval 175,000 hr t o
1,411,200 hr, or until the end of the fifth calendar year is
-
Nsp(175,OOO hr; 1,411,200 hr) =
1,411,200 - 175,000
9
4,100
= 301.512 spares.
For the last two years, or from the end of the fifth year t o the
end of the seventh year, the average number of spares is
-
N S P (1,411,200 hr; 3,360,000 hr) =
3,360,000 - 1,411,200
7
4,100
or
-
NSp(1,411,200 hr; 3,360,000 hr) = 475.317 spares.
Therefore, the average number of spares, before the time of ma-
turity is 61.649, say 62; from the time of maturity up to the end
of the fifth year is 301.512, say 302; during the last two calendar
years is 475.317, say 476; and the total average number of spares
for seven calendar years is
-
Nsp +
= 61.649 301.512 + 475.317,
= 838.478 spares,
or
-
N s p = 839 spares.
1 ~:1-0.3076)133,600 ,
-
(1 - 0.3076)( 100) 0
1 T?924/ 33,600 7
- -69.24
0
SPARES PROVISIONING 579
or
-
N s p ( 0 ; 33,600hr) = 19.66 spares.
If we assume that the number of failures occurring in any time in-
terval is statistically independent of the number of failures in any
intervd which does not overlap the first interval, then the non-
homogeneous Poisson process may be applied. Using Eq. (14.5)
the upper, one-sided confidence limit on spares can be calculated
by choosing the smallest NSP-UI such that
pSp(t1; -
P"(t) 5 NSP-u11 = c
NSP-u1
j=O
t 4 j e--NSP(tl;f2)
j! 7
>CL=l-a. (14.56)
At the risk level of (Y = 5% the upper, one-sided confidence limit
for the first year is given by
Nsp-ul (19.66)j e-19.66
c
j=O j!
20.95.
or
(NSp-UI
1 = 0.95,
( N s p - u ~-I-0.5) - 19.66
= 1.645.
4.434
Solving for Nsp-uI yields
Nsp-uI = 26.454 spares.
Rounding up to the nearest integer yields
N s p - u ~= 27 spares.
For the two-sided confidence limits on the spares, round out to
the next higher integer value of NsP-L:! such that
(14.57)
580 SPARES PRO VISIONING
j=O j!
,
a
3 1-- (14.58)
2'
Then, N s p - ~ zand N s p - u z are the two-sided, lower and upper
confidence limits on the spares, respectively.
At the risk level of a = 5% the lower, two-sided confidence limit
on the spares for the first year is given by
NSP-LZ
0.05
C (1g;6)j ,-19.66 5 2 9
j=O
or
or
-
( N s p - , ~ 0.5) - 19.66 = -1.96.
4.434
Solving for N s p - ~ zyields
N S P - L ~= 11.47 spares,
or
N S P - L ~= 12 spares.
At the risk level of cr = 5% the upper, two-sided confidence limit
on the spares for the first year is given by
or
168,000
-
1
100
Ta-Oa307= dTa
504,000 - 175,000
t 7
4,100
175,000
-
-- 0.6924
+ 80.244,
= 1.718 t 80.244,
or
-
N s p ( 168,000 hr; 504,000 hr) = 81.962 spares.
At the risk level of a = 5% the upper, one-sided confidence limit
on the spares for the third year is given by
NSP-UI
(81*962)j
,-81.962
10.95.
C
j=O j!
582 SPARES PROVISIONING
or
(NSP-UI
1
(NSp-Ui t 0.5) - 81.962 = 1.645.
9.053
Solving for Nsp-UI yields
Nsp-ul = 96.354 spares,
or
Nsp-ul = 97 spares.
At t e risk level of Q = 5% the rawer, two-sided confi-ace limit
on the spares for the third year and using the normal approxi-
mation to the Poisson pdf yields
(Nsp-~z- 0.5) - 81.9621
= 0.025,
or
-
(Nsp-~z- 0.5) 81.962 = -1.96.
9.053
Solving for Nsp-~zyields
Nsp-~z= 64.718 spares,
or
N S P - L ~= 65 spares.
At the risk level of Q = 5% the upper, two-sided confidence limit
on the spares for the third year and using the normal approxi-
mation to the Poisson pdf yields
+ 0.5) - 81.962 = 0.975,
(NsP-u~
or
+ 0.5) - 81.962 = 1.96.
(NsP-u~
9.053
Solving for N S P - U ~yields
Nsp-uz = 99.206 spares,
SPARES PROVISIONING 583
or
Nsp-uz = 100 spares.
According t o the M T B F growth curve, the M T B F after 175,000
accumulated hours of operation should be a t the constant value
of 4,100 hr. Consequently, the average number of spares for the
fourth and subsequent years can be calculated lrom
For example, the average number of spares €or the fourth year is
given by
-
Nsp(504,OOO hr; 1,176,000 hr) =
1,176,000 - 504,000
9
4,100
or
-
Nsp(504,OOO hr; 1,176,000 hr) = 163.9 spares.
The upper, one-sided and both the lower and upper, two-sided
confidence limits on the number of spares, at a given risk level,
can be calculated using Eqs. (14.56), (14.57) and (14.58), as il-
lustrated for the first and third year.
The upper, one-sided confidence limits on the number of spares,
a t various risk levels, are given in Table 14.4 and both lower
and upper, two-sided confidence limits, at various risk levels, are
given in Table 14.5.
5 57.366 59 61 64 67
~~
70’ 75 - 77 81
’ 6 229.463 233 237 242 249 254 265 268 276
7 245.a50 250 254 259 266 272 282 286 294
1 1 1
nu?,
bly of Example 14-14.
AIn;fer A;,
fr/106 hr
102
I ci,
cost/unit,
3
500
500
Ni 7
number of units
in the assembly
7
11
500 7
500 5
500 2
500 1
-
N s - E = 8.45,
and
-
Ns-F = 4.80.
The optimum kit of amplifiers is determined using a form of the marginal
assurance as follows:
or
N:+l
C
x=o
where
is the Poisson term, and N;' is the number of a specific amplifier in the
optimum kit
SPARES P R 0 VISIONING 589
i=l r = O
C ( N * )= c c i Ni’.
p* = -1 0.997007
500 l o g l o 0.995340’
or
y* = 1.454 x loe6
1
- log1
c
2
x=o
This yields N2+ = 41. Similarly the number of the remaining amplifiers
in the kit are determined yielding the optimum kit
.V’ = (50,41,38,16,17,11),
Next Page
(15.1)
635
636 DISTRIBUTIONAL TEST A N D REPAIR TIMES
0.4
tl = ll.3hr.
0.1
08
At station No. 3
r, = 1.9hr.
02
At station No.4
' t
0' 2 4 6 t 8 10 12 14 16 18 20
At station No. 5
4 = 0.3hr.
1.o
1.0 2.0
0.10
At station No.6
la = 9 2 hr.
0.02
1 N ( p = 10;a= 1)
2 N ( p = 20;a= a)
3 G(P = 9 ; =~6)
4 G(P = 1 0 ; =
~ 1)
5 E(X = 5 )
6 x2(u = 10)
I
N = normal pdf,
G = gamma pdf,
E = exponential pdf,
x2 = chi-square pdf,
p = mean,
u = standard deviation,
,B = shape parameter,
7 = scale parameter,
u = degrees of freedom.
638 DISTRIBUTIONAL TEST AND REPAIR TIMES
a; = c
n=6
u;i. (15.2)
Station number
1 2 3 4 5 6
5 10 20 1.50 10 0.20 10
1 2 0.25 10 0.04 20
and
P ( t I 6 5 . 2 hr) = 99%,
where
p { ( t ) = p i ( z ) = first moment about zero,
= h(tl, t 2 , * * * ,431,
640 DISTRIBUTIONAL TEST AND REPAIR TIMES
and
8%
- d2h
means - evaluated at the mean value of all
at; at; variables involved, or of the t’s.
Most books only give the first term of Eq. (15.3) and consider the
accuracy sufficient. The first term only provides an exact result for
our problem because a l l second and higher order partial derivatives
are zero. Equation (15.3) contains only up to second order terms of a
multivariate infinite Taylor’s series. Hence, it is only approximate in
the general case. Also,
p2(1) = V A R ( z )= U: = pi - (pi)’,
where
p2(z) = second moment about the mean.
The Taylor’s series expansion for the variance of the system’s perfor-
mance, with uncorrelated variables and retaining up to third order
terms, is given by
where p ~ ( t iis) the third central moment for the ith variate. Most texts
use only the first term, which may be a satisfactory approximation.
The third central moment is given by
(15.5)
retaining only the lowest-order non-zero term, and the fourth central
moment is given by
2 2 [(s)2
(s)2
+ 6 i L j + l j=1 dtj at;
1
V A R ( t j ) V A R ( t ; ) . (15.6)
HOW TO APPLY 641
(15.9)
and
These equations are in the most convenient form for calculation, if the
raw data are available. If the pdf's of the data are given then,
Cc3(t) = P i -
3 $2 r; t 2 MI3. (15.11)
It is related to the coefficient of skewness, as, which is given by
(15.12)
Also,
P40) = CL: - 4 Pi Cci i-6 P i
(CL:)z 3 (r9" - (15.13)
It is related t o the coefficient of kurtosis, a d , which is given by
(15.14)
and
Pk(t) =q t
00
- P‘llC’
= (t - p ’ l ) k f ( t )tit; for k = 1,2,3,4,... (15.16)
= fth central moment,
= f t h moment about mean.
is1
Then,
and
Station number
1 2 3 4 5 6
Mean 10 20 1.50 10 0.20 10
Variance 1 2 0.25 10 0.04 20
1
~ 3 ( t i 0 0 0.08 20 0.02 80
P4(ti) 3 12 0.23 360 0.01 1,680
6 6
1. Find
h
1.1 - i = t .
1.2 - &= = &f = Jm.
1.3 - = hi.
1.4 - pz = 64.
2. Find in Tables 15.2 thru 15.15 the standardized percentile z& for
a chosen (Y using 81 and k.
3. Calculate the estimated 100 a% percentile from
z 4- 2; 6,
or
t , = t + %; &,
n h
and
P (t 5. &.go) = 0.90.
In this case
n
t0.W
c'
= t 4- .& &t = 51.7 + (1.32) (5.78),
or
A
t0.95 = 7 d . 9 5 bt,
+
= 51.7 (1.77)(5.78),
or
h
to.95 = 62.0 hr,
where zk,g5is found in Table 15.4,
HOW TO APPLY 645
and
P (1 5 ib.99) = 0.99,
+
h
h
to.99 = 3 z;.gg 4,
+
= 51.7 (2.71)(5.78),
or
-t0.W = 67.4,
h
EXAMPLE 15-1
Given P; = 3.49 and pi = 0.27, find the upper 10% percentage
point, a = 0.90, z' d u e .
TABLE 15.2
PERCENTAGE POINTS OF PEARSON CURVES
Lower 10% p o i n t s of t h e standardized d e v i a t e ( x
I
- [ a =0.10) - All s i g n s negative.
