TIME SCHEDULE START UP CSO COMPRESSOR C (605-K-101C)

Date
No Time
7-Nov-17 8-Nov-17 9-Nov-17 10-Nov-17 11-Nov-17 12-Nov-17 13-Nov-17

1 07.00
Preparation Unit
Preparation Unit
Shutdown and MRT -Install Cylinder Valve Shutdown and Load
Running Compressor C - Install Spool Test (Start Up)
2 08.00 (Unit Check) Conection Gas Suction
Filter
- Check Instumentation
- Start Compressor C
System
- Open Isolation Valve - Turn Condition
-Check Piping System
Cooling Water (CW) Compressor A and B to
Conection
Existing gradually to 50%
CW Compressor C and -Increase Compressor C
Running 2nd Water Turn to 50%
3 09.00 Fiiling Cooling Water pump TCW. Hold until -Check Compressor
System C minimum Temperature Running
- Compressor A& B
Continue Check DCS keep running
and ESS - Monitoring
Temperature TCW

4 10.00

SPARE DAY SPARE DAY

Motor Test Status Air Start Mechanical


5 11.00 -Decrease Load
fin Cooler Running test Compressor A to 0
(No Load) - Increase
LoadCompressor C to
75%
6 12.00 -Check Compressor
Running
Main Motor Status and - N2 Purging
7 13.00
Control
- Unloader Test
8 14.00 Increase Load
- Snubber Discharge
Compressor C t0 100%
Check
-Check Compressor
9 15.00 - Filling Grease Main Turn Off Compressor C Running
Motor Preparation Mechanical
Running Test (MRT). CW from Compressor C
10 16.00 Lube oil, Turning Unit, keep open
air Fan Cooler Solo run,
Vibration Air fin Cooler Unloader Check
Test
11 17.00

Compressor Ready for


operation
12 18.00

13 19.00

14 20.00

Done

Abreviation CW Cooling Water Line


TCW Tempered Cooling Water Unit
MRT Mechanical Running Test

Note
This Schedule is tentative, test will be follow as per actual condition on site