Full Version of SCDR-A Close-Out Report (Dated051107)
Full Version of SCDR-A Close-Out Report (Dated051107)
This document contains information that has been prepared by MMHE SDN BHD and all information contained
herein shall be held in confidence. Disclosure, reproduction, or other use of this document is prohibited without
the prior written consent of MMHE SDN BHD
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
TABLE OF CONTENTS
A. CONSTRUCTION 1 - 13
PROJECT OVERVIEW 1
2. Contract Summary 2
3. Contract Representative 2
3.1 SSB Representative 2
3.2 MMHE Representative 2
5. Organization 2
5.1 Project Organizational Chart 2
6. Manpower 2
6.1 Manpower Histogram 2
7. Subcontractor 3
8. Fabrication 3
8.1 Introduction 3
8.2 Fabrication Yard 3
8.3 Structural Works 4-5
8.4 Piping Works 5
8.5 Mechanical Works 6
8.6 Electrical & Instrumentation Works 7
8.7 Blasting & Painting Works 8
9. Statistics 8
10. Testing & Pre-Commissioning 9 -10
11. Inter-Departmental Assessment 11-12
12. Lesson Learnt 13
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
B. QHSE 14 - 20
2. Inter-Departmental Assessment 20
C. PROCUREMENT 21 - 23
D. ENGINEERING 24 - 26
1.0 Statistics 24
2.0 Inter-Departmental Assessment 25
3.0 Lesson Learnt 26
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
E. QA/QC 26 - 27
1.0 Statistics 27
2.0 Lesson Learnt 27
F. COST CONTROLLER 28 - 31
1.0 Statistics 28
2.0 Change Orders 29
3.0 Budget Cost Over-run, Reasons and mitigating Action 29
4.0 Project Cash Flow Status & Lesson Learnt 30
5.0 Inter-Departmental Assessment 30
6.0 Lesson Learnt 31
G. APPENDIXES
Department: Construction
Scope: SCDR-A Topsides: The scope of work consists of Construction, Engineering, Procurement
and supply of materials, Fabrication, Inspection, Testing, and On-Shore Commissioning,
Loadout & Seafastening of the SCDR-A Topsides and Associated Appurtenances.
Project Background: The Shallow Clastics field covers an area of ca. 600km.sq., (40-km x 15-km)
consisting of alternating sand shale sequences in which eight-gas bearing intervals have been
identified to date. The field comprises two en-enchelon ENE-WSW trending culminations that
overlie the F13 and E11 carbonate fields in the northern and mid part of the field, respectively.
SCDR-A will be place on the SW area of the Shallow Clastics field with four highly deviated wells
and one back-up well and tied back to the E11K-A Platform via a single 6.4-km, 14-inch (0.35-m)
carbon steel pipeline. The gas and condensate from the SW area of the reservoir will be
transported wet as a multiphase mixture to the E11K-A facilities, where the fluids will be
separated, dehydrated and re-combined prior to export to MLNG DUA.
The SCDR-A is an unmanned drilling riser topsides design for a “minimum facilities” concept. The
minimum facilities consists of Flow lines, Wet Gas System, Wellhead Desander System, Vents and
Drains Systems, Fresh Water System, Pedestal Crane, Process Control System, IPS, Fire and Gas
System, Telecommunication System, etc.
1 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
5.0 MANPOWER
2 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
8.0 SUBCONTRACTOR
Actual
Planned Planned Actual
Discipline Company Award
Award Date Mob Date Mob Date
Date
Architectural Arrow Platform (M) Sdn Bhd 16-Mar-07 26-Feb-07 17-Mar-07 08-Mar-07
Weighing UES Logistics (M) Sdn Bhd 25-Jun-07 25-June-07 26-Jun-07 07-Jun-07
Load Out Asian Lift PTE Ltd. 10-Aug-07 30-July-07 11-Aug-07 09-Sep-07
9.0 Fabrication
9.1 Introduction
The SCDR-A Topsides Project structure was consists of Cellar Deck, Mezzanine Deck, Main
Deck, Wellhead Platform, Intermediate Platform and Flare Boom. The total weight is
approximately 1,700 metric tons. In additional to that, there is fabrication of ship loose
items for SCDR-A pipeline tie-in works at existing E11K-A Platform.
3 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
4 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
The test pressure of each package was as shown in the hydro test packages.
The extent of the package that hydrotested was barricaded and with warning
signboard during hydro test.
Hydro test results were recorded on pressure recorders and all data/charts were
clearly marked and compiled at the completion of the Flushing and Hydro-
testing activities. A Flushing and Hydro-Test Procedure was developed. After
hydrostatic testing, the piping systems was thoroughly drained to remove all the
water and following by air-drying.
8.4.4 Reinstatement Test
Reinstatement test was carried out after hydro-test. The following activities were
completed before the reinstatement test commenced:
All temporary components used during the hydro test were removed.
All piping, valves, instrument, equipment and line elements were installed.
The piping system within the reinstatement package was made up to the
final operating condition.
All reinstatement packages was developed and line checks was carried out
prior to reinstatement testing, which include sequence of building up test
pressure up to the specific test pressure and the sequence for depressurizing
including safety requirement was observed during the actual testing.
5 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
8.5.2 All mechanical supports/sitting fabrication works was done inside the workshop
taking into account the as-built measurement of the equipment skid supports
and the deck levelness. Specific installation heavy lift procedure for major
equipment was developed.
8.5.3 Prior to delivery, MMHE ensured that the equipment was inspected and tested
either at vendor premises or upon delivery at MMHE.
8.5.4 MMHE completed all required testing & inspection prior to installation.
8.5.5 Major equipment, which required PTW or special permit for lifting, were erected
to location pending its availability.
8.5.6 Equipments, which are sensitive to moist, humidity, extreme heat or duct, MMHE
provided adequate protection. The preservation covered throughout the
fabrication period.
8.5.7 Major Mechanical equipments installed are, but not limited to the following:
Major HVAC equipments installed are, but not limited to the following:
6 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
8.6.2 Prior to delivery, MMHE ensured that the equipments and devices were inspected
and tested either at vendor premises or upon delivery at MMHE.
8.6.3 MMHE completed all required testing & inspection prior to installation.
8.6.4 Equipments and devices with sensitive control devices and electronic devices
were stored in an enclosed air condition storage area prior to installation. The
preservation covered throughout the fabrication period.
8.6.5 All E&I supports, brackets and stands were fabricated inside the workshop as per
approved IFC dwgs. All supports, brackets & stands were full seal welded and
painted in accordance with SSB specifications unless shown otherwise on the IFC
dwgs.
8.6.6 All fabricated E&I supports, brackets & stands accepted by SSB were installed in
accordance with latest IFC dwgs. Full welding was done only after confirmation if
no obstruction/alteration within the areas concerned.
8.6.7 All E&I equipment were installed strictly on accordance with manufacturer’s
instruction and specification. Specific installation heavy lift procedure for major
equipment was developed.
8.6.8 The major E&I equipments installed are, but not limited to the following:
Electrical
• Power Transformer
• 6.6KV Ring Main Unit
• LV Distribution Board (8 nos.)
• AC Uninterruptible Power Supply (UPS)
• Interposing Relay Panels (2 nos.) – (1 no. ship loose for E11-KA)
• 400V Switchboard
• Splitter Box
Instrumentation
7 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
8.7.1 All raw fabricated materials (i.e. supports, brackets, stands, etc) were blasted
and applied approved Epoxy or Main Coating / Primer Epoxy Glass Flake prior to
erection.
8.7.2 For tubular, diagonal braces and columns were blasted and applied main coat
prior to erection.
8.7.3 All main steel assembled at ground level were spot blast on the welded
connection and welded attachment area and painted by the main coating
prior to lifting of the deck to its position.
8.7.4 The finished coat was applied right after the primary steel box-up and damage
portion thereafter was repaired and cosmetic painted during and after all
interdisciplinary components are installed, prior to MCD.
9.0 STATISTICS
Risk Change
Site Technical
No Discipline Notification
Query Issued
Identified De-risked Issued
1 Mechanical 11 11 8 31
2 Structural 6 6 33 67
3 E&I 20 12 5 38
4 Architectural 2 2 6 14
5 Piping 9 9 9 23
6 HVAC 2 2 2 2
7 B&P 3 7
8 QA 1 1 4 8
9 T&C 1
8 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
10.1 Testing & Pre-commissioning outline the final inspection and onshore pre-commissioning
of the package system including the equipment installation works on SCDR-A Topsides
Project.
Onshore pre-commissioning proved that all equipment available have been installed
and connected in accordance with IFC drawings and operation is in line with the
design concept.
All inspection and test results are recorded on the SSB format of check sheets, Shell EP
Asia Pacific (EPA) format. The check sheet overview for each system is provided in the
detailed procedure. MMHE assigned personnel that performed the testing, inspection &
onshore pre-commissioning of various types of system and equipment, followed the
approved detailed procedure.
MMHE requested all tests and witnessed by SSB Commissioning Team. MMHE recorded
all test and counter signed by SSB Representative after testing was completed.
Original copy of check sheets were handed over progressively throughout the pre-
commissioning period and were kept in accordance with the commissioning system
numbering for final documentation.
10.2.2 Function test of electrical protection relays such as earth fault relays, overload
relays and etc.
10.2.4 Loop checking and static function test of all control panels.
10.2.6 System function test inclusive of over-all testing and shutdown matrices.
10.2.10 Full commissioning of HVAC, Pedestal Crane, etc. and maximize the
commissioning works onshore wherever possible.
9 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
10 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Assessment
No Item
Excellent Good Fair Poor
1 Procurement
2. Materials delivery beyond the planned To firm up the PO earlier and closely
schedule, as a result Fabrication and Testing & monitor the delivery of materials.
Commissioning works has been delayed (e.g. :
Launcher Receiver End Closure, E&I materials).
Prior to this also delivery of those
materials/equipment need to accelerate,
resulting cost increase.
3. Some of materials/equipment delivered not To revisit the vendor list and technical
meet targeted quality (e.g.: Closed Drain person / PMT should evaluate the proposed
Vessel & Condensate Pod – Too many punch vendor/supplier before award PO.
list and affecting others disciplines activities).
4. Materials specification changes not highlighted Should consult with design team, PMT and
to PMT and Client. As results too many re-test client before conclude to deviate from
conducted & time consumed & cost impact original specification.
(e.g.: Piping Duplex 8” seamless changes to
welded type).
5. The quality of procurement reporting is poor. To provide a detail and correct information
on the procurement report.
2. Design quality is poor. Inter clash check in Design should improve in quality of
between designs disciplines is almost nil, designing & be very strong in justifying
resulting too many major clashing at site. related queries and should work as a team
among design team when finalizing the
drawings.
Design team should be the frontline in
11 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
3. Too many unplanned PR. Cost and time To improve the quality on justifying the
impact. details drawings.
3 Cost Controller
4 Planner
12 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
C. Lessons Learnt
1) Design team should be the frontline in advising the project team at beginning stage for any
materials shortage or clashes or any related activities that are not highlighted by the client’s
consultant. The time frame for justification and advising the project team also should be at a
high-speed mode. Not to copy and paste only the client’s entire only consultant drawing
details.
Design should improve in quality of designing & be very strong in justifying related queries
and should work as a team among design team when finalizing the drawings.
2) Procurement department should improve in delivery the PO and should transparent in
reporting the delivery of materials.
3) Material Control should tally the information materials delivery to project team to avoid too
many urgent releases given during project implemented.
4) Planning should detail out all activities and proactive in advising the impact of planned work
delivered.
13 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Department: QHSE
Category Accumulative
Total Man-hours without LTI 462,640
Near Miss 0
First Aid 0
Occupational Health 0
MTC 0
RWC 0
No. of Fire/Explosion Incident 0
Property/Equipment Damage 0
LTI 0
Permanent Total Disability 0
Fatality 0
Total Recordable Occupational Illness 0
TRCF 0
Cost of Accidents 0
No. of Days LTI Free 405
No. of Unsafe Act walkabout findings 1364
No. of Unsafe Condition walkabout findings 1162
Total UCUX submission 2257
Legend:
TRCF : Total Recordable Case Frequency
MTC : Medical Treatment Case
RWC : Restricted Work Case
LTI : Lost Time Injury
14 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
1.5 Housekeeping
The project workforce carried out daily housekeeping and cleaning activities at site
before/after work and weekly “Gotong Royong” on Saturday. These programs were aimed
at increasing job efficiency, improving safety performance, reducing risks of fire / explosion
and preventing trip / fall accidents
1.6 Drills
The project executed two drills, the first on 14th February 2007 for First Aid, Rescue and
Evacuation Drill and on 17th July 2007, and the second one on Rescue, Evacuation and Fire
Drill. Both exercises successfully done as per our expectation.
15 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Toolbox Meetings were also being used as an educational forum to improve employee’s
knowledge and understanding of health and safety systems, rules and requirement.
The topic of the HSE Talk are predominantly focused on the risks, known hazards, unsafe
acts or practices related to the daily activities. The HSE talk also acted as a tool for
management and workers inter communication to convey information and to mobilize
action on current aspect of health safety and the protection of the environment.
All MMHE employees and subcontractors who are involved with the fabrication of SCDR-A
were required to attend the talk and attendance was taken. Any absenteeism without
good reason is considered non-compliance to HSE Plan. To ensure sufficient space to
accommodate all the workers and to protect the place from rain and sun, we erected a
zinc roof shed with a staged podium to ensure this important gathering is always carried out
despite the weather conditions.
16 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Safety Audits / “Walkabout” were conducted on every Monday at 8:30 a.m. It was
participated by a group of personnel, which consists of SSB Company Site Representative
(CSR), MMHE Project Manager, Subcontractor Project Managers, Discipline Superintendent,
HSE Executive, HSE Supervisor, Discipline Engineers, Discipline Supervisors and Subcontractors
Supervisors. Any hazards or unsafe act/conditions will be highlighted and action will be
taken to eliminate or rectify immediately, unresolved findings will be discussed during the
HSE meeting for further action.
17 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
The purpose of the Walkabout is to ensure the work site is safe and in compliance with HSE
rules and regulations. The findings will be discussed in the HSE Weekly meeting.
Apart from the regular Monday Safety Walkabout, we have also implemented a twice-daily
safety task force walkabout among the subcontractors which was conducted by the MMHE
and subcontractor safety promoters at all work locations. The findings and action taken
were discussed in daily safety promoters meeting and submitted on a daily basis for records.
HSE education for all personnel involved in the project plays an important role in
promoting safety work practices, Although the HSE plan only requires once every two weeks
but we conducted on a weekly basis, however we have exceeded this requirement. We
were able to screen the 30 minutes safety video shows every Friday, 520 personnel have
attended. This was made possible by having our own TV and VCD player specifically
dedicated for the SCDR-A project. SSB staff generously lent the audiovisual items.
Two QHSE day celebrations were held during the onshore fabrication. The first milestone
achievement was celebrated on 10/05/07.after achieving 250,000 man-hours while the
375,000 milestone was recorded on 14/07/07.
HSE incentives in both cash vouchers and non monetary form such as t-shirts, caps and
mugs were handed out to the workforce on every Monday morning talk for the most
number of U-See, U-Act submitted during the week or month, HSE quiz. Apart from that we
also hand out tokens to those who were selected on the spot for good HSE practices where
PMT and clients top management were making their visits to site. The number of tokens
given is 215.
So far we have issued 51 SAC and 7 SVC to non-compliant at site. The objective is to
discourage workforce not to commit un-safe work practices.
The objective is to maintain a safe, healthy and productive work environment, the use and
abuse (sales, possession, trafficking & influence) of drug and alcohol. The number tested so
far, 341 all negative.
18 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Two campaigns the first one PPE Awareness Campaign was launched on 10//05//07
and the second, PTW Management Campaign on 25/06/07. A unique feature towards a
pro-active HSE management was the launch of “HSE Commitment by Contractors and
PMT Signing Ceremony”. we were serious about Safety and would ensure that they would
carry out their work in safe manner and complete it on time. Beside the campaigns, all
SCDR-A Project workforces have to wear coverall at all time as per the contract.
HSE workshops were held during the course of the project for supervisors, workers and HSE
personnel. The workshops focused on the Hazard Identification (HIRAC), proactive
interventions (PIC) and refocusing on the HSE objectives for the project with an eye on
Improving HSE performances. MMHE HSE Executive and SSB HSE Advisor jointly animated
the workshop.
All types of incident and injuries, including LTI, MTC, RWC, first aid, near miss, property and
environmental damage were required to be promptly reported within 24 hours to
MMHE/SSB representative verbally and writing.
Since the project commenced on the First Cut of Steel, 12th September 2006 until MCD
date on 28th August 2007 and Sailaway on 27th September, 2007, SCDR-A Topsides has
achieved our vision of “Nobody Gets Hurt” and the target of ZERO INCIDENT.
19 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Assessment
No Item
Excellent Good Fair Poor
1 Procurement
3 Cost Controller
4 Construction
5 Planner
20 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Department: Procurement
Overview: Project is an EPCC and a lump sum procurement contract by MMHE. Client Sarawak
Shell Berhad. Target MCD is on 28 August 2007. Sail away by 5 September 2007. This
project is a Topside Drilling Flatform and Satellite Tie-in Flatform. Location is 200
Kilometers offshore Miri-Sarawak. The Design consultant is MMC Oil & Gas Engineering
Sdn. Bhd.
Actual
No Item PR Date PO Date FRD Delivery Reason for Delay
Date
Technical clarification from
Design delay due to
External Door Type D1
1 25/08/06 23/01/07 22/12/06 18/04/07 engineer’s transition. PA was
and D2 and D3
hold. Manage to capture
installation on site
Technical clarification from
Design delay due to
External Door Type D4
2 25/08/07 23/01/07 22/12/06 05/02/07 engineer’s transition. PA was
,D4A,D5, and D6
hold. Manage to capture
installation on site.
Delay on delivery of package
due technical queries /
procurement of materials to
Pedestal Crane engine
3 05/08/06 19/10/06 15/05/07 10/07/07 proceed on production by
driven
vendor. Manage to coup up
schedule for installation on
site.
Delay cutting of Po’s &
delivery due to budgetary
4 Flush / Closed water Tank 5/8/06 19/10/06 15/05/07 10/06/07
issue. Still manage to meet
schedule on site installation
Delay cutting of Po’s &
Open Drain Caisson delivery due to budgetary
5 05/08/06 19/10/06 15/05/07 01/06/07
Pump issue. Still manage to meet
schedule on site installation
Delay cutting of Po’s &
delivery due to budgetary
6 Diesel Transfer Pump 05/08/06 19/10/06 15/05/07 10/06/07
issue. Still manage to meet
schedule on site installation
Delayed of cutting of PO’s
due to budgetary issue /
7 Sonic Vent Tip Package 07/08/06 23/01/07 07/05/07 10/07/07 technical clarification by
design. Still managed to install
as per site schedule.
Delayed of cutting of PO’s
due to budgetary issue /
Corrosion Inhibitor
8. 07/08/06 18/10/06 08/03/07 03/05/07 technical clarification by
Injection Skids
design. Still managed to install
as per site schedule.
Delayed of cutting of PO’s
due to budgetary issue /
9 Closed Drain Vessel 07/08/06 21/11/06 22/01/07 26/04/07 technical clarification by
design. Still managed to install
as per site schedule.
