Professional Documents
Culture Documents
Aluminio Extruccion
Aluminio Extruccion
Aluminio Extruccion
Abstract – In this study, a cost model based on the This model is based on the cost structure and rela-
Process-Based Cost Modelling (PBCM) methodology tionships developed in the previous models so that the
was developed for and customised to the production results obtained from the cost model can provide
of aluminium extruded heat sinks. A base case sce- relevant data for consistent benchmarking between
nario for aluminium extruded heat sinks weighing 198 technologies (i.e. liquid forging and aluminium ex-
g produced on an 1800 US Ton extrusion system is trusion).
used as the input for the cost model. It was found that,
economies of scale is achieved at an annual produc- 3 COST MODEL DEVELOPMENT
tion volume of above 25,000 parts and costs S$1.75
per part at an optimum production volume of 200,000 A top-down approach, namely the Process-Based
Cost Modelling (PBCM) methodology, is used to
parts. The four major cost drivers identified are the
material/consumable at 66.64%, equipment at 13.73%, model the aluminium extrusion process in the pro-
duction of heat sinks. Fundamentally, the concept of
tooling at 9.94%, and energy at 5.6%. In addition, a
1% increase in material recovery rate will contribute the methodology is to map the operation cost based on
the process description [2]. The key steps involved in
to a saving of S$0.0027 in the unit cost at the annual
production 200,000 parts, which is effectively the development of the cost model are: understanding
the processes and parameters involved in the manu-
S$40,000 savings per annum at a material recovery
rate of 75%. facturing process (aluminium extrusion); identifying
the cost elements; and establishing the cost structure
and relationships (based on previous existing cost
Keywords: Aluminium extrusion, Heat sink, Proc-
models) [1].
ess-based cost modelling
Aluminium Billets
1 BACKGROUND
Heating
The aluminium extrusion process has been iden-
tified as one of the existing competing technologies to
the Liquid Forging (LF) process developed by the Extrusion & Shearing
Forging Technology Group in the production of heat
sinks. The aluminium extrusion process has the ability Quenching
to create very complex cross-sections while producing
parts with excellent surface finish. To benchmark the
Stretching
cost of liquid forged heat sinks against the aluminium
extruded heat sinks, a study on the economic per-
formance and a cost modelling of the aluminium Sawing
extrusion process for the production of heat sinks has
to be carried out. Aging
As previous cost models developed are for the
cost assessment of the specific technologies (e.g.
machining, roller embossing and injection moulding Heat Sinks
processes) [1], some customisation is needed for the
cost model of the aluminium extrusion process. Fig. 1. Process flowchart of the aluminium extrusion proc-
Therefore, a separate cost model based on the same set ess in the production of heat sinks.
of cost structure and relationships must be developed
specifically for the aluminium extrusion process in the 3.1 Structuring the Cost Model
production of heat sinks.
To understand the aluminium extrusion tech-
nology, each process step is diagrammed on a process
2 OBJECTIVE flowchart as shown in Fig. 1. With this, the cost ele-
In order to study and analyse the economic per- ments are identified for each of the process in the next
formance of the aluminium extrusion process in the stage of the cost model development. Generally, these
production of heat sinks, a cost model must be de- cost elements can be classified under the fixed cost
veloped specifically to this manufacturing technology. and variable cost as shown in Table 1.
60
Cost modelling of the aluminium extrusion process
Table 1. Cost elements classified into fixed and variable. process’s cost model.
Fixed Cost Variable Cost Table 2. Process utilisation of each process step.
Equipment Materials/Consumable
Process cycT Utilisation
Floor space Tooling
Heating 0.5 s 22.86%
Fixed Overheads Labour
Extrusion & Shearing 0.59 s 26.67%
Energy
Quenching 0.59 s 26.67%
Maintenance
Stretching 0.59 s 26.67%
Sawing 2.2 s 100% (bottleneck)
Using these cost elements, the cost structure and
Aging 1.92 s 87.47%
relationships in the model can then be established.
Again, as mentioned earlier, a similar set of cost
structure and relationships from previous models are The 22.86% utilisation of the heating process in-
used to allow consistent assessment between the dicates that 77.14% (100%-22.86%) of the time when
technologies for benchmarking. The general cost the production line is running, this station is idle and
structure relating the cost elements is given by: waiting for parts or material to be processed. On the
contrary, the sawing process at 100% utilisation in-
C Total = C Fixed + C Variable (1) dicates that the station is continuously at work with
zero idle time, thus making it the bottleneck. With this
C Fixed = C Equipment + C FloorSpace + COverhead (2) functionality, simple line-balancing simulation can be
achieved on the cost model by just changing the
CVariable = CMaterial / Consumable + CTooling ‘process capacity’ parameter of each process step.
(3)
+ CLabour + CEnergy + C Maintenance 4 BASE CASE SCENARIO
where C represents the unit cost per good part. This In order to generate the necessary data from the
cost structure and relationships are essentially the cost model, a base case scenario for the input has to be
basis of the cost model’s functionality to compute the established. Once the cost model has been built, the
cost performance data required for the benchmarking. input for the model, as in the process parameters based
3.2 Added Functionality: Process Utilisa- on industrial practices in the domain of aluminium
tion and Bottleneck Indicators extrusion technology was referenced from literature
[3], textbooks [4,5], equipment datasheets and com-
In the course of developing the cost model, a panies. Table 3 summarises the categories of process
unique feature derived from the parameters of the parameters collected for the base case scenario in the
process conditions was incorporated to streamline the manufacture of aluminium extruded heat sinks.
computation of the line cycle time per part (overall
cycle time per part of the production line). As the Table 3. Categories of process parameters collected for the
cycle time per part of the overall production line is base case scenario.
