A-Bike PIPE Works Final BOQ

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 23

project: Project:- Bike water Supply and sanitation project

Cost Summary all works

S.No Description of Item Quantity Amount Total Amount

A-1 General Items 1 2,950,000 2,950,000


A-2 Pipe works 1 44,370,054 44,370,054
A-3 Civil works 1 32,576,773 32,576,773
A-4 Electromecnical 1 19,067,334 19,067,334
TOTAL 98,964,160
15% VAT 14,844,624
GRAND TOTAL 113,808,784
Summary of Pipe works
S.No Description of Item Unit Amount Total Amount
Supply of HDPE - Raising main and Fitting :-
B-1 From Borhole To 500m3 Booster Station and 20,355,000.0 20,355,000.0
from booster 1 to Service Reservior 1
B-2 Mainline welding,laying & fitting 1 1,414,000.0 1,414,000.0
Main Line Trench excavation from BH to
B-3 5,725,424.0 5,725,424.0
Service Reservoir 1
B-4 Mainline pipe Civil Works 1 483,824.2 483,824.2
B-5 Distribution pipe and fitting supply 1 8,815,776.5 8,815,776.5
Distribution laying , welding and trench
B-6 7,576,029.1 7,576,029.1
excavation 1
TOTAL 44,370,053.8
Bill No A: General Items

Unit rate
Item Description
Unit Qty (Birr)

A1 Contractor's Mobilization & demobilization


A1.1 Mobilization of contractor's man power, construction materilas
and equipment to construction site Ls 1 600,000
A1.2 Demobilization of contractor's man power, construction
materilas and equipment from construction site Ls 1 480,000
A1.3 Erect Contractor's camp site including connection to water and
power supply, fencing of the camp and site safety material for Ls 1 550,000
including all necessary material as directed by the engineers
A1.4 Provide survey control and setting out of the work for
construction of transmission mains, reservoirs, pumping stations Ls 1 60,000
and distribution network
A1.5 Provide concrete tests(compresive strength test ,slumb test,
water permeability test) ,soil tests ( bearing capacity test,
specific gravity test,moisture content tes) ,reinforcement test Ls 1 150,000
(tensile strength bend and re-bend test) and construction
material quality testing including all nesecary test as directed by
Engineer
A1.6 Fabricate and erect metallic project sign board (4 in No) for
project identification including printing of the tilles. (titles, and
size of the board to be provided by the client) No 4 35,000

A1.7 Provide Engineers Office for supervision with a minumum of


40 sqm furnished with four executive desks, four swivel chairs,
8 guest chairs, 4 shelves and all other furniture for the office
including one drawing table, desktop with A3 color printer, Ls 1 300,000
water supply , internet connection and power supply, .

A1.8 Provide all insurances for personnel, works and ,aterials liability
as well as third part liability insurances for the whole period of Ls 1 500,000
the works

A1.9 Prepare and provide shop drawings , as built-drawings albuns


of all the constructed water supply components to the scale as
approved by the Engineer No 2 65,000

A1.1 Prepare and provide operation and maintenance manual of the


0 works as approved by the Engineer
Ls 1 40,000

TOTAL CARRIED TO SUMMARY FROM Bill No 1


Total
Amount
(Birr)

600,000

480,000

550,000

60,000

150,000

140,000

300,000

500,000

130,000

40,000

2,950,000
BILL NO. B-01 SUPPLY OF RAISING MAIN PIPE
SUPPLY OF HDPE PE100 PN16 - RAISING MAIN:- From Bh To 500m3 Booster Station and
from booster 1 to Srvice Reservior
ITEM NO DESCRIPTION UNIT QNTY RATE ETH AMOUNT ETH
CLASS B-01: PIPE WORK - PIPES
B-01: SUPPLY
Supply, Transport to Site and Store, including
jointing materials, bolts gaskets, packing, jointing
B-01
glue etc., as applicable. Excluding laying and
joining.
B-01.1 HDPE PE 100 Pipes PN 16/SDR 11
B-1.1.1 OD 250mm m 10,000 2,016 20,160,000
PAGE TOTAL FOR B-01
B-02 MAIN LINE FITTING SUPPLY HDPE PE100 PN16
B-1.1.2 Fitting Supply UNIQUANTITRATE TOTAL AMOUNT
B-1.1.3 Air Release & Washout Fittings
B-1.1.4 Air Valve FOR OD250 PN16
B-1.1.5 Stub flange DN250 NO 4 6,500 26,000
B-1.1.6 HDPE butweld Tee DN250*250*100 NO 3 7,500 22,500
B-1.1.7 Flanged gate valve DN100 NO 4 12,000 48,000
B-1.1.8 Flanged air realease valve DN100 NO 3 9,000 27,000
B-1.1.9 backing ring DN250 NO 5 2,000 10,000
B-1.1.10 WASH-OUT FOR OD 250 PN16 NO 0
B-1.1.11 HDPE butweld Tee DN250*250*250 NO 3 8,500 25,500
B-1.1.12 Flanged gate valve DN250 NO 2 18,000 36,000
SUB TOTAL 195,000
TOTAL FOR PIPE AND FITTING 20,355,000
UNT ETH

