Professional Documents
Culture Documents
Time Schedule MRT CSO Compressor
Time Schedule MRT CSO Compressor
Date
No Time
7-Nov-17 8-Nov-17 9-Nov-17 10-Nov-17 11-Nov-17 12-Nov-17 13-Nov-17
1 07.00
Preparation Unit
Preparation Unit
Shutdown and MRT -Install Cylinder Valve Shutdown and Load
Running Compressor C - Install Spool Test (Start Up)
2 08.00 (Unit Check) Conection Gas Suction
Filter
- Check Instumentation
- Start Compressor C
System
- Open Isolation Valve - Turn Condition
-Check Piping System
Cooling Water (CW) Compressor A and B to
Conection
Existing gradually to 50%
CW Compressor C and -Increase Compressor C
Running 2nd Water Turn to 50%
3 09.00 Fiiling Cooling Water pump TCW. Hold until -Check Compressor
System C minimum Temperature Running
- Compressor A& B
Continue Check DCS keep running
and ESS - Monitoring
Temperature TCW
4 10.00
13 19.00
14 20.00
Done
Note
This Schedule is tentative, test will be follow as per actual condition on site