21 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
15 Pig Receiver 18/08/06 23/01/07 20/06/07 01/10/07 E11K-A ship loose material.
Delayed on delivery.
25 GPA/PA System Cabinet 23/08/06 29/12/06 01/03/07 06/05/07 Managed to capture
installation on site.
Delayed on delivery.
26 Flame Detector (IR Point) 23/08/06 31/01/07 01/03/07 06/05/07 Managed to capture
installation on site.
Delayed on delivery.
27 ESD Break glass Station 23/08/06 22/12/06 01/03/07 15/04/07 Managed to capture
installation on site.
Delayed on delivery.
28 Restriction Orifice Plate 29/08/06 29/01/07 01/03/07 30/07/07 Managed to capture
installation on site.
Delayed on delivery.
Level Gauge (using
29 30/08/06 27/03/07 01/02/07 15/08/07 Managed to capture
pressure gauge)
installation on site.
Delayed on delivery.
31 Pressure Gauges 14/09/06 05/04/07 01/02/07 07/08/07 Managed to capture
installation on site.
Delayed on delivery.
32 Level Gauges Reflex 14/09/06 16/04/07 01/02/06 08/08/07 Managed to capture
installation on site.
Delayed on delivery. Manage
33 Instrument Junction Boxes 18/11/06 12/04/07 30/04/07 11/07/07
to capture installation on site
22 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
23 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Scope: D & E scope include, but not limited to, review and checking of Client-supplied AFC drawings,
PDMS and ACADD models, MTO’s, COG, Structural analysis and other calculations related to
the execution and final completion of the project. Scope also covers procurement and
technical evaluation of contractual scope of supply such as Structural steel, Piping bulk
materials, manual valves except ball valves 2” and above and other materials required in the
Contracts; deliverables such as fabrication drawings for all disciplines and reference drawings
from Client-supplied AFC drawings and soft copies.
Overview: The Shallow Clastics field, located 140-km NW of Bintulu, was discovered in 1969 by wells
F13-1 and E11-1. The field is one of the eleven fields under the MLNG-DUA PSC, which took effect on
30 June 1993. Under the terms of this PSC, Sarawak Shell Berhad as a joint venture arrangement with
PETRONAS Carigali Sendirian Berhad will operate the Shallow Clastics field until PSC expiry on 26 May
2015. Shallow Clastics Phase 3 is the development of the SW area of the Shallow Clastics field. SCDR-
A will be placed on the SW area of the Shallow Clastics field with four highly deviated wells and one
back up well and tied back to the E11K-A platform via a single 6.4-km, 14” carbon steel pipeline. The
gas and condensate from the SW area reservoir will be transported wet as a multiphase mixture to the
E11K-A facilities, where the fluids will be separated and re-combined prior to export to MLNG-DUA.
1.0 Statistics
Instrumentation
Architectural
Mechanical
Structural
Electrical
Piping
No Subject
1 No. of shop drawing original estimation 100 174 365 684 11 598
5 No. drawing days delay nil nil nil nil nil nil
7 No. of client deliverable delay nil nil nil nil nil nil
24 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Assessment
No Item
Excellent Good Fair Poor
2.1 Procurement
2.4 Planner
25 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
3.1 PDMS model should be clash- checked after exportation of BOCAD to ensure a clash-
free piping configuration.
3.2 Thorough review and checking of Client and Yard supplied materials to avoid last
minute procurement of shortfall materials.
3.3 Close interaction between PMT and D & E to ensure the capturing of potential
problems at site such as shortage of construction materials, clashes, obstructions and
tripping hazards, etc.
3.4 Inter-disciplinary coordination should be encourage to avoid inter-disciplinary clashes
at site during installation of piping, supports, cable trays, pad eyes, etc.
3.5 Early issuance by QC of “RED-LINES” to avoid cramming on document preparation
during project close-out preparations.
Department: QA/QC
26 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
1.0 Statistics
No Subject Status
2 Quality Action Note (QAN) issued Total: 106, Close: 106, Outstanding: 0
Structural:
Length Tested (RT+UT) : 1,376,332 mm.
Defect length : 4,413 mm.
Defect rate : 0.32 %
Major Type of Defect : Slag, Lack of Fusion, & Porosity
4 Weld Repair Rate
Piping:
Length Tested (RT+UT) : 579051 mm
Defect length : 206 mm.
Defect rate : 0.04 %
Major Type of Defect : Porosity and Lack of Fusion
Vendor supplied and delivered the equipments (Closed drain vessel and Condensate Pod)
to MMHE yard without completion of Non Destructive Test and improper compilation of
Manufacturer Data Record. Rectification should be done by Project Team in order to fulfill
the Code requirements and Client specifications. The repair activities such as re-alignment
on nozzle, re-Radiography, re-Hydro test and repainted. These kinds of repairs consume a lot
material, consumables, schedule and cost as well.
Recommendation:
• Site visit for ensuring capability and performance of the selected vendor / supplier for
the project critical equipment /mechanical package
• To conduct pre-execution audit prior to fabrication commencement to give more
confidence on availability and readiness of drawing, material, project
personnel/manpower, tools and yard facilities.
• Procurement to update vendor data monitoring registry to achieve final
documentation compilation in schedule.
• To increase the frequency of inspection to vendor yard for earlier detection if any
malfunction or non-conformances occurred during fabrication phase.
27 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Project Overview: Generally SCDR-A Topsides is a profitable project but the project was largely hit
by the price escalation on Stainless Steel and Duplex Stainless Steel related
materials/equipment.
Few materials and equipment delayed of delivery due some prolonged
settlement on over-budgeted issues thus contribute to most of negative
progress of the project and catch-up progress by means of acceleration is
inevitable.
1.0 Statistics
28 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
3.1.1 Material procured last minutes to cater miss-out and modification works
entails ex-stock material is secured at higher price.
Design MTO to be doubled check by Construction to cater for potential
unavoidable clashing/modification, site routing etc
3.1.3 Price escalation especially SS and DSS based materials. Further negotiation.
3.1.4 Delayed delivery project materials i.e. DSS pipe materials entails project to
be accelerated to regain the progress would cost extra money to the
project in terms of acceleration.
3.2.1 Procure project materials thru CO mechanism for faster delivery to catch-up
the schedule. Procurement, Design and Construction to double-checked
actual materials and to cater potential site routing/re-routing, clashing or site
obstruction.
3.2.2 Repetitive/Modification
To officially highlights Client of any hindrance at site fabrication with regard
to final location etc. so as to minimize the repetitive works. PDMS review to
be conducted regularly.
3.2.3 VO to the contractor for additional work of punch list clearance of vendor
package i.e. Pedestal Crane, Vessel/ Procurement Dept. to ensure recovery
prior VO to be executed.
29 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
4.1 Payment Certificate accorded with massive materials documentation i.e. GRIN,
MAC, and PO.
Assessment
No Item
Excellent Good Fair Poor
1 Procurement
3 Construction
30 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
6.1 To regularly conduct PDMS review against AFC document issued by Client to at least
minimize site clashing/obstruction
6.2 To double-checked MTO provided by design prior to issue PR as to ensure that the
materials be secured sufficiently. Material ordered on urgent basis entails materials
be obtained ex-stock and expensive
6.3 To check detail drawing provided by design against the site condition for which items
to be installed/erected just to minimize the potential clashing prior to fabrication and
installation.
6.4 To officially highlights Client of any hindrance at site fabrication with regard to final
location etc. to minimize the repetitive works on regular basis
6.6 Material Control Coordinator to promptly extend a copy of duly approved material
documentation i.e. GRIN, MAC to Quantity Surveyor to ensure expeditious
preparation of Payment Certificate.
PROGRESS PHOTOGRAPHS
31 of 31
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
Fabrication of SCDR-A
SCD Topsides & Existing E11K-A Platform 0 19-Jul-06 05-Sep-07 19-Jul-06 A 05-Oct-07 A 0
PROJECT MILESTONE
MILEST 0 19-Jul-06 05-Sep-07 19-Jul-06 A 05-Oct-07 A 0
Construction Facilities
Facilitie 0 19-Jul-06 05-Jul-07 19-Jul-06 A 11-Jul-07 A 0
PRE1130 Set-up Contractor's Facilities 0 100% 19-Jul-06 06-Dec-06 19-Jul-06 A 20-Dec-06 A
PRE1180 Set-up SSB's site Office and Facilities 0 100% 19-Jul-06 18-Dec-06 19-Jul-06 A 29-Dec-06 A
PRE1210 Set-up EDMS system, including lease line. 0 100% 07-Oct-06 12-Jan-07 07-Oct-06 A 19-Jan-07 A
PRE1220 Set-up Completion Management System 0 100% 07-Oct-06 09-Mar-07 07-Oct-06 A 02-Mar-07 A
PRE1430 Set-up Video conferencing Facilities 0 100% 07-Oct-06 06-Nov-06 01-Nov-06 A 24-Nov-06 A
PRE1440 Welder Qualification Test 0 100% 12-Oct-06 28-Dec-06 08-Nov-06 A 26-Jan-07 A
PRE1170 Facilities for 3rd Parties 0 100% 07-Feb-07 05-Jul-07 12-Feb-07 A 11-Jul-07 A
Project Management 0 01-Aug-06 15-May-07 01-Aug-06 A 18-May-07 A 0
PRE1450 Mobilise Project Management Team, Supervision and Staff 0 100% 01-Aug-06 20-Dec-06 01-Aug-06 A 16-Mar-07 A
PRE1690 Mobilise Pre-Commissioning Team 0 100% 07-Apr-07 15-May-07 07-Apr-07 A 18-May-07 A
Procedures Preparation
Preparat 0 01-Aug-06 06-Jul-07 01-Aug-06 A 06-Jul-07 A 0
PRE1480 Prepare/Submit/Approve Planning Package 0 100% 01-Aug-06 31-Oct-06 01-Aug-06 A 18-Oct-06 A
PRE1490 Prepare/Submit/Approve HSE Procedures 0 100% 01-Aug-06 06-Nov-06 01-Aug-06 A 01-Nov-06 A
PRE1500 Prepare/Submit/Approve QA/QC Procedures 0 100% 01-Aug-06 06-Nov-06 01-Aug-06 A 04-Dec-06 A
PRE1510 Prepare/Submit/Approve Engineering Procedures 0 100% 01-Aug-06 02-Jan-07 01-Aug-06 A 06-Jul-07 A
PRE1670 Prepare/Submit/Approve Fabrication Procedures 0 100% 01-Aug-06 25-Jan-07 01-Aug-06 A 30-Mar-07 A
PRE1680 Prepare/Submit/Approve Precomm Procedures 0 100% 24-Apr-07 06-Jul-07 14-Nov-06 A 19-Feb-07 A
PRE1520 Prepare/Submit/Approve Weighing Procedures 0 100% 25-Jan-07 05-Apr-07 29-Jan-07 A 06-Jul-07 A
Insurance & Bond 0 21-Sep-06 21-Feb-07 21-Sep-06 A 29-Jun-07 A 0
PRE1530 Submit/Accept Performance Bond 0 100% 21-Sep-06 18-Nov-06 21-Sep-06 A 16-Oct-06 A
PRE1540 Submit/Accept Insurances 0 100% 21-Sep-06 16-Oct-06 21-Sep-06 A 20-Feb-07 A
PRE1550 Submit/Accept CIDB Tax 0 100% 21-Sep-06 21-Feb-07 11-Jun-07 A 29-Jun-07 A
Final Documentations 0 07-May-07 23-Aug-07 07-May-07 A 05-Oct-07 A 0
PRE1560 Prepare & Submit Final Documentation (Manual/Closeout R... 0 100% 07-May-07 23-Aug-07 07-May-07 A 05-Oct-07 A
Sub-Contractors Selection
Sele 0 01-Aug-06 10-Aug-07 01-Aug-06 A 29-Jun-07 A 0
PRE1260 Prepare Tender/Evaluate for STRUCTURAL Subcontractor 0 100% 01-Aug-06 11-Oct-06 01-Aug-06 A 01-Nov-06 A
PRE1270 Prepare Tender/Evaluate for BLASTING & PAINTING Subcontr... 0 100% 26-Sep-06 05-Dec-06 02-Oct-06 A 21-Feb-07 A
PRE1280 Prepare Tender/Evaluate for PIPING Subcontractor 0 100% 06-Oct-06 05-Jan-07 06-Oct-06 A 06-Feb-07 A
PRE1330 Prepare Tender/Evaluate for HVAC Subcontractor 0 100% 06-Oct-06 15-Nov-06 11-Oct-06 A 15-Dec-06 A
PRE1290 Prepare Tender/Evaluate for MECHANICAL Subcontractor 0 100% 23-Oct-06 13-Jan-07 30-Oct-06 A 06-Feb-07 A
PRE1300 Prepare Tender/Evaluate for ELECTRICAL Subcontractor 0 100% 17-Nov-06 20-Feb-07 27-Nov-06 A 24-Feb-07 A
PRE1310 Prepare Tender/Evaluate for INSTRUMENT Subcontractor 0 100% 17-Nov-06 20-Feb-07 27-Nov-06 A 24-Feb-07 A
PRE1320 Prepare Tender/Evaluate for ARCHITECTURAL Subcontractor 0 100% 02-Jan-07 16-Mar-07 06-Jan-07 A 26-Feb-07 A
Primary Baseline Job No : #2006351C / Planning Ref : PN5103-0A Date Revision Checked Approved
Actual Work 04-Sep-06 Rev. A0 - For Reviewed and Approval
SCHEDULE OF SCDR-A TOPSIDES AND E11K-A 18-Oct-06 Rev. 0 - For Approval
Remaining Work
SHIPLOOSE ITEMS
Critical Remaining Work
Milestone Closeout Report
Contract No : 591397 Page 2 of 12
Client : Sarawak Shell Berhad
Activity ID Activity Name Rem % BL Early Start BL Early Actual Start Actual Finish Total 2007
Dur Comp Finish Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
PRE1405 Prepare Tender/Evaluate for GRE PIPING Subcontractor 0 100% 27-Jan-07 17-Mar-07 22-Jan-07 A 07-Feb-07 A
PRE1505 Prepare Tender/Evaluate for WEIGHING Subcontractor 0 100% 27-Apr-07 25-Jun-07 07-May-07 A 25-Jun-07 A
PRE1605 Prepare Tender/Evaluate for LOAD-OUT Subcontractor 0 100% 18-Jun-07 10-Aug-07 04-Jun-07 A 29-Jun-07 A
Award Sub-Contractor
Sub-Contracto & Mobilization 0 11-Oct-06 18-Aug-07 03-Nov-06 A 10-Sep-07 A 0
PRE1265 Award & Mobilization of STRUCTURAL Subcontractor 0 100% 11-Oct-06 19-Oct-06 03-Nov-06 A 09-Nov-06 A
PRE1335 Award & Mobilization of HVAC Subcontractor 0 100% 15-Nov-06 23-Nov-06 15-Dec-06 A 22-Dec-06 A
PRE1285 Award & Mobilization of PIPING Subcontractor 0 100% 05-Jan-07 13-Jan-07 07-Feb-07 A 12-Feb-07 A
PRE1295 Award & Mobilization of MECHANICAL Subcontractor 0 100% 13-Jan-07 22-Jan-07 07-Feb-07 A 13-Feb-07 A
PRE1355 Award & Mobilization of GRE PIPING Subcontractor 0 100% 17-Mar-07 26-Mar-07 08-Feb-07 A 14-Feb-07 A
PRE1275 Award & Mobilization of BLASTING & PAINTING Subcontractor 0 100% 05-Dec-06 13-Dec-06 22-Feb-07 A 02-Mar-07 A
PRE1305 Award & Mobilization of ELECTRICAL Subcontractor 0 100% 20-Feb-07 28-Feb-07 26-Feb-07 A 02-Mar-07 A
PRE1315 Award & Mobilization of INSTRUMENT Subcontractor 0 100% 20-Feb-07 28-Feb-07 26-Feb-07 A 02-Mar-07 A
PRE1325 Award & Mobilization of ARCHITECTURAL Subcontractor 0 100% 16-Mar-07 24-Mar-07 27-Feb-07 A 08-Mar-07 A
PRE1365 Award & Mobilization of WEIGHING Subcontractor 0 100% 25-Jun-07 02-Jul-07 25-Jun-07 A 05-Jul-07 A
PRE1375 Award & Mobilization of LOAD-OUT Subcontractor 0 100% 10-Aug-07 18-Aug-07 29-Jun-07 A 10-Sep-07 A
ENGINEERING 0 04-Aug-06 06-Aug-07 04-Aug-06 A 05-Oct-07 A 0
CVE1000 Civil Engineering and Infrastructure Works 0 100% 02-Jul-07 16-Aug-07 02-Jul-07 A 16-Aug-07 A
WGH1000 1st Weighing of Topsides 0 100% 02-Jul-07 06-Jul-07 04-Jul-07 A 06-Jul-07 A
WGH1010 Final Weighing of Topsides 0 100% 10-Aug-07 15-Aug-07 22-Aug-07 A 23-Aug-07 A
LOA1000 Loadout Topsides 0 100% 29-Aug-07 31-Aug-07 11-Sep-07 A 11-Sep-07 A
LOA1010 Seafastening Topsides 0 100% 31-Aug-07 04-Sep-07 11-Sep-07 A 18-Sep-07 A
E11K-A SHIPLOOSE
SHIPLOOS ITEMS 0 21-Aug-06 24-Jul-07 21-Aug-06 A 31-Aug-07 A 0
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
1.72 2.30 29.11 20.94 30.42 23-Feb-07
Late Plan (Rev. 0)
OVERALL S-CURVE
3.36 2.54 35.09 25.46 35.44 09-Mar-07
2.65 2.49 37.74 28.10 37.93 16-Mar-07
SCDR-A TOPSIDES & E11K-A SHIPLOOSE
04-May-07
2.12 3.44 56.75 49.66 61.18 11-May-07
3.71 3.36 60.46 52.80 64.53 18-May-07
3.81 3.46 64.27 55.67 68.00 25-May-07
2.85 2.69 67.12 58.03 70.68 01-Jun-07
3.38 3.34 70.50 61.07 74.03 08-Jun-07
3.02 3.24 73.52 64.02 77.26 15-Jun-07
2.26 2.73 75.78 66.91 80.00 22-Jun-07
2.90 2.42 78.68 70.36 82.42 29-Jun-07
3.62 2.81 82.30 74.86 85.23 06-Jul-07
3.02 2.29 85.32 78.57 87.52 13-Jul-07
1.83 2.32 87.15 82.33 89.84 20-Jul-07
2.01 2.41 89.16 85.70 92.24 27-Jul-07
2.27 2.57 91.43 88.82 94.82 03-Aug-07
2.20 2.15 93.63 91.83 96.97 10-Aug-07
2.13 1.77 95.76 94.69 98.74 17-Aug-07
1.43 0.40 97.19 97.55 99.14 24-Aug-07
0.63 0.34 97.82 99.30 99.47 31-Aug-07
0.30 0.53 98.12 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
1.76 2.34 29.48 21.21 30.80 23-Feb-07
Late Plan (Rev. 0)
04-May-07
2.00 3.41 57.42 50.40 62.02 11-May-07
3.76 3.32 61.18 53.58 65.34 18-May-07
3.77 3.41 64.95 56.45 68.76 25-May-07
2.84 2.55 67.79 58.80 71.31 01-Jun-07
3.26 3.15 71.05 61.83 74.46 08-Jun-07
2.91 3.09 73.96 64.70 77.55 15-Jun-07
2.17 2.54 76.13 67.43 80.09 22-Jun-07
2.69 2.27 78.82 70.75 82.37 29-Jun-07
3.50 2.71 82.32 75.13 85.07 06-Jul-07
3.04 2.26 85.36 78.71 87.34 13-Jul-07
1.85 2.35 87.21 82.35 89.69 20-Jul-07
2.03 2.45 89.24 85.60 92.14 27-Jul-07
2.32 2.62 91.56 88.69 94.76 03-Aug-07
2.23 2.16 93.79 91.70 96.92 10-Aug-07
2.18 1.79 95.97 94.59 98.71 17-Aug-07
1.23 0.41 97.20 97.50 99.12 24-Aug-07
0.60 0.34 97.80 99.29 99.46 31-Aug-07
0.30 0.54 98.10 100.00 100.00 07-Sep-07
ENGINEERING SDN. BHD.
