Professional Documents
Culture Documents
Petitioner Respondents: Third Division
Petitioner Respondents: Third Division
DECISION
NACHURA, J : p
SO ORDERED. 11
SO ORDERED. 18
PEA and Uy then came to us with their respective petitions for review
assailing the CA ruling. PEA's petition was docketed as G.R. Nos. 147933-34,
while that of Uy was docketed as G.R. Nos. 147925-26. The petitions,
however, were not consolidated.
On December 12, 2001, this Court resolved G.R. Nos. 147933-34 in this
wise:
WHEREFORE, in view of the foregoing, the petition for review is
DENIED. The Motion to Consolidate this petition with G.R. No. 147925-
26 is also DENIED.
SO ORDERED. 19
Thus, what remains for us to resolve is Uy's petition, raising the following
issues:
I
WHETHER OR NOT RESPONDENT COURT OF APPEALS HAS DEPARTED
FROM THE ACCEPTED AND USUAL COURSE OF JUDICIAL PROCEEDINGS
IN DISMISSING PETITIONER UY'S PETITION IN CA-G.R. SP NO. 59849 ON
THE ALLEGED GROUND OF NON-COMPLIANCE WITH THE
REGLEMENTARY PERIOD IN FILING AN APPEAL
II
WHETHER OR NOT THE RESPONDENT COURT OF APPEALS, IN
AFFIRMING THE DECISION OF THE CIAC ARBITRAL TRIBUNAL INSOFAR
AS IT DENIED CERTAIN CLAIMS OF PETITIONER UY, HAS DECIDED A
QUESTION OF SUBSTANCE NOT IN ACCORDANCE WITH LAW AND THE
APPLICABLE DECISIONS OF THE HONORABLE COURT
III
The filing of the motion for correction shall interrupt the running
of the period for appeal.
With the filing of the motion for correction, the running of the period to
appeal was effectively interrupted.
CIAC was supposed to resolve the motion for correction of computation
within 30 days from the time the comment or opposition thereto was
submitted. In Uy's case, no resolution was issued despite the lapse of the 30-
day period, and Uy considered it as a denial of his motion. Accordingly, he
elevated his case to the CA on July 24, 2000. But not long thereafter, or on
August 1, 2000, the CIAC issued an Order 22 denying the motion for
correction of computation.
Obviously, when Uy filed his petition for review with the CA, the period
to appeal had not yet lapsed; it was interrupted by the pendency of his
motion for computation. There is no basis, therefore, to conclude that the
petition was belatedly filed.
The foregoing notwithstanding, inasmuch as the CA resolved the
petition on the merits, we now confront the substantive issue — the
propriety of the CA's affirmance of the CIAC decision.
Uy cries foul on the award granted by CIAC, and affirmed by the CA. He
posits that PEA already admitted its liability, pegged at P146,484,910.10, in
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
its memorandum dated January 6, 2000. Thus, he faults the CA for awarding
a lesser amount.
We meticulously reviewed the records before us and failed to discern
any admission of liability on the part of PEA.
The PEA-PMO evaluation dated January 6, 2000, 23 where PEA allegedly
admitted its liability, reads in full:
MEMORANDUM
(Sgd.) (Sgd.)
ROGELIO H. IGNACIO FLORO C. URCIA
PMO-B Asst. Project Manager
Surely, on the days that EDC was waiting for the turn over of additional work
areas, it was paying rentals for the equipment on standby. Yet, CIAC
completely ignored these delays in determining the cost of equipment on
standby, reasoning that:
It must be pointed out, however, that the division of the vast area
to be landscaped into distinct work areas with different start of work
schedules under the PERT-CPM, [Uy] could easily have shifted his
equipment from an area where the delivery was delayed to the area
where there was an advanced turn-over. 27
This is wrong.
Records establish that EDC promptly commenced the landscaping work
on every area that was turned over. EDC, in fact, shifted its equipment
where there was an advance delivery, if only to minimize the additional
expenses incurred by reason of the long delays in the turnover of the other
work areas. Thus, in addition to the award of P19,604,132.06 for cost of idle
time for equipment by reason of the reduction of scope of work, Uy is
entitled to the cost of idle time for equipment by reason of the delay
incurred in the delivery of work areas.
The period of owner-caused delay was 546 days or 18.2 months. The
rate given by the Association of Carriers and Equipment Lessors (ACEL), Inc.,
and which was also used as basis by CIAC in granting the costs for
equipment on standby, was P1,982,271.60 per month of delay. Considering
that PEA was in delay for 564 days or 18.2 months, Uy is entitled to an
additional award of P36,076,360.32. Accordingly, he is entitled to an
aggregate amount of P55,680,492.38 for the equipment rentals on standby.