- ~)/LI;
-
0.00 0.01
-
0.03 0.05 0.10
-0.70
1.8
2.0
1.3856
1.3741
1.3491
1.3475
1.3189
1.3265 1.3104 1.2747 1.2394 I I I I I
2.2
2.4
2.6
2.8
3.0
1.3545
1.3339
1.3144
1.2970
1.2816
1.3342
1.3176
1.3009
1.2854
1.2714
1.3188
1.3057
1.2913
1.2773
1.2643
1.3074
1.2972
1.2846
1.2818
1.2596
1.2828
1.2794
1.2710
1.2609
1.2505
1.2589
1.2625
1.2585
1.2512
1.2427
1.2342
1.2454
1.2462
1.2419
1.2354
1.2059
1.2183
1.2214
1.2197
1.1839
1.1965
1.2012
I I 1.1655
1.1781
1.1278
1.1501 1.1158
3.2 1.268 1.259 1.2524 1.2481 1.2406 1.2341 1.2280 1.2155 1.2012 1.1837 1.1625 1.1366
3.4 1.256 1.248 1.2421 1.2381 1.2309 1.2259 1.2208 1.2102 1.2007 1.1851 1.1687 I . 1488
3.6 1.245 1.238 1.2329 1.2293 1.2229 1.2179 1.2135 1.2046 1.1951 1.1840 1.1710 1.1554
3.8 1.236 1.229 1.2238 1.2205 1.2151 1.2108 1.2069 1.1990 1.1907 1.1816 1.1710 1.1585
4.0 1.227 1.221 1.2166 1.2136 1.2080 1.2038 1.2003 1.1935 1.1861 1.1782 1.1695 1.1593
4.2 1.220 1.213 1.2093 1.2066 1.2012 1.1976 1.1943 1.1878 1.1817 1.1753 1.1675 1.1586
4.4 1.213 1.207 1.2025 1.1998 1.1952 1.1916 1.1887 1.1834 1.1777 1.1714 1.1649 1.1574
4.6 1.207 1.201 1.1973 1.1948 1.1902 1.1866 1.1817 1.1783 1.1729 1.1675 1.1616 1.1552
4.8 1.201 1.196 1.1915 1.1890 1.1852 1.1817 i.178C 1.1737 1.1692 1.1645 1.1593 1.1535
5.0 1.196 1.191 1.1873 1.1848 1.1804 1.1775 1.1747 1.1697 1.1652 1.1606 1.1560 1.1508
5.2 1.191 1.186 1.1823 1.1800 1.1764 1.1735 1.1707 1.1656 1.1615 1.1576 1.1530 I . 1480
5.4 1.187 1.182 1.1783 1.1760 1.1724 1.1695 1.1666 1.1621 1.1586 1.1546 1.1499 1.1453
5.6 1.183 1.178 1.1743 1.1720 1.1684 1.1655 1.1631 1.1592 1.1555 1.1516 1.1477 1.1433
5.8 1.179 1.174 1.1710 1.1691 .l. 1654 1.1625 1.1601 1.1562 1.1525 1.1486 1.1446 1.1406
6.0 1.176 1.171 1.1680 1.1661 1.1624 1.1595 1.1571 1.1532 1.1494 I. 1457 1.1424 1.1386
6.2 1.172 1.168 1.1651 1.1631 1.1594 1.1565 1.1541 1.1501 1.1468 1.1437 1.1404 1.1366
6.4 1.169 1.165 1.1621 1.1601 1.1563 1.1535 1.1516 1.1482 1.1444 1.1407 1.1373 1.1339
-
6.6 1.167 1.162 1.1590 1.1573 1.1544 1.1515 I 1.1491 I 1.1451 I 1.1418 I 1.1387 I 1.1353 -
1.1323
'Prepared by Mr. Raul Krivoy. Based on "Table of percentage p o i n t s of Pearson curves, for given 6.and 8 2 . expressed
i n standard measure." Compiled by N . L. Johnson, E r i c Nixon and L1. E . A m o s , with an introduction by E. S. Pearson,
Bioaetrika. Vol. 50, Nos. 3 and 4, pp. 459-498. 1963.
PERCENTAGE POINTS OF PEkRSON CURVES
Lower 10%p oints of the standardized d e v i a t e (x' - p)/o; ( a =0. 10) - A l l signs negative*
- ~-
3.0 1.0748
3.2 1.1048 1.0674 1.0245
3.4 1.1241 1.0951 1.0606
3.6 1.1360 1.1133 1.0858 1.0538 1.0173
3.8 1.1430 1.1250 1.1029 1.0774 1.0474
4.0 1.1467 1.1321 1.1143 1.0937 1.0692 1.0411 1.0093
4.2 1.1482 1.1363 1.1216 1.1049 1.0848 1.0617 1.0352
4.4 1.1484 1.1383 1.1261 1.1122 1.0956 1.0766 1.0545 1.0292 1.0008
4.6 1.1478 1.1392 1.1287 1.1170 1.1031 1.0873 1.0688 1.0476 1.0236
4.8 1.1467 1.1391 1.1300 1.1200 1.1082 1.0951 1.0795 1.0617 1.0412 1.0181 0 .9 9 2 3
5.0 1.1447 1.1379 1.130 1.1215 1.1115 1.1002 1.0868 1.0717 1.0544 1.0347 1.0126
5.2 1.1426 1.1367 1.130 1.1225 1.1137 1.1038 1.0923 1.0793 1.0644 1.0475 1.0286
5.4 1.1405 1.1351 1.129 1.1224 1.1147 1.1062 1.0961 1.0849 1.0720 1.0574 1.0411
5.6 1.1385 1.1335 1.128 1.1224 1.1157 1.1080 1.0989 1.0889 1.0777 1.0650 1. 0508
5.8 1.1364 1.1320 1.127 1.1218 1.1157 1.1087 1.1007 1.0919 1.0820 1.0709 1.0585
6.0 1.1344 1.1305 1.126 1.1206 1.1146 1.1087 1.1019 1.0943 1.0853 1.0753 1.0643
6.2 1.1324 1.1283 1.124 1,1195 1.1145 1.1091 1.1028 1.0957 1.0876 1.0786 1.0689
6.4 1.1304 1.1269 1.123 1.1185 1.1135 1.1083 1.1025 1.0962 1.0891 1.0812 1.0725
6.6 1.1293 1.1259 1.122 1.1175 1.1125 1.1076 1.1022 1.0966 1.0903 1.0833 1.0754
'Prepared by Mr. Raul Krivoy, Based on "Table of percentage p o i n t s of Pearson curves, for given 6,and
82, expressed i n standard measure," Compiled by N. L. Johnson, Eric Nixon and D. E . Amos, with an
introduction by E. S. Pearson, Biometrika, Vol. 50, Nos. 3 and 4 , pp. 459-498, 1963.
TABLE 15.3
PERCENTAGE FOINTS OF PEARSON CURVES
- (a= 0.90)'
-
l e p e r 10% p o i n t s of the standardized d e v i a t e (x'
-
~)/IJ;
-
2
-q 0.00 0.01 0.03 0.05 0.10 0.15 0.20
-
0.30 0.40 0.50
--
0.60 0.70
'Prepared hy Flr. Raul Krivoy. Based on "Table o f percentage points of Pearson curves, for given 6,and B 2 ,
expressed in standard measure," Compiled by N. L. Johnson, Eric Nixon and D. E. Amos. w i t h an introduction by
E. S . I'earson. Bioaetrika. V o l . SO, Nos. 3 and 4, pp. 459-498, 1963.
TABLE 15.3 - Continued.
PERCENIACE POINTS OF PEAISON CURVES
I
Upper 10% p o i n t s of t h e standardized d e v i a t e ( x - V)/CI; ( a =0 . 9 0 ) *
~
0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 1.60 1.70 1.80
r
3.0 1.5170
3.2 1.4715 1.5003 1.5344
3.4 1.4346 1.4588 1.4867
3.6 1.4042 1.42.48 I . 4482 1.4718 1.49J4
3.8 1.3788 1.3967 1.4166 1.4367 1.4598
4.0 I . 3572 1.3730 -
1 3903 1.4078 1.4273 1.4470 1.4695
4.2 1.3388 1.3528 1.3680 1.3834 1.4003 1.4174 1.4364
4.4 1.3227 1.3354 1.3490 1.3626 1.3775 1.3924 1.4089 1.4258 1.4441
4.6 1.3088 1.3203 1.3324 1.3446 1.3578 1.3712 1.3856 1.4004 1.4162
4.8 1.2960 1.3066 1.3179 1.3290 1.3409 I . 3528 1.3656 1.3787 1.3927 1.4076 1.4226
5.0 1.2850 1.2948 1.305 1.3152 1.3260 1.3368 1.3483 1.3600 1.3724 1.3855 1.3987
5.2 1.2751 I . 2844 1.294 1.3033 1.3129 1.3227 1.3331 1.3438 1.3548 1.3665 1.3783
5.4 1.2661 1.2749 1.284 1.2925 1.3013 1.3103 1.3198 I . 3294 1.3395 1.3500 1.3606
5.6 1.2582 1.2659 1.274 1.2824 1.2911 1.2994 1.3080 1.3167 1.3259 1.3354 1.3450
5.8 1.2513 1.2585 1.266 1.2735 I . 2812 1.2890 1.2972 1.3054 1.3138 1.3225 1.3313
6.0 1 - 2443 1.2515 1.259 1.2661 1.2733 1.2805 1.2880 1.2954 1.3030 1.3110 1.3190
6.2 1.2383 1.2451 1.252 1.2581 1.2652 1.2750 1.2844 1.2910 1.2958 1.3006 1.3076
6.4 1.2334 1.2391 1.245 1.2515 1.2583 1.2648 1.2714 1,2779 1.2845 1.2913 1.2982
6.6 1.2274 1.2337 1.240 1.2457 1.2514 1.2573 1.2635 1.2697 1.2761 1.2826 1.2892
"I'repared by Mr. Raul Krivoy, Based on "Table o f percentage points of Peerson c u r v e s , for given 6,and
8 2 , expressed in standard measure," Compiled by N . L. Johnson, Eric Nixon and D.E. Amos, with an
introduction by E. S. Pearson. Biometrika, Vol. 5 0 , Nos. 3 and 4 , pp. 459-498, 1963.
I ' I
I I ! I
n
I ' I
.I - I 1
650
e"
0
E
0
II I
6 6
I
I '
I
c:
U
6
,3 1 I
651
652 DlSTRTB UTIONAL T E S T A N D R E P A I R T I M E S
TABLE 15.8
P E R C W A G E POINTS OF P U R S O S CURVES
Lower 5% poinu of the rt.ndmiircd devhte It. -
d/8, (a 0.05). Note that for pxitive rkeunma,
k .H > 0. the d e v r t a in thL table are ncytive.
-
\
61
7
0.00 I I 0.01 0.03 I I 0.05 0.10 I 0.15 I 0.20 I 0.30 I I 1
0.40 0.50 0.60 10.70
1 I I I I 1 I I I I I
1.2 1.1547
1.4 1.3191
1.6 1.4639
1.0899
1.2450
1.3899
1.m.5 0.9954
1.lm 1.1368
1.3270 1.2794
1.04i7 0.9Z’l 0.9170
1.1839 1.1055 1.0380 0.9254 0 8331
j
1.8 1.55% 1.4936 1.4364 1.3880 1.30i8 1.2312 1.1614 10389 0.936 0.849i 0 3 4 6
2.0 1.6108 1.5156 1.5097 1.4746 1 . W 7 1.3342 1.2710 I 1316 1 ot33 0.9133 0 ~ ( 0 . 7 9 3 4
2.2 1.6361
2.4 1. M i
1.5893
1.6064
1.5513 1.5226
1.5743 1.5504
I 4 6 2 2 1.40i4 1.3544 1.2494 1 1463 1.0485 0.9393 0 8806
1.5006 1.4559 1 4124 1 3247 1.2342 1.1427 1.0534 ! O . 9699
I
2.6 1.6495 1.6141 1.5664 1.5659 1.5241 l.4S70 1.4511 1 3iR6 I30?5 1.2213 I 1397’1.05i6
2.8 1.5463 1.6165 1.5921 1.5742 1 . W 2 1 jo67 I 4766 1.4162 I.U?61.2845 1.212111.1367
3.0 1.6449 1.8160 1 . W 1.5781 I 5464 1.5192 1.4933 1.44?? I 3887 1.3313 1 269311.2030
3.2 1.5264 1.5043 1 460? 1 4145 1.36.5.3 1 3 1 3 0 j l . w 8
3.4 1 I;?: I 4331 1.3912 1,3460 1.2969
3.6 I 4466 1.4100 1.3i09 1.3283
3.8 1 4241 1.3900 1.3528
4.0 I I 1 . 4 W 1.3716
4.2 , I , l 386?
I I l i I I I I I I I I
- -
1
0.80 0.90 1.00
-1.10 1.20 1.30
-
1.W
=P-
2.2
2.4
2.6
2.8
3.0
3.2
0.8107
0.8944
0.9792
1.060s
1.1337
1,1947
0.74M
0.8267
0.9068
0.9672
1.0632
1.1304
0.7659 1 71WJ
o m i 2 I . 7820
0.9179 J n w i
0.OoJR I . 927;
1.DbM 5.m3
I 7252 0,6188
1 i966 0. i440
1 . w 3 0.8100
1 9362 0 8769
1
0 6956
0.im
0 82??