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
0.00 0.00 0.00 0.00 0.00 23-Feb-07
Late Plan (Rev. 0)
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
0.00 0.00 0.00 0.00 0.00 23-Feb-07
Late Plan (Rev. 0)
Pre-Commissioning S-CURVE
0.00 0.00 0.00 0.00 0.00 06-Apr-07
0.00 0.00 0.00 0.00 0.00 13-Apr-07
0.00 0.00 0.00 0.00 0.00 20-Apr-07
0.00 0.00 0.00 0.00 0.00 27-Apr-07
Actual (Rev.0)
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
1.85 2.76 20.83 11.62 22.81 23-Feb-07
Late Plan (Rev. 0)
Fabrication S-CURVE
FABRICATION OF SCDR-A TOPSIDES
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
1.63 0.83 55.81 53.74 56.25 23-Feb-07
Late Plan (Rev. 0)
Procurement S-CURVE
16-Mar-07
0.78 1.40 62.56 56.64 60.81 23-Mar-07
3.26 1.58 65.82 57.41 62.39 30-Mar-07
1.87 1.93 67.69 57.69 64.32 06-Apr-07
2.16 3.49 69.85 57.98 67.81 13-Apr-07
0.93 3.50 70.78 58.34 71.31 20-Apr-07
3.88 2.06 74.66 59.08 73.37 27-Apr-07
Actual (Rev.0)
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
2.36 2.78 78.71 62.95 76.84 23-Feb-07
Late Plan (Rev. 0)
Engineering S-CURVE
0.43 2.47 86.62 72.81 84.84 16-Mar-07
0.78 1.81 87.40 76.10 86.64 23-Mar-07
1.09 1.75 88.49 79.43 88.39 30-Mar-07
0.49 1.47 88.98 82.45 89.86 06-Apr-07
1.02 1.25 90.00 85.60 91.11 13-Apr-07
0.88 1.13 90.88 87.70 92.24 20-Apr-07
0.37 0.83 91.25 89.81 93.07 27-Apr-07
Actual (Rev.0)
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
1.86 1.62 59.50 53.85 60.04 23-Feb-07
Late Plan (Rev. 0)
Preliminaries S-CURVE
16-Mar-07
1.42 1.68 66.66 57.54 66.33 23-Mar-07
1.36 1.32 68.02 57.98 67.65 30-Mar-07
0.82 0.92 68.84 58.43 68.57 06-Apr-07
2.44 1.64 71.28 59.15 70.21 13-Apr-07
1.33 1.75 72.61 60.49 71.96 20-Apr-07
1.67 1.82 74.28 61.99 73.78 27-Apr-07
Actual (Rev.0)
Rev. No : 0
Weekly Plan
0
10
20
30
40
50
60
70
80
90
100
Actual (Rev.0)
Weekly Actual
Late Plan (Rev. 0)
Early Plan (Rev. 0)
Job No : #2006351C
Contract No : 591397
0.00 0.00 0.00 0.00 0.00
14-Jul-06
( Manhrs Based )
0.45 0.10 10.57 7.04 10.92 23-Feb-07
Late Plan (Rev. 0)
Electrical
Pipe Fitter
Rev. No : 0
Scaffolder
Instrument
Struct Fitter
Proc Coord
Pipe Welder
Electrical (F)
Architectural
Struct Welder
Instrument (F)
Legend
Manpower Direct
Mechanical Fitter
Mechanical Tech
Corrd+Designer+etc
Job No : #2006351C
Weighing Technician
Contract No : 591397
Project Management
100
150
200
250
300
350
50
0
Actual 432 - 432 8 1 1 6 8 21-Jul-06
Plan 319 - 319 7 7 7
4-Aug-06
Actual 540 - 540 10 1 1 8 10 28-Jul-06
Scaffolder
Pipe Fitter
27-Oct-06 20-Oct-06
Actual 1,710 450 1,260 38 1 5 3 1 10 8 9 11 28
Plan 3,827 448 3,379 85 0 6 1 1 2 10 25 32 19 75
Project Management
3-Nov-06 27-Oct-06
Actual 3,015 585 2,430 67 2 6 4 1 13 15 10 29 54
Plan 3,698 448 3,250 82 0 6 1 1 2 10 24 32 16 72
10-Nov-06 3-Nov-06
Actual 3,240 765 2,475 72 3 5 4 1 4 17 15 10 30 55
Plan 3,957 1,076 2,881 88 2 1 6 3 5 7 24 23 26 15 64
17-Nov-06 10-Nov-06
Actual 3,645 1,125 2,520 81 6 4 3 2 10 25 15 10 31 56
Proc Coord
Pipe Welder
2-Feb-07
Actual 8,145 5,445 2,700 181 23 10 8 8 32 40 121 20 10 30 60
2-Feb-07
Plan 10,488 8,734 1,754 233 17 9 5 5 8 29 52 68 194 23 9 6 39
9-Feb-07
LoadOut and Seafastening
23-Mar-07
Actual 11,250 9,090 2,160 250 32 14 2 2 4 2 5 2 10 12 3 1 35 24 32 22 202 15 11 22 48
23-Mar-07
Plan 11,568 10,072 1,496 257 9 8 10 7 3 9 4 21 22 2 1 47 25 28 28 224 12 13 8 33
30-Mar-07
Actual 11,565 9,450 2,115 257 30 14 3 4 5 2 6 2 11 12 3 1 37 27 31 22 210 14 11 22 47 30-Mar-07
Plan 10,442 9,025 1,417 232 8 7 7 11 7 4 9 5 17 19 2 2 29 22 27 23 201 10 15 6 31
6-Apr-07
Actual 12,060 10,035 2,025 268 31 17 5 5 7 2 8 2 12 14 2 1 40 25 31 21 223 13 11 21 45 6-Apr-07
4-May-07
Actual 11,565 9,765 1,800 257 30 20 13 5 8 4 9 5 15 17 3 2 34 19 16 17 217 9 10 21 40 4-May-07
11-May-07
Actual 11,205 9,405 1,800 249 27 22 13 8 8 4 9 5 16 17 3 2 21 20 20 14 209 9 10 21 40 11-May-07
10-Aug-07
Actual 10,350 8,775 1,575 230 4 20 17 12 2 2 7 16 6 11 9 12 14 14 7 8 14 12 8 195 7 8 20 35
Plan 7,524 7,191 333 167 13 23 51 0 1 6 2 2 47 10 5 160 1 6 7 17-Aug-07
17-Aug-07
Actual 8,955 7,470 1,485 199 4 20 15 10 1 1 6 12 5 9 7 9 10 12 7 8 10 12 8 166 6 7 20 33
Plan 1,690 1,416 274 38 24 2 4 1 31 1 5 6 24-Aug-07
24-Aug-07
Actual 8,235 6,885 1,350 183 4 18 14 12 1 1 6 12 5 9 7 9 10 7 4 6 8 12 8 153 6 4 20 30
Plan 1,425 1,425 - 32 22 10 32 31-Aug-07
31-Aug-07
Actual 7,515 6,300 1,215 167 16 16 12 12 5 10 5 6 6 7 8 5 4 6 6 10 6 140 4 3 20 27
MALAYSIA MARINE AND HEAVY ENGINEERING SDN.
1 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
2 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
3 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO1740 PR/PO of Piping Specialty Items 0.06 03-Oct-06 23-Nov-06 260 Comt'd Qty 80% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Gasket Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Studbolt with Nuts Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pipe Support Mat'l Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pipe Support - U-Bolts/Clamps Comt'd Qty 20% 1 1 1 1 1 1 100.00
PRO1750 PR/PO of Pipe Bends & Barred Tees 0.07 03-Oct-06 28-Nov-06 280 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Reduced Barred Tee Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO1760 PR/PO of Associated Fittings & Acc. for Launcher 0.06 18-Oct-06 18-Dec-06 260 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- Launcher (L-2900) & Receiver (L-2960) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Pig Trap End Closure (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Eccentric Reducer (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Weldolet (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
- Welding Neck Flanges (Launcher Material) Comt'd Qty 20% 1 1 1 1 1 1 100.00
PRO1770 PR/PO of All Remaining Piping Mat'l 0.04 27-Oct-06 27-Dec-06 180 Comt'd Qty 100% 5 5 5 5 5 5 100.00 100.00 100.00 100.00 0.00
- All Remaining Materials Comt'd Qty 100% 5 5 5 5 5 5 100.00
Mechanical 0.62 07-Aug-06 16-Nov-06 2,615 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1780 PR/PO of Flush Water Tank 0.04 12-Aug-06 30-Oct-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1790 PR/PO of Fresh Water Tank 0.04 12-Aug-06 30-Oct-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1800 PR/PO of Closed Drain Vessel 0.04 15-Aug-06 13-Oct-06 175 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1810 PR/PO of Condensate Pod 0.04 15-Aug-06 11-Oct-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1820 PR/PO of Diesel Transfer Pump 0.03 24-Aug-06 28-Oct-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1830 PR/PO of Open Drain Caisson Pump 0.03 23-Aug-06 19-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1840 PR/PO of Flush Water Pump 0.03 22-Aug-06 20-Oct-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1850 PR/PO of Fresh Water Pump 0.03 22-Aug-06 20-Oct-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1860 PR/PO of Closed Drain Transfer Pump 0.03 23-Aug-06 19-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1870 PR/PO of All Remaining Pumps 0.03 26-Aug-06 06-Nov-06 120 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1880 PR/PO of HP Vent Tip 0.03 17-Aug-06 03-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1890 PR/PO of CO2 Vent Snuffing System 0.03 17-Aug-06 03-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1900 PR/PO of Manual Operated Trolley Hoists 0.03 21-Aug-06 07-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1910 PR/PO of Padestal Crane 0.07 07-Aug-06 02-Oct-06 280 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1920 PR/PO of Swing Jib Cranes with Manual Operated Hoist 0.03 21-Aug-06 17-Oct-06 135 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1930 PR/PO of Corrosion Inhibitor Injection Package 0.05 18-Aug-06 17-Oct-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1940 PR/PO of All Remaining Mechanical Items 0.04 29-Aug-06 16-Nov-06 150 Comt'd Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Corrosion Probe and Coupon Assembly Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Chemical Injection and Sampling Conection Fitting Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Y-Type Strainers Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Spring Hangers Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Bird Screens Comt'd Qty 17% 1 1 1 1 1 1 100.00
- Sight Glasses Comt'd Qty 17% 1 1 1 1 1 1 100.00
Electrical 0.60 12-Aug-06 09-Jan-07 2,530 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1960 PR/PO of Power Transformer 0.08 12-Aug-06 30-Oct-06 340 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1970 PR/PO of 6.6KV Ring Main Unit 0.07 18-Aug-06 14-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1980 PR/PO of LV Distribution Board 0.07 18-Aug-06 14-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO1990 PR/PO of Powered Navigational Aids System 0.04 18-Oct-06 29-Dec-06 160 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2000 PR/PO of Cable Trays, Ladder & Accessories 0.05 11-Sep-06 14-Nov-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Cable Ladder / Tray & Accessories Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO2010 PR/PO of Electrical / Control Cables, Fitting & MCT's 0.07 29-Aug-06 08-Nov-06 300 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Cables (Power & Control, AC/DC UPS, Lighting & Small Power). Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Multicable Transit (MCT) & Accessories Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO2020 PR/PO of Junction Boxes and Control Panels 0.04 22-Sep-06 15-Dec-06 180 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Interposing Relay Panel Comt'd Qty 100% 1 1 1 1 1 1 100.00
PRO2030 PR/PO of Remote Control Units and Safety Switches 0.05 14-Oct-06 30-Dec-06 210 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Socket, Plug & Switches Comt'd Qty 50% 1 1 1 1 1 1 100.00
- Remote Control Station Comt'd Qty 50% 1 1 1 1 1 1 100.00
PRO2040 PR/PO of Light Fitting, Photocells Mounting and Accessories 0.07 29-Sep-06 21-Dec-06 300 Comt'd Qty 100% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Fluorescent, Exit Light & Floodlights Lighting Fixture Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Power & Lighting Junction Boxes Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Lighting Poles Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Beacon AOL Photocell Comt'd Qty 25% 1 1 1 1 1 1 100.00
PRO2050 PR/PO of Earthing Accessories 0.03 02-Nov-06 15-Dec-06 120 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2060 PR/PO of All Other Electrical Items 0.03 10-Nov-06 09-Jan-07 120 Comt'd Qty 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
- Electrical Steel Mat'l Comt'd Qty 100% 2 2 2 2 2 2 100.00
Instrument 0.90 21-Aug-06 19-Dec-06 3,837 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2070 PR/PO of Wellhead Control Panel 0.05 24-Aug-06 11-Nov-06 200 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2080 PR/PO of Sand Monitoring System 0.03 13-Sep-06 17-Nov-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2090 PR/PO of GPA/PAPA 0.04 07-Sep-06 11-Nov-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2100 PR/PO of Restriction Orifice Plates 0.03 31-Oct-06 12-Dec-06 128 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2110 PR/PO of Orifice Plates 0.03 31-Oct-06 12-Dec-06 128 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2120 PR/PO of Ultrasonic Flowmeters 0.04 26-Aug-06 28-Oct-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2130 PR/PO of Level Gauges (Reflex Type) 0.03 14-Oct-06 29-Nov-06 138 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2140 PR/PO of Level Gauges (Using Pressure Gauge) 0.03 14-Oct-06 29-Nov-06 138 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
4 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO2150 PR/PO of Pressure Gauges 0.03 20-Sep-06 14-Nov-06 145 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2160 PR/PO of Choke Valves 0.07 29-Aug-06 08-Nov-06 300 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2170 PR/PO of Pig Signallers 0.03 28-Oct-06 04-Dec-06 130 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2180 PR/PO of IR Flame Detector 0.03 02-Nov-06 12-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2190 PR/PO of IR Point Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2200 PR/PO of IR Open Path Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2210 PR/PO of Smoke Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2220 PR/PO of Hydrogen Gas Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2230 PR/PO of ESD Break Glass Station 0.03 08-Nov-06 11-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2240 PR/PO of Acoustic Leak Detector 0.03 02-Nov-06 11-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2250 PR/PO of Heat Detector 0.03 02-Nov-06 08-Dec-06 122 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2260 PR/PO of Control, Ball and Operated Valves 0.05 21-Aug-06 07-Nov-06 220 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2270 PR/PO of Ultra Sonic Flare Gas Meter 0.04 23-Aug-06 02-Nov-06 150 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2280 PR/PO of Field Instrument & Mounting Stands & Supports etc. 0.03 16-Sep-06 08-Nov-06 140 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2290 PR/PO of Cable Tray & Ladders 0.04 22-Sep-06 18-Nov-06 151 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2300 PR/PO of Instrument Cable, Junction Boxes & MCT's 0.03 19-Sep-06 14-Nov-06 140 Comt'd Qty 100% 4 4 4 4 4 4 100.00 100.00 100.00 100.00 0.00
- Instrument Cables Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Cable Glands Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Junction Boxes Comt'd Qty 25% 1 1 1 1 1 1 100.00
- Multicable Transit (MCT) & Accessories Comt'd Qty 25% 1 1 1 1 1 1 100.00
PRO2310 PR/PO of Instrument Tubing, Fittings & Valves 0.03 28-Sep-06 22-Nov-06 148 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO2320 PR/PO of All Remaining Instrumentation Items 0.04 10-Nov-06 19-Dec-06 183 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
Architectural 0.08 24-Nov-06 06-Jan-07 352 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1680 PR/PO of Architectural Mat'l (floor/wall/ceiling panels, doors and w 0.08 24-Nov-06 06-Jan-07 352 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Doors, Frames and Accessories Comt'd Qty 100% 1 1 1 1 1 1 100.00
HVAC 0.08 11-Dec-06 15-Jan-07 321 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO1950 PR/PO of HVAC System Package 0.08 11-Dec-06 15-Jan-07 321 Comt'd Qty 100% 10 10 10 10 10 10 100.00 100.00 100.00 100.00 0.00
Safety 0.07 29-Nov-06 29-Jan-07 300 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2330 PR/PO of Safety Equipment and Fire Protection Equipment 0.05 02-Dec-06 29-Jan-07 200 Comt'd Qty 100% 15 15 15 15 15 15 100.00 100.00 100.00 100.00 0.00
- Flexible Hose and Hose Coupling Conection Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Hosereels Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Fire Extinguishers Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Liftraft Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Lifejackets Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Lifejacket Containers Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Knotted Rope Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Ring Life Buoy Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Safety Shower & Self-Contained Eyewash Station Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Helicopter Crash Box & Cabinet Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Fireman's Equipment Comt'd Qty 7% 1 1 1 1 1 1 100.00
- First Aid Kit Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Smoke Hoods and Container Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Breathing Apparatus Set and Cabinet Comt'd Qty 7% 1 1 1 1 1 1 100.00
- Firewater Monitor Comt'd Qty 7% 1 1 1 1 1 1 100.00
PRO2340 PR/PO of Safety Signs 0.02 29-Nov-06 04-Jan-07 100 Comt'd Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
- Safety Signs Comt'd Qty 100% 1 1 1 1 1 1 100.00
Others Materials 0.03 02-Dec-06 08-Feb-07 130 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO2350 PR/PO of Any Other Materials not included above 0.03 02-Dec-06 08-Feb-07 130 Comt'd Qty 100% 10 10 10 10 10 10 100.00 100.00 100.00 100.00 0.00