AL AMOUNT
BILL NO. B-03
MAIN LINE TRENCH EXCAVATION (RAISING AND TRANSMISSION MAIN) EARTHWORK
B-03.1 FROM BH TO BOOSTER STATION 1
B-03.1.1 Earth Work unit qty
site clearance cutting bushes ,tree with 2.5m width and
B-03.1.1.1 2,500m length for the raising mainlienes to make acces m^2 6,250.00
road accesible
Trench excavation in ordinary soil to a dimension
(1mx1.2mx2,421.6m )width ,depth and length respectively
B-03.1.1.2 m3 2,906.00
required disposal of surplus excavated material as per
standard drawing trench depth detail
Trench excavation in soft rock for pressure mains to a
B-03.1.1.3 1mx1.2mx1,480m width ,depth and length and disposal of m3 1,776.00
surplus excavated material
Trench excavation in Hard rock for pressure pipes to a
B-03.1.1.4 (1mx1.2mx1,102m) width ,depth and length and disposal of m3 1,322.40
surplus excavated material
Supply and spread 150 mm deep approved bedding material
B-03.1.1.5 m3 897.12
below the pipe in all Trench excavation,
backfill with excavated native material above the pipe in
B-03.1.1.6 m3 2,542.00
Trench excavation, for normal soil

Back filling with imported approved selected material from


B-03.1.1.7 the site not more than 1km for soft rock and hard rock for m3 2,711.00
Trench excavation,
SUB TOTAL B-03.1.1.7
B-03.2 From Booster 1 to Bike Service Reservoir
B-03.2.1 Earth Work unit qty
site clearance cutting bushes ,tree with 2.5m width ,2,000m
B-03.2.1.1 m^2 6,250.00
length for the raising mainliene
Trench excavation in ordinary soil to a depth of 1.2m *1m
B-03.2.1.2 wide and disposal of surplus excav`ated material as per m3 3,116.00
standard drawing trench depth detail
Trench excavation in soft rock for pressure mains to a depth
B-03.2.1.3 of 1.2m & 1m wide and disposal of surplus excavated m3 1,200.00
material
Trench excavation in Hard rock for pressure pipes to a
B-03.2.1.4 depth of 1.2m & 1m wide and disposal of surplus excavated m3 1,800.00
material
Supply and spread 150 mm deep approved bedding material
B-03.2.1.5 m3 1,680.00
below the pipe in all Trench excavation,
Back filling with imported approved granular material from
B-03.2.1.6 m3 2,625.00
the site for hard rock and soft rock Trench excavation,
Back filling with Native material in ordinary soil for Trench
B-03.2.1.7 m3 3,272.00
excavation
SUB TOTAL FOR B-03.2
Grand Total FOR B-03
RTHWORK

