Professional Documents
Culture Documents
Chapter 9.flood Control Plans 9.1 Basic Concepts For Formulating Flood Control Plans
Chapter 9.flood Control Plans 9.1 Basic Concepts For Formulating Flood Control Plans
(1) Design Discharge in the Upstream Reach of the KBT: 140m 3/s
The design discharge in the upstream reach of the KBT is to be set at 140m 3/s for
considering the original design discharge of the Inlet Gate of 145m 3/s (source: Detail
Desain Sistem Sungai Dolok Penggaron (Kanal Banjir Timur – Dombo Sayung),
PT.Jasapatria Gunatama, November 2009 (DD study)).
However, according to the hydraulic model test conducted in 2007, if the 6 sliding
gates of the inlet gate of KBT are fully opened under the high floodwater level in the
Penggaron River, about 215m3/s will be discharged through the inlet gate to the KBT.
Hence, in order to limit the discharge through the inlet gate of KBT with maximum
140m3/s under the condition of design discharge of the Penggaron River, only 4 sliding
gates among the 6 gates can be fully opened during floods (215/6 x 4 =143m3/s). It is
based on the rating curve of KBT made by the hydraulic model test in 2007. The rest
of the 2 gates are to be closed during the floods.
N
Penggaron River System:
Jawa Sea
Utilize the Natural Retarding
Basin as it is.
Dombo-Sayung River Improvements of the KbT,
River Babon and Dombo-Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
River Drainage
Improvement:
For not increasing Legend:
flood discharge of
KBT the Dombo- River
Candi Sayung River Main Drainage Channel
River Downstream so Major Road
much, drainage
Bajak water is Railway
River recommended to Existing Overflow Weir
Kudung Close gate
Mundu during be treated Existing Gated Weir
River floods separately for
flowing down to Natural Retarding
Pucanggading Basin
the sea.
River Improvement
Penggaron Drainage Improvement
River Kebon-
between Dombo-
Batur Canal Barang Weir Sayung and Dolok
Rivers
Figure 9.3.1 Penggaron River System_Alt-1: River Improvements and Utilization of the
Natural Retarding Basin
N
Penggaron River System:
Jawa Sea
Utilize the Natural Retarding
Basin as it is.
Dombo-Sayung River Improvements of the KBT,
River Babon and Dombo-Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
River Drainage
Improvement:
For not increasing Legend:
flood discharge of River
KBT the Dombo- Main Drainage Channel
Candi Sayung River
Downstream so Major Road
River
much, drainage Railway
Bajak water is Existing Overflow Weir
River recommended to
Kudung Close gate Existing Gated Weir
Mundu during be treated
River floods separately for Strengthening of the
flowing down to Retarding Basin
Pucanggading the sea. River Improvement
Penggaron Drainage Improvement
River Kebon- between Dombo-
Batur Canal Barang Weir Sayung and Dolok
Rivers
Reduction of the peak discharge of the floodwater in the upstream by the proposed
Dolok Dam or without reduction of the peak discharge without Dolok Dam
To follow the present river course in the upstream reach of the Dolok River for river
improvement or to construct a bypass floodway
Current river course in the upstream reach has many small meanderings and houses
and small towns along the river. For river improvement along the upstream reach
needs short-cuts of the meanderings. Bypass floodway is set for flowing down
floodwater by avoiding this present upstream reach with many meanderings and
houses. A control weir (gated weir or closing dike with a hole for flowing small
water quantity to the downstream) and an overflow weir are to be installed in the
Dolok River and the Bypass Floodway respectively to control water, so that only
floodwater enters into the Bypass Floodway during floods.
Alternatives considerable in the Dolok River improvements are as follows:
Alternative-1 (Alt-1): River improvement along the present river course without Dolok Dam
Alternative-2 (Alt-2): River improvement and the Bypass Floodway without Dolok Dam
Alternative-3 (Alt-3): River improvement along the present river course with Dolok Dam
Alternative-4 (Alt-4): River improvement and Bypass Floodway with Dolok Dam to Figure
9.3 .6 show the above alternatives of the Dolok River. Starting site of the Bypass
Floodway is shown in .