Purchase Order to Delivery 0.00 03-Oct-06 23-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
Structural 0.00 30-Oct-06 04-Apr-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2360 PO to Del of Structural Tubulars 0.00 30-Oct-06 29-Nov-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2370 PO to Del of Structural Beams 0.00 07-Nov-06 12-Dec-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2380 PO to Del of Structural Plates 0.00 15-Nov-06 30-Dec-06 - Linear 100% 0.00 0.00 0.00 0.00
PRO2390 PO to Del of Ancillary Steel (grating, stair tread, etc.) 0.00 30-Nov-06 27-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2400 PO to Del of Miscellaneous Sections (angles, chanels, SHS etc.) 0.00 24-Nov-06 10-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2410 PO to Del of Fire/Blast Walls 0.00 11-Dec-06 13-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2420 PO to Del of Passive Fire Projection (PFP) 0.00 16-Dec-06 04-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2430 PO to Del of All Remaining Structural Mat'l 0.00 19-Dec-06 14-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
Piping 0.00 06-Nov-06 30-May-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2450 PO to Del of Carbon Steel (CS) Pipes & Fitting 0.00 06-Nov-06 15-Jan-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2460 PO to Del of Stainless Steel (SS) Pipes & Fitting 0.00 11-Nov-06 13-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2470 PO to Del of Duplex Stainless Steel (DSS) Pipes & Fitting 0.00 22-Nov-06 26-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2480 PO to Del of GRE Pipes & Fitting 0.00 11-Nov-06 28-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2490 PO to Del of Valves 0.00 18-Dec-06 04-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2500 PO to Del of Piping Specialty Items 0.00 11-Dec-06 23-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2510 PO to Del of Pipe Bends & Barred Tees 0.00 19-Dec-06 30-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2520 PO to Del of Associated Fittings & Acc. for Launcher 0.00 05-Jan-07 27-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2530 PO to Del of All Remaining Piping Mat'l 0.00 27-Dec-06 12-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
Mechanical 0.00 03-Oct-06 23-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2540 PO to Del of Flush Water Tank 0.00 30-Oct-06 17-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2550 PO to Del of Fresh Water Tank 0.00 30-Oct-06 28-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
5 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO2560 PO to Del of Closed Drain Vessel 0.00 13-Oct-06 04-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2570 PO to Del of Condensate Pod 0.00 11-Oct-06 04-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2580 PO to Del of Diesel Transfer Pump 0.00 28-Oct-06 26-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2590 PO to Del of Open Drain Caisson Pump 0.00 19-Oct-06 30-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2600 PO to Del of Flush Water Pump 0.00 20-Oct-06 21-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2610 PO to Del of Fresh Water Pump 0.00 20-Oct-06 21-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2620 PO to Del of Closed Drain Transfer Pump 0.00 19-Oct-06 09-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2630 PO to Del of All Remaining Pumps 0.00 07-Nov-06 13-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2640 PO to Del of HP Vent Tip 0.00 03-Nov-06 01-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2650 PO to Del of CO2 Vent Snuffing System 0.00 03-Nov-06 01-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2660 PO to Del of Manual Operated Trolley Hoists 0.00 07-Oct-06 22-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2670 PO to Del of Padestal Crane 0.00 03-Oct-06 12-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2680 PO to Del of Swing Jib Cranes with Manual Operated Hoist 0.00 17-Oct-06 30-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2690 PO to Del of Corrosion Inhibitor Injection Package 0.00 17-Oct-06 14-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2700 PO to Del of All Remaining Mechanical Items 0.00 16-Nov-06 23-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
Electrical 0.00 30-Oct-06 10-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2720 PO to Del of Power Transformer 0.00 30-Oct-06 10-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2730 PO to Del of 6.6KV Ring Main Unit 0.00 14-Nov-06 14-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2740 PO to Del of LV Distribution Board 0.00 14-Nov-06 04-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2750 PO to Del of Powered Navigational Aids System 0.00 29-Dec-06 18-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2760 PO to Del of Cable Trays, Ladder & Accessories 0.00 14-Nov-06 15-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2770 PO to Del of Electrical / Control Cables, Fitting & MCT's 0.00 09-Nov-06 28-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2780 PO to Del of Junction Boxes and Control Panels 0.00 15-Dec-06 07-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2790 PO to Del of Remote Control Units and Safety Switches 0.00 30-Dec-06 25-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2800 PO to Del of Light Fitting, Photocells Mounting and Accessories 0.00 21-Dec-06 26-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2810 PO to Del of Earthing Accessories 0.00 15-Dec-06 13-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2820 PO to Del of All Other Electrical Items 0.00 10-Jan-07 22-May-07 - Linear 100% 0.00 0.00 0.00 0.00
Instrument 0.00 28-Oct-06 29-Jun-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2830 PO to Del of Wellhead Control Panel 0.00 11-Nov-06 03-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2840 PO to Del of Sand Monitoring System 0.00 17-Nov-06 20-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2850 PO to Del of GPA/PAPA 0.00 11-Nov-06 21-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2860 PO to Del of Restriction Orifice Plates 0.00 12-Dec-06 17-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2870 PO to Del of Orifice Plates 0.00 12-Dec-06 23-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2880 PO to Del of Ultrasonic Flowmeters 0.00 28-Oct-06 27-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2890 PO to Del of Level Gauges (Reflex Type) 0.00 29-Nov-06 09-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2900 PO to Del of Level Gauges (Using Pressure Gauge) 0.00 29-Nov-06 09-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2910 PO to Del of Pressure Gauges 0.00 14-Nov-06 06-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2920 PO to Del of Choke Valves 0.00 09-Nov-06 29-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2930 PO to Del of Pig Signallers 0.00 04-Dec-06 14-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2940 PO to Del of IR Flame Detector 0.00 12-Dec-06 28-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2950 PO to Del of IR Point Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2960 PO to Del of IR Open Path Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2970 PO to Del of Smoke Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2980 PO to Del of Hydrogen Gas Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO2990 PO to Del of ESD Break Glass Station 0.00 11-Dec-06 10-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3000 PO to Del of Acoustic Leak Detector 0.00 11-Dec-06 27-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3010 PO to Del of Heat Detector 0.00 09-Dec-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3020 PO to Del of Control, Ball and Operated Valves 0.00 08-Nov-06 04-May-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3030 PO to Del of Ultra Sonic Flare Gas Meter 0.00 02-Nov-06 26-Apr-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3040 PO to Del of Field Instrument & Mounting Stands & Supports etc. 0.00 09-Nov-06 26-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3050 PO to Del of Cable Tray & Ladders 0.00 18-Nov-06 07-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3060 PO to Del of Instrument Cable, Junction Boxes & MCT's 0.00 14-Nov-06 16-Feb-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3070 PO to Del of Instrument Tubing, Fittings & Valves 0.00 22-Nov-06 20-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3080 PO to Del of All Remaining Instrumentation Items 0.00 19-Dec-06 13-Jun-07 - Linear 100% 0.00 0.00 0.00 0.00
Architectural 0.00 08-Jan-07 12-Mar-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2440 PO to Del of Architectural Mat'l (floor/wall/ceiling panels, doors an 0.00 08-Jan-07 12-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
HVAC 0.00 15-Jan-07 12-Mar-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO2710 PO to Del of HVAC System Package 0.00 15-Jan-07 12-Mar-07 - Linear 100% 0.00 0.00 0.00 0.00
Safety 0.00 04-Jan-07 09-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO3090 PO to Del of Safety Equipment and Fire Protection Equipment 0.00 29-Jan-07 09-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
PRO3100 PO to Del of Safety Signs 0.00 04-Jan-07 21-May-07 - Linear 100% 0.00 0.00 0.00 0.00
Others Materials 0.00 08-Feb-07 16-Jul-07 - 0.00 0.00 0.00 #DIV/0! #DIV/0!
PRO3110 PO to Del of Any Other Materials not included above 0.00 08-Feb-07 16-Jul-07 - Linear 100% 0.00 0.00 0.00 0.00
Materials Receiving Inspection 3.63 29-Nov-06 08-Aug-07 15,383 Delivered to Site Accepted 100.00 100.00 100.00 100.00 0.00
Structural 0.55 29-Nov-06 20-Apr-07 2,322 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3120 Receive/Accept of Structural Tubulars 0.09 29-Nov-06 14-Dec-06 400 Nos. 100% 111 111 111 100.00 100.00 100.00 100.00 0.00
- Secondary Pipes Type III (PR #68) Nos. 100% 111 111 111 100.00
PRO3130 Receive/Accept of Structural Beams 0.09 12-Dec-06 03-Jan-07 384 Nos. 100% 335 335 335 100.00 100.00 100.00 100.00 0.00
- Secondary Beam Type III (PR #66) Nos. 90% 329 329 329 100.00
- Monorail Beam Type III (PR #67) Nos. 10% 6 6 6 100.00
PRO3140 Receive/Accept of Structural Plates 0.07 30-Dec-06 20-Jan-07 288 Nos. 100% 168 168 168 100.00 100.00 100.00 100.00 0.00
- Deck Plating (PR #121) Nos. 100% 168 168 168 100.00
6 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO3150 Receive/Accept of Ancillary Steel (grating, stair tread, etc.) 0.06 27-Jan-07 15-Feb-07 270 Nos. 100% 9449 9449 9449 100.00 100.00 100.00 100.00 0.00
- Grating and Clips Materials (PR #112) Nos. 17% 7722 7722 7722 100.00
- Handrail Materials (PR #129) Nos. 17% 554 554 554 100.00
- Flatbars and Kickplates Round Bar (PR #130) Nos. 17% 143 143 143 100.00
- Stair Tread (PR #131) Nos. 17% 716 716 716 100.00
- T-6700 Structural Scope Materials (PR #134) Nos. 17% 34 34 34 100.00
- Hex Bolt and Nuts (PR #129) Nos. 17% 280 280 280 100.00
PRO3160 Receive/Accept of Miscellaneous Sections (angles, chanels, SHS e 0.06 11-Jan-07 31-Jan-07 275 Nos. 100% 216 216 216 100.00 100.00 100.00 100.00 0.00
- Channels Type III (PR #111) Nos. 25% 4 4 4 100.00
- Angles Type III (PR #111) Nos. 25% 129 129 129 100.00
- SHS (PR #111) Nos. 25% 15 15 15 100.00
- Deck Drain Materials (PR #139) Nos. 25% 68 68 68 100.00
PRO3170 Receive/Accept of Fire/Blast Walls 0.06 13-Mar-07 03-Apr-07 240 Nos. 100% 423 423 423 100.00 100.00 100.00 100.00 0.00
- Wall Platings & Angular Support CHL & AGL (PR #117) Nos. 40% 209 209 209 100.00
- Wall Cladding (PR #197) Nos. 30% 140 140 140 100.00
- Fire/Blast Walls (PR #179) Nos. 30% 74 74 74 100.00
PRO3180 Receive/Accept of Passive Fire Projection (PFP) 0.05 04-Apr-07 20-Apr-07 220 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3190 Receive/Accept of All Remaining Structural Mat'l (PR #98/166/151/ 0.06 14-Feb-07 09-Mar-07 245 Nos. 100% 27 27 27 100.00 100.00 100.00 100.00 0.00
Piping 0.59 15-Jan-07 18-Jun-07 2,517 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3210 Receive/Accept of Carbon Steel (CS) Pipes & Fitting 0.09 15-Jan-07 14-Feb-07 400 Nos. 100% 475 475 475 100.00 100.00 100.00 100.00 0.00
- Carbon Steel Pipes (PR #42) Nos. 60% 58 58 58 100.00
- Flange CS (PR #56) Nos. 20% 168 168 168 100.00
- Fitting CS (PR #59) Nos. 20% 249 249 249 100.00
PRO3220 Receive/Accept of Stainless Steel (SS) Pipes & Fitting 0.07 13-Feb-07 10-Mar-07 288 Nos. 100% 10034 10034 10034 100.00 100.00 100.00 100.00 0.00
- SS Pipes (PR #52) Nos. 60% 93 93 93 100.00
- Flange SS (PR #56) Nos. 10% 227 227 227 100.00
- Fitting SS (PR #59) Nos. 10% 341 341 341 100.00
- Gasket (PR #71) Nos. 5% 1166 1166 1166 100.00
- Studbolt with Nuts (PR #78) Nos. 5% 7339 7339 7339 100.00
- Pipe Support Mat'l (PR #79) Nos. 5% 155 155 155 100.00
- Pipe Support - U-Bolts/Clamps (PR #142) Nos. 5% 713 713 713 100.00
PRO3230 Receive/Accept of Duplex Stainless Steel (DSS) Pipes & Fitting 0.10 17-May-07 07-Jun-07 410 Nos. 50% 1955 1955 1955 100.00 100.00 100.00 100.00 0.00
- DSS Pipes (PR #52) Nos. 50% 904 904 904 100.00
- Flange Duplex SS (PR #56) Nos. 25% 411 411 411 100.00
- Fitting Duplex SS (PR #59) Nos. 25% 640 640 640 100.00
PRO3240 Receive/Accept of GRE Pipes & Fitting 0.06 28-Feb-07 26-Mar-07 270 Nos. 100% 1626 1626 1626 100.00 100.00 100.00 100.00 0.00
- GRE Pipes & Fittings (PR #65) Nos. 100% 1626 1626 1626 100.00
PRO3250 Receive/Accept of Valves 0.10 04-May-07 31-May-07 420 Nos. 100% 116 116 116 100.00 100.00 100.00 100.00 0.00
- Ball Valves (PR #32) Nos. 20% 5 5 5 100.00
- Ball Valves for GRE lines (PR #33) Nos. 20% 3 3 3 100.00
- Globe, Gate & Check Valves (PR #38) Nos. 20% 74 74 74 100.00
- Check Valves for GRE lines (PR #39) Nos. 20% 3 3 3 100.00
- Double Block & Bleed Valve (PR #41) Nos. 20% 31 31 31 100.00
PRO3260 Receive/Accept of Piping Specialty Items (PR #20&23) 0.04 23-Mar-07 14-Apr-07 154 Nos. 100% 45 45 45 100.00 100.00 100.00 100.00 0.00
PRO3270 Receive/Accept of Pipe Bends & Barred Tees 0.04 30-May-07 18-Jun-07 175 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
- Reduced Barred Tee (PR #10) Nos. 100% 1 1 1 100.00
PRO3280 Receive/Accept of Associated Fittings & Acc. for Launcher 0.04 27-Apr-07 17-May-07 190 Nos. 100% 45 45 45 100.00 100.00 100.00 100.00 0.00
- Pig Launcher & Receiver (PR #40) Nos. 20% 1 1 1 100.00
- Pig Trap End Closure (Launcher Material) (PR #34) Nos. 20% 2 2 2 100.00
- Eccentric Reducer (Launcher Material) (PR #35) Nos. 20% 2 2 2 100.00
- Weldolet (Launcher Material) (PR #36) Nos. 20% 19 19 19 100.00
- Welding Neck Flanges (Launcher Material) (PR #37) Nos. 20% 21 21 21 100.00
PRO3290 Receive/Accept of All Remaining Piping Mat'l 0.05 12-Apr-07 09-May-07 210 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Mechanical 0.94 28-Apr-07 08-Aug-07 3,967 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3300 Receive/Accept of Flush Water Tank 0.05 17-May-07 01-Jun-07 220 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3310 Receive/Accept of Fresh Water Tank 0.06 28-Apr-07 12-May-07 240 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3320 Receive/Accept of Closed Drain Vessel 0.10 04-Jul-07 17-Jul-07 420 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3330 Receive/Accept of Condensate Pod 0.08 04-Jun-07 16-Jun-07 320 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3340 Receive/Accept of Diesel Transfer Pump 0.04 26-Jun-07 07-Jul-07 175 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3350 Receive/Accept of Open Drain Caisson Pump 0.04 30-May-07 13-Jun-07 180 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3360 Receive/Accept of Flush Water Pump 0.04 21-Jun-07 03-Jul-07 150 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3370 Receive/Accept of Fresh Water Pump 0.04 21-Jun-07 03-Jul-07 150 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3380 Receive/Accept of Closed Drain Transfer Pump 0.04 09-Jun-07 25-Jun-07 180 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3390 Receive/Accept of All Remaining Pumps 0.03 13-Jul-07 28-Jul-07 142 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3400 Receive/Accept of HP Vent Tip 0.05 01-Jul-07 14-Jul-07 200 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3410 Receive/Accept of CO2 Vent Snuffing System 0.04 01-Jul-07 13-Jul-07 150 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3420 Receive/Accept of Manual Operated Trolley Hoists 0.03 23-May-07 09-Jun-07 120 Nos. 100% 4 4 4 100.00 100.00 100.00 100.00 0.00