rate total

35.00 218,750.00

104.00 302,224.00

320.00 568,320.00

410.00 542,184.00

225.00 201,852.00

80.00 203,360.00

240.00 650,640.00

2,687,330.00

rate total
35.00 218,750.00

104.00 324,064.00 2596.66667

320.00 384,000.00 1000

410.00 738,000.00 1500

225.00 378,000.00 5096.66667

80.00 210,000.00

240.00 785,280.00
3,038,094.00
5,725,424.00
BILL NO. B-02 : Welding & Laying, of Main line 250mm PN16 HDPE PE100 Pipes & Components of
air release valve and washout and pressure line Testing
Item No Description unit Qty Rate
Raising mainline to booster station 1 and from booster station
B-02.1
1 to Bike Service Reservoir pipe Welding and Laying
HDPE PE 100 Pipes PN 16/SDR 11 OD 250 mm wellding
B-02.1.1 WP 1,111 450
points
HDPE PE 100 Pipes PN 16/SDR 11 OD 250 mm laying m 10,000 45
SUB TOTAL- B-02.1
B-02.2 Air Release & Washout Fittings
B-02.2 Air Valve FOR OD250 PN16
B-2.2.1 Butwel stub flange DN250 NO 2 6,500
B-2.2.2 Butweld tee DN250*250*110 NO 3 7,500
B-2.2.3 Flanged gate valve DN110 NO 10 12,000
B-02.3 WASH-OUT FOR OD 250 PN16
B-02.3.1Tee DN 250X250X100 NO 3 7,500
B-02.3.2Flanged gate valve DN100 NO 3 12,000
SUB-TOTAL For B-02.2 and B-02.3
B-02.4 PRESSURE TESTING AND DISINFECTION
Disinfection of pipelines: flushing with clear water, filling with
water containing 0.15 g/l calcium hypo chloride, left for 24
B-02.4.1 Ls 1 250,000
hours. This includes supply of all necessary equipment,
chemical and water
SUB TOTAL FOR B-02.4
Total Carried to Summary FOR BILL NO. B-02
pes & Components of
total

500,000
450,000
950,000

13,000
22,500
120,000
0
22,500
36,000
214,000

250,000

250,000
1,414,000
BILL NO. B-0.4.1 Construction of Valve chambers, crossings and Thrust & anchor blocks for pr
line
River Crossing Type OD 250mm HDPE #2
B-04.1.0 Description unit Quantity unit rate
Foumdation Excavation of (1m *1m ) width and
B-4.1.1 depth respectively m3 45.00 104.00
B-4.1.2 C- 30 Concrete Casting works m3 12.50 3,899.00
provide ,cutt ,bend and fix of reinforcement Price
B-04.2 should include tying wires.
B-04.2 diameter 12 mm. plain bars kg 177.63 75.20
B-4.1.3 diameter 6mm plain bar kg 88.82 101.90
B-4.1.4 Blackwire kg 10.00 90.00
B-04.3 Form work m2 50.00 500.00
B-04.3 Back fill m3 35.00 80.00
Subtotal for B-04.1 one River Crossing
Subtotal for Two River Crossing 4.1
B-04.4 River Crossing Type OD 250mm HDPE #2
B-04.5 Description unit Quantity unit rate
Foumdation Excavation of (1m *1m ) width and
B-04.6 depth respectively m3 20.00 104.00
B-04.7 C- 30 Concrete Casting works m3 5.00 3,899.00
provide ,cutt ,bend and fix of reinforcement
B-04.8 Price should include tying wires.
B-04.9 diameter12 mm.plain bars kg 85.26 75.20
B-04.10 diameter 6mm plain bars kg 35.53 101.90
B-04.12 Form work m2 20.00 500.00
B-04.13 Back fill m3 14.00 80.00
Subtotal for B-04.2 one River Crossing
Subtotal for Two River Crossing
River Crossing Type OD 250mm HDPE #1
B-04.1.0 Description unit Quantity unit rate
Foumdation Excavation of (1m *1m ) width and
B-4.1.1 depth respectively m3 45.00 104.00
B-4.1.2 C- 30 Concrete Casting works m3 12.50 3,899.00
provide ,cutt ,bend and fix of reinforcement Price
B-04.2 should include tying wires.
B-04.2 diameter 12 mm. plain bars kg 177.63 75.20
B-4.1.3 diameter 6mm plain bar kg 88.82 101.90
B-4.1.4 Blackwire kg 10.00 90.00
B-04.3 Form work m2 50.00 500.00
B-04.3 Back fill m3 35.00 80.00
Subtotal for B-04.1 one River Crossing
B-04.14 Concrete Valve Chamber #4

Material Cost
It. No Type of material Unit Qty Unit rate
B-4.15 Excavation in normal soil m3 27.00 104.00
B-4.16 Hard Core m3 5.80 203.00
B-4.17 Concrete C -20 for wall m3 1.98 3,424.00
B-4.18 Back fill m3 3.70 80.00
B-4.19 Concrete cover slab
B-4.20 Concrete C-20 m3 0.97 3,424.00
B-4.21 Form Work m2 11.84 500.00
B-4.22 Bar kg 12.00 75.20
sub-Total
Total for four Concrete valve chamber 4.3
Grand Total for pipe civil works
st & anchor blocks for pressure