Jawa Sea
Dombo-Sayung
River Dolok River System:
River Improvement
Close the Inlet Gate of the Kebon
Dolok
East Floodway Batur Canal during floods
River
(KBT) Without Dolok Dam
Babon
Penggaron River System:
River
Existing Rivers
Existing Natural Retarding Basin
KBT
Candi
River
Bajak
River Legend:
Kudung Close gate River
Mundu during Major Road
floods
River Railway
Pucanggading Existing Overflow Weir
Existing Gated Weir
Penggaron Natural Retarding
River Kebon- Basin
Batur Canal Barang Weir River Improvement
Jawa Sea
Dolok River System:
Dombo-Sayung River Improvement and Bypass
River
Floodway
Close the Inlet Gate of the Kebon
Dolok
Batur Canal
East Floodway River Without Dolok Dam
(KBT) Penggaron River System:
Babon
River Existing Rivers
Existing Natural Retarding Basin
KBT
Candi Legend:
River River
Bajak Major Road
River Railway
Kudung Close gate Existing Overflow Weir
Mundu during
floods Existing Gated Weir
River
Natural Retarding
Pucanggading
Basin
Penggaron River Improvement
River Kebon- New Overflow Weir
Batur Canal Barang Weir New Control Weir
Close the Bypass Floodway
new gate
during
floods
Figure 9.3.4 Dolok River_Alt-2: River Improvement and Bypass Floodway without Dolok
Dam
Jawa Sea
Dombo-Sayung
River
Dolok River System:
River improvement
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
With Dolok Dam
River Penggaron River System:
Existing Rivers
Existing Natural Retarding Basin
KBT
Candi
River
Bajak
River Legend:
Kudung Close gate River
Mundu during Major Road
floods
River Railway
Pucanggading Existing Overflow Weir
Existing Gated Weir
Penggaron Natural Retarding
River Kebon- Basin
Batur Canal Barang Weir River Improvement
Jawa Sea
Dolok River System:
Dombo-Sayung
River River Improvement and Bypass
Floodway
With Dolok Dam
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal
(KBT) Penggaron River System:
Babon
River Existing Rivers
Existing Natural Retarding Basin
KBT
Candi Legend:
River River
Bajak Major Road
River Railway
Kudung Close gate Existing Overflow Weir
Mundu during
floods Existing Gated Weir
River
Natural Retarding
Pucanggading
Basin
River Improvement
Penggaron
Kebon- New Overflow Weir
River
Batur Canal Barang Weir New Control Weir
Close the Bypass Floodway
new gate Proposed
during Dolok Dam Proposed Dolok Dam
floods
Figure 9.3.6 Dolok River_Alt-4: River Improvement and Bypass Floodway with Dolok
Dam
Bifurcation Place of the Bypass View to the Starting Place of the Bypass
Floodway from the Dolok River Floodway
Legend:
Bypass
Floodway
N
Penggaron River System:
Jawa Sea
Utilize the Natural Retarding
Basin as it is.
Dombo-Sayung River Improvements of the BKT,
River Babon and Dombo -Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
River Drainage
Improvement:
Legend:
For not increasing
flood discharge of River
the Dombo- Main Drainage Channel
Candi Sayung River
Major Road
River Downstream so
much, drainage Railway
Bajak water is Existing Overflow Weir
River recommended to
Kudung Existing Gated Weir
Mundu be treated
separately for Natural Retarding
River Close gate
Basin
during flowing down to
Pucanggading River Improvement
floods the sea.
Drainage Improvement
Penggaron between Dombo-
River Kebon-
Sayung and Dolok
Batur Canal Barang Weir
Rivers
Figure 9.4.8 Penggaron River System_Alt-1: Design Discharge (50-Year Return Period)
N
Penggaron River System:
Jawa Sea
Strengthening of the Retarding
Basin by excavation.
Dombo-Sayung River Improvements of the BKT,
River Babon and Dombo -Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
River Drainage
Improvement:
For not increasing Legend:
flood discharge of River
the Dombo- Main Drainage Channel
Candi Sayung River
Downstream so Major Road
River
much, drainage Railway
Bajak water is Existing Overflow Weir
River recommended to
Kudung Existing Gated Weir
Mundu be treated
River Close gate separately for Strengthening of the
during flowing down to Retarding Basin
Pucanggading floods the sea. River Improvement
Penggaron Drainage Improvement
River Kebon- between Dombo-
Batur Canal Barang Weir Sayung and Dolok
Rivers
Figure 9.4.9 Penggaron River System_Alt-2: Design Discharge (50-Year Return Period)
Reference: Effect of Inflow Discharge from the Drainage Basin of D-9-1 and D-9-2:
Figure 9.4.3 and Figure 9.4.4 show the design discharge of the Dombo-Sayung River etc. under
the condition of inflowing the runoff discharge from the drainage channels between the Dombo-
Sayung River and the Dolok River (D-9-1 and D-9-2). In this case, the design discharge in the
downstream reach of the Dombo-Sayung River becomes 285m 3/s for Alt-1 and 180m3/s for Alt-
2, which are 1.8 to 2.1 times bigger than the case of without inflowing the runoff discharge of
D-9-1 and D-9-2 into the Dombo-Sayung River. This phenomenon makes river improvement to
be difficult especially due to many relocation of houses to be required by bigger design cross
sections. Therefore, it is recommended to drain D-9-1 and D-9-2 directly to the sea (not though
the Dombo-Sayung River).