PRO3430 Receive/Accept of Padestal Crane 0.13 12-Jul-07 25-Jul-07 540 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3440 Receive/Accept of Swing Jib Cranes with Manual Operated Hoist 0.05 30-Apr-07 17-May-07 210 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3450 Receive/Accept of Corrosion Inhibitor Injection Package 0.11 14-Jun-07 28-Jun-07 450 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
7 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO3460 Receive/Accept of All Remaining Mechanical Items 0.03 23-Jul-07 08-Aug-07 120 Nos. 100% 32 32 32 100.00 100.00 100.00 100.00 0.00
- Corrosion Probe and Coupon Assembly (PR #25) Nos. 17% 4 4 4 100.00
- Chemical Injection and Sampling Conection Fitting (PR #21) Nos. 17% 14 14 14 100.00
- Y-Type Strainers (PR #23) Nos. 17% 5 5 5 100.00
- Spring Hangers (PR #26) Nos. 17% 5 5 5 100.00
- Bug Screens (PR #27) Nos. 17% 3 3 3 100.00
- Sight Glasses (PR #24) Nos. 17% 1 1 1 100.00
Electrical 0.51 15-Feb-07 19-Jul-07 2,147 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3480 Receive/Accept of Power Transformer 0.09 10-Jul-07 19-Jul-07 400 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3490 Receive/Accept of 6.6KV Ring Main Unit 0.08 14-Jun-07 01-Jul-07 360 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3500 Receive/Accept of LV Distribution Board 0.04 04-Apr-07 23-Apr-07 175 Nos. 100% 8 8 8 100.00 100.00 100.00 100.00 0.00
PRO3510 Receive/Accept of Powered Navigational Aids System 0.03 18-May-07 01-Jun-07 110 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3520 Receive/Accept of Cable Trays, Ladder & Accessories 0.05 15-Feb-07 05-Mar-07 200 Nos. 100% 2669 2669 2669 100.00 100.00 100.00 100.00 0.00
- Cable Ladder & Accessories (PR #58 & #80) Nos. 35% 1711 1711 1711 100.00
- Cable Tray & Accessories (PR #58) Nos. 35% 940 940 940 100.00
- Cable Gland & Accessories (PR #53) Nos. 30% 18 18 18 100.00
PRO3530 Receive/Accept of Electrical / Control Cables, Fitting & MCT's 0.05 28-Mar-07 14-Apr-07 210 Nos. 100% 862 862 862 100.00 100.00 100.00 100.00 0.00
- Cables (Pwr & Ctrl, AC/DC UPS, Lighting & Small Power) (PR #18) Nos. 50% 8 8 8 100.00
- Multicable Transit (MCT) & Accessories (PR #116) Nos. 50% 854 854 854 100.00
PRO3540 Receive/Accept of Junction Boxes and Control Panels 0.03 07-Apr-07 25-Apr-07 140 Nos. 100% 3 3 3 100.00 100.00 100.00 100.00 0.00
- Interposing Relay Panel (PR #17) Nos. 75% 2 2 2 100.00
- Power Junction Boxes (PR #76) Nos. 25% 1 1 1 100.00
PRO3550 Receive/Accept of Remote Control Units and Safety Switches 0.03 25-Apr-07 14-May-07 130 Nos. 100% 68 68 68 100.00 100.00 100.00 100.00 0.00
- Socket, Plug & Switches (PR #75) Nos. 50% 61 61 61 100.00
- Remote Control Units (PR #114) Nos. 50% 7 7 7 100.00
PRO3560 Receive/Accept of Light Fitting, Photocells Mounting and Accesso 0.05 30-Mar-07 26-Apr-07 210 Nos. 100% 331 331 331 100.00 100.00 100.00 100.00 0.00
- Fluorescent, Exit Light & Floodlights Lighting Fixture (PR #51) Nos. 50% 197 197 197 100.00
- Lighting Junction Boxes (PR #76) Nos. 50% 134 134 134 100.00
PRO3570 Receive/Accept of Earthing Accessories 0.02 13-Mar-07 03-Apr-07 100 Nos. 100% 183 183 183 100.00 100.00 100.00 100.00 0.00
- Earthing Cable & Cable Lug (PR #74) Nos. 100% 183 183 183 100.00
PRO3580 Receive/Accept of All Other Electrical Items 0.03 23-May-07 13-Jun-07 112 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Instrument 0.82 07-Feb-07 18-Jul-07 3,460 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3590 Receive/Accept of Wellhead Control Panel 0.14 03-Apr-07 25-Apr-07 600 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3600 Receive/Accept of Sand Monitoring System 0.02 21-Apr-07 08-May-07 90 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3610 Receive/Accept of GPA/PAPA 0.03 21-Mar-07 16-Apr-07 140 Nos. 100% 88 88 88 100.00 100.00 100.00 100.00 0.00
PRO3620 Receive/Accept of Restriction Orifice Plates 0.01 17-May-07 02-Jun-07 60 Nos. 100% 13 13 13 100.00 100.00 100.00 100.00 0.00
PRO3630 Receive/Accept of Orifice Plates 0.01 24-May-07 09-Jun-07 60 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3640 Receive/Accept of Ultrasonic Flowmeters 0.03 27-Feb-07 19-Mar-07 140 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3650 Receive/Accept of Level Gauges (Reflex Type) 0.02 09-Apr-07 27-Apr-07 100 Nos. 100% 5 5 5 100.00 100.00 100.00 100.00 0.00
PRO3660 Receive/Accept of Level Gauges (Using Pressure Gauge) 0.02 09-Apr-07 26-Apr-07 100 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3670 Receive/Accept of Pressure Gauges 0.02 06-Mar-07 24-Mar-07 70 Nos. 100% 18 18 18 100.00 100.00 100.00 100.00 0.00
PRO3680 Receive/Accept of Choke Valves 0.08 29-Jun-07 18-Jul-07 320 Nos. 100% 5 5 5 100.00 100.00 100.00 100.00 0.00
PRO3690 Receive/Accept of Pig Signallers 0.02 14-Mar-07 02-Apr-07 80 Nos. 100% 4 4 4 100.00 100.00 100.00 100.00 0.00
PRO3700 Receive/Accept of IR Flame Detector 0.02 28-Apr-07 12-May-07 75 Nos. 100% 23 23 23 100.00 100.00 100.00 100.00 0.00
PRO3710 Receive/Accept of IR Point Gas Detector 0.02 26-Apr-07 10-May-07 70 Nos. 100% 6 6 6 100.00 100.00 100.00 100.00 0.00
PRO3720 Receive/Accept of IR Open Path Gas Detector 0.02 26-Apr-07 10-May-07 70 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
PRO3730 Receive/Accept of Smoke Detector 0.02 26-Apr-07 09-May-07 70 Nos. 100% 27 27 27 100.00 100.00 100.00 100.00 0.00
PRO3740 Receive/Accept of Hydrogen Gas Detector 0.02 26-Apr-07 12-May-07 70 Nos. 100% 2 2 2 100.00 100.00 100.00 100.00 0.00
PRO3750 Receive/Accept of ESD Break Glass Station 0.01 10-May-07 24-May-07 60 Nos. 100% 9 9 9 100.00 100.00 100.00 100.00 0.00
PRO3760 Receive/Accept of Acoustic Leak Detector 0.02 27-Apr-07 12-May-07 80 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3770 Receive/Accept of Heat Detector 0.02 26-Apr-07 11-May-07 70 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3780 Receive/Accept of Control, Ball and Operated Valves 0.08 04-May-07 24-May-07 340 Nos. 100% 16 16 16 100.00 100.00 100.00 100.00 0.00
- Ball Valves (PR #32 & 33) Nos. 50% 8 8 8 100.00
- Operated Valves (PR #145) Nos. 50% 8 8 8 100.00
PRO3790 Receive/Accept of Ultra Sonic Flare Gas Meter 0.02 26-Apr-07 11-May-07 80 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO3800 Receive/Accept of Field Instrument & Mounting Stands & Supports 0.03 26-Mar-07 19-Apr-07 140 Nos. 100% 106 106 106 100.00 100.00 100.00 100.00 0.00
PRO3810 Receive/Accept of Cable Tray & Ladders 0.04 07-Feb-07 28-Feb-07 180 Nos. 100% 2449 2449 2449 100.00 100.00 100.00 100.00 0.00
- Cable Ladder & Accessories (PR #58) Nos. 50% 1509 1509 1509 100.00
- Cable Tray & Accessories (PR #58) Nos. 50% 940 940 940 100.00
PRO3820 Receive/Accept of Instrument Cable, Junction Boxes & MCT's 0.04 16-Feb-07 14-Mar-07 160 Nos. 100% 22774 22774 22774 100.00 100.00 100.00 100.00 0.00
- Instrument Cables (PR #101) Nos. 26% 21647 21647 21647 100.00
- Cable Glands (PR #148) Nos. 20% 568 568 568 100.00
- Junction Boxes (PR #146) Nos. 20% 15 15 15 100.00
- Multicable Transit (MCT) & Accessories (PR #153) Nos. 15% 259 259 259 100.00
- Earthing Materials (PR #155) Nos. 19% 285 285 285 100.00
PRO3830 Receive/Accept of Instrument Tubing, Fittings & Valves 0.04 20-Mar-07 11-Apr-07 160 Nos. 100% 52 52 52 100.00 100.00 100.00 100.00 0.00
- Instrument Materials (PR #144) Nos. 100% 52 52 52 100.00
PRO3840 Receive/Accept of All Remaining Instrumentation Items 0.02 13-Jun-07 03-Jul-07 75 Nos. 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Architectural 0.09 12-Mar-07 07-Apr-07 380 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3200 Receive/Accept of Architectural Mat'l (floor/wall/ceiling panels, d 0.09 12-Mar-07 07-Apr-07 380 Nos. 100% 47129 47129 47129 100.00 100.00 100.00 100.00 0.00
- Doors, Frames and Accessories (PR #54) Nos. 18% 9 9 9 100.00
8 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
- Ceiling & TNF Panel Nos. 18% 750 750 750 100.00
- Raise Floor Nos. 20% 400 400 400 100.00
- Copper Coated Pin Nos. 5% 22000 22000 22000 100.00
- Rockwool Nos. 16% 1200 1200 1200 100.00
- Aluminium Foil Rolls 10% 20 20 20 100.00
- Galvanize Speed Clip Nos. 4% 22000 22000 22000 100.00
- Anti Skid Paint Nos. 9% 750 750 750 100.00
HVAC 0.05 12-Mar-07 02-Apr-07 220 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3470 Receive/Accept of HVAC System Package 0.05 12-Mar-07 02-Apr-07 220 Unit 100% 60 60 60 100.00 100.00 100.00 100.00 0.00
- Condenser Fan & Motor Unit 12% 6 6 6 100.00
- DX Coil Unit 10% 4 4 4 100.00
- Compressor Unit 12% 6 6 6 100.00
- Condenser Coil Unit 12% 6 6 6 100.00
- Exhaust Fan & Motor Unit 11% 4 4 4 100.00
- Motorized Damper Unit 11% 8 8 8 100.00
- Duct Heater Unit 10% 3 3 3 100.00
- HVAC Control Panel Unit 12% 3 3 3 100.00
- Support Unit 10% 20 20 20 100.00
Safety 0.07 22-May-07 30-Jul-07 300 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3850 Receive/Accept of Safety Equipment and Fire Protection Equipme 0.06 09-Jul-07 30-Jul-07 240 Nos. 100% 131 131 131 100.00 100.00 100.00 100.00 0.00
- Flexible Hose and Hose Coupling Conection (PR #20) Nos. 8% 40 40 40 100.00
- Hosereels (PR #22) Nos. 8% 10 10 10 100.00
- Fire Extinguishers (PR #88) Nos. 8% 33 33 33 100.00
- David Liferaft and Safety Equipment (PR #93) Nos. 8% 3 3 3 100.00
- Lifejacket (PR #92) Nos. 8% 3 3 3 100.00
- Lifejacket Container (PR #92) Nos. 8% 3 3 3 100.00
- Knotted Rope (PR #91) Nos. 8% 3 3 3 100.00
- Ring Life Buoy (PR #94) Nos. 8% 20 20 20 100.00
- Safety Shower & Self-Contained Eyewash Station (PR #95) Nos. 8% 9 9 9 100.00
- First Aid Kit (PR #90) Nos. 8% 3 3 3 100.00
- Smoke Hoods and Container (PR #97) Nos. 8% 2 2 2 100.00
- Breathing Apparatus Set and Cabinet (PR #96) Nos. 8% 1 1 1 100.00
- Firewater Monitor (PR #89) Nos. 7% 1 1 1 100.00
PRO3860 Receive/Accept of Safety Signs 0.01 22-May-07 04-Jun-07 60 Nos. 100% 120 120 120 100.00 100.00 100.00 100.00 0.00
- Safety Signs (PR #107) Nos. 100% 120 120 120 100.00
Others Materials 0.02 16-Jul-07 31-Jul-07 70 80% 20% 100.00 100.00 100.00 100.00 0.00
PRO3870 Receive/Accept of Any Other Materials not included above 0.02 16-Jul-07 31-Jul-07 70 Nos. 100 100 100 100.00 100.00 100.00 100.00 0.00
FABRICATION OF SCDR-A TOPSIDES 69.20 22-Sep-06 20-Aug-07 293,578 100.00 100.00 100.00 100.00 0.00
Structural 24.10 12-Oct-06 18-Jun-07 102,218 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Fabrication 19.16 12-Oct-06 23-May-07 81,284 Pieces Joints 100.00 100.00 100.00 100.00 0.00
FAB1370 Fabricate and Arrange Temp. Supports 0.32 12-Oct-06 06-Dec-06 1,370 No. of Pcs 100% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00 100.00 100.00 100.00 0.00
- Fab. Skid Shoes W 30 x 132 Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Fab. Jacking Beam W 30 x 132 Nos. 23% 6 6 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Fab. Transverse Jacking Beam W 36 x 210 Nos. 19% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Fab. Column 752 dia x 12.7 wt Nos. 15% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Fab. Temp. Column Support 1498 dia x 25.4 wt Nos. 10% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Fab. Temp. Column Support 1193.6 dia x 25.4 wt Nos. 10% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00
FAB1380 Fab/Assem Cellar Deck (In-Situ) 5.03 14-Nov-06 21-Feb-07 21,319 No. of Pcs 100% 1646 1646 100.00 2390 2390 100.00 2390 100.00 2390 100.00 100.00 100.00 100.00 100.00 0.00
- Top Ring Plate 50mm Nos. 2% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Bottom Ring Plate 50mm Nos. 2% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Top Flange Plate Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Bottom Flange Plate Nos. 1% 1 1 100.00 2 2 100.00 2 100.00 2 100.00 100.00
- Top Insert Plate Nos. 2% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- W 36 x 210 Nos. 15% 28 28 100.00 67 67 100.00 67 100.00 67 100.00 100.00
- W 24 x 94 Nos. 13% 15 15 100.00 32 32 100.00 32 100.00 32 100.00 100.00
- W 24 x 68 Nos. 13% 99 99 100.00 200 200 100.00 200 100.00 200 100.00 100.00
- W 18 x 50 Nos. 9% 36 36 100.00 72 72 100.00 72 100.00 72 100.00 100.00
- W 12 x 35 Nos. 8% 82 82 100.00 164 164 100.00 164 100.00 164 100.00 100.00
- W 8 x 15 Nos. 10% 424 424 100.00 848 848 100.00 848 100.00 848 100.00 100.00
- Pipe 457 x 20.6 Nos. 2% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Ins. Plates / Gratings Nos. 7% 570 570 100.00 570 570 100.00 570 100.00 570 100.00 100.00
- Stiffeners Nos. 5% 347 347 100.00 347 347 100.00 347 100.00 347 100.00 100.00
- Transition Pieces (Cone 1219 x 1524 x 40 wt) Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stabbing Guide (Cone 1444 x 500 x 30 wt) Nos. 3% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stabbing Guide (Cone 1139 x 500 x 30 wt) Nos. 3% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Closure Plate 20mm x 480 dia Nos. 2% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Spacer Plate 3mm to 1444 dia Nos. 1% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Spacer Plate 3mm to 1139 dia Nos. 1% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
9 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
FAB1390 Fabricate Columns, Diagonals & Braces 1.12 22-Dec-06 27-Feb-07 4,748 No. of Pcs 100% 97 97 100.00 194 194 100.00 194 100.00 194 100.00 100.00 100.00 100.00 100.00 0.00
Column - 1524 dia. x 50 wt Nos. 6% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 1524 dia. x 40 wt Nos. 8% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
Column - 1219 dia. x 40 wt Nos. 14% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Column - 1219 dia. x 25 wt Nos. 10% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Column - 813 dia. x 23 wt Nos. 5% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 457 dia. x 16 wt Nos. 6% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Column - 356 dia. x 13 wt Nos. 5% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
Column - 273 dia. x 13 wt Nos. 5% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
Column - 219 dia. x 13 wt Nos. 3% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
Column - 168 dia. x 08 wt Nos. 4% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
Diagonal braces - 660 dia. x 25 wt Nos. 6% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
Diagonal braces - 610 dia. x 25 wt Nos. 12% 26 26 100.00 52 52 100.00 52 100.00 52 100.00 100.00
Diagonal braces - 610 dia. x 20 wt Nos. 8% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
Diagonal braces - 356 dia. x 13 wt Nos. 5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
Diagonal braces - 219 dia. x 13 wt Nos. 3% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
FAB1400 Fabricate Main Deck 4.40 29-Dec-06 27-Mar-07 18,671 No. of Pcs 100% 1104 1030 93.30 1705 1626 95.37 1626 95.37 1626 95.37 100.00 100.00 100.00 100.00 0.00
- Top Ring Plate 50mm Nos. 2% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Bottom Ring Plate 50mm Nos. 3% 6 6 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Top Flange Plate Nos. 2% 3 3 100.00 6 6 100.00 6 100.00 6 100.00 100.00
- Bottom Flange Plate Nos. 3% 7 7 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Top Insert Plate Nos. 3% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 36 x 210 Nos. 12% 29 29 100.00 58 58 100.00 58 100.00 58 100.00 100.00
- W 24 x 94 Nos. 13% 39 39 100.00 78 78 100.00 78 100.00 78 100.00 100.00
- W 24 x 68 Nos. 11% 70 70 100.00 140 140 100.00 140 100.00 140 100.00 100.00
- W 18 x 50 Nos. 8% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 12 x 35 Nos. 8% 23 23 100.00 46 46 100.00 46 100.00 46 100.00 100.00
- W 10 x 45 Nos. 7% 9 9 100.00 18 18 100.00 18 100.00 18 100.00 100.00
- W 10 x 22 Nos. 3% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- W 8 x 15 Nos. 8% 240 240 100.00 480 480 100.00 480 100.00 480 100.00 100.00
- Ins. Plates / Gratings Nos. 7% 87 87 100.00 87 87 100.00 87 100.00 87 100.00 100.00
- Stiffeners Nos. 4% 347 347 100.00 347 347 100.00 347 100.00 347 100.00 100.00
- Fab. Skid Beams Nos. 8% 196 122 62.24 323 244 75.54 244 75.54 244 75.54 100.00