0 gsOg
0 7110
0 7716
I 66i2 I
1.1251 0 M20,0 M I 9
I
3.4 1.213i 1.1668 1.1m1.0653 1.0036 0.9433 OW63 om? 1.7836 0 7380 ! 0 6957
3.6 1.2824 1.2326 1.1m 1.1232 1.W? 10069 0 9496 0 8946 1.8427 0 i946 10 7498
3.8 1.3127 1.2692 1.pP 1.1720 I 1192 1 M 4 6 1 0093 0 9546 1.9017 0 Bil4 I 0 8046
4.0 1.3363 ,39821.2569 1.2124 1.1550 1.1151 0634 I 0 1 0 9 J.958i 0 9013 10 8591
4.2 1.3sso ,32121.ZM 1.- 12031 11581 1108 1 0617 1.0117 0 9618 I 0 0129
1.1064 I .om 1 0120 0 9e42
4.4
4.6
1.3688 ,3200 1.3072 1.2122
.35u 1.3254 1.-
12346 11943
1 . 2 m 1.2244
1514
.I857 1.1448 1.1018 1 0572 1 0117 I
4.a 1.5103 1.3121 1.2819 1.2494 ,2145 1.1775 1.1363 10971 1 O W
b.0 1.3268 1.299: 1.2701 ,2387 1.2052 1.1695 1 1318 1 0924
b.2 1.3142 1.287e ,2591 1.22% i . i m i 1 18181 I 1255
5.4 1.302: .2762 1.2484 1.218I 1 18751 1 . 1 a
5.6 l . m 1.2653 1.W I 20921 1.1700
b.8 1.3030 1.2791 I.%$ 122Sj,12045
6.0
6.2
1.2920 1.2691 12448 1 2 1 0 0
I .a11 12589 l a 1 I
6.4 1 2111’ 12490
I 1 2612
--- -
6.6
- .
1 -
HOW TO APPLY 653
TABLE 15.9
\01
0.00 0.01 0.03 0.05 0.10 0.15 0 3 0 . 0.30 0.40 0.50 0.60 0.70
:I
4.2
I !
8330 1 8618 1 8911
1 816011 6429 18698
' 1 8258 1 8508
I 18338
- --
- .oo
- 1 1.10 1.20 1.30 1.40
I
1.50 1.60
-
1.70
-
1.80
?O
? ?
1 7453 1 0 8 0 3
1 9377 1 8596 18221 1 1532
I
24
2 6
? 0 3 3 ?a%? 0119
2 o m 2 0 9 2 ? 100;
1.9614 1.9924 1.8210
?.loz? 2 . 0 i 9 2 ?.02W
I
1.9s30' 1.8847
29 ?CUM 2 0 7 4 3 2.1100 ?.I402 1.1602 2.1632 ?.I415 2.0910 2,0197 1 9451
3 0 2 m 3 ?oMI ? 0859 2.1249 2.1619 2.1935 2.2152 2.poO ?.1997 2 1499 2.o n ?
3.2 1 976i ? 0136 2.0519 2.091? ?.1314 2.1715 2.2096 2.2429 2.2665 ? 1;3? 2 254'
3 4 1 9476 1 9816 2.0170 ?.a510 ? 0926 2 1325 2.1736 2.2147 ? 2543 2 1 9 3 ? 3146
3.6 1 9111 1 9523 l . W i 2 0 1 8 5 2 0541 2 0913 2.1304 2.1711 2 '2130 ? 25% 2 2965
3.8 1 8 9 7 3 19259 1.9535 1 . 9 W 2.0187 2.052e 2.0881 2.1261 2 . l W ? 3 i 3 2 3503
4.0 1 8 7 6 3 1 W26 1 9 2 9 6 1.957'7 1.9871 2 0179 2.0503 2 0846 2.1207 ? 1589 2 1993
4.2 1 B5i3 I BBli I W6i 1.9324 1.95Y? 1.9872 2 0186 2 . M i 5 2.0801 2 114f 2 1511
4.4 1 &07 1 M31 1.8861 1.9100 1.9%5 1 . m 1 1.9868 2.0148 ?.M43 2 07s 2 la?
4.6 1 8879 1.8899 1.9126 1.9361 1.m 1 . w 1 2 0 1 s ? 046 2 0704
4.8 1.8517 1.8722 1.8932 1.9148 1.9374 1.0608 1 9852 2 Oloi 2.0374
so 18562 1.8758 1.8859 1.91661 1.0383 1 9607 1 W C 2.0084
5.2 1.6602 1.87sc 1.8983 l.OI& 19389 19606 19828
5.1
6.6
5.11
6.0
I I 1.8817 1.9003 1.9191 1 939t
1.8670 1.m 1.9023 1 *
1.8531, 1.8699 1.6367 1 OM[
! 1.8561 1,8725 1888;
1 .wM
1 we
1.9217
19054
6.2 1 8741 1.8906
6.4 1WZ 1 .an1
6.6 1 m 7
-
654 DISTRTBUTIONAL TEST AND REPAIR TIMES
TABLE 15.10
' 0.W 0.01 0.03 0.05 0.10 0.15 0.20 0.30 0.10 0.50 0.60 0.70
i l l
1.6132 1.5548 1.4922
1 5883 1 5 3 1 3
1.5840
4.2
I 1 I I I I I , I 1 1
--1.10 I .20
-
1.80
2.2
2.4
2.6
2.8
3.0
3.2
3.4
0.8107
n
17484
) S2G D i W
894.1
0 9811 1 9 0 i 2 0 8412
I MOO 39903 n 9189
1.1373 I . O i l 7 D 9 9 8 3
I 2386 I 1 5 6 8 1 0786
1.3112 I ,2329 1 1 m
0.7loY
0 7820
0.0545
0. m 2
1 ,0055
tzsz
D 6788
7966 0 7440 0 6956
8666 0 8100 0 7 5 M
,9383 0 87i6 0 8222
.OlI5 0 9467 0 8874
1.0815
TT
I7110
I7716
I8332
0 6672
0 7251 0 6620 0.6419
0 7&36 0 i380 0 695i
0 8433 0 7946 0.7491)
3.6 1.33.9 1.3009 1.2252 1.1% .083i 1 0 1 6 6 0 9540 18982
3.8 1 4272 1.3600 1 2911 1.2213 1524 1 0851 1 0207 ) 9602 0 WO 0 8524 n ma
4.0 1.4722 1.4106 1.3470 1.2818 2158 1 1 5 0 1 l o s s 0240 09655 0 9 1 0 9 0.8603
4.2 1.5100 1 453: 1.3952 1.3348 2720 1 2100 1 1474 loss 10264 09699 0.9169
4.4 1.5420 1.4900 14366 .3231 1 2 8 4 0 1 2 M l
1 .ssoci ilU3 10853 l m s l 0.9736
4.0 I . 4721 ,3611 1 3 1 1 8 1 2%
1.42oc I 1982 I 1 4 M 1 W U 1.0293
4.8 1.- 1.4549,105s 1 3 5 4 1 1 3 0 1 2 I 2470 1 1922 1 1372 1 .m
5.0 1.a7 .43a 1 SWS 1.3417 I2908 1.238f 1 1 8 8 1 1.1333
5.2 ,487619 1.1235 1 3773 I3297 12808 1- 1.1800
6.4 1 4519 1 (089 I3643 13183 1 ?il( 1 . 2 2 2 i
5.6 I 4366 13648 1351: 1307: 1.2612
5.8 1.4611 14220 13814 1339: 1.2959
6.0 14460 1 1 0 7 0 1 w I ,3177
6.2 1 4315 1394: 1.3559
0.4
6.6
- - I l1 417'
1.3812
1.4041
-
HOW TO APPLY 655
TABLE 15.11
PEICEKTAGE POINTS O F P U R S O N CURVES
Uppar 2.5% poiDu d the sundudiied v u k u (z. L)/., (0 -
0.875). -
a03 om 0.10 0.1s 0.20 0.30 0 . ~ 0 as0 0.60 0.70
3S.8
.6 I I
-
0.80 0.90 Im 1.10
-
1.20 1.30 1.40 1.50 I 1.60
2
2
2
2
2
3
0
2
4
t
s
0
1.7455 1 m -3
I @M4 1 UHI'J 1.8??3
2.1596 2 109s ?MI1
2.2813 2 2667 2 2344
2.3156 23551 23532
2 3141 2.3966 2.413n
1 7532
1.m;
2 18-9
2.33%
2.4212
I
2
1
2
8 9 3 I . 8211-1
1115 2 03366 1.9584
;)LEA 2.2496 2 , l i 9 5
4l%? 2.- 2.3W
-tT
1 864;
20998 2 m 1
2 3113 2 2402
1 9151
2 1% 2 0187
3 2 2.3829 2 4115 2.43i1 2.4506 2 4743 2.4519 2.4763 2 M a 2 4245 2 36ns 2 2975
3 4 2.3814 2.4121 2.4421 2 W 2 4047 2.5158 2.5311 2 5 3 8 3 2s345 2 5161 ? 4799
3 6 2.3145 2 -061 2.4371 2.46i2 2 4983 2.5236 2.5483 2569? 25813 2 5915 2 5871
3 8 2.3653 2.;LW ? . a 3 2 Cs60 2 4 w 2.5111 2 , a w 2 5 i 4 0 2 548; 2 6195 ? 6347
4 0 2.3548 2 3851 2.4153 2 4436 2 1i39 2.3061 2 . w 25857 2 w 2 a218 2 6(gi
4.2 2 . 3 4 1 2.3734 2.40!27 ?.&I21 2 4610 2 4YI4 2.5214 2 5514 2 5814 2 6111 2 MW
4 4 2.3336 2.3617 2.3900 2.1183 2 4468 2 4137 2 5030 25343 2 w 2 5915 2 6244
4 6 2.3776 2.4%; 2 4323 2.4800 2.4862 2 5168 2 5 4 6 0 2 5735 260s
4.8 2.365; 2.3918 2 4182 2 4448 2,4720 2 4 w 2 sne 2 w 1 2WI
5.0 2.3791 2 40050 2 4304 2,456.5 24829 2 w 2 5311 2 5651
5.2 2 3925 2.4170 2.4418 2 M i 3 24928 2 5100 2 5(58
5 4 2.4043 2 . 4 1 1 2 4523 2 4769 2 5019 2.5275
5 6 2 4152 2 43a5 2 4621 2 48.59 2.5100
5.8 2.4033 2luB144a2 2 4711 2 4M1
6 0 2 4136 2 4352 2 45i3 2 4795
6 2 2 (232 24444 246.59
6.4 2 43u 2 4s30
6.6 2 4410
- - 1
656 DISTMBUTIONAL TEST AND REPAIR TIMES
TABLE 15.12
PERCENTAGE POINTS OF PEARSOP4 CURVES
Larcr 1% pobU of Ihc BC.adudkd &U k -
. #)/el (8 .I0.01). SOU: II LI > 0, the & v k h
h rbL table .rc ne+auve.
0.00 I Io m I
0.01 0.0s I I I os I I I
0.10 a15 0.30 0.w 0.50 0.w I 0.70
I I I I I I I I I I i i
- - 1.w I
- 0.80 1 0.90 I .30
--
1.40 1.jO 1.70 1.so
2 2
2.1
2.6
2.8
3.0
3.2
3.4
0.8107 0 7464
0.8944 0.826i
0.9816 0.9072
1.0731 0.9912
1.1w 1 . o i w
1.2648 1.1699
1.3586 1.2612
0.i659
D.8412
0.9189
0.9998
1.0842
1.1700
0.7109
0.782U
0.8545
0.9295
1.0075
1.0885
0.7?$2
0.i966
0.8666
0.9391
1.0113
0.7440
0.8100
0,8776
0.9477
0 6956
U 7.564
1
i l l 0 0 . 6672
0.3222 1.7716 0.7251 0 6820 0 6419
D.81176 ,8332 0 7836 0.7380 0 695:
3.6 1.4467 1.3497 1.2574 1.1713 1.0921 1.020- 0,9532 18966 0 &33 0.7916 0 i498
3.8 1.5274 1.4329 1.3411 1.2531 1.1710 1.0018 1 u252 19619 0 . W 6 0.8524 0 6046
4.0 1.5997 1.5092 1.4199 1.3327 1.2492 1.1703 1.0969 10294 0.9678 0.9119 08606
4.2 1.WO 1.5781 1.4923 1.4074 1.3145 1.24+6 1.1690 0982 1.0329 0.9729 0 9181
4.4 1.72M 1.6394 1.- 1.4763 1.3954 1.3162 1.300 16i2 1.0989 1.0% 0.9772 .