N
Penggaron River System:
Jawa Sea
Utilize the Natural Retarding
Basin as it is.
Dombo-Sayung River Improvements of the BKT,
River Babon and Dombo-Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(KBT)
Babon
River
Inflow
Legend:
runoff
River
discharge
Main Drainage Channel
of D-9-1
Candi Major Road
River and D-9-2
Railway
Bajak Existing Overflow Weir
River
Kudung Existing Gated Weir
Mundu Natural Retarding
River Close gate
Basin
during
Pucanggading floods River Improvement
Drainage Improvement
Penggaron between Dombo-
River Kebon-
Sayung and Dolok
Batur Canal Barang Weir
Rivers
Figure 9.4.10 Alt-1 as Reference: Inflow Discharge of D-9-1 and D-9-2 to the Dombo-
Sayung River Downstream Reach
N
Penggaron River System:
Jawa Sea Strengthening of the Retarding
Basin by excavation.
Dombo-Sayung River Improvements of the BKT,
River Babon and Dombo-Sayung Rivers.
Dolok River System:
Existing River
Dolok Close the Inlet Gate of the Kebon
East Floodway River Batur Canal during floods
(BKT)
Babon
River
Inflow
runoff Legend:
discharge River
Figure 9.4.11 Alt-2 as Reference: Inflow Discharge of D-9-1 and D-9-2 to the Dombo-
Sayung River Downstream Reach
Jawa Sea
Dombo-Sayung
River
Dolok
East Floodway River
(KBT)
Babon
River
Candi Legend:
River River
KBT Major Road
Bajak
River Railway
Close gate
Kudung during
Existing Overflow Weir
Mundu floods Existing Gated Weir
River Natural Retarding
Pucanggading Basin
River Improvement
Penggaron
Kebon- Design Discharge of 50
River 380
Batur Canal Year Return Period
Barang Weir
(m3/s)
Jawa Sea
Dombo-Sayung
River
Dolok
East Floodway River
(KBT)
Babon Legend:
River River
Major Road
Railway
Existing Overflow Weir
KBT Existing Gated Weir
Candi
Natural Retarding
River
Basin
Bajak River Improvement
River Close gate
Kudung New Overflow Weir
during
Mundu New Control Weir
floods
River
Bypass Floodway
Pucanggading Bypass
Floodway Design Discharge of 50
380
Year Return Period
Penggaron (m3/s)
Kebon-
River
Batur Canal Barang Weir
Close the
new gate
during
floods
Jawa Sea
Dombo-Sayung
River
Dolok
East Floodway River
(KBT)
Babon
River
Candi Legend:
River River
KBT Major Road
Bajak
River Railway
Close gate
Kudung during
Existing Overflow Weir
Mundu floods Existing Gated Weir
River Natural Retarding
Pucanggading Basin
River Improvement
Penggaron Proposed Dolok Dam
River Kebon-
Batur Canal Design Discharge of 50
Barang Weir 200
Year Return Period
Proposed (m3/s) with Dolok Dam
Dolok Dam
Jawa Sea
Dombo-Sayung
River
Dolok
East Floodway River
(KBT)
Babon
River Legend:
River
Major Road
Railway
KBT Existing Overflow Weir
Candi Existing Gated Weir
River
Natural Retarding
Bajak Basin
River Close gate River Improvement
Kudung
during New Overflow Weir
Mundu floods
River New Control Weir
Pucanggading Bypass
Bypass Floodway
Floodway
Proposed Dam
Penggaron
Kebon-
River 200 Design Discharge of 50
Batur Canal Barang Weir Year Return Period
Close the (m3/s) with Dolok Dam
new gate Proposed
during Dolok Dam
