2 COTMA Overview Amanda Koh 2
2 COTMA Overview Amanda Koh 2
A m a n d a Ko h
Pr incipal Senior Associate
T. 6 8 3 7 8 1 5 9 / 9 6 4 4 5 4 4 3
E . a m a n d a ko h @ e l d a n l aw. c o m
I. Scope and application of the COTMA
• Provides temporary and targeted protection for qualifying individuals and businesses
who are unable to fulfill their contractual obligations due to the COVID-19 pandemic.
Part 2 :Temporary Reliefs for inability to perform contracts
Temporary relief and protection ends 30 September 2021
Yes
Is the contractual obligation which you are unable to No
or will be unable to perform is one that is to be
performed on or after 1 Feb 2020?
Yes
Yes
NOT
ELIGIBLE
ELIGIBLE
“ T O A M AT E R I A L E X T E N T C AU S E D B Y A
C OV I D - 1 9 E V E N T ”
Definition of “COVID-19 event” (Section 2)
Section 6(6):
“Despite anything in the contract, where the subject inability is the inability to supply goods
or services in accordance with the terms of the contract and such inability occurs on or after 1
February 2020 but before the expiry of the prescribed period, the fact that the inability to
perform the obligation in the contract was a material extent caused by a COVID-19 event is a
defence to a claim for a breach of contract in respect of the subject inability”
Section 6(7):
- Any contractual right or obligation that accrues before 1 Feb 2020 and after 30 Sept 2021
will not be affected
- Any judgment, arbitral award, adjudication determinations, compromise or settlement given
or made before notification for relief is served will not be affected
PA RT 2 - N O T I F I C AT I O N F O R
RELIEF (NFR)
• Prescribed period : 20 April 2020 to 30 September 2021
• Submission of prescribed form (Form 1) via the electronic system on
Min Law’s website
• Service on the other party to the contract, surety or guarantor of the
subject obligation and issuer of the performance bond (if applicable)
• The Assessor’s determination is binding on all parties to the application and all parties
claiming under or through them. (Section 13(9))
• There is no appeal from an assessor’s determination (Section 13(10))
Eligible contracts:
PA RT 8 A –
• Construction contract entered into before
EXTENSION OF 25 March 2020 and remains in force on 2
TIME FOR November 2020
C O N S T RU C T I O N
CONTRACTS • As at 7 April 2020, any construction
(SECTIONS 39A, works to be performed under the
39B) construction contract have not been
certified in accordance with the
construction contract as completed
• 122 days to be reduced by the number of days EOT granted under the construction
contract or otherwise agreed by parties in the period between 7 April 2020 to 6 August
2020
• 122 days not applicable if:
(a) any of the construction works were performed any time between 20 April 2020 and 30 June
2020 (both days inclusive); or
(b) Court or arbitration proceedings have, before 2 November 2020, commenced in relation to
the failure to comply with the completion date
(c) Any judgment, arbitral award, or compromise or settlement entered into in the course of
result of proceedings, has been given or made before 2 November 2020
( B C A ) E O T- P U B L I C
S E C T O R C O N S T RU C T I O N
CONTRACTS
BCA Circular 27 April 2021 (Simplified Claim process for
EOT)
(Beyond COTMA)
• Common ex-gratia EOT for loss of productivity between 7
Aug 2020 to 31 Dec 2020 – Total 49 days
Aug Sep Oct Nov Dec
Eligible contracts:
• Tender closed on or before 1 June 2020
• Not terminated on or before 7 Aug 2020
• Not certified substantially completed on or before 7 Aug 2020
Eligible contracts:
• Construction contract entered into before 25
March 2020 and remains in force on 2 November
2020
C O N S T RU C T I O N
• Preconditions:
CONTRACTS 1. “unable to complete any of those
construction works by the completion date”
(SECTIONS 39C
TO 39F) 2. “inability is to a material extent caused by a
COVID-19 event”
Quantum:
• 50% of qualifying costs incurred
• Capped at 0.2% of contract sum per calendar month, maximum total
amount must not exceed 1.8% of contract sum
PA RT 8 B - C O S T S H A R I N G
• Claim for cost sharing “must” be claimed in a payment claim – Section 39D(6)
• The amount may be claimed as a “debt due” in arbitration or court proceedings.
• Disputes on cost-sharing may be submitted to adjudication under the SOP Act
- The adjudication application must provide all information and documents relevant to the claim, including
extract of the supporting contract relating to the qualifying costs, invoices and receipts showing amount of
costs and date the costs were incurred, and information and documents showing the amount of relief that the
contractor may have received from other reliefs.
• The adjudicator must determine (a) whether Part 8B of the COMTA applies; and (b) the
amount under the respondent is liable to pay
- Overrides Section 17(2A) of the SOPA preventing claims for loss or expense
BCA circular dated 27 April 2021 (Circular on simplified claim process for prolongation costs in
public sector contracts)- eligible contracts up to $100 million- GPEs will co-share 0.1% of
contract sum for every month of delay rising from COVID-19 events
Commenced on 6 Aug 2021
• Framework to adjust contract sum to
address the increase in foreign manpower
salary
PA RT 1 0 A - Applicable contracts
INCREASE IN • construction contracts as defined under the
SOPA
M A N P OW E R
COST Preconditions:
• Contract entered into before 1 October
(SECTIONS 79A 2020;
TO 79K) • Works not certified completed by 10 May
2021;
• Not terminated before 10 May 2021 or no
notice of termination given before 10 May
2021
PA RT 1 0 A - C L A I M F O R I N C R E A S E I N
M A N P OW E R C O S T S
• Application to Part 10A Assessor for adjustment in contract sum to take into account
increase in the amount of foreign manpower salary costs at any time between 1 October 2020
and 30 September 2021 because of a COVID-19 event.
- Time to make application: by 14 October 2021
- Claim for foreign manpower salary can include bonuses, allowances and overtime payments
• Pre-condition: Applicant must have made a reasonable attempt to negotiate with the
Respondent for the adjustment - Evidence to be included in the application
https://constructionlaw.sg
A M A N DA KO H
Principal senior associate
T. 6837 8159/ 96445443
E. a m a n d a k o h @ e l d a n l a w. c o m