4.6 1.6171 1 . m 1.4611 1.3838 1.3081 234: 1.1649 1 . m 1.03i6
4.8 1.- 1.5958 1.5213 1.*66 1 ,3725 ,2999 1.2296 l.l62! 1 .OM6
5.0 1.6469 1.S75i ].so34 1.43% ,3614 1.2916 1.2240 1.1591
5.2 1.6251 1.Wi 1.4879 ,4185 1.3507 1.W6 1.2183
s.4 1.6045 1.5386 4720 1.405Y 1.m 1.2751
S.6 I.a8 1.5211 1.1569 1.3930 1.3295
S.8 1.6268 1.5658 1.w 1.4424 1.3806
6.0 1 b O a 1.sn 1.- 14.282
6.2 1.5815 1.5302 1.4724
6.4 1.5m 1.5133
1.5511
-
6.6
--- -
657
HOW TO APPLY
TABLE 15.13
0.00 0.01 0.03 0.05 0.10 0.15 0.20 om 0.4 0.50 0.60 0.70
1.2 1 . 1 ~ 1.2056
1 1.2326 1.2458
1.4 1 . W 1.3831 1.4151 1.4308 1.4453 1.4440 1.4348
1.6 1.3019 1.5786 1.6169 1.(u58 1.6543 1- 1 8128 1 6oa3 1 . W
1.8 1.6974 1.7764 1 11208 1.8444 1.8713 1 8762 1 8686 1.8320 1.7791 1.7200 1 8598
2 0 1 Mi 1.9511 1.9999 2.0274 '2.0644 2 0794 2 0815 2 Wl1 2.0145 1.9532 1.8811 1.813;
2.2 2.0097 2 0918 3 1425 2.1126 2.2175 ? 2418 2 2.541 2.2.548 2.2304 2.1655 2 1238 2.0507
2 I 2 . 1 ~ 27 . m 2.2512 2.2826 2 33% ?.363? 2.3833 2 (030 2.4W 2 3798 2 rn 2.m~
2 6 2.2061 ?.28,',' 2.3333 2.3649 ?.ali? 2 4521 2 . 4 7 3 ? 5103 2.5253 2.5219 2 Sees 2.4183
2.8 ?.2?37 2 3469 2.39S7 2 4270 2.4803 2 5174 2 M59 ? 3672 2.6136 2.6280 2.6308 2.6215
30 2.3263 2.3963 ? U3G 2.4744 2.5278 2 5659 2 3961 ?.64?4 2.6163 2 7003 2 71% 2.7?li
3.2 2 6025 ?.6336 2 68% ?.t?ll ?.is13 2 7743 2.7911
3.4 2 5129 2 5536 2.i.375 2 8138 2.mW
3 6 2.5ii5 2.8137 ? &30 2.0i23
3.8 2 835 ?.8659 2.895;
4.0 2 8Mn 2.9122
4.2 ? ,9237
-- _I -- - -
-
0.90 1.on
- i.in
- -- --
1.40 1.30 1.60 I .30 1.80
? 0 I 7435
? ? 1 9727 1 x9.56 I R3?B
? I 2 1144 2' 1344 ? OSOP I W 1 8925
2 6 ? 4313 ? 369ll ? 293? ? MF7 I 8%
? \ 2 5991 ? 56?1 2 sin1 2' 443: 2 IA67 2 1006 2 Mot
3 0 2 ilRj ? iN7 2 6767 2'63s 2 4251 2 . &WG 2 24i6 ? 160? ? 078:
3 2 ? 80135 ? ulE1 2 794.5 2 i i 6 3 2 WJ9 2 Si16 ? 487i 2' 9369 ? w9
3 I 2 8569 ? SG3? ? A i i l 2 8i34 2 no04 ?.i631 2 iO?R 2 6?$7 2 54%
3 6 2 8937 ? DI4D ? m3 ? 939p ? 9257 ?.WR 2 8679 2 819ri ? 7577
3 8 2 9225 2 94s9 ? !M? ? 9%; 2 0040 2 BOM 28838 ? 9592 2 9??7
4 0 29409 ? 9612 2 win 3 0121 a Iws9 3 0616 3 0616 3 0513 3 0384
4 2 2 9537 2 991R 3 001; 3 0116 3 OR98 3.1032 3 1126 3 1Iil 3 1159
4 4 2 9623 ? DO12 3 0186 3 rn44 a I l l 8 3.1299 3.1453 3 lSi9 3 1661
4 6 3 0 2 2 3 0.525 3 12% 3 1468 3 1662 3 1836 3 198:'
4 a 3 ow1 3 a515 3 1334 3.1569 3 1i89 3 1993 3 2li9
so 3 0601 3 1377 3 1623 3 IA59 32084 32296
5 2 3 1400 3 . 1 W 3 1894 3 2128 32356
54 3 1138 3 1395 3 la; 3.18% 3 2138 3 2379
5 6 3 1381 3 . 1 W 3.1883 3.2131 3 2312
5 0 3 1356 3 1611 3 ledc 3.2110 3 2349
6 0 3 . 1 W 3 183( 3 mi3 3 2320
6 2 3.lfl)E 32033 3 me
6 4 3 1991 3 2231
----
6 6 3.2179
-- I_
658 DISTRTBUTIONAL TEST AND REPAIR TIMES
TABLE 15.14
PERCLYTACE POINTS OF PEARSOS CURVES
0.3% poinu of the # t ~ d v d k d
d 8 V U l a (2. -
d/#,(a 0.CC-i. Sole: 11
in thh a l e are negative.
> 0. the vrrkta
y
01
0.00 0.01 om ao5 QIO 0.15 I 0.20
I
0.30
I I
1.2 1.1541 1.0899 1.0353 0.9954
1.4 1.- 1.2468 1.1635 1.1311 I.oli? 0 . 9 3 0.9110
1.6 1.51OS 1.4208 1.3459 1.2915 1.1676 1.1064 I 0381 0.9254 0.8331
1.8 1.1141 1.6113 1 . ~ i.wa
2 1 . ~ 1 11 . 2 4 1~ . 1 ~ 11.0386 u 9 3 n~MY;
2.0 1.9115 1.8057 1.7120 l . W 1 . W 5 1 . 0 1 , 1 . 1.1621 ~ I.IW.51 n.9461 0 R63C 0 7934
2.2 1.1008 l.w 1.8906 1.8190 1.6770 1.5613 1.4613 1.ZMkI I.lCI.5 LW'1 0 !Wdi 0 ~WIW
2.2s62 2.1437 2.0496 1 .9191 1.83;s 1 .71951 I .61X I 43.56 1 .?%!I 1.1632 I 11.5% n ijil?
2.4
2.6
2.8
2.3816 2.n58 2.1854 2.1116 1.9809 1.W 1.7616 1 5 E 4 I.4lbi 1 28''
2.4896 1.3851 2.m2.2348 2.l&U 1.9946 1.m1 7126 15?02 1 4036 1.27S7 I IGGi
1 I655 1 I=
3.0 2.5158 2.4158 2.5930 2.3330 2.21OS 2.1062 2.0110 1 ri?G2 1.6760 1.521: 1 395: I 2741
3.2 2.?017 '2 1120 1.9480 1.7915 I 646? I 5107 1 . S c O
3.4 2 0 4 2 2 1.11051 I 7547 I 6210 1.4947
3.6 1 9 w 1 852s I 7232 1 59N
3.8 1 oleo 1.9161 1.6952
4.0 1 SW7 1 7836
4.2 I.M34
- -
I 1.00 - - -
7
I
0.9n i
1.10 1.20 .3n
-1.311 1.60 1.70 1.80
1
5.6 5935 I 5144 I 4313 1 3624
5.8 1.6SIS 1 5146 1 49% 1 4238
6.0 l.iO61 16309 15563 14827
6.2 IWG 16IOh 15385
6.4 1 66IU 1.5912
1 6408
6.6
-- -
HOW TO APPLY 659
TABLE 15.15
I .2
1.4
1.6
1 8
2 0
1.2326 1 . 2 4 s
1.4151 1.4306
l . m z 1.6388
I . M I 1.-
2.0594 2.0870
1.4453 1.4440 1.1358
1.6561 1.6543 1.6433 l.w 1.m
i . u m 1.- Isne
I I I i
1.0330 1.7796 1.7m1.U98
2.1197 2.1118 2.1219 2.0644 2.0258 1.9569 1.8847 1.8137
2 2 2 . m 2 2.2818 2.3242 2.- 2.345t 2.3250 2.2784 2.2133 2.1366 2 &%ti
24 2.1081 2.4426 2.4928 2.5193 2.5322 2.5319 2.- 2.45i7 2.3922 2.3145
2 6 2 . 5 3 0 3.5119 2.6273 2.6603 2.681C 2.6981 2 B14 2.6652 2.6212 2 5601
2 8 2.6389 2.6753 2.7340 2.7715 2.797@ 2.8280 2 . m 2.8304 2.8072 2.1687
3 0 2.1217 2.7583 2.8188 2.85M 2.6893 2.9292 2 . W 2.9580 2.9521 2.9333
32 2.9294 2.- 3.- 3.- 3.0566 3.0636 3.6641
34 3.0712 5.1075 3.1329 3.1492 3.1570
36 3.1618 3.1928 3.2151 3.2311
3 8 3.2393 3.2680 3.2898
4 0 3.3092 3 3352
4.2 3.3711
-
I 0.90 I
-
-r
0.60 1.00 1.40
2 0
? ?
I 7455
81 9731 1 A950 1 8223
I I
2 1 2 22ib 2 13113 2 0513 1.9694 18928
2 C 216% 23996 2 3 M 2.21% 2 I222 2.W3 1.9584
2 4 2 7151 2 6466 2 5653 2.4741 2.3771 2 . W 2.1675 2. lax
3 0 2 win 2 8550 2 7950 2.7213 2.6356 2.5409 2.4415 2.3426 2.2483 2.1602
3 ? 3 Iw.% 3 0197 2 081.5 2 9300 2.8655 2.7879 2.6990 Z.WI9 2 5008 2.m 2.3Q56
3 4 3 1561 3 im 3 1258 3.00(Y 3.WP 2.Wil 2.92114 2.6484 3.7572 2 . e S w 2.5582
3 6 3 2406 3 2121 3 2360 3.2213 3.1972 3.1674 3.1163 3 0519 2.9869 2 . m 1 2.8111
36 3303.5 33156 33100 3.3173 3.3412 3.2890 3.2611 3.2pg 3.1748 3.1138 3.0406
4 0 3 3563 3 3128 3 3841 3.3902 3.3909 3.- 3.3717 3.3510 3.3108 3.- 3.2291
42 3 3962 3 4173 3 4339 3 . M 3.4346 3.4579 3 . w 3.- 3.4318 3.4093 3.3759
4.4 3 4279 3 4513 3 4121 3.4u99 3.5038 3.5137 3.5102 3.5203 3.5155 3.5051 3.4875
46 3 5031 3.5241 3.MI9 3.5564 3.3677 3.5756 3.5793 3.5782 3.5718
I
4.8 3.5510 3.5714 3.5900 3.6053 3.8183 3.6277 3.6335 3.6354
5.0 3.5721 3.5958 3.6156 3.0342 3.&512 3 . W 7 3.6760 3.6840
5.2 3.6136 3.6364 3.6669 3.61b4 3.6037 3 . 7 m 3.7206
5.4 13.5275 3.6524 3.6155 3.6909 3.7155 3.7328 3.7w
5.6 3 . m 3.7116 3.1333 3.7528 3.nm
5 8 3.7008 3.1245 3.7467 3.16881 3.7873
6.0 3.7341 3.7572 3.7796 3.8010
6.2 3 . 7 6 0 3.7885 3.8111
6,4 3.7959 a.sm
6,6 3.lll47
-
660 DISTRIBUTIONAL TEST AND REPAIR TIMES
and
I
= 1.3406.
%+2
Using these values, find
6; = 1.3223 - 2 (1.3041)+ 1.2848 = -0.0011,
6:+, = 1.3406 - 2 (1.3223)+ 1.3041 = 0.0001.
These values are used to calculate
0 = [Pi - P1(.,] 10,
e = “0.27) - (0.20)l 10 = (0.07) 10,
or
e = 0.7.
Substitution of these values into Eq. (15.17)yields
1
z* = (1 - e) %
,: + e . z+;l - -4 e (1 - e) (62. + . z;+l) ,
= (1 - 0.7) (1.3041)+ (0.7)(1.3223)
1
--(0.7)(1 - 0.7)[(-0.0011)(1.3041)
4
+
(0.0001)(1.3223)],
= 0.39123 + 0.92561 - (0.0525)[(-0.0014345) (0.0001322)], +
= 1.31684 - (0.0525)(-0.0013023),
+
= 1.31684 0.000068,
HOW TO APPLY 66 1
or
Z* = 1.316908.
The value of z', z* = 1.3169, corresponds to p; = 3.49, p; = 0.27,
and a = 0.90.
EXAMPLE 15-2
Given p; = 4.92, 3/; = 0.76, and cr = 0.10 find the lower 10%
percentage point, Q = 0.10, z value.
SOLUTION TO EXAMPLE 15-2
Do the following:
Prepare the following table using linear interpolation:
P2
4.80 1.1593 1.1535 1.1467 1.1391
/3; = 4.92 z L - ~= 1.1573 Z; = 1.1519 z ; + ~ = 1.1455 z ; + ~= 1.1384
5.00 1.1560 1.1508 1.1447 1.1379
and
I
~,+2 = 1.1384.