- Flange Plate Nos. 1.5% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Stopper Plate Nos. 1.0% 2 2 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Web Plate 38mm Nos. 1.5% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Ring Plate 50mm Nos. 1.5% 12 12 100.00 24 24 100.00 24 100.00 24 100.00 100.00
- End Plate 38mm Nos. 0.5% 8 8 100.00 16 16 100.00 16 100.00 16 100.00 100.00
- Cap Plate 38mm Nos. 0.5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Pipe 1219 x 12 wt Nos. 0.5% 4 4 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Stiffeners Plate Nos. 1.0% 64 64 100.00 128 128 100.00 128 100.00 128 100.00 100.00
FAB1410 Fabricate Mezzanine Deck 2.60 10-Jan-07 10-Mar-07 11,047 No. of Pcs 100% 878 878 100.00 1257 1257 100.00 1257 100.00 1257 100.00 100.00 100.00 100.00 100.00 0.00
- W 24 x 68 Nos. 24% 56 56 100.00 112 112 100.00 112 100.00 112 100.00 100.00
- W 18 x 50 Nos. 17% 30 30 100.00 60 60 100.00 60 100.00 60 100.00 100.00
- W 12 x 35 Nos. 18% 43 43 100.00 86 86 100.00 86 100.00 86 100.00 100.00
- W 8 x 15 Nos. 20% 150 150 100.00 300 300 100.00 300 100.00 300 100.00 100.00
- Ins. Plates / Gratings Nos. 12% 499 499 100.00 499 499 100.00 499 100.00 499 100.00 100.00
- Stiffeners Nos. 9% 100 100 100.00 200 200 100.00 200 100.00 200 100.00 100.00
FAB1420 Fabricate Stairways & Ladder 0.19 15-Feb-07 07-Apr-07 822 No. of Pcs 100% 29 29 100.00 29 29 100.00 29 100.00 29 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 30% 8 8 100.00 8 8 100.00 8 100.00 8 100.00 100.00
- Cellar Deck Nos. 40% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- Mezzanine Deck Nos. 16% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Wellhead Access Platform Nos. 9% 4 4 100.00 4 4 100.00 4 100.00 4 100.00 100.00
- Intermediate Platform Nos. 5% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00
FAB1430 Fabricate Handrails 0.27 05-Feb-07 29-Mar-07 1,140 No. of Pcs 100% 187 187 100.00 187 187 100.00 187 100.00 187 100.00 100.00 100.00 100.00 100.00 0.00
- Main Deck Nos. 35% 51 51 100.00 51 51 100.00 51 100.00 51 100.00 100.00
- Cellar Deck Nos. 36% 70 70 100.00 70 70 100.00 70 100.00 70 100.00 100.00
- Mezzanine Deck Nos. 13% 40 40 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- Wellhead Access Platform / Wing Deck Nos. 9% 14 14 100.00 14 14 100.00 14 100.00 14 100.00 100.00
- Intermediate Platform Nos. 7% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
FAB1440 Fabricate Framing for Switchgear, ILE Rooms, W.Shelter & Worksho 1.21 24-Jan-07 15-Mar-07 5,149 No. of Pcs 100% 152 152 100.00 197 197 100.00 197 100.00 197 100.00 100.00 100.00 100.00 100.00 0.00
Roof Framing and Plating Nos. 40% 45 45 100.00 90 90 100.00 90 100.00 90 100.00 100.00
- W 18 x 50 Nos. 14% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- W 14 x 38 Nos. 12% 20 20 100.00 40 40 100.00 40 100.00 40 100.00 100.00
- W 12 x 35 Nos. 9% 5 5 100.00 10 10 100.00 10 100.00 10 100.00 100.00
- Roof Plate 6mm Nos. 5% 10 10 100.00 20 20 100.00 20 100.00 20 100.00 100.00
Wall Framing and Plating Nos. 60% 107 107 100.00 107 107 100.00 107 100.00 107 100.00 100.00
- W 8 x 28 Nos. 17% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- Pipe 219 x 8 wt Nos. 9% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
10 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
11 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
12 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
Touch-Up Accept
90% 10%
FAB2110 Touch-Up Painting 0.23 11-Apr-07 31-Jul-07 986 SM 100% 2600 2600 2600 100.00 100.00 100.00 100.00 0.00
PFP/BW Accept
90% 10%
FAB2120 Apply Passive Fire Proofing 0.12 01-Jun-07 15-Jun-07 526 Pcs 100% 100 100 100 100.00 100.00 100.00 100.00 0.00
FAB2130 Apply Fire/Blast Walls 0.23 10-May-07 01-Jun-07 980 Pcs 100% 10 10 10 100.00 100.00 100.00 100.00 0.00
Piping 15.04 13-Jan-07 15-Aug-07 63,793 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Dia Total Dia
Done % Done % Done % Done %
Fabrication 5.38 13-Jan-07 31-Jul-07 22,831 Inch Inch 100.00 100.00 100.00 100.00 0.00
FAB2100 Fabricate Pipe Supports 0.67 13-Jan-07 28-Mar-07 2,830 Dia Inch 100% 510 510 100.00 555 555 100.00 555 100.00 555 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 11% 110 110 100.00 110 110 100.00 110 100.00 110 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 19% 90 90 100.00 90 90 100.00 90 100.00 90 100.00 100.00
- Mezzanine Deck Dia Inch 48% 200 200 100.00 245 245 100.00 245 100.00 245 100.00 100.00
- Main Deck Dia Inch 22% 110 110 100.00 110 110 100.00 110 100.00 110 100.00 100.00
FAB2630 Fabricate CS Pipe Spools 1.69 14-Feb-07 25-Apr-07 7,163 Dia Inch 100% 1796 1796 100.00 1796 1796 100.00 1796 100.00 1796 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 18% 330 330 100.00 330 330 100.00 330 100.00 330 100.00 100.00
- Mezzanine Deck Dia Inch 68% 1214 1214 100.00 1214 1214 100.00 1214 100.00 1214 100.00 100.00
- Cellar Deck Dia Inch 11% 198 198 100.00 198 198 100.00 198 100.00 198 100.00 100.00
- Main Deck Dia Inch 3% 54 54 100.00 54 54 100.00 54 100.00 54 100.00 100.00
FAB2840 Fabricate SS Pipe Spools 0.81 10-Mar-07 03-May-07 3,423 Dia Inch 100% 1300 1300 100.00 1300 1300 100.00 1300 100.00 1300 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 28% 357 357 100.00 357 357 100.00 357 100.00 357 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 21% 285 285 100.00 285 285 100.00 285 100.00 285 100.00 100.00
- Mezzanine Deck Dia Inch 31% 400 400 100.00 400 400 100.00 400 100.00 400 100.00 100.00
- Main Deck Dia Inch 20% 258 258 100.00 258 258 100.00 258 100.00 258 100.00 100.00
FAB2850 Fabricate DSS Pipe Spools 1.02 07-Jun-07 31-Jul-07 4,337 Dia Inch 100% 5985 5985 100.00 5985 5985 100.00 5985 100.00 5985 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 5% 477 477 100.00 477 477 100.00 477 100.00 477 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 17% 1027 1027 100.00 1027 1027 100.00 1027 100.00 1027 100.00 100.00
- Mezzanine Deck Dia Inch 78% 4481 4481 100.00 4481 4481 100.00 4481 100.00 4481 100.00 100.00
FAB2860 Fabricate GRE Pipe Spools 0.73 26-Mar-07 15-May-07 3,104 Dia Inch 100% 5876 5876 100.00 5876 5876 100.00 5876 100.00 5876 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Dia Inch 22% 1388 1388 100.00 1388 1388 100.00 1388 100.00 1388 100.00 100.00
- Cellar Deck & Switchgear/LER Dia Inch 20% 1137 1137 100.00 1137 1137 100.00 1137 100.00 1137 100.00 100.00
- Mezzanine Deck Dia Inch 40% 2326 2326 100.00 2326 2326 100.00 2326 100.00 2326 100.00 100.00
- Main Deck Dia Inch 18% 1025 1025 100.00 1025 1025 100.00 1025 100.00 1025 100.00 100.00
FAB2870 Fabricate Piping Specialty Items 0.47 14-Apr-07 28-May-07 1,974 Dia Inch 100% 620 620 100.00 620 620 100.00 620 100.00 620 100.00 100.00 100.00 100.00 100.00 0.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Dia Total Dia
Done % Done % Done % Done %
Installation 9.66 24-Jan-07 15-Aug-07 40,964 Inch Inch 100.00 100.00 100.00 100.00 0.00
FAB2820 Install Pipe Supports Below Cellar Deck 0.59 24-Jan-07 12-Mar-07 2,510 Nos. 100% 203 203 100.00 203 203 100.00 203 100.00 203 100.00 100.00 100.00 100.00 100.00 0.00
FAB2830 Install CS Pipe Spools 1.56 08-Mar-07 22-May-07 6,627 Nos. 100% 412 412 100.00 412 412 100.00 412 100.00 412 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 14% 57 57 100.00 57 57 100.00 57 100.00 57 100.00 100.00
- Mezzanine Deck Nos. 79% 325 325 100.00 325 325 100.00 325 100.00 325 100.00 100.00
- Cellar Deck Nos. 7% 30 30 100.00 30 30 100.00 30 100.00 30 100.00 100.00
FAB2880 Install SS Pipe Spools 0.90 06-Apr-07 14-May-07 3,798 Nos. 100% 302 302 100.00 302 302 100.00 302 100.00 302 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 12% 54 54 100.00 54 54 100.00 54 100.00 54 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 17% 65 65 100.00 65 65 100.00 65 100.00 65 100.00 100.00
- Mezzanine Deck Nos. 36% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00
- Main Deck Nos. 35% 83 83 100.00 83 83 100.00 83 100.00 83 100.00 100.00
FAB2890 Install DSS Pipe Spools 1.38 30-Jun-07 11-Aug-07 5,861 Nos. 100% 1150 1150 100.00 1150 1150 100.00 1150 100.00 1150 100.00 100.00 100.00 100.00 100.00 0.00
- Cellar Deck & Switchgear/LER Nos. 47% 193 193 100.00 193 193 100.00 193 100.00 193 100.00 100.00
- Mezzanine Deck Nos. 53% 957 957 100.00 957 957 100.00 957 100.00 957 100.00 100.00
FAB2900 Install GRE Pipe Spools 0.69 16-Apr-07 12-Jun-07 2,931 Nos. 100% 1762 1762 100.00 1762 1762 100.00 1762 100.00 1762 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 17% 293 293 100.00 293 293 100.00 293 100.00 293 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 21% 379 379 100.00 379 379 100.00 379 100.00 379 100.00 100.00
- Mezzanine Deck Nos. 44% 789 789 100.00 789 789 100.00 789 100.00 789 100.00 100.00
- Main Deck Nos. 18% 301 301 100.00 301 301 100.00 301 100.00 301 100.00 100.00
FAB2910 Install Piping Specialty Items 0.58 10-May-07 01-Jul-07 2,444 Nos. 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB2920 Install Pipe Bends & Barred Tees 0.45 17-Jul-07 06-Aug-07 1,926 Nos. 100% 1 1 100.00 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB2930 Install Associated Fitting & Acc for Launcher 0.38 17-May-07 13-Jun-07 1,631 Nos. 100% 15 15 100.00 15 15 100.00 15 100.00 15 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB2940 Valve Installation 0.92 21-May-07 13-Jul-07 3,896 Nos. 100% 187 Note; o/s 4 nos. Glove Valve (Monitor under punchlist ite 187 100.00 187 100.00 100.00 100.00 100.00 100.00 0.00
LC / Flush 20% Hydrotest 60% Reinstate 10% Accept 10%
Total
Done % Done % Done % Done %
Pack
FAB2950 Hydrotest/Reinstatement 0.81 09-Jun-07 15-Aug-07 3,423 Lines 100% 102 102 100.00 102 100.00 102 100.00 102 100.00 100.00 100.00 100.00 100.00 0.00
Insulation 90% Accept 10%
Total
Done % Done %
Lines
FAB2960 Pipe Insulation 0.58 09-Jul-07 06-Aug-07 2,445 Lines 100% 100 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
13 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
14 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
Install Cable Tray Mtrs 53% 456 456 100.00 456 100.00 100.00
- Main Deck Mtrs 9% 78 78 100.00 78 100.00 100.00
- Cellar Deck Mtrs 19% 165 165 100.00 165 100.00 100.00
- Mezzanine Deck Mtrs 15% 132 132 100.00 132 100.00 100.00
- Switchgear,LER,Battery,Welter Shelter & Transfomer Rooms Mtrs 10% 81 81 100.00 81 100.00 100.00
FAB3260 Install Electrical / Control Cables, Fitting & MCT's 0.74 14-Apr-07 24-May-07 3,140 Mtrs 100% 22 22 100.00 22 100.00 100.00 100.00 100.00 100.00 0.00
Install Electrical Coaming Mtrs 60% 13 13 100.00 13 100.00 100.00
- Cellar Deck Mtrs 32% 8 8 100.00 8 100.00 100.00
- Mezzanine Deck Mtrs 24% 4 4 100.00 4 100.00 100.00
- Main Deck Mtrs 4% 1 1 100.00 1 100.00 100.00
Install Electrical MCT's Nos. 40% 9 9 100.00 9 100.00 100.00
- Switchgear,LER,Battery,Welter Shelter & Transfomer Rooms Nos. 40% 9 9 100.00 9 100.00 100.00
FAB3270 Install Light Fitting, Photocells Mounting and Accessories 0.56 14-May-07 20-Jun-07 2,394 Nos. 100% 190 190 100.00 170 89.47 100.00 100.00 100.00 100.00 0.00
Install Light Fitting Nos. 100% 190 190 100.00 170 89.47 100.00
- Intermediate Platform Nos. 10% 9 9 100.00 9 100.00 100.00
- Cellar Deck Nos. 56% 111 111 100.00 111 100.00 100.00
- Mezzanine Deck Nos. 27% 54 54 100.00 54 100.00 100.00
- Main Deck Nos. 7% 16 16 100.00 16 100.00 100.00
Pull/Lay 90% Accept 10%
Done % Done %
FAB3280 Cable Pulling 0.92 02-May-07 15-Jun-07 3,907 Runs 100% 605 605 100.00 605 100.00 100.00 100.00 100.00 100.00 0.00
Power Cable Runs 16% 12 12 100.00 12 100.00 100.00
- Cable @ RMU (RMU-7505) Runs 9% 8 8 100.00 8 100.00 100.00
- Cable @ 6.6 kv Transformer (TF-7501) Runs 7% 4 4 100.00 4 100.00 100.00
Control Cable Runs 51% 215 215 100.00 215 100.00 100.00
- Cable 400v @ Switchgear (SB-7505) Runs 11% 113 113 100.00 113 100.00 100.00
- Cable 230v @ AC UPS (LCPA-8955) Runs 9% 5 5 100.00 5 100.00 100.00
- Cable 230v @ AC UPS (UPS-7805) Runs 9% 33 33 100.00 33 100.00 100.00
- Cable 230v @ AC UPS (DB-7815) Runs 9% 53 53 100.00 53 100.00 100.00
- Cable HVAC @ Control Panel Runs 6% 7 7 100.00 7 100.00 100.00
- Cable MOV @ Distribution Board (DB-7745) Runs 7% 4 4 100.00 4 100.00 100.00
DC Runs 10% 20 20 100.00 20 100.00 100.00
- Cable 24V DC @ Distribution Board (DB-7925) Runs 10% 20 20 100.00 20 100.00 100.00
Lighting/small power cables Runs 23% 358 358 100.00 358 100.00 100.00
- Cable @ Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Runs 6% 48 48 100.00 48 100.00 100.00
- Cable @ Outdoor Lighting Distribution Board (Normal DB-7735) Runs 6% 50 50 100.00 50 100.00 100.00
- Cable @ Small Power Distribution Board (DB-7715) Runs 7% 153 153 100.00 153 100.00 100.00
- Cable @ Outdoor Lighting Emergency (DB-7845) Runs 4% 107 107 100.00 107 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3290 Install Junction Boxes and Control Panels 0.49 11-May-07 14-Jun-07 2,096 Nos. 100% 119 119 100.00 119 100.00 100.00 100.00 100.00 100.00 0.00
- JB's Sump Deck Nos. 11% 13 13 100.00 13 100.00 100.00
- JB's Cellar Deck & Switchgear/LER Nos. 53% 63 63 100.00 63 100.00 100.00
- JB's Mezzanine Deck Nos. 26% 31 31 100.00 31 100.00 100.00
- JB's Main Deck Nos. 10% 12 12 100.00 12 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3310 Install Power Transformer 0.23 19-Jul-07 03-Aug-07 984 Nos. 100% 1 1 100 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3320 Install 6.6KV Ring Main Unit 0.22 04-Jul-07 25-Jul-07 946 Nos. 100% 4 4 100 4 100.00 4 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB3330 Install Remote Control Units and Safety Switches 0.27 01-Jun-07 30-Jun-07 1,140 Nos. 100% 17 17 100.00 17 100.00 100.00 100.00 100.00 100.00 0.00
- Sump Deck Nos. 5% 2 Note : 2 100.00 2 100.00 100.00
- Cellar Deck & Switchgear/LER Nos. 18% 8 34 pcs RCU will plan to be install at Offshore due to late 8 100.00 8 100.00 100.00
- Mezzanine Deck Nos. 67% 3 delivery. Tentative arrive at PG ETA 31/09/07 (Consider 3 100.00 3 100.00 100.00
under punclist monitoring)
- Main Deck Nos. 10% 4 4 100.00 4 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3340 Install LV Distribution Board 0.23 27-Apr-07 23-May-07 957 Nos. 100% 7 7 100 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
- Install Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Nos. 10% 1 1 100 1 100.00 1 100.00 100.00
- Install Outdoor Lighting Distribution Board (Normal DB-7735) Nos. 12% 1 1 100 1 100.00 1 100.00 100.00
- Install Outdoor Lighting Emergency (DB-7845) Nos. 12% 1 1 100 1 100.00 1 100.00 100.00
- Install Small Power Distribution Board (DB-7715) Nos. 18% 1 1 100 1 100.00 1 100.00 100.00
- Install 24V DC Distribution Board (DB-7925) Nos. 17% 1 1 100 1 100.00 1 100.00 100.00
- Install 230V AC UPS Distribution Board (DB-7815) Nos. 17% 1 1 100 1 100.00 1 100.00 100.00
- Install MOV Distribution Board (DB-7745) Nos. 14% 1 1 100 1 100.00 1 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3350 Install Powered Navigational Aids System 0.17 27-Jun-07 17-Jul-07 717 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Glnd/Trmt 90% Accept 10%
15 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
Done % Done %
FAB3360 Glanding & Termination 0.25 22-May-07 28-Jun-07 1,074 Nos. 100% 1210 1210 100.00 1210 100.00 100.00 100.00 100.00 100.00 0.00
Power Cable Nos. 16% 24 24 100.00 24 100.00 100.00
- Cable @ RMU (RMU-7505) Nos. 9% 16 16 100.00 16 100.00 100.00
- Cable @ 6.6 kv Transformer (TF-7501) Nos. 7% 8 8 100.00 8 100.00 100.00
Control Cable Nos. 51% 430 430 100.00 430 100.00 100.00
- Cable 400v @ Switchgear (SB-7505) Nos. 11% 226 226 100.00 226 100.00 100.00
- Cable 230v @ AC UPS (LCPA-8955) Nos. 9% 10 10 100.00 10 100.00 100.00
- Cable 230v @ AC UPS (UPS-7805) Nos. 9% 66 66 100.00 66 100.00 100.00
- Cable 230v @ AC UPS (DB-7815) Nos. 9% 106 106 100.00 106 100.00 100.00
- Cable HVAC @ Control Panel Nos. 6% 14 14 100.00 14 100.00 100.00
- Cable MOV @ Distribution Board (DB-7745) Nos. 7% 8 8 100.00 8 100.00 100.00
DC Nos. 10% 40 40 100.00 40 100.00 100.00
- Cable 24V DC @ Distribution Board (DB-7925) Nos. 10% 40 40 100.00 40 100.00 100.00
Lighting/small power cables Nos. 23% 716 716 100.00 716 100.00 100.00
- Cable @ Indoor Lighting Distribution Board (Normal/Emergency DB-7725) Nos. 6% 96 96 100.00 96 100.00 100.00
- Cable @ Outdoor Lighting Distribution Board (Normal DB-7735) Nos. 6% 100 100 100.00 100 100.00 100.00
- Cable @ Small Power Distribution Board (DB-7715) Nos. 7% 306 306 100.00 306 100.00 100.00