floods
400
300
200
100
0
13:00
14:00
17:00
18:00
21:00
22:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
15:00
16:00
19:00
20:00
23:00
0:00
KBT
Babon
Candi Q
Dombo-sayung
Bajak Q QP:270m3/s
QP:140m3/s
Kedun Mundu Q QP:120m3/s
Penggaron Q
: Result of inundation
: Hydrodynamic model : Input Inflow data Analysis (MKE FLOOD)
(MKE11) Result of runoff analysis
500
Discharge (m3/s)
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Figure 9.5.4 Inflow Discharge to KBT
Candi River
25 300
Bajak River
20 Kedung Mundu 250
Water Level (m)
Discharge (m3/s)
15 200
10 150
5 100
0 50
-5 0
0
400
800
1,200
1,600
2,000
2,400
2,800
3,200
3,600
4,000
4,400
4,800
5,200
5,600
6,000
6,400
6,800
7,200
7,600
8,000
8,400
8,800
9,200
9,600
10,000
10,400
10,800
11,200
11,600
12,000
12,400
12,800
13,200
13,600
14,000
Distance from river mouth (m)
25 300
Water Level (m)
20 250
Discharge (m3/s)
15 200
10 150
5 100
0 50
-5 0
10,000
12,000
12,500
13,000
15,000
15,500
16,000
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,500
11,000
11,500
13,500
14,000
14,500
16,500
Distance from river mouth (m)
180
35
Water Level (m)
150
Discharge (m3/s)
25
120
90
15
60
5
30
-5 0
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
0
500
10,000
10,500
11,000
11,500
12,000
12,500
13,000
13,500
14,000
14,500
15,000
15,500
16,000
16,500
17,000
17,500
18,000
18,500
19,000
Strengthening Area 1 to 2m
A=0.55 km2 Excavated ground surface
Excavation Volume: about 2.7 million m3
550m
1.6 km
The excavation volume was estimated 2.7 million m 3 by using satellite elevation data.
The plan cross section was set that the low water channel depth was 1 to 2m.
1.15MCM
400
300
200
100
0
0:00
2:00
4:00
6:00
8:00
9:00
1:00
3:00
5:00
7:00
10:00
13:00
15:00
17:00
19:00
21:00
22:00
23:00
0:00
11:00
12:00
14:00
16:00
18:00
20:00
200
0
10:00
14:00
15:00
16:00
17:00
23:00
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
11:00
12:00
13:00
18:00
19:00
20:00
21:00
22:00
0:00
Drainage
KBT basin
Babon
Dombo-sayung
Candi Q
Bajak Q
QP:
18 220
Discharge (m3/s)
16 200
14 180
12 160
10 140
8 120
6 100
4 80
2 60
0 40
-2 20
-4 0
0
400
800
1,200
1,600
2,000
2,400
2,800
3,200
3,600
4,000
4,400
4,800
5,200
5,600
6,000
6,400
6,800
7,200
7,600
8,000
8,400
8,800
9,200
9,600
10,000
10,400
10,800
11,200
11,600
12,000
12,400
12,800
13,200
13,600
14,000
Distance from river mouth (m)
28 180
24 160
Water Level (m)
Discharge (m3/s)
20 140
16 120
12 100
8 80
4 60
0 40
-4 20
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
10,500
11,000
11,500
12,000
12,500
13,000
13,500
14,000
14,500
15,000
15,500
16,000
16,500
Distance from river mouth (m)
Discharge (m3/s)
20 75
3,950m
15 60
6,150m 11,350m 18,850m
10 45
5 30
0 15
-5 0
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
10,500
11,000
11,500
12,000
12,500
13,000
13,500
14,000
14,500
15,000
15,500
16,000
16,500
17,000
17,500
18,000
18,500
19,000
Figure 9.5.10 Calculated Longitudinal Profile of Water Level and Discharge (Alt-2)