Using these values, find
6; = 1.1455 - 2 (1.1519) + 1.1573 = -0.001,
6:+1 = 1.1384 - 2 (1.1455) + 1.1519 = -0.0007,
6' = [(0.76)- (0.7)] 10,
and
9 = 0.6.
662 DISTRIBUTIONAL T E S T A N D REPAIR TIMES
f ( R N ;P o = 0,Pl = 1) = {1 ()
0 < R ~ < 1 ,
elsewhere.
where
i = 1,2, - .,6 = random variables involved,
and
j = 1 , 2 , ~ * ~ , 1 0 , 0 0 0number
, ~ ~ ~ =of trials, or sets of random
numbers generated,
or do as shown in Fig. 15.4.
tl ‘1. 1
Fig. 15.2a - Procediire for determining the cumulative Fig. 15.2b - Determine the cumulative distribution
distribution function of variable tl. function of variable t 2 .
I
Fig. 1 5 . 2 ~- Determine the cumulative distribution Fig. 15.2d - Determine the cumulative distribution
function of variable 13. function of variable t6.
666 DISTRIBUTIONAL TEST AND REPAIR TIMES
0 I
RN
4, 1 (1
Fig. 15.4a - Procedure for finding a randomly selected Fig. 15.4b - Procedure for finding a randomly selected
value of variable 11. value of variable &3.
668
HOW TO APPLY 669
or
where
N = 10,000or more, preferably.
For example, one set of such random values for each variable
could be
Station number 1 2 3 4 5 6
Random value,
t i , hr 11.3 17.5 1.9 6.3 0.3 9.2
10. Calculate the four moments from the Monte Carlo values of the
output, or o f t , and use these in a Pearson distribution approxi-
mation; namely, /?I and /?2, or obtain an empirical fit to the his-
togram constructed from the Monte Carlo values and find the ap-
proximations t o the desired percentiles. The moments calculated
from the Monte Carlo values are very close to those obtained by
the moments method, consequently, similar approximations are
obtained.
Q = It'
-=,0,7
f(t) dt = M ( t a ) , (15.18)
To
-
1
60.0 65.0 70.0
39.9 44-949.9 54.9 59.9 64.9 69.9 74.9
Total hours
Lognorin al
Jolirrsoll Sq
,
Johnsou Su
I
TABLE 15.16 - Continued.
~~~ ~~~
Distribution to
be simulated Probability density function Procedure to obtain random value d
Beta
(integral
values of and 7)
Weibull f(y) = 5 $--le-(:)@, 05y5 00.
-
Poisson f(y)=A
Y
%,
-a
y=0,1,2,..-. y‘ = k , where k is the lowest
integer such that
Binomial
i = 1,2,---,n.
RN is a random vi ie from the normal distribution with fi = 0 anc r = l . & i s a
random value from the uniform distribution over interval (1,O). When more than
one value is required, a typical value is designated as R N o
~r Rui. All values are
taken independently of one another [I, pp. 242-2431.
676 DISTRTBUTIONAL TEST AND REPAIR TIMES
and
pu2 = 0.975.
Therefore,
P[0.875 5 M ( t = 60 hr) 5 0.9751 = 0.95,
whereas for N = 100 trials
M^(t = 60 hr) = 0.94.
To increase the accuracy; i.e., to narrow the confidence bounds about
M ( t ) , the number of Monte Carlo trials, N , should be increased. For
example for N = 1,000 the confidence limits for a CL = 0.95 become
p,52 = 0.925,
and
pu2 = 0.955,
if 940 of the trials gave t 5 60 hr, where now
-
p=--
940 - 0.940.
1,000
Then,
P[0.925< M ( 1 = 60 hr) < 0.9551 = 0.95,
or a significantly narrower interval within which the actual maintain-
ability lies, with 1,000 Monte Carlo trials.
The process may also be used to determine the number of Monte
Carlo trials which provide the maximum allowable error, E , in esti-
mating M ( t ) . To accomplish this specify E , CL, and p', an initial
estimate of p , or of M ( t ) . For example, I want to be 95% sure that my
M ( t ) estimate will not differ by more than f0.05 from the final esti-
mated value. Assume an initial estimate of p' = 0.80. If 1,000 Monte
Carlo trials are conducted and 800, or 80%, have values t 5 60 hr, the
resulting 95% confidence interval for M ( t ) is
P[0.775 _< M ( t = 60 hr) 5 0.8251 = 0.95,
from Fig. 15.8. Similarly, for N = 400
P[0.755 5 M ( t = 60 hr) _< 0.8401 = 0.95,
678 DISTRIBUTIONAL TEST AND REPAIR TIMES
(15.20)
(15.21)
Q
CL = 0.95 = 1 - a; Q = 0.05; - = 0.025,
2
21-0.025 = 20.975 = 1.960,
and for
CL = 0.99 = 1 - (Y; (Y = 0.001; -a2 = 0.005,
21-0.005 = 20.995 = 2.576.
In this case, for a CL = 0.95,
ERROR BOUNDS 679
or
N 2 246.
This approximation is usually adequate for N p' or N (1 - p') equal t o
or greater than 5. If a one-sided bound is needed, instead of two-sided
bounds, then only the difference of the upper (or lower) curve from
the diagonal line of Fig. 15.8 is used to find N. In the equation for N
use instead of . z ~ - 2Q , or 1.282 for 90% CL, 1.645 for 95% C L and
2.326for 99% CL. It must be noted that in finding N, an estimate of p,
or of M ( t ) , was required, which is the very quantity t o be determined
by the Monte Carlo study. This is because the size of the confidence
interval is a function of p, or M ( t ) , as can be seen from examining
Fig. 15.8 and Eq. (15.21)for N. The largest sample size, however, is
required when p = 0.5. Therefore, if p is not known ahead of time, use
p' = 0.5 to get the most conservative sample size. Or conduct some
Monte Carlo trials, get an estimate of p', and use this to obtain N and
the additional trials t o get the desired accuracy or error bounds.
To find N for a desired error, E, in estimating the mean of the
output, or i, with a desired CL = 1 - a,the estimate of the standard
deviation, & is needed. Then,
(15.22)
where
p = 2.0, q = 3.0 hr and 7 = 0.5 hr.
2. Station 2
where
-
t' = 0.5 log, hr and up = 1.0 log, hr.
3. Station 3
where
p = 6 and q = 4 hr.
ERROR BOUNDS 681
Do the following:
1. Find the time to repair-and-checkout for the maintainabilities of
90%, 95% and 99%, using the Monte Carlo Simulation method,
with 100, 1,000 and 5,000 t values.
2. Discuss the simulation results.
The mean, range and variance of the results in Table 15.17 are
given in Table 15.18 and plotted in Figs. 15.9, 15.10 and 15.11. It
may be seen that the simulation results converge as the number of
simulations, N , increases; i.e., for a particular value of the percentile,
p , the range and standard deviation values decrease as N increases.
Also, the variation in the simulated percentiles strongly depends on
the value of p ; i.e., for the same number of simulations, on the average,
the variation increases as the percentile increases. For example, for the
case of N = 100, the variance for the 99th sample percentile is larger
than that of the 95th and 90th percentiles. This may be explained as
follows:
Consider that the variation of the simulation results is only caused
by the limited number of simulations. Let F ( t ) and f ( t ) be the cdf
-.
and pdf of the test-and-repair times, t , and let the t i ( i = 1,2, - ,M )
be a sample from t of size M , obtained by simulations. Arrange the
ek
t;(i = 1,2, - . -,Ad) in increasing value, and denote this set by (MI(k =
1 , 2 , . . . , M ). Then tiM’is the order statistic of t . The (iM)’s are
random variables with the following cdf [l,pp. 124-1281
M
@kAt(z) = p(<iM’5 z) = [F(z)ln[1- p(z)]’-n,
n=k
682 DISTRIBUTIONAL TEST AND REPAIR TIMES
99th
90th 95th
11.272 ** 14.085 ** 22.023
9.165 * 11.999 * 21.542
11.250 13.790 21.659
10.560 12.960 20.250
10.557 12.417 20.435
~ 10 11 .loo 13.710 22.080
10.511 13.159 20.088 *
11.250 13.940 21.890
11.044 13.577 21.783
11.209 13.701 23.032 **
11.122 13.577 21.462
ie minimum lue in the col m.
7
5.243 2.944
RMge = 4 . 4 7 5
\ Range = 2.107
.Standard
deviation 0 0.626
p a n 9 10.822
I
90th p e r c e n t i l e s
Fig. 15.9 - The plot of the simuiation results for the 90th
percentile, in terms of the mean, range and stan-
dard deviation for Example 15-3.
ERROR BOUNDS 685
-- z b n g e = 2 .086
Stvldard
deviation = 0.657
deviation=O.720
9 5 t h percentiles
Fig. 15.10 - The plot of the simulation results for the 95th
percentile, in terms of the mean, range and stan-
dard deviation for Example 15-3.
686 DISTHBUTIONAL TEST AND REPAIR TIMES
Standard
deviation, - Y
16.27
i
30 - I
X
_tz
M.an.?S .J5 1
9 9 t h percentiles.
Fig. 15.11 -The plot of the simulation results for the 99th
percentile, in terms of the mean, range and stan-
dard deviation for Example 15-3.
PROBLEMS 687
(15.23)
1. Station 1
g E ( t 1 ) = pe-M *I
where
p = 2 repairs/hr.
2. Station 2
where
p = 2.5, 7 = 3.0 hr, and 7 = 0.5 hr.
3. Station 3
where
-
t'3 = 0.6 log, hr, and ul; = 1.0 log, hr.
4. Station 4
where
= 8, and 77 = 5 hr-'.
Do the following:
1. Find the time t o repair-and-checkout for the maintainabili-
ties of 90%, 95% and 99%, using the Central Limit Theorem
method.
2. Same as in Case 1, but using the Monte Carlo Simulation
method, with 100 and also with 5,000 simulated T values.
3. Discuss comparatively the results of Cases 1 and 2.
4. What is the required number of Monte Carlo Simulations t o
determine the 90% maintainability with error of fO.01 and
90% confidence?
5. What is the required number of Monte Carlo trials to deter-
mine the mean time to repair-and-checkout the trucks with
an error on the mean time of &lo% and 90% confidence?
In all cases above write out all equations used and give the step-
by-step procedures used to get your results in addition to the
computer programs used.
PROBLEMS 689
where
p = 2 repairs/hr.
2. Station 2
where
/3 = 2.5, 71 = 3.0 hr, and 7 = 0.5 hr.
690 DISTRIBUTIONAL TEST AND REPAIR TIMES
3. Station 3
where
-
t’3 = 0.1 log, hr, and ot; = 0.2 log, hr.
4. Station 4
where
P = 8, and q = 5 hr-*.
Do the following:
1. Find the time to repair-and-checkout for the maintainabili-
ties of 90%, 95% and 99%, using the Central Limit Theorem
method.
2. Same as in Case 1, but using the Monte Carlo Simulation
method, with 100 and also with 5,000 simulated T values.
3. Discuss comparatively the results of Cases 1 and 2.
4. What is the required number of Monte Carlo Simulations to
determine the 90% maintainability with error of f O . O 1 and
90% confidence?
5. What is the required number of Monte Carlo trials to deter-
mine the mean time to repair-and-checkout the trucks with
an error on the mean time of &2% and 90% confidence?
In all cases above write out all equations used and give the step-
by-step procedures used to get your results in addition to the
computer programs used.
15-4. Using the simulated total times to repair-and-checkout trucks of
Problem 15-3, do the following:
1. Calculate the four moments two ways:
1.1 Fit the normal, lognormal, Weibull and the extreme-
value-of-the-maxima distributions t o the first 100 simu-
lated total times to repair-and-checkout the trucks, i.e.,
find thir parameters. Any good method is acceptable!
Then calculate all four moments using these parame-
ters.
REFERENCES 691
REFERENCES
1. Hahn, G. T. and Shapiro S. Samuel, Statistical Models in Engi-
neering, John Wiley & Sons, New York, N Y, 355 pp., 1967.
2. Lindgren, B. W., Statistical Theory, The MacMillan Company,
Collier-MacMillan, London, 521 pp., 1968.
3. Cramer, H. Mathematical Methods of Statistics, Princeton Uni-
versity Press, Princeton, 575 pp., 1951.
4. Krivoy Raul, based on Table of Percentage points of Pearson
Curves for Given f i and p2, Expressed in Standard Measure,
Compiled by Johnson, N. L., Eric Nixon and Amos, D. E. with
an introduction by Pearson, E. S., Biometrika, Vol. 1, Table 41,
1954.