Cost

4,680.00
48,737.50

13,358.10
9,050.76
900.00
25,000.00
2,800.00
104,526.36
209,052.71

Cost

2,080.00
19,495.00

6,411.55
3,620.51
10,000.00
1,120.00
42,727.06
85,454.12

Cost

4,680.00
48,737.50

13,358.10
9,050.76
900.00
25,000.00
2,800.00
104,526.36

Total cost
2,808.00
1,177.40
6,779.52
296.00

3,314.43
5,920.00
902.40
21,197.75
84,791.01
483,824.19
BILL NO. C -B.05.0
SUPPLY OF DISTRIBUTION PIPE
DISTRIBUTION supply Unit Qty Rate
B-05.1 Supply of HDPE PIPE PE 100 PN10
B-05.1.1 HDPE PIPE PE100 PN10 OD 40 m 750 34.8
B-05.1.2 HDPE PIPE PE100 PN10 OD 50 m 850 55.2
B-05.1.3 HDPE PIPE PE100 PN10 OD 63 m 1,448 85.2
B-05.1.4 HDPE PIPE PE100 PN10 OD 75 m 2,880 121.3
B-05.1.5 HDPE PIPE PE100 PN10 OD 90 m 1,300 158.4
B-05.1.6 HDPE PIPE PE100 PN10 OD 110 m 3,406 256.8
B-05.1.7 HDPE PIPE PE100 PN10 OD 125 m 850 330.0
B-05.1.8 HDPE PIPE PE100 PN10 OD 140 m 441 420.0
B-05.1.9 HDPE PIPE PE100 PN10 OD 160 m 3,686 540.0
B-05.1.10 HDPE PIPE PE100 PN10 OD 180 m 760 660.0
B-05.1.11 HDPE PIPE PE100 PN10 OD 200 m 371 842.4
B-05.1.12 HDPE PIPE PE100 PN10 OD 225 m 1,200 1,030.9
B-05.1.13 HDPE PIPE PE100 PN10 OD 280 m 950 1,562.7
SUBTOTAL FOR C-01.1 18,892.0
B-05.1.13 supply and Installation of PN 10 HDPE & GS
Pipe Fittings
B-05.1.14 Hdpe butweld Reducer Tee OD 200*110 No 4 7,500
B-05.1.15 Hdpe butweld Reducer Tee OD 110*90 No 6 3,390
B-05.1.16 Hdpe butweld Reducer Tee OD 160*90 No 4 4200.0
B-05.1.17 Hdpe butweld Reducer Tee OD 160*75 No 6 4100.0
B-05.1.18 Hdpe butweld Reducer Tee OD 110*75 No 5 3,150
B-05.1.19 Hdpe butweld Reducer Tee OD 160*110 No 9 4,500
B-05.1.20 Hdpe butweld Reducer Tee OD 160*140 No 2 5,200
B-05.1.21 Hdpe butweld Reducer Tee OD 90*63 No 2 2,800
B-05.1.22 Hdpe butweld Reducer Tee OD 63*50 No 4 2,500
B-05.1.23 Hdpe butweld Reducer Tee OD 75*50 No 6 2,690
B-05.1.24 Hdpe butweld Tee OD 110 No 3 3,600
B-05.1.25 Hdpe butweldTee OD 75 No 2 3,000
B-05.1.26 Hdpe reducer stright but weld OD 160*110mm No 2 4,080
B-05.1.27 HDPE cross Tee OD 90mm No 2 3,800
B-05.1.28 HDPE cross Tee equal sides OD 160*110mm No 1 6,500
B-05.1.29 Hdpe butweld Reducer Tee OD 225*200*225 No 2 7,500
