Final Daily Report Availbility (7!12!2020)
Final Daily Report Availbility (7!12!2020)
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Night Breakdown C/O R.H Indicator 08-Dec-20 1:00 AM 08-Dec-20 2:00 AM
DT006 1.00 95.83% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Night Planned 1000 H Service , Backlog Jobs 07-Dec-20 7:00 PM
DT008 10.00 58.33% 1 Down
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Engine Day Breakdown Leaking Coolant From Main Pump Pipe C/O 07-Dec-20 6:30 AM 07-Dec-20 12:45 PM
DT010 6.25 73.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Trans and TC-ELE Day Breakdown Trans. ECM Err body up 07-Dec-20 8:30 AM 07-Dec-20 2:30 PM
DT015 6.00 75.00% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 500 H Service 03-Dec-20 5:30 AM
DT022 24.00 0.00% 1 Down
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Night Breakdown C/O L.H Rear Light 07-Dec-20 7:30 PM 07-Dec-20 8:00 PM
DT023 0.50 97.92% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned Full Life 07-Dec-20 5:45 AM
DT027 23.25 3.13% 1 Down
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 250H Service,Backlog Jobs 07-Dec-20 6:00 AM 08-Dec-20 1:45 AM
DT028 19.75 17.71% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Steering Day Breakdown Noiae at HMU/RH&LH Accumulators C/O 07-Dec-20 7:45 AM 07-Dec-20 4:15 PM
DT029 8.50 64.58% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Night Planned Inflate# 1,3 07-Dec-20 7:00 PM 07-Dec-20 7:15 PM
DT030 0.25 98.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Night Planned Inflate# 1 07-Dec-20 6:15 PM 07-Dec-20 6:30 PM
DT032 0.25 98.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Tires Night Planned Inflate# 2 07-Dec-20 7:45 PM 07-Dec-20 8:00 PM
DT037 0.25 98.96% 1
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 250H Service,Backlog Jobs 06-Dec-20 6:15 AM
DT042 24.00 0.00% 1 Down
Availability Daily Report Monday, December 7, 2020
No of Equipment 14 Total Down (Hours) 132.75
Dump Trucks 775G Availability % 100.00% MTD Ava 95.83% Number of Equip 5 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Engine Day Opportune Check Eng. Oil Sample 07-Dec-20 7:30 AM 07-Dec-20 2:00 PM
DT101 0.00 100.00%
No of Equipment 1 Total Down (Hours) 0.00
Availability Daily Report Monday, December 7, 2020
Ancillary
Project Excavators Availability % 100% MTD Ava 87.65% Number of Equip 2 Suspended
Wheel Loaders Availability % 100% MTD Ava 98.16% Number of Equip 3 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Final Drive & Diff Day Breakdown Broken LH Front Axle 07-Dec-20 6:30 AM
GR006 22.50 6.25% 1 Down
No of Equipment 4 Total Down (Hours) 39.75
Availability Daily Report Monday, December 7, 2020
Water Trucks Availability % 80.56% MTD Ava 76.04% Number of Equip 6 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned Mid Life 07-Dec-20 6:30 AM
WT004 22.50 6.25% 1 Down
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Day Breakdown Water Tank Lamp on/Sensor 07-Dec-20 2:30 PM 07-Dec-20 8:00 PM
WT007 5.50 77.08% 1
No of Equipment 2 Total Down (Hours) 28.00
Articulated Dump Truck Availability % 100% MTD Ava 98.36% Number of Equip 3 Suspended
Services Truck Availability % 100% MTD Ava 100.00% Number of Equip 2 Suspended
Integrated Tool Carrier Availability % 100% MTD Ava 95.41% Number of Equip 7 Suspended
Compact Roller Availability % 57.29% MTD Ava 93.90% Number of Equip 2 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
PM Day Planned 2000H Service,Backlog Jobs 07-Dec-20 8:30 AM
CM002 20.50 14.58% 1 Down
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Night Opportune Radio ( C/O Fuse ) 07-Dec-20 11:00 PM 07-Dec-20 11:15 PM
CM001 0.00 100.00%
No of Equipment 2 Total Down (Hours) 20.50
Telehandler Availability % 66.67% MTD Ava 66.67% Number of Equip 3 Suspended
Equipmen DT Avail % Stopage Status Compartement Shift Stoppage Equipment Fault Desc. Date In Time In Date Out Time Out
Electrics Night Breakdown No Move (Wiring Fault ) 16-Nov-20 5:00 PM
TL002 24.00 0.00% 1 Down
No of Equipment 1 Total Down (Hours) 24.00