5 . Pearson, E. S., and Hartley, H. O., Biometrika, Tables for Statis-
titians, Cambridge University Press, Cambridge, England, Vol.
1, Table 41, 1954.
6 . Kececioglu, D., and Jiang, J., Proceedings - Institute of Environ-
mental Science, Error Bound Estimation O n Monte Carlo Sim-
ulations, pp. 124-128,April 23-27,1990.
692 APPENDIX 15A
APPENDIX 16A
PROOF OF EQ. (16.23) [2, p. 3671
Consider a sample of size M from a continuous distribution, with
cdf F ( z ) and pdf f(z). Let ap denote the percentile of order p of the
distribution, i.e., the root of the equation F ( a p )= p , where 0 < p < 1.
We assume that, in some neighborhood of x = a p , the p d f , f(z) is
continuous and has a continuous derivative f ' ( x ) .
[l - F(z + dz)l'-('+').
APPENDIX 15A 693
Therefore,
dx = (7) ( M - W w r [ 1 - F(4lM - ( I + l )
fW dx,
or
15A.2
then
15A.3
The pdf of Y can be expressed as
where
or
.-,J) = -
f (.PI
,/T(y) ( M - I),
Then,
or
since (1 - M p ) / J M p (1 - p ) + 0 , then
APPENDIX 15A 695
and
M-(l+l)
or
or
A3 = I * II,
As M + 00, p M --.t 1, M - ( Z t 1)-+M-1 4 ( 1 - p ) M = n.
Let
and
then,
696 APPENDIX 15A
= e [-b v2+0(*)] 9
(16.1)
Condition 1 is
P [ N ( t ,t + A t ) = 01 = 1- A ( t ) At + o(A t) , (16.2)
697
698 THE WEIBULL PROCESS OF REPAIRABLE UNITS
(16.6)
The conditional reliability of Trythe time to the rth failure, given
the times of the first ( T - 1) failures, can be found from
R(Tr1 TI = tl,Tz = t 2 , * * .,Tr-l = t r - 1 ) = R(Tr( TT-1 = tr-l), (16.7)
by Condition 2; i.e., the distribution of Tr,given the times of the first
(T - 1) failures only depends on the time of the ( T - 1) failure. Then,
the conditional reliability of surviving by Tr,given it got repaired after
the failure at t r - 1 , or for T r , and given that Tr-1 = t r - 1 , Eq. (16.6)
becomes
(16.8)
T H E w m u L L PROCESS AND ITS CHARACTERISTICS 699
X - failure point
o - endofrepair
,.
0
Accumulated operating and repair times
(16.9)
or
m, = (16.10)
Jtr-1
where
dTr= 2 X Z' - 1
dx.
D
THE ESTIMATION OF A WEIBULL PROCESS 701
(tr-\-
'> p
;
1
p] , (16.13)
where
~ ( xn); = 1e-t tn-1 dt
or
7 e(W)'{r(;)
m, = -
P
; ;I}. (16.14)
or
(16.15)
(16.16)
or
(16.18)
In this case, using the values j l / n = 1 with Tj, = 9.7, and j2/n = 10
with Tj, = 900, yields
A(T) = -
or
X(T) = 0.1605 T-0.4917.
2. From Eq. (16.7) the conditional reliability for 2'1, = 2,400 hr
and t = 10 hr is
h![T16= (2,400 + 10) I Ti = t i , * * *, Ti5 = 2,4001
=e
-16.5007 + 16.4659
or
R[T16 = (2,400 + 10) I 2'15 = 2,4001 = 0.9658.
8
Q)
0
c.)
bcu
oiE
c=
705
706 THE WEIBULL PROCESSES OF REPAIRABLE UNITS
3. J3om Eq.(16.14)the mean time between the 15th and the 16th
failure is
m16 =- *’
0.5083 0.5083
where
and
1’0.5083
= I(16.4659 ; 1.9673) = 0.9866114.
Therefore,
m16 = (2.70208 x 108)(0.9866126 - 0.9866114) = 326.50 hr.
4. The reliability for a mission of 10 hr starting at age zero, from
Eq. (16.6),is
R(T1 = 10) = e -(%)’ = e-(3)0*5083
- - 0.3622,
e-1.0156
and the mean time to the first failure, from Eq. (16.11),is
(16.19)
THE ESTIMATION OF A WEIBULL PROCESS 707
(16.22)
where
j = number of cumulative failures up to the accumulated test
time, Tj.
The paired data, (Tj, Xj), are plotted as in Fig. 16.3 yielding an
acceptable straight line, hence 7 = 0. Pick two points on the straight
line, as indicated in Fig. 16.3, and use Eq. (16.22) t o determine pa-
rameter p from
10g1,(0.0034) - lOg10(0.033)
P= log,,( 10,000) - log,,( 100)
+ 1 = 0.5065.
Using Eq. (16.20) the parameter 7 is obtained from
1
(T;?.-)P-' B
'= [ I(Ti) ] *
(16.23)
N
$
s!
.-
0
T:
0
.CI
R
708
THE ESTIMATION OF A WEIBULL PROCESS 709
In this case, for T = 10,000 hr and x(T = 10,000 hr) = 0.0034 fr/hr,
'= ( 0.0034
= 9.47 hr.
p Tr-7 P-l - ( F ) P + ( m ) @
=-(7)
77
e q .
-
The joint density function of the total of T* times to failure, (2'1, - ., Tr*),
which occur during the test period [0, t ] ,is the product of the individ-
ual conditional density functions [2], or
r*
L = n f ( T r 1 T 1 = t l , T 2 = t 2 , . * . T r - 1~ t r - 1 ) ~
r=l
or
(16.24)
(1G.25)
710 THE WEIBULL PROCESSES OF REPAIRABLE UNITS
(16.26)
and
(16.27)
T*
-
P
- T* log, (V)+ r*
Clog,
r=l
(U
17 )0,
=
or
v*
(16.29)
(16.30)
p
But, the estimates of and 7j given by Eqs. (16.29) and (16.30) are
biased. An unbiased estimate of p is given by [3]
(16.31)
qt = (Tr* - 7) (16.32)
T.8
WHEN TESTING MORE THAN ONE UNIT 711
EXAMPLE 16-3
Find the maximum likelihood estimates of the parameters of the
Weibull process represented by the data given in Table 16.1.
SOLUTION T O EXAMPLE 16-3
From Eqs. (16.29) and (16.31)
fi= 15 =-
15 = 0.5441,
27.569
r=l
and
Pt = p (T* - 1) - 0.5441(15 - 1) = 0.5078.
f* 15
From Eq. (16.32)
$=--2,400
I - 11.59 hr.
15o.sols
The results are close to those of Examples 16-1 and 16-2.
syst n l
Cumulative Cumulative Cumulative Cumulative
number of test number of test times
failures, times, failures, t o failure,
j Tj,hr j Tj,hr
1 1.30
2 3.50
1 5.75
2 8.50
3 10.70
3 14.55
4 16.65
4 28.25
5 31.55
5 35.30
6 36.50
7 38.85
6 46.95
8 47.75
7 49.05
9 50.55
10 66.00
8 71.10
11 73.85
12 74.50
13 83.60
9 95.35
10 96.50
11 99.35
14 125.95
15 141.25
12 143.05
W H E N TESTING MORE THAN ONE UNIT 713
or
,8 = 0.7067.
Then, the failure rate function is
0.7067 T 0*7067-1
X(T) = -
3.0 (G) ’
or
where the test time, T , is the accumulated test time to failure for each
system.
714 THE WElBULL PROCESS OF REPAIRABLE UNITS
j j/2
7
Tj,hr fr/103 hr
1 0.5 1.30 * 384.615
2 1.o 3.50 * 285.714
3 1.5 5.75 260.870
4 2.0 8.50 235.294
5 2.5 10.70 * 233.645
6 3.0 14.55 206.186
7 3.5 16.65 * 210.210
8 4.O 28.25 141.593
9 4.5 31.55 * 142.631
10 5.0 35.30 141.643
11 5.5 36.50 150.685
12 6.0 38.85 154.440
13 6.5 46.95 * 138.445
14 7.0 47.75 146.597
15 7.5 49.05 * 152.905
16 8.0 50.55 158.259
17 8.5 66.00 128.788
18 9.0 71.10 * 126.582
19 9.5 73.85 128.639
20 10.0 74.50 134.228
21 10.5 83.60 125.598
22 11.0 95.35 * 115.364
23 11.5 96.50 * 119.171
24 12.0 99.35 * 120.785
25 12.5 125.95 99.246
26 13.0 141.25 92.03:
27 -
13.5 143.05 * 94.37:
* The asteriskt times are fc System 1.
715
716 THE WEIBULL PROCESS OF REPAIRABLE UNITS
Graphical Method 2
Fkom Eq. (16.15) the average number of failures of n systems in
time interval [y, T ]is
(,>",
=n T-7
(16.33)
where
n = number of systems in test,
and
n(T-7) = unit-hours of test time accumulated by n systems in
time interval [7,TI.
Taking the logarithm of Eq. (16.33) yields
(16.34)
(16.35)
(16.36)
WHEN TESTING MORE THAN ONE UNIT 717
where
j = total number of failures up to time Tj,
and
n(Tj - 7) = unit-hours of test time accumulated by n sys-
tems in time interval [y, Tj].
Here 7 is an unknown parameter. However, 7 may be assumed to be
zero for the initial plot. If the J;(Tj)versus Tj points fall acceptably
well on a straight line, then the assumption 9 = 0 is confirmed. If
the X(Tj) versus Tj points do not fall on a straight line, then there are
two possibilities. The first possibility is that the test-analyze-fix-test
process is not a Weibull process, and the second possibility is that 7 is
not equal to zero. These will be discussed later.
In this example, when 7 = 0, the cumulative failure rates, using
Eq. (16.36), are calculated from
and
r-1
log, (4) = 18.714,
or
P I = = = l2 0.6412,
and
el=--1143.05
2 m
- 2.968.
For System 2, T* = 15, Tr* = 141.25 hr, and
5 (g)=
r*-1
r-1
log, 18.7252,
or
15
= 0.8011,
jZ= 18.7252
720 THE WEIBULL PROCESS OF REPAIRABLE UNITS
and
Pi = (121i
"(0.6412) = 0.5878,
and
+-- 143.05
- 2.0870.
1 2 h
For System 2
Pi = (151i
1)(0.8011) = 0.7477,
and
141.25
&--
150.7477
- 3.7761.
Then, better estimates of p and q may be obtained by averaging them,
or from
- pit Pi
pt=-= 0.5878 t 0.7477 = 0.6678,
2 2
and
-
qt=-=7; t q! 2*0870 3'7761 = 2.9316 hr.
2 2
Therefore,
X(T)= -
0.6678 (-
T )0mw78-1,
2.9316 2.9316
or
T
X(T) = 0.2278 (E) -0.3322
.
3. The predicted value of the failure rate of this system at 500 hr,
using the results in Case 1, for Graphical Method 1, is
or
X(T = 500 hr) = 0.05254 fr/hr = 52.54 fr/103 hr,
and for Graphical Method 2 is
-0.2888
X(T = 500 hr) = 0.2181
or
X(T = 500 hr) = 0.05099 fr/hr = 50.99 fr/103 hr.
4. The predicted value of the failure rate of the system at 500 hr,
using the results in Case 2, or the MLE’s, is
-0.3322
X(T = 500 hr) = 0.2278 -
(2.E6) ’
or
X(T = 500 hr) = 0.04132 fr/hr = 41.32 fr/103 hr.
and after time TI the failures follow a Weibull process with the failure
rate function
or
log10 0.7 - log,, 0.1
= 0.3811,
= log,, 1,650 - log,, 10
and for the second process, pick two points, say, (T3 = 2,65O,j3/n = 1)
and (2'4 = 6,000, j4/n = 6.8). Then,
log10 6.8 - log,, 1
= 2.3457.
P2 = log,, 6,000 - log,, 2,650
The parameters and Q may be found from the plot directly, for
j / n = 1, yielding
q1 = 4,000 hr,
and
772 = 2,650 hr.
Thus, the composite Weibull process is determined. Its failure rate
function then becomes
0.3811 ( T )o*sll-l,
X(T) = - -
4,000 4,000
or
A(T) = 9.5275 X 10'' , for 0 ,< T ,< 2,400,
and
724 THE WEIBULL PROCESS OF REPAIRABLE UNITS
2.3457 ( T )2*u57-1 ,
X(T) = - -
2,650 2,650
or
X(T) = 8 8 . 5 1 7 ~ , for T > 2,400.
