BIKE TOWN WATER SUPPLY AND SAINTATION PROJECT
1. GENERAL INFORMATION
Background
Supply of Adequate water is one of the hot issue that contribute the standard life of communities
through improving health so that increasing the productivity of society.
The Somali regional state Water Resources Development Bureau as the client, has planned to
undertake Construction of Bike Town Water Supply and sanitation project and has begun the
Construction Works in order to ensure the water sufficiency in terms of quantity and acceptable
quality to meet target.
2. Working Hours
3. Weather Condon’s
4. Project Description
The water source for this project is the deep well drilled near dera elle Kebele at an average elevation
of 1030m and its far 10,000m from the town. The water will be pumped to rectangular cooling tanks
located at well site by a submersible pump and then after cooling the water will be fill by gravity to
underground 200 m3 reservoirs 80 m far from cooling tanks by gravity then its fills artificial wet
wells pumped to 500 m3 booster station which Fars 4,900m and also after fill artificial wells fills its
pumped to 1000 m3 service reservoirs at bike town and gravitated to the demand area 13 km
distribution pipes to the town and surrounding community.
Civil works
At Bore Holes
Construction of rectangular cooling tanks - 98% done except minor works
Underground 200m3 reservoirs 98% on progress ready for artificial well connection
Construction of generator and guard house 98% except electric installation
Construction of public toilets 98% except electric installation
Construction of Artificial wet well are in progress 98% except out let fittings joint but it
supply
At Booster Station
Construction 500m3 reservoirs 96% progress for connection to artificial wells
Construction of generator and guard house 98% except electric installation
Artificial wet well are in progress due to excavation of ped Roch and bar cutting is done
At Service Reservoirs
Construction 1000m3 reservoirs 96% ready on progress for fencing and connection of inlet
and out let
Construction of public toilets 98% except electric installation
Construction of Guad house 98% except electric installation
Construction of utility offices
construction of office in progress by lay block works and Colum
construction of meeting hull, mosque and stores is foundation casting is done and ready for
placing block
Construction of water point and cattle troughs
construction of 13 pcs of water points is done except the finishing works 75%
construction of 2 cattle and goat troughs is done 80%
6. Remain works
THE AVERAGE PROGRESS STATUS OF THE PROJECT 82.9% PHYSICALLY AND 64%
FINANCIALLY
still the distribution surveying works and set out not done
Price escalation of pipes ,fittings and pumps may influence the project completion periods