B-05.1.30 Hdpe strigth Reducer butweld OD 225*160mmNo 1 6,800
B-05.1.31 Stub flange but weld DN 110mm No 1 3,300
B-05.1.32 Stub flange but weld DN 75mm No 1 2,600
B-05.1.33 Stub flange but weld DN 90mm No 4 2,760
B-05.1.34 Hdpe Reducer Tee OD 280*225 No 2 8,500
B-05.1.35 Hdpe RudecerTee OD 280*160 No 1 8,000
B-05.1.36 Hdpe 45 degree Y OD 280 No 3 1,000
B-05.1.37 Hdpe Elbow 90 degree OD 160 No 2 4,500
B-05.1.38 Hdpe Elbow 90 degree OD 110 No 3 3,500
B-05.1.39 Hdpe Elbow 90 degree OD 90 No 2 3,008
B-05.1.40 Hdpe equal tee OD 63 No 2 2,450
B-05.1.41 Flanged both side Gate valve OD 280 No 2 26,000
B-05.1.42 Flanged both side Gate valve OD 250 No 4 22,000
B-05.1.43 Flanged both side Gate valve OD 225 No 2 19,800
B-05.1.44 Flanged both side Gate valve OD 200 No 2 17,500
B-05.1.45 Flanged both side Gate valve OD 180 No 2 15,000
B-05.1.46 Flanged both side Gate valve OD 160 No 5 13,600
B-05.1.47 Flanged both side Gate valve OD 110 No 4 12,000
B-05.1.48 Flanged both side Gate valve OD 90 No 3 9,500
B-05.1.49 Flanged both side Gate valve OD 75 No 3 8,230
B-05.1.50 Flanged both side Gate valve OD 63 No 20 3,500
B-05.1.51 Stub flange but weld DN 200mm No 2 4,500
B-05.1.52 Stub flange but weld DN 140mm No 1 4,000
B-05.1.53 Stub flange but weld DN 90mm No 1 2,800
B-05.1.54 Stub flange but weld DN 75mm No 1 2,450
B-05.1.55 Stub flange but weld DN 63mm No 1 2,200
B-05.1.56 Hdpe Comperssion reducer 50*40 No 6 2,100
B-05.1.57 Comperssion Adapter OD 40*40 No 7 1,600
B-05.1.58 Reducer comperssion 63*40 No 10 1,290
B-05.1.59 Bolt nut washer Ø24 No 15 250
B-05.1.60 Water Meter 280mm No 3 25,000
B-05.1.61 Backing ring flanged 180mm No 2 450
B-05.1.62 Backing ring flanged 200mm No 3 500
B-05.1.63 Backing ring flanged 40mm No 2 240
B-05.1.64 Backing ring flanged 63mm No 5 190
B-05.1.65 Backing ring flanged 75mm No 2 180
B-05.1.66 Backing ring flanged 90mm No 10 220
B-05.1.67 Water Meter 180mm No 2 18000.00
B-05.1.68 Water Meter 160mm No 1 12,000
B-05.1.69 Water Meter 140mm No 5 10,000
B-05.1.70 Water Meter 75mm No 4 6,500
B-05.1.71 Water Meter 63mm No 20 3,800
B-05.1.72 Water Meter 50mm No 15 3,000
sub total B-05