- Cable @ Outdoor Lighting Emergency (Normal DB-7845) Nos. 4% 214 214 100.00 214 100.00 100.00
Earthing 90% Accept 10%
Done % Done %
FAB3370 Install Earthing Accessories 0.20 23-Apr-07 05-Jul-07 855 Nos. 100% 950 950 100.00 950 100.00 100.00 100.00 100.00 100.00 0.00
Install 90% Accept 10%
Done % Done %
FAB3380 Install All Other Electrical Items 0.13 13-Jun-07 20-Jul-07 569 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3400 Install AC Uninterruptible Power Supply (UPS) 0.24 03-May-07 23-May-07 1,038 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3750 Install 400V Switchboard 0.25 07-May-07 30-May-07 1,051 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Instrument 7.32 28-Feb-07 08-Aug-07 31,040 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB3020 Fabricate Instrument Supports 0.33 28-Feb-07 03-Apr-07 1,404 Nos. 100% 523 523 100.00 523 523 100.00 523 100.00 523 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Tray Support Nos. 64% 320 320 100.00 320 320 100.00 320 100.00 320 100.00 100.00
- Major Equipment / JB Nos. 3% 21 21 100.00 21 21 100.00 21 100.00 21 100.00 100.00
- Instrument Support Nos. 4% 20 20 100.00 20 20 100.00 20 100.00 20 100.00 100.00
- Fire & Gas Nos. 13% 73 73 100.00 73 73 100.00 73 100.00 73 100.00 100.00
- Telecom Nos. 2% 7 7 100.00 7 7 100.00 7 100.00 7 100.00 100.00
- AVA Nos. 2% 12 12 100.00 12 12 100.00 12 100.00 12 100.00 100.00
- GPA / PA Nos. 9% 48 48 100.00 48 48 100.00 48 100.00 48 100.00 100.00
- MCT / Coaming Nos. 3% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00
Lift / Position 20% Fit-Up 30% Weld 40% Accept 10%
Total Total
Done % Done % Done % Done %
Pieces Joints
FAB3030 Install Instrument Supports 0.48 27-Mar-07 02-May-07 2,043 Nos. 100% 523 523 100.00 523 523 100.00 523 100.00 523 100.00 100.00 100.00 100.00 100.00 0.00
- Cable Ladder/Tray Support Nos. 64% 323 323 100.00 323 323 100.00 323 100.00 323 100.00 100.00
- Plint / JB Nos. 4% 21 21 100.00 21 21 100.00 21 100.00 21 100.00 100.00
- Fire & Gas Nos. 13% 66 66 100.00 66 66 100.00 66 100.00 66 100.00 100.00
- Telecom Nos. 1% 7 7 100.00 7 7 100.00 7 100.00 7 100.00 100.00
- AVA Nos. 2% 11 11 100.00 11 11 100.00 11 100.00 11 100.00 100.00
- GPA / PA Nos. 7% 43 43 100.00 43 43 100.00 43 100.00 43 100.00 100.00
- MCT / Coaming Nos. 4% 22 22 100.00 22 22 100.00 22 100.00 22 100.00 100.00
- Fusible Plug Nos. 5% 30 30 100.00 30 30 100.00 30 100.00 30 100.00 100.00
Calib'n 80% Accept 20%
Done % Done %
FAB3040 Instrument Calibration 0.20 10-May-07 26-Jun-07 845 Nos. 100% 126 126 100.00 126 100.00 100.00 100.00 100.00 100.00 0.00
- Flow Transmitter (FT) Nos. 10% 10 10 100.00 10 100.00 100.00
- Level Transmitter (LT) Nos. 3% 5 5 100.00 5 100.00 100.00
- IRCD (MOV) Nos. 8% 6 6 100.00 6 100.00 100.00
- Pressure Regulator (PCV) Nos. 3% 1 1 100.00 1 100.00 100.00
- Diff Pressure Transmitter (PDT) Nos. 4% 5 5 100.00 5 100.00 100.00
- Pressure Gauge (PG) Nos. 21% 47 47 100.00 47 100.00 100.00
- Pressure Relief Valve (PSV) Nos. 12% 12 12 100.00 12 100.00 100.00
- Pressure Transmitter (PT) Nos. 6% 7 7 100.00 7 100.00 100.00
- Pressure Vacuum Relief Valve (PVSV) Nos. 7% 4 4 100.00 4 100.00 100.00
- Pressure Transmitter (PZT) Nos. 14% 13 13 100.00 13 100.00 100.00
- Temperature Transmitter (TT) Nos. 4% 7 7 100.00 7 100.00 100.00
- Actuated Ball Valve (UZV) Nos. 8% 9 9 100.00 9 100.00 100.00
Pull/Lay 90% Accept 10%
Done % Done %
16 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
FAB3050 Cable pulling 0.31 04-May-07 16-Jun-07 1,335 Mtrs 100% 13859 13859 100.00 13859 100.00 100.00 100.00 100.00 100.00 0.00
- DCS & IPS Mtrs 55% 7755 7755 100.00 7755 100.00 100.00
- GPA / PA Mtrs 13% 1860 1860 100.00 1860 100.00 100.00
- Telecom Mtrs 5% 665 665 100.00 665 100.00 100.00
- AVA Mtrs 7% 750 750 100.00 750 100.00 100.00
- FGS Mtrs 20% 2829 2829 100.00 2829 100.00 100.00
Glnd/Trmt 90% Accept 10%
Done % Done %
FAB3060 Glanding & Termination 0.19 07-Jun-07 02-Jul-07 799 Nos. 100% 954 954 100.00 954 100.00 100.00 100.00 100.00 100.00 0.00
- DCS & IPS Nos. 48% 390 390 100.00 390 100.00 100.00
- GPA / PA Nos. 22% 196 196 100.00 196 100.00 100.00
- Telecom Nos. 2% 38 38 100.00 38 100.00 100.00
- AVA Nos. 4% 56 56 100.00 56 100.00 100.00
- FGS Nos. 24% 274 274 100.00 274 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3390 Install Cable Tray & Ladders 0.59 05-Apr-07 22-May-07 2,507 Mtrs 100% 467 467 100.00 467 100.00 100.00 100.00 100.00 100.00 0.00
- Install Cable Tray & Ladder Mtrs 85% 326 Note ; 15mtr under shiploose item will be instl at offshore 326 100.00 326 100.00 100.00
- Install Tubing Tray Mtrs 15% 141 141 100.00 141 100.00 100.00
FAB3410 Install Instrument Cable Junction Boxes & MCT's 0.39 16-May-07 27-Jun-07 1,675 Mtrs 100% 75 75 100.00 75 100.00 100.00 100.00 100.00 100.00 0.00
Junction Boxes Nos. 80% 70 70 100.00 70 100.00 100.00
- Fire & Gas Nos. 12% 4 4 100.00 4 100.00 100.00
- Telephone Nos. 10% 3 3 100.00 3 100.00 100.00
- Instrument JB Nos. 20% 22 22 100.00 22 100.00 100.00
- GPA / PA Nos. 33% 40 40 100.00 40 100.00 100.00
- Fibre Optic Nos. 5% 1 1 100.00 1 100.00 100.00
MCT Nos. 20% 5 5 100.00 5 100.00 100.00
Lvl & Fit 60% Hook-Up 30% Accept 10%
Done % Done % Done %
FAB3420 Install Wellhead Control Panel 0.31 25-Apr-07 24-May-07 1,335 Nos. 100% 1 1 100.00 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
Fit-Up 50% Weld 40% Accept 10%
Done % Done % Done %
FAB3430 Install Field Instrument & Mounting Stands & Supports etc. 0.44 08-May-07 28-May-07 1,880 Nos. 100% 184 184 100.00 184 100.00 184 100.00 100.00 100.00 100.00 100.00 0.00
- Impulse Line Nos. 50% 26 Note ; 2 nos of Pig Signaller ETA 26 100.00 26 100.00 26 100.00 100.00
- Instrument Devices Nos. 50% 158 06/11/07, plan to install offshore. 158 100.00 158 100.00 158 100.00 100.00
Install 90% Accept 10%
Done % Done %
FAB3440 Install Sand Monitoring System 0.10 05-Jun-07 25-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3450 Install Ultrasonic Flowmeters 0.10 18-May-07 05-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3460 Install Pig Signallers 0.10 24-May-07 12-Jun-07 420 Nos. 100% 2 Note ; 2 nos of Pig Signaller ETA 06/11/07, plan to install 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3470 Install Choke Valves 0.16 18-Jul-07 08-Aug-07 694 Nos. 100% 5 offshore. 5 100.00 5 100.00 100.00 100.00 100.00 100.00 0.00
FAB3480 Install GPA/PAPA 0.10 24-May-07 23-Jun-07 420 Nos. 100% 49 49 100.00 49 100.00 100.00 100.00 100.00 100.00 0.00
- Install Strobe Light Nos. 28% 16 16 100.00 16 100.00 100.00
- Install Outdoor Speaker Nos. 27% 18 18 100.00 18 100.00 100.00
- Install Indoor Speaker Nos. 14% 4 4 100.00 4 100.00 100.00
- Install Pushbutton Station Nos. 21% 9 9 100.00 9 100.00 100.00
- Install Sounder Nos. 10% 2 2 100.00 2 100.00 100.00
FAB3490 Install Control, Ball and Operated Valves 0.31 25-May-07 29-Jun-07 1,310 Nos. 100% 8 Note ; 1 no ball valve under shiploose items. 8 100.00 8 100.00 100.00 100.00 100.00 100.00 0.00
FAB3500 Install Distributed Control System (DCS) and (AVA) 0.17 21-Apr-07 22-May-07 711 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3510 Install ESD Break Glass Station 0.10 12-Jun-07 25-Jun-07 413 Nos. 100% 9 9 100.00 9 100.00 100.00 100.00 100.00 100.00 0.00
FAB3520 Install IR Flame Detector 0.10 26-May-07 12-Jun-07 420 Nos. 100% 23 23 100.00 23 100.00 100.00 100.00 100.00 100.00 0.00
FAB3530 Install IR Point Gas Detector 0.10 26-May-07 13-Jun-07 420 Nos. 100% 16 16 100.00 16 100.00 100.00 100.00 100.00 100.00 0.00
FAB3540 Install IR Open Path Gas Detector 0.10 26-May-07 12-Jun-07 420 Nos. 100% 20 20 100.00 20 100.00 100.00 100.00 100.00 100.00 0.00
FAB3550 Install Smoke Detector 0.10 30-May-07 14-Jun-07 420 Nos. 100% 27 27 100.00 27 100.00 100.00 100.00 100.00 100.00 0.00
FAB3560 Install Hydrogen Gas Detector 0.10 30-May-07 12-Jun-07 420 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3570 Install Acoustic Leak Detector 0.10 28-May-07 15-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3580 Install Heat Detector 0.10 31-May-07 15-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3590 Install Ultra Sonic Flare Gas Meter 0.10 22-May-07 12-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3600 Install IPS System 0.20 21-Apr-07 14-May-07 858 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3610 Install Restriction Orifice Plates 0.07 11-Jun-07 25-Jun-07 291 Nos. 100% 13 13 100.00 13 100.00 100.00 100.00 100.00 100.00 0.00
FAB3620 Install Orifice Plates 0.07 18-Jun-07 01-Jul-07 291 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3630 Install Instrument Tubing, Fittings & Valves 0.47 10-May-07 05-Jun-07 1,993 Mtrs. 100% 2073 2073 100.00 2073 100.00 100.00 100.00 100.00 100.00 0.00
FAB3640 Install Level Gauges (Reflex Type) 0.10 21-May-07 06-Jun-07 420 Nos. 100% 5 5 100.00 5 100.00 100.00 100.00 100.00 100.00 0.00
FAB3650 Install Level Gauges (Using Pressure Gauge) 0.10 18-May-07 04-Jun-07 420 Nos. 100% 2 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
FAB3660 Install Pressure Gauges 0.10 19-May-07 06-Jun-07 420 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3670 Install All Remaining Instrumentation Items 0.14 03-Jul-07 04-Aug-07 585 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3710 Install F&G System 0.20 21-Apr-07 12-May-07 858 Nos. 100% 11 11 100.00 11 100.00 100.00 100.00 100.00 100.00 0.00
FAB3720 Install Wellhead Control System (WHCS) 0.27 21-Apr-07 19-May-07 1,151 Nos. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
FAB3730 Install Telecommunication Equipment 0.30 07-May-07 07-Jun-07 1,278 Nos. 100% 23 23 100.00 23 100.00 100.00 100.00 100.00 100.00 0.00
- Install Antena Nos. 40% 3 Note ; 1no antena under shiploose items. 3 100.00 3 100.00 100.00
- Install Outdoor Telephone Nos. 12% 3 3 100.00 3 100.00 100.00
17 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
18 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
19 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
WGH1000 1st Weighing of Topsides 0.25 02-Jul-07 06-Jul-07 1,050 Comp. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
WGH1010 Final Weighing of Topsides 0.25 10-Aug-07 15-Aug-07 1,050 Comp. 100% 1 1 100.00 1 100.00 100.00 100.00 100.00 100.00 0.00
E11K-A SHIPLOOSE ITEMS 1.88 21-Aug-06 24-Jul-07 7,972 100.00 100.00 100.00 100.00 0.00
ENGINEERING 0.12 21-Aug-06 25-Jan-07 520 Prep MTO / ShpDwg Submitted Approved 100.00 100.00 100.00 100.00 0.00
60% 20% 20%
PRE1700 Prepare/Submit/Approve of MTO 0.03 21-Aug-06 25-Nov-06 140 Nos. 100% 26 26 26 26 100.00 100.00 100.00 100.00 0.00
- Structural Nos. 18% 1 1 1 1 100.00
- Piping Nos. 27% 7 7 7 7 100.00
- Mechanical Nos. 19% 2 2 2 2 100.00
- Electrical Nos. 19% 8 8 8 8 100.00
- Instrument Nos. 17% 8 8 8 8 100.00
PRE1710 Prepare/Submit/Approve of Shop Drawings 0.09 03-Oct-06 25-Jan-07 380 Nos. 100% 934 934 934 934 100.00 100.00 100.00 100.00 0.00
Structural Nos. 17% 20 20 20 20 100.00
- IFA Shop Drawings Nos. 6 6 6 6 100.00
- IFC Shop Drawings Nos. 14 14 14 14 100.00
Piping Nos. 27% 254 254 254 254 100.00
- IFA Shop Drawings Nos. 127 127 127 127 100.00
- IFC Shop Drawings Nos. 127 127 127 127 100.00
Mechanical Nos. 16% 16 16 16 16 100.00
- IFA Shop Drawings Nos. 3 3 3 3 100.00
- IFC Shop Drawings Nos. 13 13 13 13 100.00
Electrical Nos. 19% 82 82 82 82 100.00
- IFA Shop Drawings Nos. 41 41 41 41 100.00
- IFC Shop Drawings Nos. 41 41 41 41 100.00
Instrument Nos. 21% 190 190 190 190 100.00
- IFA Shop Drawings Nos. 95 95 95 95 100.00
- IFC Shop Drawings Nos. 95 95 95 95 100.00
PROCUREMENT 0.19 05-Oct-06 05-Jun-07 798 PR RFQ BCD TBE PO 100.00 100.00 100.00 100.00 0.00
Purchase Request to Purchase Order 0.07 05-Oct-06 22-Jan-07 300 30% 10% 10% 40% 10% 100.00 100.00 100.00 100.00 0.00
PRO4440 PR/PO of Structural Matl's 0.01 08-Nov-06 03-Jan-07 30 Comp. Qty 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
PRO4450 PR/PO of Pipe Matl's 0.02 05-Oct-06 30-Nov-06 84 Comp. Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Ball, Globe, Gate & Check Valves (PR No.#62) Comp. Qty 21% 1 1 1 1 1 1 100.00
- Pipes (PR No.#63) Comp. Qty 29% 1 1 1 1 1 1 100.00
- Flange and Pipe Fitting (PR No.#64) Comp. Qty 19% 1 1 1 1 1 1 100.00
- Gasket (PR No.#83) Comp. Qty 9% 1 1 1 1 1 1 100.00
- Stud Bolt with Nuts (PR No.#136) Comp. Qty 8% 1 1 1 1 1 1 100.00
- Pipe Supports Matl's (PR No.#103) Comp. Qty 14% 1 1 1 1 1 1 100.00
PRO4470 PR/PO of Mechanical Matl's 0.01 26-Oct-06 20-Dec-06 46 Comp. Qty 100% 6 6 6 6 6 6 100.00 100.00 100.00 100.00 0.00
- Pig trap end closure Comp. Qty 22% 1 1 1 1 1 1 100.00
- Eccentric Reducer Comp. Qty 17% 1 1 1 1 1 1 100.00
- Weldolet Comp. Qty 12% 1 1 1 1 1 1 100.00
- Welding Neck Flanges Comp. Qty 15% 1 1 1 1 1 1 100.00
- Equal Barred Tee (PR No.#11) Comp. Qty 24% 1 1 1 1 1 1 100.00
- Corrosion Monitoring System (PR No.#13) Comp. Qty 10% 1 1 1 1 1 1 100.00
PRO4490 PR/PO of Electrical Matl's 0.02 25-Nov-06 22-Jan-07 70 Comp. Qty 100% 7 7 7 7 7 7 100.00 100.00 100.00 100.00 0.00
- Electrical Cables (PR No.#70) Comp. Qty 24% 1 1 1 1 1 1 100.00
- Electrical Cable Gland (PR No.#73) Comp. Qty 20% 1 1 1 1 1 1 100.00
- Electrical Earthing Matl's (PR No.#74) Comp. Qty 7% 1 1 1 1 1 1 100.00
- Electrical Cable Ladder (PR No.#80) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Electrical HV Cable Termination (PR No.#69) Comp. Qty 12% 1 1 1 1 1 1 100.00
- Electrical Cable Power (PR No.#72) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Electrical Steel Mat'l (PR No.#77) Comp. Qty 9% 1 1 1 1 1 1 100.00
PRO4500 PR/PO of Instrument Matl's 0.02 25-Nov-06 22-Jan-07 70 Comp. Qty 90% 7 7 7 7 7 7 100.00 100.00 100.00 100.00 0.00
- Control Valve (PR No.#29) Comp. Qty 21% 1 1 1 1 1 1 100.00
- Instrument Cables (PR No.#102) Comp. Qty 19% 1 1 1 1 1 1 100.00
- Instrument Cables Glands (PR No.#149) Comp. Qty 15% 1 1 1 1 1 1 100.00
- Instrument Hook-Up Matl's (PR No.#144) Comp. Qty 14% 1 1 1 1 1 1 100.00
- Instrument Earthing Matl's (PR No.#156) Comp. Qty 7% 1 1 1 1 1 1 100.00
- Instrument Steel Matl's (PR No.#158) Comp. Qty 9% 1 1 1 1 1 1 100.00
- Instrument MCT & Misc. Items (PR No.#154) Comp. Qty 5% 1 1 1 1 1 1 100.00
Purchase Order to Delivery 0.04 30-Nov-06 24-May-07 174 Expedite 100.00 100.00 100.00 100.00 0.00
100%
PRO4460 PO to Del Structural Matl's 0.01 03-Jan-07 15-May-07 26 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4510 PO to Del Pipe Matl's 0.01 30-Nov-06 14-Apr-07 48 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4520 PO to Del Electrical Matl's 0.01 22-Jan-07 23-May-07 35 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4530 PO to Del Instrument Matl's 0.01 22-Jan-07 24-May-07 35 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
PRO4540 PO to Del Mechanical Matl's 0.01 20-Dec-06 19-May-07 30 Linear 100% 100 100.00 100.00 100.00 100.00 100.00 0.00
Materials Receiving Inspection 0.08 14-Apr-07 05-Jun-07 324 Delivered to Site Accepted 100.00 100.00 100.00 100.00 0.00
80% 20%
PRO4580 Receive/Accept of Structural Matl's 0.01 15-May-07 23-May-07 60 Nos. 100% 1 1 1 100.00 100.00 100.00 100.00 0.00
20 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
PRO4590 Receive/Accept of Pipe Matl's 0.02 14-Apr-07 04-May-07 98 Nos. 100% 1648 1648 1648 100.00 100.00 100.00 100.00 0.00
- Ball, Globe, Gate & Check Valves (PR No.#62) Nos. 23% 25 25 25 100.00
- Pipes (PR No.#63) Nos. 27% 108 108 108 100.00
- Flange and Pipe Fitting (PR No.#64) Nos. 19% 212 212 212 100.00
- Gasket (PR No.#83) Nos. 10% 128 128 128 100.00
- Stud Bolt with Nuts (PR No.#136) Nos. 8% 1164 1164 1164 100.00
- Pipe Supports Matl's (PR No.#103) Nos. 13% 11 11 11 100.00
PRO4600 Receive/Accept of Electrical Matl's 0.02 24-May-07 05-Jun-07 72 Nos. 100% 1012 1012 1012 100.00 100.00 100.00 100.00 0.00
- Electrical Cables (PR No.#70) Nos. 24% 250 250 250 100.00
- Electrical Cable Gland (PR No.#73) Nos. 20% 18 18 18 100.00
- Electrical Earthing Matl's (PR No.#74) Nos. 7% 183 183 183 100.00
- Electrical Cable Ladder (PR No.#80) Nos. 14% 222 222 222 100.00
- Electrical HV Cable Termination (PR No.#69) Nos. 12% 2 2 2 100.00
- Electrical Cable Power (PR No.#72) Nos. 14% 310 310 310 100.00
- Electrical Steel Mat'l (PR No.#77) Nos. 9% 27 27 27 100.00
PRO4610 Receive/Accept of Instrument Matl's 0.02 25-May-07 05-Jun-07 70 Nos. 100% 1711 1711 1711 100.00 100.00 100.00 100.00 0.00
- Control Valve (PR No.#29) Nos. 24% 1 1 1 100.00
- Instrument Cables (PR No.#102) Nos. 20% 1478 1478 1478 100.00
