Dam Safety Guidelines Brief Overview - MD
Dam Safety Guidelines Brief Overview - MD
Dam Safety Guidelines Brief Overview - MD
A Brief Overview
April 2010
Mustafa Darwash
Preface
This purpose of this paper is to give a very brief overview of the major points presented
in the CDA’s Dam Safety Guidelines report. This paper will attempt to shed light on the
risk areas that dam projects entail. This paper is in no way to be taken as a complete
reference for dam safety guidelines and does not act to substitute the original document
by the CDA.
Dam Safety Management
Many factors can contribute and play a major role in rating a Dam project’s risk, whether
a new or existing dam. Hence, it is critical to identify all elements that can influence the
Potential Consequences
When referring to potential consequences or damages it is important to classify the type or
category of these consequences that may arise as a result of an undesirable event, such as a
dam failure or breach;
Life Safety/loss
Economic Impacts
Environmental Impacts (must be evaluated in terms of whether restoration of env. is
feasible and long it would take)
Cultural loss
Etc.
Furthermore, it is also important to evaluate each of the latter based on magnitude and duration
of impact. Factors that can affect severity include:
Flow rate
Depth
Topography
Transportation routes
Mobility of the population
Site access
Advance warning
Dam Failure Inundation Zone (DFIZ)
Population At Risk (PAR): all persons directly exposed to floodwaters within the DFIZ.
- Flat terrain: failure could inundate a huge are and large PAR, but would be slow-moving
and shallow. Hence, Potential Loss of Life (PLOL) would be minimal.
Dam
Spillway
Foundation
Abutments
Reservoir
Tailraces
Etc.
Dam Function
A dam’s function is vital information that must be known prior to rating a dam project
because it can play a great role in identifying potential consequences of any undesirable
Water storage
Mining tailings impoundment
Power generation
Flood control
Recreation
Navigation
Etc.
One of the factors that will help define the risk level of any dam project is the retained
substance by Dam:
Water
Water with any other substance
Fluid waste
Fluid tailings
Contaminants
Etc.
The retained substance will determine the potential consequences of a seepage, leaks
or dam failure based on whether there will be release of fluids that can harm the public
or the environment.
It is important to identify the potential failure modes (See Table 1 in appendix) of a dam
and assess the consequences by estimating the resulting discharge. The resulting
discharge can help quantify the consequences of both downstream and upstream
the discharge hydrograph (flow rate), flood wave routing (rout flood waves to an area
where the effects would be negligible) and inundation map (flood area).
Loss Life
Injury
Disruption of life
Property damage
Contamination
Etc.
Dam Breach
A dam breach shape and timing can depend on the type of dam:
1. Concrete gravity dam: tend to have partial breach, monolith sections formed during
construction are forced apart. Also, Concrete dams with abutments are resistant to
erosion and can withstand overtopping without serious damge.
2. Embankment dam: do not tend to have complete or sudden failure. Breach will erode a
portion of dam slowly. Also, embankments are more likely to fail in case of overtopping
than for concrete dam.
4. Buttress Dam
Design
In order to define design requirements (return periods) the consequences of a dam
failure should be analyzed for a random (i.e. earthquake, mis-operation, or other event)
failure as well as for a flood scenario. Therefore, the maximum flood for which the
selected on the basis of the potential consequences of failure. The Earthquake Design
and should be based on the consequences of dam failure. See Table 5-1.
Emergency Preparedness
Emergency response/preparedness plan should exist for construction and operations
phases of a dam and especially where significant cofferdams are required. For a new
dam, the final plans should be in place prior to first filling of the reservoir.
Dam Maintenance
Maintenance of the equipments and systems of a Dam is very important to ensure
operational availability, safe operation and integrity whether for an existing or new dam
- Sealing of cracks.
Hence, a concrete related risk that should be emphasized is loss of structural integrity
due to pattern cracking. Alkali Aggregate Reaction must be taken into consideration and
diagnosed for as it can cause concrete to lose strength. Where cold climates exists,
For existing dams some findings which typically necessitate follow‐up include:
Note 1: There is no identifiable population at risk, so there is no possibility for loss of life other than by
unforeseeable misadventure.
Note 2: People are only temporarily in the dam‐breach inundation zone: for example, passing through on
transportation routes, or voluntarily participating in recreational activities.
Note 3: The population at risk is ordinarily located in the dam‐breach inundation zone, e.g. as permanent
residents. Three classes (High, Very High, Extreme) are proposed to allow for more detailed estimates of
potential loss of life to assist decision‐making if the dam owner is able to do the appropriate level of
analysis.
Note 4: In general, loss of life is a random variable characterized by a probability distribution bounded by
0 and the PAR (i.e. one probability of X fatalities, a different probability of Y fatalities, etc., over the
range from 0 to PAR). The shape of this distribution depends almost entirely on assumptions in the
estimation process. In specific cases, a certain value of this random variable could be selected to provide a
single‐value estimate of loss of life.
Note 5: The appropriate level of safety required at a dam where people are temporarily at risk depends on
the number of people, the exposure time, nature of activity and other conditions. The requirements could
correspond to a higher class. However, the design flood requirement, for example, might not be higher if
the temporary population is not likely to be present during the flood season.
Notes:
1. As defined in Table 1‐1, Suggested Dam Classification Scheme.
2. Depends on the number of people exposed, length of exposure, seasonal nature of flooding and
consequences, and other considerations.
3. For purposes of probabilistic risk analysis, the annual exceedance probability (AEP) of that flood may
be assumed as 10‐4.
4. Extrapolation of flood statistics beyond 1/1000 year flood (10‐3 AEP) is discouraged. The flood
defined as 1/3 between 1/1000‐year and PMF should be used instead of any previously estimated
1/10,000 year flood.
5. For purposes of probabilistic risk analysis, the AEP of that flood may be assumed as 10‐5.
6. For purposes of probabilistic risk analysis, the AEP of the PMF may be assumed as 10‐6.
7. AEP levels are to be used for the “mean” rather than the “median” estimates of the hazard.