As to the awards of P2,275,721.00, for the cost of idle manpower, and
P6,050,165.05, for the construction of the nursery shade net area, we find
no reason to disturb the same, as Uy never raised this issue in his petition.
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
Next, we resolve Uy's claims for costs for additional hauling distance of
topsoil and for mobilization of water truck.
The approved hauling cost of topsoil was only P12.00/kilometer or
P120.00 for the 10 kms original source. Uy, however, claims that due to the
delay in delivery of work areas, the original source became depleted; hence,
he was constrained to haul topsoil from another source located at a much
farther distance of 40 kms. Uy insists that the exhaustion of topsoil at the
original source was solely attributable to the delay in the turnover of the
project site. Thus, he claims from PEA the increased cost of topsoil
amounting to P37,780,200.00.
Article 1724 of the Civil Code provides:
ART. 1724. The contractor who undertakes to build a
structure or any other work for a stipulated price, in conformity with
plans and specifications agreed upon with the land-owner, can neither
withdraw from the contract nor demand an increase in the price on
account of the higher cost of labor or materials, save when there has
been a change in the plans and specifications, provided:
By this article, a written authorization from the owner is required before the
contractor can validly recover his claim. The evident purpose of the provision
is to avoid litigation for added costs incurred by reason of additions or
changes in the original plan. Undoubtedly, it was adopted to serve as a
safeguard or a substantive condition precedent to recovery. 28
This provision is echoed in the Landscaping Contract, viz.:
ARTICLE IX
Change of Work
xxx xxx xxx
9.3. Under no circumstances shall PEA be held liable for the
payment of change of work undertaken without the written approval of
the PEA General Manager . . . .
ARTICLE X
Extra Work
xxx xxx xxx
10.3. Under no circumstances shall PEA be held liable for the
payment of extra work undertaken without the written approval of the
PEA General Manager to perform the said work. 29
Admittedly, EDC did not secure the required written approval of PEA's
general manager before obtaining the topsoil from a farther source. As
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
pointed out by the CIAC:
There is no change order authorizing payment for the increased
cost upon which this claim is based. There is, therefore, no legal right
based upon contract (the landscaping agreement or a change order)
that would impose such a liability upon [PEA]. In a lump sum contract,
as that entered into by the parties, the matter of how the contractor
had made [a] computation to arrive at [a] bid that he submits is
completely irrelevant. The contract amount of delivered topsoil is
P780.00 per truckload of 5.5 cubic meters sourced from a distance of
[10] km. or 100 [meters]. There is nothing in Exhibit "L" or in the
landscaping contract (Exhibit "A") that would indicate an agreement of
[PEA] to pay for the increase in hauling cost if the source of topsoil
exceeds 10 kilometers. Corollarily, there is also nothing therein to show
that [PEA] would also be entitled to decrease said costs by paying less
if the distance would have been less than 10 kilometers. Had there
been such a counterpart provision, there might have been more
arguable claim for [Uy]. Unfortunately, no such provision exists. 30
Neither can we hold PEA liable based on solutio indebiti, the legal
maxim that no one should enrich itself at the expense of another. As we
explained in Powton Conglomerate, Inc. v. Agcolicol, 35
the principle of unjust enrichment cannot be validly invoked by
the respondent who, through his own act or omission, took the risk of
being denied payment for additional costs by not giving the petitioners
prior notice of such costs and/or by not securing their written consent
thereto, as required by law and their contract.
Uy cannot, therefore, claim from PEA the costs of the additional hauling
distance of topsoil, and of the mobilization of water trucks.
Uy also assails the grant of attorney's fees equivalent to 10% of the
total amount due. Citing paragraph 24.4 of the Landscaping and
Construction Agreement, Uy asserts entitlement to attorney's fees of twenty
percent (20%) of the total amount claimed. He ascribes error to the CIAC and
the CA for reducing the stipulated attorney's fees from 20% to 10% of the
total amount due.
Paragraph 24.4 of the agreement provides:
Should the PEA be constrained to resort to judicial or quasi-
judicial relief to enforce or safeguard its rights and interests under this
Agreement, the CONTRACTOR if found by the court or [the] quasi-
judicial body, as the case [may be], to have been at fault, shall be
liable to PEA for attorney's fees in an amount equivalent to twenty
CD Technologies Asia, Inc. © 2021 cdasiaonline.com
percent (20%) of the total [amount] claimed in the complaint, exclusive
of [any] damages and costs of suit. 36
The Court finds Uy's claim for attorney's fees equivalent to 20% of
whatever amount is due and payable to be exorbitant. The CIAC and the CA,
therefore, correctly awarded 10% of the total amount due and payable as
reasonable attorney's fees.
Finally, on the propriety of the writ of injunction. TcEDHa
Footnotes