PROBLEMS
failure occurred a t 1,960 hr, and the mean time t o the first
failure.
(4) Same as in Case 3, but using the results in Case 2.
(5) Find the reliability for a mission of 10 hr after the 10th
repair at time 1,960 hr, and find the reliability for a mission
of 10 hr starting from age zero, using the results in Case 1.
(6) Same as in Case 5, but using the results in Case 2.
System 2
Cumulative Cumulative Cumulative Cumulative
number of test times number of test times
failures, to failure, failures, to failure,
Tj,hr j Tj, hr
1 180
1 260
2 380
2 490
3 790
3 870
4 950
4 950
5 1,040
5 1,130
6 1,270
6 1,330
7 1,350
7 1,470
8 1,630
8 1,650
9 1,690
9 1,830
10 1,960
11 2,080
10 2,160
12 2,280
732 THE WEIBULL PROCESS OF REPAIRABLE UNITS
Syst n l Svstem 2
Cumulative Cumulative Cumulative Cumulative
number of test times number of test times
failures, to failure, failures, to failure,
j Tj, hr j Tj,hr
1 100
1 140
2 220
2 270
3 420
3 480
4 510
4 530
5 570
5 640
6 730
6 730
7 780
7 810
8 910
8 930
9 980
9 1,010
10 1,130
10 1,190
11 1,210
12 1,320
734 THE WEIBULL PROCESS OF REPAIRABLE UNITS
System 1
Cumulative Cumulative Cumulative Cumulative
number of test times number of test times
failures, to failure, failures, to failure,
j Tj,hr j Tj,hr
1 260
1 310
2 460
2 620
3 680
4 750
5 860
3 1,060
6 1,140
4 1,160
5 1,370
6 1,550
7 1,640
7 1,860
8 1,970
9 2,050
8 2,120
10 2,370
9 2,420
11 2,520
10 2,600
12 2,750
11 3,340
PROBLEMS 735
m l
SYS Svstem 2
Cumulative Cumulative Cumulative Cumulative
number of test times number of test times
failures, to failure, failures, to failure,
j Tj,hr j T,, hr
1 190
1 230
2 340
2 450
3 500
4 560
5 640
3 770
4 850
6 860
5 1,000
6 1,140
7 1,210
7 1,360
8 1,450
9 1,510
8 1,560
10 1,750
9 1,770
11 1,860
10 1,910
12 2,040
11 2,440
12 2,540
736 THE WEIBULL PROCESS OF REPAIRABLE UNITS
and the repaired system is tested again. Assume that the repair
time is negligible and this test-fix-test process follows a Weibull
process based on the test times of each individual system. Do
the following:
(1) Determine the parameters of this Weibull process using the
two graphical methods.
(2) Determine the parameters of this Weibull process using their
maximum likelihood estimates.
(3) Predict the value of the failure rate of this system at a total
test time of 1,600 hr, using the results of Case 1.
(4) Same as in Case 3, but using the results of Case 2.
16-10. Two prototypes of an electronic system are tested simultane-
ously and the cumulative times to failure are recorded separately
for each system with the incorporation of repairs. The cumulative
test time at each failure for each system is given in Table 16.13.
Assume that after each failure a repair is performed immediately,
and the repaired system is tested again. Assume that the repair
time is negligible and this test-fix-test process follows a Weibull
process based on the test times of each individual system. Do
the following:
(1) Determine the parameters of this Weibull process using the
two graphical methods.
(2) Determine the parameters of this Weibull process using their
maximum likelihood estimates.
(3) Predict the value of the failure rate of this system at a total
test time of 900 hr, using the results of Case 1.
(4) Same as in Case 3, but using the results of Case 2.
PROBLEMS 737
REFERENCES
1. Gisela, Hartler, “Graphical Weibull Analysis of Repairable Systems,”
Qualify and Reliabilify Engineering Iniemational, Vol. 1, pp. 23-26,
1985.
2. Crow, L.H.,“Confidence Interval Procedures for Reliability Growth
Analysis,” Army Material systems Analysis Activity Technical Report
197, ADA044788, Defense Technical Information Center, Alexandria,
VA, 1977.
3. Tsun Ming, T. Lin, “A New Method for Estimating Duane Growth
ei
Mode Parameters,” Proceedings Annual Reliabiliiy and Maintainability
Symposium, pp. 389-393, 1985.
Chapter 17
RELIABILITY OF COMPONENTS
WITH A POLICY OF
REPLACING THOSE THAT FAIL
BY A PRESCRIBED OPERATING
TIME
These are replaced by fresh ones and they operate n cycles thereafter.
The number of these components that will fail after n additional cycles
of operation, using Eq. (li’.l),would be
739
740 RELIABILITY OF COMPONENTS
(17.4)
or
Ns-NR(ni + n) = N o R(ni + n). (1 7.10)
Out of the N o that started out, the number of those that survive, after
replacement of those that failed by nl, is given by the sum of Eqs.
(17.8) and (17.10), or
+ n) = No {[I - R(nl)]R(n)+ R(n1 + n)}.
Ns-R(~I (17.11)
Therefore, the total combined reliability of such components, under
the replacement policy considered, is
(17.12)
(17.16)
and
or
(1 7.17)
742 RELIABILITY OF COMPONENTS
EXAMPLE 17-1
Identical aluminum spindles are operating at an alternating stress
level of 25,000 psi. Their cycles t o failure distribution is lognormally
distributed with parameters ii' = 5.827 and crn1 = 0.124.These param-
eters are determined using the logarithms t o the base 10.
1. If 1,000 such fresh spindles are operating, how many will survive
after 500,000 cycles of operation and how many will fail?
2. If the failed spindles are replaced by new ones and all of them
operate for n = 330,000 cycles thereafter, how many of the fresh
ones will fail?
3. Of those that survived n1 cycles, how many will fail during the
additional n cycles?
4. What is the total number of spindles that will fail by (nl -t n )
cycles given that 1,000 started at age zero, and that those that
fail by n1 cycles are replaced?
5. What is the total number of components surviving after (n1+ n )
cycles when we follow the policy of replacing the failed ones by
nl cycles?
6. What is the total combined reliability of the components under
this replacement policy?
7. What is the reliability for (nl + n) cycles without a replacement
policy? Compare the answer with that of Case 6.
then,
R(n)= J 9wdz,
4.')
and
log10 330,000- ii'
t ( n ' )= 3
Un.1
or
5.518514 - 5.827
z(n') = = -2.48779,
0.124
and
Then,
b'F-R(n = 330,000 Cycles) = 1, ooo( 1 - 0.849081)( 1 - 0.993573),
or
N~-~(330,000 cycles ) = 1,000(0.150919)(0.006427) = 0.97, say 1.
Therefore, one spindle out of the 151 fresh, replaced ones will
fail.
744 RELIABILITY OF COMPONENTS
I , = NF-NR(~OO,
N F - N R ( ~ n) 000 cycles; 330,000 cycles),
or
- 5.827
~ ( 5 0 0 , 0 0 0cycles + 330,000 cycles)' = log10 830,000
0.124 7
= 0.742565.
Therefore,
N ~ - ~ ( 5 0 0 , 0 0cycles;
0 330,000 cycles) = 849 (1 - ::z3 '
= 849(0.730447),
or
N ~ , ~ ( 5 0 0 , 0 0 cycles;
0 330,000 cycles) = 620.15, say 620.
R(n1 + n ) = 7
z(n1 +n)'
4(z)dz,
-- 5.91908 - 5.827
0.124 '
or
~ ( 8 3 0 , 0 0 0cycles)' = 0.742565.
Then,
R(830,OOO cycles) = 7
J
0.742565
4 ( z ) dz = 0.228872, or 22.9%.
Consequently,
WITH A POLICY OF REPLACEMENT 747
since
22.9% < 37.9%,
or R(830,OOO cycles) with replacement is 65% larger than with-
out replacement!
EXAMPLE 17-2
Identical types of bearings have a Weibull times-to-failure distribu-
tion with the following parameters:
/3 = 2, 7 = 2,000 hr, 7 = 0 hr.
Determine the following:
1. If 100 of such bearings are operating in identical equipment at
the same application and operation stress level, how many will
survive if each one operates 2'1 = 1,300 hr at 675 rpm, and how
many will fail?
2. If the failed bearings are replaced by new ones and all of them
operate for T = 700 hr thereafter, how many of the fresh ones
will fail?
3. Of those that survived 2'1 hr, how many will fail during the ad-
ditional T hr of operation?
4. What is the total number of bearings that will fail by (TI+ T ) hr
of operation, given that 100 started at age zero, and that those
that fail by TIhr are replaced?
5 . What is the total number of bearings surviving after (TI t T )
hr of operation when we follow the policy of replacing the failed
ones by TI hr?
6. What is the total combined reliability of the components under
the replacement policy?
+
7. What is the reliability for (TI T ) hr of operation without a
replacement policy? Compare the answer with that of Case 6.
748 RELIABILITY OF COAfPONENTS
1300 2
R( 1,300 hr) = ,-(*I = 0.522046.
The number of bearings that will survive is
or
N F - R ( T ~= 1,300 hr) = lOO(1- 0.522046), say 48.
2. If the failed bearings are replaced by new ones and all of them
operate for T = 700 hr thereafter, the number of fresh ones which
will fail can be determined using Eq. (17.2),or
NF-R(T) = No - W 1 ) 1 [ 1 - R(T)J,
where
R(T = 700 hr) = e-($)' = e-(*)' = 0.884706.
Then,
NF-R(T = 700 hr) = lOO(1- 0.522046)(1- 0.884706),
3. Of those that survived 2'1 hr, the number that will fail during
the additional T hr of operation, from Eq. (17.4), is
From Case 1,
Ns(T1) = No R(T1)= lOO(0.522046) = 52.2046, say 52.
and
R(T1 + T ) = e-(*)
T +T $ 1300 700 2
= e'( '2120 = 0.367879.
Then, from Eq. (17.4)
N F - . ~ R1,300
( hr; 700 hr) = 15.36, say 15.
Therefore, 15 bearings out of the 52 will fail during the additional
T = 700 hr of operation.
4. The total number of bearings that will fail by (Tlt T) hr of
operation, given that 100 started at age zero, and that those
that fail by 2'1 hr are replaced, is obtained from Eq. (17.7), or
+
NF-T(TI T )= N0[2 - R(T1) - R ( T )
tR(Tl)R(T) - R(T1 t T ) ] ,
+
5. The total number of bearings surviving after (Tl T ) hr of op-
'
eration when we follow the policy of replacing the failed ones by
1'2 hr is found from Eq. (17.11), or
+
N s - ~ ( 2 , 0 0 0hr) = 100[(0.477954)(0.884706) 0.3678791,
+
, hr + 700 hr) = (1 - 0.522046)(0.884706) 0.367879,
R T - R ( ~300
= 0.790728,
or
79.07
, hr
R T - R ( ~300 + 700 hr) = R T - R ( ~000)
, = -- 0.7907.
100
Therefore, the combined reliability is 79.1%.
1 3 0 0 700 2
R( 1,300 hr t 700 hr) = e-( ' 2,ok ) ,
or
R(2,000 hr) = e-l = 0.367879, say 36.8%.
Consequently,
R(2,OOOhr) WITHOUT < R(2,OOOhr) WITH
REPLACEMENT REPLACEMENT
since,
36.8% < 79.1%,
or R(2,000 hr) with replacement is more than double that without
replacement.
PROBLEMS
17-1. Derive the equation for calculating the total combined reliability
if the age of the units which have been put into operation at the
beginning of the mission is not zero, or TO# 0, but 2'1.
17-2. Find the total combined reliability for the following replacement
policy: At the prescribed replacement time 2'1, those that are
found to have failed by TI are replaced by fresh ones, and p
percent of those that have not failed by 2'1 are also replaced by
fresh ones.
17-3. Find the optimal value of the p given in Problem 17-2 in terms
of cost, assuming that
C1 = replacement cost per unit,
Cz = unit cost,
C3 = salvage value of an unfailed unit at replacement
time T I ,
and
Cd = failure cost at the end of the mission.
3. Of those that survived 2'1 hr, how many will fail during the
additional T hr of operation?
+
4. What is the total number of bearings that will fail by (2'1
T ) hr of operation, given that 100 started at age zero, and
that those that fail by TI hr are replaced?
5. What is the total number of bearings surviving after (2'1 tT)
hr of operation when we follow the policy of replacing the
failed ones by TIhr?
6. What is the total combined reliability of the components
under the replacement policy?
7 . What is the reliability for (TI
+T) hr of operation without a
replacement policy? Compare the answer with that of Case
6.
