RENCANA KERJA PERTAMINA PRIOK

selasa rabu kamis jumat


JUMLAH
NO DESCRIPTION HARI 1 2 3 4
1 FAT ke supplier 2
1 INVOICE 1
1 kirim ke bar bending 3
1 Pabrikasi banding 0
2 Checklist bending
3 kirim ke workshop/welding 0
4 Pabrikasi 0
-Setting titik nozzle
Setting, pengelasan flange & fitting
Dyepenetran
Checklist
Painting pipe
5 Gate pass pipa
- dokumentasi dan QTY
6 Survey schafolding

5 patra paint (menunggu) 0


6 Painting patra 0
7 0
8 Gate pass pipa 0
9 kirim pipa ke site project 0
10 Invoice nozzle 0
11 pasang nozzle 0
12 Qty schafolder 1
13 Invoice schafolding 0
14 Sertifikat schafolder 1
15 Metode schafolder 1
16 onsite scafolding 0
17 survey tim schafolder 0
18 Gate pass schafolding 0
19 kirim schafolding ke site 0
20 instalasi schafolding 0
21 Ceklist HSSE 0
22 Pembongkaran pipa riser & erection 0
23 Instalasi pipa riser 0
24 Pembongkaran pipa ring ex & erection ke site o 0
25 Instalasi pipa ring & erection 0
26 Ceklist & finishing 0
27 tescom 0
28 Terbit BA 0
29 Bongkar peranca 0
30 Cleaning area 0

hydro test (14 bar selama 2 jam)


JA PERTAMINA PRIOK

FEBRUARI
sabtu minggusenin selasa rabu kamis jumat sabtu minggu senin selasa rabu kamis jumat

5 6 7 8 9 10 11 12 13 14 15 16 17 18
open fat close FAT
DP close

open
TANGKI 4-A
sabtu minggu senin selasa rabu kamis jumat sabtu minggu senin selasa rabu

19 20 21 22 23 24 25 26 27 28 1 2

open do open do open do

open
open
A
MARET
kamis jumat sabtu minggu senin selasa rabu kamis jumat sabtu minggusenin selasa rabu kamis

3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
RET
jumat sabtu minggusenin selasa rabu kamis jumat sabtu minggusenin selasa rabu kamis

18 19 20 21 22 23 24 25 26 27 28 29 30 31