Update Progress Series – Part 2: How to use Activity Steps
But by this solution, you can only record your progress based on your steps.
How to use:
After that you should now, how these steps assigned to the activities. In the Activity
Sheet go to “Activity Details” then please find “Steps” and after that you can create
your steps:
Date: 17-Jan-2020
Page 1 of 4
Prepared By: @YouTube/ Global Project Control
Update Progress Series – Part 2: How to use Activity Steps
But if you expect to use these steps to another activities, for instance develop steps
for Engineering section activities as per below table:
In this situation, I suggest you to create “Steps Template” in “Enterprise > Activity
Steps Templates” you can create all kind of template based on your Progress
Measurement System. For instance, I created Sample Webinar Template with
above Table on below picture
Date: 17-Jan-2020
Page 2 of 4
Prepared By: @YouTube/ Global Project Control
Update Progress Series – Part 2: How to use Activity Steps
And now if you go to Step Tab in activity sheet, you can assign these three steps to
each activity in engineering section just by select “Add from Template” bottom.
And if you record the progress by steps, it will be appeared to your progress column
(for example Physical % complete).
Important Note:
When updating activity with steps you MUST first record an ACTUAL START then
go through STEPS
When you change your project setting to Activity Steps, Other activities
remain to Duration and Unit % complete type.
Each step is assigned a Step Weight, which then determines the Step Weight
Percent. You can insert it by using it to STEP Column (below Picture). The total of
all the steps will automatically equal 100%.
Date: 17-Jan-2020
Page 3 of 4
Prepared By: @YouTube/ Global Project Control
Update Progress Series – Part 2: How to use Activity Steps
Summary:
If you have complex activity and you don’t want to share more information in your
schedule, Activity Steps is the best solution in Primavera P6.
If you need more help you can contact me, I am always available for further
information. Also, I am ready to share you below information:
1. PDF File
2. Sample Project
3. Video file https://youtu.be/mzR_upytJxI
https://www.youtube.com/c/GlobalProjectControl
https://www.instagram.com/globalprojectcontrol/
https://www.facebook.com/FBglobalprojectcontrol
Date: 17-Jan-2020
Page 4 of 4
Prepared By: @YouTube/ Global Project Control