I. PROJECT BACKGROUND
Page 1 of 14
II. SCOPE OF WORK
Page 2 of 14
a). Data Collection
Owner Requirement
Survey Location (Pictures and supporting
Data)
Interview (if necessary)
Program Plan
Concept Plan
Skecth Idea
3D Perspective (Exterior)
Page 3 of 14
slopes, turns maneuver & any other
consideration etc
Appearance
Section
3D Perspective
Detail Plan for Doors and Windows
Detail Plan for Walls
Detail Plan for Floor
Detail Plan for Plafond
Detail Plan for Bath Rooms
b). Structure
Detail Plan for pole’s Foundation &
foundation loads
Detail Plan for Reinforced Steel for Work
Floor
Detail Plan for Work Floor
Detail Plan for Container and its
Modification
Detail Plan for Roof Frame
Detail Plan for Terrace Roof Frame
Detail Plan for Water Tower
Page 4 of 14
proposal, calculation & electrical
requirement.
Plan of Clean Water InstallationConductor
mounting & components accessories.
Installation & testing
\Plan of Waste and Used Water
Installation
Plan of Water Pumps
Drawing of MCB Diagram and Lamps Point
Drawing of Switch Installation
Drawing of Socket/Jack/Plug-in
Installation
d). Others
Time Schedule
Budget Plan for Construction (RAB)
Component spare part is 10% from total
component/accessories supplied, 1000m
insulated conductor etc
B. Construction
1. General Preparation
Mobilization and Demobilization (Workers and
Work-Tools and other material)
Warehouse and ”Direksi Keet” Installation
Workers Temporary HouseCamp (Bedeng)
Electrical Line (from PLN or Genset),
electrical source will be provide by the
Owner/SERDcontractor.
Page 5 of 14
2. Construction Work of Block-B and Block-C
a). Preparation Work
Measurement and Bouwplank worksSite
Survey
Clearance of Area
c). Earthwork
Earthwork for Foundation and Septictank
placement,
Earth-fill works
Page 6 of 14
Reinforced steel, concrete pouring and
cement plaster for work floor works
Concrete foundation type & height
Concrete loads mounting the conductor,
electrical/ mechanical component &
accessories etc
Walls
Partition Wall Installation ( 2 side and 1 side)
Wall Insulation Installation
Wall Painting
Plafond
Gypsum Plafond Installation
Plafond Insulation Work
Plafond Painting Work
Floors
Sitting area Floor
Terrace are Floor
Bed Room and Living Room Floors
Bath Room Floor and Wall
Page 7 of 14
Installation of Closet, Sink, Shower and
Faucet.Rated current : 40A
Procure and Install the Water PumpShort
time withstand current : 25kA
Water Tower workRated Frequency : 50Hz
Surge Arrester Rating : 10kA
Voltage Drop : 3 %
Outdoor termination Joint Box with IP65
Altitude for derating factors : 1960 mASL
f). ElectricalMechanical
Lighting Armature Installation
Electric Socket and Switch Installation
Electric Panel Installation.
c). Open field in an area of 8,610 m2 with the
following detail:
Football field: 4,050 m2
Track area: 2,280 m2
Track & Field area: 2,280 m2
Sports Venue
Page 8 of 14
Closed field (for futsal, basket ball, Badminton, volley ball, function room): 1000 m 2
Page 9 of 14
Schematic design
Layout + spatial program
Landscape masterplan illustration
Perspective
Survey topography and soil structure test
Design development
Views and Cross-sections
Ceiling and light points design
Pattern design and floor structure material
Mechanical & Electrical
Hardscape & Softscape plan
Drainage
Walking Access and Parking
Page 10 of 14
IV. PERSONNEL QUALIFICATION
Contractor shall provide a team consisting of at least
:
i. Team leader, having expertise in design and
supervisiosupervision of n of building/camp
acommodation and sports center construction
ii. Civil, and ArchitecturalMechanical & Electrical
Engineering Designer for Building and Sports
Centercamp accommodation Structuresproject
iii. Landscape and Utility Engineering Designer for
Buildings and Sports Center Structure
iv. Technical Supervisor for construction of
building/Camp accommodationproject and sports
center
V. CONTRACTOR’S RESPONSIBILITIES
a. Contractor shall be responsible to make sure that
all the personnel are in good health condition.
Contractor shall submit to the Company a valid
result of medical check-up (conducted within one
year).
b. Contractor shall be responsible to provide
technical drawings including the required copies
during the work execution.
Page 11 of 14
c. Contractor shall be responsible to accompany
building construction bidders during the tender
process for a maximum of five (5) times visit. If
additional site visit is required, the Company
will be responsible for the costs incurred which
costs shall be previously approved by the
Company.
d. Ensure planning results are technically
accountable.
e. Provide standard personal protective equipment
while working at the project site.
Page 12 of 14
COMPANY:
PT. Supreme Energy Muara LabohRantau Dedap
Menara Sentraya, 23rd Floor
Jl. Iskandarsyah Raya No. 1A
Kebayoran Baru, Jakarta 12160
Phone: +62-21-27882222 (Hunting)
Fax: +62-21-27882333
Page 13 of 14
1. Faishal Dwi Ismail
Email: faishal-dwi@supreme-energy.com
2. Hary Wibowo, Sr. Manager SCM
Email: hary-wibowo@supreme-energy.com
CONTRACTOR:
Contractor’s Representative:
Oke S. Suharyono (Managing Director)Arfan
Email: officke.kaioo@garispradamail.com
Phone: +62 8186 0981858 2696669xxx
Page 14 of 14