Final Daily Report Availbility (7!11!2020)
Final Daily Report Availbility (7!11!2020)
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
GET Day Opportune C/O 3x Tips&1x Cover 07-Nov-20 11:15 AM 07-Nov-20 11:30 AM
SH003 0.00 100.00%
No of Equipment 3 Total Down (Hours) 1.00
Excavators RH120E Availability % 82.29% MTD Ava 89.10% Number of Equip 4 Suspended
Equipmen DTAvail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 250H Service,Backlog Jobs 06-Nov-20 6:45 AM 07-Nov-20 9:30 AM
EX001 4.50 81.25% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Night Planned 1000H Service,Backlog Jobs 07-Nov-20 6:00 PM
EX003 11.50 52.08% 2 Down
Lubrication System Day Breakdown Grease Hose 07-Nov-20 6:30 AM 07-Nov-20 7:00 AM
Cab/ Chassis & Superst Day Breakdown Fit RH Glass Window 07-Nov-20 6:30 AM 07-Nov-20 7:00 AM
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Lubrication System Day Breakdown Bucket Cut off 07-Nov-20 2:00 PM 07-Nov-20 3:00 PM
EX005 1.00 95.83% 1
No of Equipment 3 Total Down (Hours) 17.00
Excavators RH90 Availability % 95.83% MTD Ava 98.66% Number of Equip 1 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Day Breakdown Radio C/O Voltage Convertor 07-Nov-20 9:00 AM 07-Nov-20 9:45 AM
EX007 1.00 95.83% 2
Electrics Day Breakdown Radio Not Working 07-Nov-20 6:00 AM 07-Nov-20 6:15 AM
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Night Planned 1000H Service,Backlog Jobs 07-Nov-20 8:45 PM 08-Nov-20 1:45 AM
DT015 5.00 79.17% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Hydraulic Night Breakdown Hyd. Oil Leak C/O PTO Seal 08-Nov-20 2:15 AM 08-Nov-20 4:45 AM
DT021 2.50 89.58% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Attachments Day Breakdown RH Diff. Guard Missing 07-Nov-20 5:30 AM 07-Nov-20 7:00 AM
DT022 3.50 85.42% 3
Trans and TC Night Breakdown Drain TRN oil&Top Hyd. Oil 07-Nov-20 9:00 PM 07-Nov-20 10:30 PM
Hydraulic Day Breakdown adjust level hyd. Oil Too hi 07-Nov-20 3:00 PM 07-Nov-20 3:30 PM
Trans and TC Day Breakdown adjust level Trans. Oil Too hi 07-Nov-20 3:00 PM 07-Nov-20 3:30 PM
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned Full Life 11-Oct-20 8:00 AM 07-Nov-20 6:00 PM
DT023 13.00 45.83% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Night Planned inflate pos#6 07-Nov-20 7:15 PM 07-Nov-20 7:30 PM
DT027 0.25 98.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Engine Night Breakdown C/O Starter Motor 08-Nov-20 2:00 AM 08-Nov-20 3:15 AM
DT032 1.25 94.79% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Day Planned inflate Pos#4&5 07-Nov-20 1:00 PM 07-Nov-20 1:15 PM
DT041 0.25 98.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 250H Service,Backlog Jobs 07-Nov-20 1:30 PM
DT042 15.50 35.42% 1 Down
Tires Day Planned C/O Rear Tyres(Worn out) 07-Nov-20 1:30 PM
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Night Planned inflate pos#1 07-Nov-20 8:45 PM 07-Nov-20 9:15 PM
DT046 0.50 97.92% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Night Planned 500H Service,Backlog Jobs 07-Nov-20 5:45 PM 08-Nov-20 2:30 AM
DT047 8.75 63.54% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Day Planned inflate pos#4 07-Nov-20 1:15 PM 07-Nov-20 1:30 PM
DT048 0.25 98.96% 1
No of Equipment 12 Total Down (Hours) 53.25
Dump Trucks 775G Availability % 80.00% MTD Ava 77.80% Number of Equip 5 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Availability Daily Report
Compartement Shift Stoppage Equipment Fault Desc.
Saturday, November 7, 2020
Date In Time In Date Out Time Out
Equipmen DT Avail % Stopage Status
Rebuild Night Planned Mid Life 01-Nov-20 1:30 AM
DT101 24.00 0.00% 1 Down
No of Equipment 1 Total Down (Hours) 24.00
Availability Daily Report Saturday, November 7, 2020
Ancillary
Project Excavators Availability % 96.88% MTD Ava 55.65% Number of Equip 2 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Hydraulic Night Breakdown C/O Implement ECM -Pump Combination Valve 25-Jul-20 10:30 PM 07-Nov-20 6:30 AM
EX002 1.50 93.75% 1 (W.P)
Water Trucks Availability % 79.17% MTD Ava 78.89% Number of Equip 6 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Hydraulic Day Breakdown Hyd. Tube Leak(Weld 2x Tube) 07-Nov-20 9:00 AM 07-Nov-20 3:00 PM
WT005 6.00 75.00% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Engine Day Planned Full Life 15-Oct-20 6:30 AM
WT006 24.00 0.00% 1 Down
No of Equipment 2 Total Down (Hours) 30.00
Articulated Dump Truck Availability % 81.25% MTD Ava 68.25% Number of Equip 3 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Engine Day Breakdown Articulation Bearing & Line Booring (W.P) 30-Aug-20 1:00 PM 07-Nov-20 6:30 PM
AT002 13.50 43.75% 1
Electrics Day Breakdown FSS 30-Aug-20 1:00 PM 07-Nov-20 6:30 PM
Integrated Tool Carrier Availability % 100% MTD Ava 94.73% Number of Equip 7 Suspended
Compact Roller Availability % 100% MTD Ava 100.00% Number of Equip 2 Suspended