TOTAL FOR BILL NO. B-05 CARIED TO SUMMERY


Total

26,100.0
46,920.0
123,369.6
349,401.6
205,920.0
874,660.8
280,500.0
185,220.0
1,990,440.0
501,600.0
312,530.4
1,237,090.9
1,484,597.2
7,618,350.5

30,000
20,340
16,800
24,600
15,750
40,500
10,400
5,600
10,000
16,140
10,800
6,000
8,160
7,600
6,500
15,000
6,800
3,300
2,600
11,040
17,000
8,000
3,000
9,000
10,500
6,016
4,900
52,000
88,000
39,600
35,000
30,000
68,000
48,000
28,500
24,690
70,000
9,000
4,000
2,800
2,450
2,200
12,600
11,200
12,900
3,750
75,000
900
1,500
480
950
360
2,200
36,000
12,000
50,000
26,000
76,000
45,000
1,197,426

8,815,777
BILL NO. B-06.0 DISTRIBUTION NETWORKS WORKS
DISTRIBUTION welding of HDPE PIPE
m Qty Rate Total
PE 100 PN10
B-06.1.1 HDPE PIPE PE100 PN10 OD 50 WP 8 180 1,364
B-06.1.2 HDPE PIPE PE100 PN10 OD 63 WP 15 180 2,633
B-06.1.3 HDPE PIPE PE100 PN10 OD 75 WP 29 185 5,382
B-06.1.4 HDPE PIPE PE100 PN10 OD 90 WP 73 190 13,905
B-06.1.5 HDPE PIPE PE100 PN10 OD 110 WP 70 220 15,292
B-06.1.6 HDPE PIPE PE100 PN10 OD 125 WP 35 240 8,500
B-06.1.7 HDPE PIPE PE100 PN10 OD 140 WP 37 245 9,118
B-06.1.8 HDPE PIPE PE100 PN10 OD 160 WP 311 260 80,874
B-06.1.9 HDPE PIPE PE100 PN10 OD 180 WP 47 290 13,705
B-06.1.10 HDPE PIPE PE100 PN10 OD 200 WP 24 320 7,541
B-06.1.11 HDPE PIPE PE100 PN10 OD 225 WP 122 340 41,549
B-06.1.12 HDPE PIPE PE100 PN10 OD 280 WP 123 380 46,888
B-06.1.13 SUBTOTAL FOR C-06.0 246,750
DISTRIBUTION laying of HDPE PIPE PE
100 PN10
B-06.1.14 HDPE PIPE PE100 PN10 OD 50 m 750 10 7,500
B-06.1.15 HDPE PIPE PE100 PN10 OD 63 m 850 12 10,200
B-06.1.16 HDPE PIPE PE100 PN10 OD 75 m 1448 15 21,720
B-06.1.17 HDPE PIPE PE100 PN10 OD 90 m 2,880 18 51,840
B-06.1.18 HDPE PIPE PE100 PN10 OD 110 m 1,300 25 32,500
B-06.1.19 HDPE PIPE PE100 PN10 OD 125 m 850 30 25,500
B-06.1.20 HDPE PIPE PE100 PN10 OD 140 m 3,406 36 122,616
B-06.1.21 HDPE PIPE PE100 PN10 OD 160 m 441 44 19,404
B-06.1.22 HDPE PIPE PE100 PN10 OD 180 m 3,686 50 184,300
B-06.1.23 HDPE PIPE PE100 PN10 OD 200 m 760 60 45,600
B-06.1.24 HDPE PIPE PE100 PN10 OD 225 m 371 69 25,599
B-06.1.25 HDPE PIPE PE100 PN10 OD 280 m 1,200 75 90,000
SUBTOTAL FOR C-06.0 17,942 636,779
Civil Work Construction m Qty Rate total
Construction of Valve chambers, crossings
and casings
Construction of 1mx.1m masonry Valve
chambers as shown in the drawing including
70cmX70cm C-20 concrete cover for manhole
B-06.1.30 with thickness 10cm with all accessories. No 20 10,000 200,000
Concrete class C-25, of rivers, streams and
gullies crosses including cost for excavation not
exceeding 2m , form work, 12mm
reinforcement bars including all required
accesseries as instructed by the engineer and
B-06.1.31 the drawing provided No 10 5,500 55,000
supply and installationsteel casing of Dia
200mm for road crossings as per standard
drawings, price includes excavation not
B-06.1.33 exceeding 2m m 90 3,000 270,000
Sub Total For B-06.1.80 525,000
PRESSURE TESTING AND DISINFECTION

Pipeline testing, leakage corrections and


commissioning for the whole distribution
B-06.1.37 system, including all necessary works ls 190,000
Disinfection of pipelines: flushing with clear
water, filling with water containing 0.15 g/l
calcium hypo chloride, left for 24 hours. This
includes supply of all necessary equipment,
B-06.1.38 chemical and water ls 285,000
Sub Total Total carried B-06.1.81 475,000
Trench excavation for distribution
DISTRIBUTION EARTH WORK
Earth Work unit qty rate total
site clearance for distribution trench by
B-06.1.45 0.6m*.7m width and depth respectively m^2 2,100 35 73,500.00
Trench excavation in ordinary soil to a depth of
0.9m &1m wide and disposal of surplus
excavated material as per standard drawing
B-06.1.46 trench depth detail m3 15,000 104 1,560,000.00
Trench excavation in soft rock for distribution
mains to a depth of 0.9m & 1m wide and
B-06.1.47 disposal of surplus excavated material m3 2,000 320 640,000.00
Trench excavation in Hard rock for distribution
pipes to a depth of 0.9cm & 1m wide and
B-06.1.48 disposal of surplus excavated material m3 1,000 410 410,000.00
Supply and spread 80mm deep approved
bedding material below the pipe in ordinary soil
B-06.1.49 for Trench excavation, m3 750 225 168,750.00
Supply and spread 100mm deep approved
bedding material above and below the pipe in
B-06.1.50 soft and hard rock Trench excavation, m3 250 225 56,250.00
Back filling with imported approved granular
material from the site for hard rock and soft
B-06.1.51 rock Trench excavation, m3 2,400 80 192,000.00
Back filling with Native material in ordinary soil
B-06.1.52 for Trench excavation m3 10,800 240 2,592,000.00
Total carreid For B-06.88 5,692,500.00
Grand Total for B.06 7,576,029.11

You might also like