dependant on its slowest process step in series, the line
Category Parameter
cycle time per part is governed by
Production Conditions • Working Hours per Shift
cycT Line = max{ cycT Pr ocess } (4)
• Shifts per Day
• Working Days per Year
PT
cycTPr ocess = (5) • Average Line Productivity
pc
Economic Conditions • Discount Rate
where cycT is the cycle time per part, PT the time for • Accounting Life
the process to complete a cycle, and pc the process Cost Element Parameters • Part Weight
capacity or the number of parts effectively processed
• Raw Material Price
per cycle. This implies that the process step with the
longest cycle time per part will effectively be the • Consumable Price
bottleneck and thus, the overall line cycle time. • Equipment Price
From this, the utilisation percentage of each • Tooling Price
process step can be computed by: • Labour Salary
cycTPr ocess • Floor Space Rental
Util = × 100% (6)
• Energy Price
cycTLine
• Cost Factor for Overheads
where Util is the process utilisation or the amount of Process Parameters for • Capacity
time when the process station is doing useful work each Process Step • Cycle Time
when in the line is in production mode. Table 2
represents the actual values of the process utilisation • Material Scrap Rate
indicators integrated into the aluminium extrusion • Part Reject Rate
61
J. S. C. Low
4
Unit Cost (S$)
3 Total Cost
2 Fixed Cost
1 Variable Cost
0
0 25 50 75 100 125 150 175 200 225 250 275 300
Annual Production Volume (000's)
$1.40
Material / $1.20
Consumable
$1.00 Energy
Unit Cost (S$)
66.64% Tooling
Tooling $0.80
9.94% Material /
$0.60 Consumable
$0.40 Equipment
$0.20
Labour
0.45% $0.00
Quenching
Stretching
Aging
Sawing
& Shearing
Extrusion
Heating
Overhead
Equipment Maintenance
2.11% Floor Space Energy
0.33% 13.73% 1.20% 5.60%
62
Cost modelling of the aluminium extrusion process
5.3 Impact of Material Recovery Rate on savings of S$40,000 per annum for an annual pro-
Cost duction volume of 200,000 parts.
In addition to these findings, an integrated proc-
As identified in section 5.2, material cost (i.e.
ess utilisation and bottleneck indicator has been in-
Al6061 aluminium billets) makes up a large part of
corporated to provide simple line-balancing func-
the unit cost. The possibility of recycling the scrap and
tionality to the cost model. This in effect offers an-
the waste from rejected parts by channelling the alu-
other option of setting technical performance targets
minium back into the process (closed loop) can reduce
for the technology being assessed.
the amount of raw material required, hence reducing
the cost. The rate of material recovery from the scrap
7 INDUSTRIAL SIGNIFICANCE
and waste examined is to observe its effect on the unit
cost. The unit cost at the annual production volume of This cost study provides a comprehensive and
200,000 parts is plotted against the material recovery close representation of the aluminium extrusion
rate of 0% up to 75% in Fig. 5. From the graph, it process in the production of heat sinks and also a
shows that for an increase of every 1% in material platform for the Forging Technology Group to
recovery, there is a unit cost saving of S$0.0027 at the benchmark the liquid forging process.
annual production volume of 200,000 parts. This in
effect gives a total of S$40,000 in savings per annum.
REFERENCES
6 CONCLUSION [1] R.S. Ng, X.J. Xiao, H.M. Lee, Q.Z. Yang and B. Song,
“Assessment and benchmarking of Roll-embossing & in-
In modelling the economic performance of the jection moulding im microfluidics manufacturing
aluminium extrusion process in the production of heat processes”, SIMTech Tech. Rpt., vol. 9(2), pp. 108-114,
sinks, the unit cost related to the annual production 2007.
volume was studied, the cost drivers were identified [2] R. Kirchain and F. Field, “Process-based Cost Mod-
and the impact of material recovery rate on the unit eling: Understanding the Economics of Technical De-
cost was investigated. cisions”, Encyclopedia of Materials Science and En-
Based on the findings, with the high initial capital gineering, Oxford: Elsevier Press, 2000.
[3] C.T. Kwan, F.S. Jan, W.C. Lee, “An optimum die fillet
investment in items like the equipments, economies of design for minimizing the difference in extruded fin
scale for aluminium extruded heat sinks can only be lengths of straight-fin heat sink extrusion”, J. Mater.
achieved at a minimum annual production volume of Process. Technol., vol. 201, pp. 145-149, 2008.
25,000 parts while reaching optimum annual produc- [4] M. Bauser, G. Sauer, K. Siegert, Extrusion, 2nd ed.,
tion volume at 200,000 parts at a unit cost of S$1.75 at ASM International, 2006.
0% material recycling rate. The four major cost ele- [5] P.K. Saha, Aluminium Extrusion Technology, ASM
ments at the annual production volume of 200,000 International, 2006.
parts with 0% material recycling identified are the [6] E. Fuchs, E.J. Bruce, R.J. Ram and R. Kirchain,
material/consumable cost at 66.64%, equipment at “Process-Based Cost Modeling of Photonics Manu-
facture: The Cost Competitiveness of Monolithic In-
13.73%, tooling at 9.94% and energy 5.6%. Due to the
tegration of a 1550-nm DFB Laser and a Electroab-
high contribution of material cost, it was also found sorptive Modulator on an InP Platform”, J. Lightwave
that for every 1% increase in material recycling rate, Technol., vol. 24(8), pp. 3175-3186, 2006.
there is a unit cost saving of S$0.01 and a total cost
$1.80
$1.75
Unit Cost
$1.70
$1.65
$1.60
$1.55
$1.50
0% 10% 20% 30% 40% 50% 60% 70%
Material Recovery Rate
63