- Instrument Cables Glands (PR No.#149) Nos. 15% 54 54 54 100.00
- Instrument Hook-Up Matl's (PR No.#144) Nos. 16% 52 52 52 100.00
- Instrument Earthing Matl's (PR No.#156) Nos. 14% 10 10 10 100.00
- Instrument Steel Matl's (PR No.#158) Nos. 7% 106 106 106 100.00
- Instrument MCT & Misc. Items (PR No.#154) Nos. 4% 10 10 10 100.00
PRO4620 Receive/Accept of Mechanical Matl's 0.01 21-May-07 30-May-07 24 Nos. 100% 3 3 3 100.00 100.00 100.00 100.00 0.00
- Equal Barred Tee (PR No.#11) Nos. 60% 1 1 1 100.00
- Corrosion Monitoring System (PR No.#13) Nos. 40% 2 2 2 100.00
FABRICATION SHIPLOOSE ITEMS 1.57 04-May-07 24-Jul-07 6,654 100.00 100.00 100.00 100.00 0.00
Structural 0.19 24-May-07 05-Jul-07 801 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1000 Fab. Misc Structural Members E11K-A 0.19 24-May-07 05-Jul-07 801 No. of Pcs 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
Mechanical 0.05 30-May-07 04-Jul-07 200 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1120 Fab. Mechanical Items 0.05 30-May-07 04-Jul-07 200 Pcs 100% 3 3 100.00 3 3 100.00 3 100.00 3 100.00 100.00 100.00 100.00 100.00 0.00
Piping 1.04 04-May-07 13-Jul-07 4,411 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Dia Total Dia
Done % Done % Done % Done %
Inch Inch
SHP1010 Fabricate Pipe Supports 0.18 04-May-07 11-Jun-07 751 Dia Inch 100% 33 33 100.00 33 33 100.00 33 100.00 33 100.00 100.00 100.00 100.00 100.00 0.00
SHP1030 Fabricate CS Pipe Spools 0.28 04-May-07 07-Jun-07 1,200 Dia Inch 100% 495 495 100.00 495 495 100.00 495 100.00 495 100.00 100.00 100.00 100.00 100.00 0.00
SHP1040 Testing & Preservation of Pipe Spools 0.04 16-Jun-07 06-Jul-07 160 Dia Inch 100% 11 11 100.00 11 11 100.00 11 100.00 11 100.00 100.00 100.00 100.00 100.00 0.00
SHP1160 Fabricate Duplex Pipe Spools 0.33 26-May-07 21-Jun-07 1,401 Dia Inch 100% 803 803 100.00 803 803 100.00 803 100.00 803 100.00 100.00 100.00 100.00 100.00 0.00
SHP1170 Fabricate SS Pipe Spools 0.14 13-Jun-07 01-Jul-07 599 Dia Inch 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
SHP1180 Fabricate GRE Pipe Spools 0.07 26-Jun-07 13-Jul-07 300 Dia Inch 100% 100 100 100.00 100 100 100.00 100 100.00 100 100.00 100.00 100.00 100.00 100.00 0.00
Electrical 0.11 05-Jun-07 11-Jul-07 480 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1050 Fabricate Electrical Supports 0.07 05-Jun-07 29-Jun-07 300 Pcs 100% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Handling 90% Accept 10%
Done % Done %
SHP1140 Electrical Shiploose Items 0.04 21-Jun-07 11-Jul-07 180 Pcs 100% 7 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
Instrument 0.11 05-Jun-07 11-Jul-07 480 Mark & Cut 20% Fit-Up 30% Weld 40% Accept 10% 100.00 100.00 100.00 100.00 0.00
Total Total
Done % Done % Done % Done %
Pieces Joints
SHP1060 Fabricate Instrument Supports 0.07 05-Jun-07 29-Jun-07 300 Pcs 100% 2 2 100.00 2 2 100.00 2 100.00 2 100.00 100.00 100.00 100.00 100.00 0.00
Handling 90% Accept 10%
Done % Done %
SHP1150 Instrument Shiploose Items 0.04 21-Jun-07 11-Jul-07 180 Pcs 100% 7 7 100.00 7 100.00 100.00 100.00 100.00 100.00 0.00
Blasting/Painting 0.07 11-Jun-07 24-Jul-07 282 Prep B/P 1st Coat 2nd Coat Accept 100.00 100.00 100.00 100.00 0.00
10% 30% 25% 25% 10%
SHP1070 Blasting/Painting Pipe Supports 0.02 11-Jun-07 28-Jun-07 72 Pcs 100% 33 33 33 33 33 33 100.00 100.00 100.00 100.00 0.00
SHP1080 Blasting/Painting Pipe Spools 0.02 06-Jul-07 24-Jul-07 70 Pcs 100% 100 100 100 100 100 100 100.00 100.00 100.00 100.00 0.00
SHP1090 Blasting/Painting Electrical Supports 0.01 29-Jun-07 09-Jul-07 30 Pcs 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
SHP1100 Blasting/Painting Instrument Supports 0.01 29-Jun-07 09-Jul-07 30 Pcs 100% 2 2 2 2 2 2 100.00 100.00 100.00 100.00 0.00
SHP1110 Blasting/Painting Structural Members 0.01 05-Jul-07 17-Jul-07 40 Pcs 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
SHP1130 Blasting/Painting Mechanical Items 0.01 04-Jul-07 13-Jul-07 40 Pcs 100% 1 1 1 1 1 1 100.00 100.00 100.00 100.00 0.00
LOADOUT & SEAFASTENING SHIPLOOSE 0.05 08-Aug-07 11-Aug-07 192 100.00 100.00 100.00 100.00 0.00
Prep/Chk Packing LO SF Accept
30% 40% 10% 10% 10%
LOA1020 Loadout & Seafastening Shiploose Items 0.05 08-Aug-07 11-Aug-07 192 Compl 100% 100 100 100 100 100 100 100.00 100.00 100.00 100.00 0.00
21 of 22
PROG. COD : 28-Sep-07 CUMM PROGRESS THIS WEEK
SUMMARY of ENGINEERING
Review Materials 16.22 4-Aug-06 2-Jan-07 5,183 100.00 100.00 100.00 100.00 0.00
Construction Drawings 83.78 4-Aug-06 6-Aug-07 26,771 100.00 100.00 100.00 100.00 0.00
Overall ENGINEERING Progress 100.00 4-Aug-06 6-Aug-07 31,954 100.00 100.00 100.00 100.00 0.00
SUMMARY of PROCUREMENT
Client Supply Materils 8.57 17-Aug-06 23-Aug-07 3,017 100.00 100.00 100.00 100.00 0.00
MMHE Supply Materials 91.43 7-Aug-06 8-Aug-07 32,179 100.00 100.00 100.00 100.00 0.00
Purchase Request to Purchase Order 52.20 7-Aug-06 8-Feb-07 16,796 100.00 100.00 100.00 100.00 0.00
Purchase Order to Delivery 0.00 3-Oct-06 23-Jul-07 - 0.00 0.00 0.00 0.00 0.00
Materials Receiving Inspection 47.80 29-Nov-06 8-Aug-07 15,383 100.00 100.00 100.00 100.00 0.00
Overall PROCUREMENT Progress 100.00 7-Aug-06 23-Aug-07 35,196 100.00 100.00 100.00 100.00 0.00
22 of 22
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
SUB-CONTRACT NO : 36006607
WORK DESCRIPTION : STRUCTURAL WORKS @ SCDR-A TOPSIDES
SUB-CONTRACTOR : KEJUYUTERAAN WIJAYA SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ARNEL MENDOZA
DESIGNATION : SCTRUCTURAL/ACHITECTURAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 13, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average
VII SUBCONTRACTS
Selection of Subcontractors 4 Average
Personnel/ Supervision 4 Average
VIII EXPEDITING 4 Average
IX BULK MATERIAL CONTROL 4 Average
ESTIMATING, COST REPORTING & COST
X 4 Average
CONTROL.
XI PLANNING/ SCHEDULING IN WORK 4 Average
XII PROCESSING OF CHANGES IN WORK 4 Average
XIII FIELD EFFICIENCY 4 Average
OVERALL RATING 4 Average, Few weaknesses.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
Management is short of comments that leads to unpleasant discussion..
2. Any special factors that affected subcontractor’s performance on this project.
Submitted plan were just for compliance but not workable.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007629
WORK DESCRIPTION : ARCHITECTURAL WORKS
SUB-CONTRACTOR : ARROW PLATFORM (M) SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ARNEL MENDOZA
DESIGNATION : SCTRUCTURAL/ACHITECTURAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 5 Low Average, with some weaknesses
VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, Few weaknesses.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
They can perform the work but unable to meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
Expediting effort on submission of Vendor Data or on delivery of materials, failed to
expedite successfully.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007625
WORK DESCRIPTION : FABRICATION & INSTALLATION OF PIPING WORKS
SUB-CONTRACTOR : JURUNATURE SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : MOHD SUBHA B. RI
DESIGNATION : PIPING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 3 Generally meets desired standard of performance.
VII SUBCONTRACTS
Selection of Subcontractors 3 Generally meets desired standard of performance.
Personnel/ Supervision 4 Average, low of supervision & monitoring.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses of monitoring.
ESTIMATING, COST REPORTING & COST
X 3 Generally meets desired standard of performance.
CONTROL.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 3 Generally meets desired standard of performance.
XIII FIELD EFFICIENCY 3 Generally meets desired standard of performance.
OVERALL RATING 3 Generally meets desired standard of performance.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
They can perform the work & meet the desired MMHE standard of performance.
2. Any special factors that affected subcontractor’s performance on this project.
Strong support to the Project Team.
Meet the project schedule.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007624
WORK DESCRIPTION : FABRICATION & INSTALLATION OF GRE PIPES
SUB-CONTRACTOR : AMERSTARND ENGINEERING SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : MOHD SUBHA B. RI
DESIGNATION : PIPING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.
VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
Average, with few weaknesses of
IX BULK MATERIAL CONTROL 4
monitoring.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, with few weaknesses.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
They can perform the work but cannot meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
Strong support to the Project team.
Meet the project schedule.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007625
WORK DESCRIPTION : MECHANICAL INSTALLATION WORKS
SUB-CONTRACTOR : JURUNATURE SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351
NAME OF RATER : ABD RAZAK ABU BAKAR
DESIGNATION : MECHANICAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
Performed works and meet the desired standard of performance.
2. Any special factors that affected subcontractor’s performance on this project.
Strong team personnel/supervision at site.
All materials meet the delivery target/schedule.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007628
WORK DESCRIPTION : ELECTRICAL & INSTRUMENTATION WORKS
SUB-CONTRACTOR : ASADRA (M) SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : TEODORO D. FLORES
DESIGNATION : ELECTRICAL / INSTRUMENTATION SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 10, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.
VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
Many weaknesses. Can perform work
OVERALL RATING 6 but cannot meet the desired standard
of performance.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
Many weaknesses. Can perform work but cannot meet the desired standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
Delay in delivery of materials.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36007627
WORK DESCRIPTION : BLASTING & PAINTING WORKS
SUB-CONTRACTOR : BB TECH SERVICES SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : SANUSI HANAFI
DESIGNATION : BLASTING & PAINTING SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 18, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average, with few weaknesses.
VII SUBCONTRACTS
Selection of Subcontractors 4 Average, with few weaknesses.
Personnel/ Supervision 4 Average, with few weaknesses.
VIII EXPEDITING 4 Average, with few weaknesses.
IX BULK MATERIAL CONTROL 4 Average, with few weaknesses.
X ESTIMATING, COST REPORTING & COST CONTROL. 4 Average, with few weaknesses.
XI PLANNING/ SCHEDULING IN WORK 4 Average, with few weaknesses.
XII PROCESSING OF CHANGES IN WORK 4 Average, with few weaknesses.
XIII FIELD EFFICIENCY 4 Average, with few weaknesses.
OVERALL RATING 4 Average, Few weaknesses.
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
They can perform the work but unable to meet the desired MMHE standard of
performance.
2. Any special factors that affected subcontractor’s performance on this project.
Sometimes lack of manpower & equipment.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
SUB-CONTRACT NO : 36006616
WORK DESCRIPTION : HVAC SYSTEM FABRICATION & INSTALLATION
SUB-CONTRACTOR : DYNAC SDN BHD
NAME OF PROJECT/ JOB NO : SCDR-A TOPSIDES - 20066351C
NAME OF RATER : ABD RAZAK ABU BAKAR
DESIGNATION : MECHANICAL SUPERINTENDENT
SIGNATURE :
DATE OF RATING : August 17, 2007
VI MATERIAL PURCHASING
Knowledge of Vendors 4 Average.
VII SUBCONTRACTS
Meets the desired standard of
Selection of Subcontractors 3
performance.
Meets the desired standard of
Personnel/ Supervision 3
performance.
VIII EXPEDITING 4 Average
IX BULK MATERIAL CONTROL 4 Average.
Meets the desired standard of
X ESTIMATING, COST REPORTING & COST CONTROL. 3
performance.
XI PLANNING/ SCHEDULING IN WORK 4 Average
XII PROCESSING OF CHANGES IN WORK 4 Average
Meets the desired standard of
XIII FIELD EFFICIENCY 3
performance.
OVERALL RATING 4 Average
GENERAL COMMENTS:
1. Detail comments on subcontractor’s performance.
Meet the desired standard of performance, but needs to improve planning work schedule.
2. Any special factors that affected subcontractor’s performance on this project.
Shortage / less manpower working direct at site.
Improve procurement of material schedule.
Need improvement on Planning, Procurement & key personnel at site.
3. Any reservation on this subcontractor getting future MMHE work.
Recommend for future MMHE work.
Page 1 / 1
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
01
PROVISIONAL SUM-PART 3;SCHEDULE OF PRICES AND RATES;ITEM 9 - SUPPLY ADDITIONAL HOOK-UP MATERIALS, OFFSHORE COMMISSIONING SPARES, START-UP SPARES and 1 Year OPERATING SPARES
Structural
12/12/06 175,066.45 175,066.45 In Progress Approved
Pipe Supports
27/03/07 1,793.22 1,793.22 In Progress Approved
TOTAL VOP 1,144,714.20 65,049.60 1,042,699.36 79% 827,617.64 38,753.62 65,049.60 65,049.60
TOTAL PS+VOP + RFQ 1,374,410.59 76,659.60 1,272,395.75 85% 1,076,919.39 38,753.62 76,659.60 65,049.60
MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD
ENGINEERING AND CONSTRUCTION DIVISION
CONTRACT TITLE : FABRICATION OF SCDR-A TOPSIDES
CONTRACT NO : 591397
REQUEST FOR QUOTATION REGISTER
Date : 20-Oct-2007
001 PPE For Fabrication : Use of Coverall 20/12/06 65,049.60 65,049.60 Aproved CO-1/VO-1
002 Red Color Painting For Firewater Lines 08/05/07 23,662.62 Rejected
Revised Sand Bin Leg Connection
Incoporated in AFB/AFC
003 16/05/07 1,312.00 1,312.00
remeasurement for Mechanical
Approved
004 WHCP Accumulator Material Substitution From Bladder Type To Piston 16/05/07 278,351.00 SSB to Reply
Additional Cantilever Beam for Blastwall support (STQ no. A- Amount agreed in
007 008),Additional steel works to infill the gaps (STQ no A-009),Additional 25/05/07 25,534.90 25,534.90 principle.SSB to issue SSB to issue CO
wings plates (STQ no-045),Wiremesh Material Proposal CO
Amount agreed in
008 Additional AFC Rev A due to VDI(Desender) 09/06/07 24,309.74 24,309.74 principle.SSB to issue SSB to issue CO
CO
STQ-S-50;material substitution from 50mm thk to 60mm thk. (SSB
009 15/06/07 12,483.87 SSB to Reply
supply)
010 First Fill - Chemical For Corrosion Inhibitor Skid 21/06/07 166,603.50 SSB to Reply
011 Additional Flanges (as per STQ No. P-013 & P-019) 29/06/07 22,977.00 SSB to Reply
012 Additional Switches for toilet, STQ-E-013 18/07/07 1,473.00 SSB to Reply
013 Additional Beacon, STQ-E-008 & E-012 19/07/07 21,288.88 SSB to Reply
Fabricate and Install Cageladder and Handrail @battery Room, STQ-S-
SSB to Reply
014 058 24/07/07 16,127.56
Additional 10mm Thick Plate (S-055), Additional Structural Support for
015 Lift Raft Along Platform (S-062), and Fabricate and Install Deck Drain (S- 28/07/07 4,937.46 SSB to Reply
065)
Re-routing and Change of Piping Material of Portable Water Line to
016 08/01/2007 3,191.48 SSB to Reply
Toilet,STQ-P-21
017 Supply Ball Valves on behalf of COMPANY 13/8/2007 225,341.50 SSB to Reply
018 Lifebuoy Quantity (STQ No. M-027) 15/8/2007 1,397.50 SSB to Reply
019 IRP-7875 and IRP-7802 Rewiring - New Scope (STQ-E-031) 22/8/2007 6,450.00 MMHE to resubmit
VARIATION ORDER PROPOSAL
AMOUNT VOP PROCESSING
VOP No. DESCRIPTION DATE SUBMITTED APPROVED REMARKS
ISSUED RM RM
020 Change of specification for Washdown Hose Reel 25/8/2007 7,839.98 SSB to Reply
022 Cost Impact for STQ No. M-032 and STQ No. M-033 28/8/2007 38,524.94 SSB to Reply
024 AUX Power Supply From UPS DB-7815 to TF-7505 (STQ No. E-030) 09/07/2007 750.00 SSB to Reply
025 Additional Portable Eyewash Station (STQ No. E-035) 09/11/2007 1,483.50 SSB to Reply
026 Additional 2 nos of MCT and cable ladders due to reroute of cable from
14/9/2007 7,012.50 SSB to Reply
RMU to Transformer (STQ No. E-019)
027 Supply and Install Sunshade 10/04/2007 21,983.51 SSB to Reply
028 Cost Impact for STQ P-023 and S-069 10/05/2007 19,413.16 SSB to Reply
Note :
SCDR-A Topsides & E11K-A Shiploose Items
Close-Out Report
Sarawak Shell Bhd.
19-09-07 SHIPLOOSE
(8’’ x 150’ x 5 LENGTHS/PACK x PP ROPE x BOTH END
CANVAS EYE)
25-09-07 SHIPLOOSE
(PART OF INTERMEDIATE PLATFORM STRUCTURE)