17-8. Using the replacement policy of Problem 17-2 determine the
total combined reliability of the components given in Problem
17-7 assuming that the percent, p , of those that have not failed
by TI= 1,500 hr, but are replaced, is 30%.
17-9. Identical units have a Weibull times-to-failure distribution with
the following parameters: ,B = 1.75, 7 = 3,000 hr and 7 = 0
hr. The replacement policy is as follows: Those that are found
to have failed at 1,500 hr are replaced with units which have to
have a Weibull times-to-failure distribution with the following
parameters: ,B = 2.50, 77 = 1,500 hr and y = 0 hr. Do the
following:
1. If 1,000 such units are operating in identical equipment at
the same application and operation stress level, how many
will fail if each one operates TI= 1,500 hr?
2. If the failed ones are replaced according to the given policy,
how many will fail when operating for t = 500 hr thereafter?
3. Of those that survive 2'1 = 1,500 hr, how many will fail
during the additional t = 500 hr of operation?
4. What is the total combined reliability of these components
under the replacement policy of Case 3?
17-10. Using the replacement policy of Problem 17-2 determine the
total combined reliability of the components given in Problem
17-9 assuming that the percent, p , of those that have not failed
by n1 = 500,000 cycles but are replaced, is 30%.
Chapter 18
RELIABILITY OF MAINTAINED
EQUIPMENT WHEN KEEPING
TRACK OF THE AGES OF ALL
COMPONENTS WITH
EXPONENTIAL AND
WEIBULLIAN PDF’S
755
756 RELIABILITY OF MAINTAINED EQUIPMENT
Nci
- = proportion of identical components which fail due
Ni to chance causes,
and
N ; = total number of components in the equipment, assum-
ing the components exhibit chance as well as wear-out
failures, as would be the general case.
The parameters N d , Nw;,X;,yi,qi and pi in Eq. (18.2)may be de-
termined using known techniques [ l , pp. 215-263;271-3311.
After the first mission, the reliability of this equipment for the
second mission is given by
~ 2 s ( t~) =
1 n
N
i=l
~ 2 i ( ~t )2 , ,
where T 2 is the age at the beginning of the second mission and t is the
duration of the second mission, or
(18.3)
Rjs(Tj, t ) L R G O A L ( ~ ) .
MEAN LIFE 757
If some components fail during the previous mission and are re-
placed with fresh ones, the equipment’s reliability for any mission may
be obtained from
where the T; are the ages of the respective components and a,ll parame-
ters are for these ages, and Tj is the age of the system at the beginning
of the j t h mission.
(18.7)
EXAMPLE 18-1
In a three-unit system, the units function reliabilitywise in series.
Each unit can fail due to chance as well as wear-out causes. The pa-
rameters of each unit’s times-to-failure distribution are listed in Table
18.1. Assume that only the failed unit is replaced and then the system
is readied for the next mission. Do the following:
758 RELIABILITY O F MAINTAINED EQUIPMENT
1. Find the system's reliability for the third mission of 50 hr, if the
duration of the first and second missions was 35 hr and they both
were successful.
2. If Unit 1 fails at 40 hr during the first 50-hr mission and then
Unit 3 fails at 30 hr during the second 50-hr mission, find the
system's reliability for the third 50-hr mission.
3. Determine the mean life of the system in Case 2, for the first
three missions.
4. Discuss the results in Cases 1 and 2 comparatively.
The units that fail during a mission are replaced with fresh ones at the
beginning of the next mission.
TABLE 18.1 - The parameters of the times-to-failure dis-
tribution of each unit in Example 18-1.
3. The system's mean life for the first mission, is given by Eq. (18.6),
or
M31s = 1
00
R31s(Ti,t ) dt ,
From these results, it may be seen that the system's mean life
for the first mission is the longest. This is always true, because
all units in the system are fresh for the first mission.
4. In Cases 1 and 2, the cumulative mission times are the same and
are equal to 120 hr, but the reliability values are different. The
reliability of the system in Case 2 is greater than that in Case 1;
i.e.,
[Rs(Case 1) = 89.08%] < [Rs(Case 2) = 92.71%].
The reason is that in Case 2, there are two fresh units which are
the replacements for the two units that failed during the first two
missions.
PROBLEMS
1.o
0.7
1. Find the mean life to the first failure of the machine, or when
each failed unit is replaced by an identical one that had op-
erated a period equal to the period of operation of the failed
unit that is being replaced by a fresh unit.
2. Find the mean time between the second and third failures if
Unit 1 fails f i s t at the age of 500 hr and is replaced with a
new identical unit, and Unit 3 fails next at the age of 7,000
hr and is replaced with a new identical unit.
3. Find the stabilized mean time between failures of this ma-
chine, when the failed units are replaced by fresh units.
4. Calculate and plot the reliabilities for the follow-
ing two cases:
4.1 Case 1.
4.2 Case 2.
18-2.In a three-unit system, the units function reliabilitywise in series.
Each unit can fail due to chance as well as wear-out causes. The
parameters of each unit’s times-to-failure distribution are listed
in Table 18.3. Assume that only the failed unit is replaced and
then the system is readied for the next mission. Do the following:
1. Find the system’s reliability for the third mission of 50 hr, if
the duration of the first and second missions was 35 hr and
both missions were successful.
2. If Unit 1 fails at 40 hr during the first 50-hr mission and then
Unit 3 fails at 30 hr during the second 50-hr mission, find the
system’s reliability for the third 50-hr mission.
3. Determine the mean life of the system in Case 2, for the first
three missions.
PROBLEMS 763
The units that fail during a mission are replaced with fresh ones
at the beginning of the next mission.
18-4. A machine consists of three units which function reliabilitywise
in series, with the useful life failure rates and wear-out pdf pa-
rameters given in Table 18.5. Do the following:
1. Find the mean life to the first failure of the machine, or when
each failed unit is replaced by an identical one that had op-
erated a period equal to the period of operation of the failed
unit that is being replaced by a fresh unit.
764 PROBLEMS
1 2 3 4 5 6 7
Number
of xi 7 Ti, 77i,
unit % % fr/106 hr hr hr
1 0.15 0.85 40 20 500 2.0
unit fr/106 hr hr hr
1 1.5 5,000 900
1
2
3 1 0.9
0.7 I I I
7,000 500
3,000 800
1 2 3 4 5 6 7
Number
of A; , Yi, qi,
unit % % fr/106 hr hr hr pi
1 0.35 0.65 40 20 500 2.0
2 0.30 0.70 45 50 300 1.5
3 0.20 0.80 70 0 400 2.5
2. Find the mean time between the second and third failures if
Unit 1 fails first at the age of 600 hr and is replaced with a
new identical unit, and Unit 3 fails next at the age of 5,000
hr and is replaced with a new identical unit,
3. Find the stabilized mean time between failures of this ma-
chine, when the failed units are replaced by fresh units.
4. Calculate and plot the reliabilities for the following two cases:
4.1 Case 1.
4.2 Case 2.
3. Determine the mean life of the system in Case 2, for the first
four missions.
4. Discuss the results in Cases 1 and 2 comparatively.
The units that fail during a mission are replaced with fresh ones
at the beginning of the next mission.
1. Find the mean life t o the first failure of the machine, or when
each failed unit is replaced by an identical one that had op-
erated a period equal to the period of operation of the failed
unit that is being replaced by a fresh unit.
PROBLEMS 767
1 2 3 4 5 6 7
Number
of xi 9 7i9 77i,
unit % % fr/106 hr hr hr pi
1 0.20 0.80 40 10 500 2.0
2 0.20 0.80 45 40 300 1.5
3 0.20 0.80 70 20 400 2.5
2. Find the mean time between the third and fourth failures if
Unit 1 fails first at the age of 500 hr and is replaced with a
new identical unit, Unit 3 fails next at the age of 7,000 hr and
is replaced with a new identical unit, and Unit 4 fails next at
the age of 8,000 hr and is replaced with a new identical unit.
3. Find the stabilized mean time between failures of this ma-
chine, when the failed units are replaced by fresh units.
18-9. Work out Problem 18-8 again assuming that % = 0.3 and% =
0.7 for all three units and compare the results with those obtained
in Problem 18-8.
18-10. In a three-unit system, the units function reliabilitywise in se-
ries. Each unit can fail due t o chance as well as wear-out causes.
The parameters of each unit’s times-to-failure distribution are
listed in Table 18.9. Assume that only the failed unit is replaced
and then the system is readied for the next mission. Do the
following:
1. Find the system’s reliability for the third mission of 50 hr, if
the duration of the first and second missions was 35 hr and
they both were successful.
2. If Unit 1 fails at 40 hr during the first 50-hr mission and then
Unit 3 fails at 30 hr during the second 50-hr mission, find the
system’s reliability for the third 50-hr mission.
3. Determine the mean life of the system in Case 2, for the first
three missions.
4. Discuss the results in Cases 1 and 2 comparatively.
The units that fail during a mission are replaced with fresh ones
a t the beginning of the next mission.
REFERENCE
REFERENCE
10. He has been consulted extensively by over 100 industries and gov-
ernment agencies worldwide on Reliability Engineering, Reliabil-
ity & Life Testing, Maintainability Engineering, and Mechanical
Reliability matters.
Accessibility, figures 55
Additional maintenance policy
multistage replacement policy 402
opportunistic replacement policy 413
optimal inspection frequency 438
maximization of profit 438
maximization of equipment
availability 441
optional replacement policy 385
preventive replacement policy for
capital equipment 433
Age replacement policy 551
with minimal repair 560
spares provisioning 551
ARINC 22
Atlas guidance system 9
Availability, defined 24
Availability maximization 615
Failure Rate,
corrective for Policy I 269
Forward recurrence time (FRT) 371 379
definition 371
pdf 371
Maintainability
A posteriori determination 115
A priori determination 115
comprehensive definition 30
defined 24 91
Maintainability Engineering
benefits derived from 8
functions 77
objectives and benefits 4
Maintainability Program Plan
see also MIL-STD-470
Maintained equipment,
reliability when tracking ages
of all components 755
mean life 757
Maintenance
corrective maintenance 40
corrective 138
defined 37
maintenance personnel factors 44
maintenance personnel safety factors 45
maintenance support facilities and
equipment 46
operating time and
down-time categories 41
preventive 37 138 243
age replacement – Policy I 244
block replacement – Policy II 275
concepts 243
group of parts replacement 284
single exponential unit 253
Man-Hours, mean
corrective maintenance 129
maintenance to repair and replace 130
maintenance to replace 129
tests 163 178
Marginal assurance analysis 585
for optimum spare kit determination 583
Maximum maintenance time 102
MBRP see Modified block replacement policy
Mean active corrective and
preventive maintenance time 100
Mean active corrective
maintenance time 99
Mean active preventive maintenance time 100
Mean time to repair 93 97
MIL-STDs see Government Specifications
Military aircraft study 14
Minuteman missile 9
Mission reliability, defined 24
Modified block replacement policy
(MBRP)
multiple block replacement
with idle time cost 378
with inventory of spares 362
multi-period model, cost of 366
multi-period model, description of 366
single-period model, cost of 362
single-period model, description of 362
Operational Readiness 24 27
defined 24
Opportunistic replacement policy 413
application 423
conditions 422
cost model 413
principle 413
spares requirement model 423
Optimal cost limits,
finite time horizon 501
Optimal inspection frequency,
max imization of profit 438
Packaging practices 57
Periodic replacement policy 335
Modified periodic replacement
policy (MPRP) 338
Ordinary periodic replacement
policy (OPRP) 335
Poisson distribution 534
for spare parts prediction 535
Preventive maintenance policies 551
spares provisioning 551
Preventive maintenance
mean active preventive maintenance time 100
objectives 40
Preventive replacement policy for capital equipment 433
description 433
model 433
Serviceability 25
Spares provisioning
at a desired confidence level 533
confidence level selection 543
for a decaying population 544
for units that fail by
a prescribed operating time 546
inventory costs consideration 609
availability maximization
per cost ratio model 615
dynamic spares provisioning approach 612
understock and overstock cost model 609
under preventive maintenance policies 551
age replacement policy 551
age replacement with minimal repair 560
block replacement policy 554
group replacement policy 557
modified block replacement policy 564
Theoretical considerations
for optimum spare kit determination 591
Time categories
active repair time 25
administrative time 25 41
down time 25
free time 25
logistics time 25 41
operating time 25
storage time 25
times associated with maintenance 43
Warranty 573
spares provisioning 573
Weibull distribution 111
Weibull process
composite Weibull process 721
graphical estimates 701
maximum likelihood estimates 709
when testing more than one unit 711
WSEIAC reports 21