Dombo-Sayung Alt-2
DOMBO 3950.00 DOMBO 6150.00
DOMBO 11350.00 DOMBO 18850.00
120
60
Time of peak is different due
40 to the strengthening retarding
area at upstream of Penggaron
20 River.
0
0:00:00
1:00:00
2:00:00
3:00:00
4:00:00
5:00:00
6:00:00
7:00:00
8:00:00
9:00:00
10:00:00
11:00:00
14:00:00
15:00:00
16:00:00
19:00:00
20:00:00
21:00:00
23:00:00
12:00:00
13:00:00
17:00:00
18:00:00
22:00:00
45 400
Road
Water Level (m)
35 320
Discharge (m3/s)
Rail way
25 240
Road
15 160
5 80
-5 0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
10,500
13,500
14,000
14,500
15,000
17,500
18,000
18,500
19,000
21,500
22,000
22,500
23,000
0
11,000
11,500
12,000
12,500
13,000
15,500
16,000
16,500
17,000
19,500
20,000
20,500
21,000
23,500
24,000
24,500
25,000
Distance from river mouth (m)
5,000m
12,000m
:Hydrodynamic
model (MIKE11)
24,700m
350
300
Discharge (m3/s)
250
200
150
100
50
0
0:00
2:00
4:00
7:00
9:00
0:00
1:00
3:00
5:00
6:00
8:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
350
45
Road 300
Water Level (m)
35
Discharge (m3/s)
Rail way 250
25 200
Road 150
15
100
5
50
Dolok Bypass Flood way
-5 0
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
11,000
11,500
12,000
12,500
13,000
13,500
14,000
14,500
15,000
15,500
20,500
21,000
21,500
22,000
22,500
23,000
23,500
24,000
10,000
10,500
16,000
16,500
17,000
17,500
18,000
18,500
19,000
19,500
20,000
24,500
25,000
Distance from river mouth (m)
5,000m
12,000m
16,500m
Bypass
:Hydrodynamic
model (MIKE11)
25,500m
350
300
Discharge (m3/s)
250
200
150
100
50
0
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
11:00
12:00
14:00
15:00
18:00
21:00
0:00
10:00
13:00
16:00
17:00
19:00
20:00
22:00
23:00
Source: Feasibility Study Dan Basic Design Bendungan Dolok Kapupaten Demak Provinsi Jawa
Tengah, November 2015
Figure 9.5.16 H-A-V Curve of Alternative-1
110
100
EL. (m)
90
80
70
60
0 5 10 15 20 25 30 35 40
Volume (MCM)
Figure 9.5.17 Revised H-V Curve
(2) Outflow
Outflow of Dolok dam is estimated by using the revised H-V curve.
Table 9.5.2 Outflow of Dolok Dam (50 year)
Hour 50 year Return Period Reservoir Water Reservoir
Inflow Outflow Surface Storage Volume
3 3 3
(hr) (m /s) (m /s) (RL. m) (m )
0.0 0.0 102.0 0
1.0 0.1 0.0 102.0 181
2.0 0.1 0.0 102.0 544
3.0 0.1 0.0 102.0 905
4.0 0.1 0.0 102.0 1,264
5.0 0.1 0.0 102.0 1,621
6.0 0.1 0.0 102.0 1,975
7.0 0.1 0.0 102.0 2,325
8.0 0.1 0.0 102.0 2,673
9.0 0.1 0.0 102.0 3,017
10.0 0.1 0.0 102.0 3,357
11.0 1.6 0.0 102.0 6,352
12.0 91.2 2.9 102.1 170,536
13.0 316.9 32.6 102.5 856,086
14.0 250.4 87.8 103.0 1,656,810
15.0 146.5 115.9 103.2 1,993,881
16.0 92.1 118.3 103.3 2,021,774
17.0 53.9 104.6 103.2 1,862,829
18.0 38.3 89.6 103.0 1,679,332
19.0 30.5 76.0 102.9 1,505,648
20.0 21.5 64.3 102.8 1,346,825
21.0 17.5 54.4 102.7 1,203,908
22.0 19.0 46.7 102.7 1,088,423
23.0 21.1 41.3 102.6 1,002,619
24.0 11.8 36.4 102.6 921,588
25.0 10.7 31.7 102.5 839,709
26.0 4.6 27.3 102.5 760,973
27.0 1.5 23.1 102.4 681,262
28.0 0.5 19.5 102.4 608,283
29.0 0.2 16.6 102.3 544,841
30.0 0.1 14.1 102.3 490,379
104 500
103
RESERVOIR WATER SURFACE ELEVATION (m) .
102 400
101
DISCHARGE (m3/s) .
100 300
99
98 200
97
96 100
95
94 0
0.0 3.0 6.0 9.0 12.0 15.0 18.0 21.0 24.0 27.0 30.0
(Hour)
Reservoir… INFLOW… OUTFLOW…
45 200
Road
Water Level (m)
35 160
Discharge (m3/s)
Rail way
25 120
Road
15 80
5 40
-5 0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
11,500
12,500
13,000
14,000
15,500
16,500
17,000
18,000
19,500
20,500
21,000
22,000
23,500
24,500
26,000
27,000
27,500
28,500
0
10,500
11,000
12,000
13,500
14,500
15,000
16,000
17,500
18,500
19,000
20,000
21,500
22,500
23,000
24,000
25,000
25,500
26,500
28,000
29,000
Distance from river mouth (m)
5,000m
12,000m
24,700m :Hydrodynamic
model (MIKE11)
Dolok Dam
250
Discharge (m3/s)
200
150
100
50
0
0:00
1:00
2:00
3:00
4:00
5:00
6:00
7:00
8:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
45 200
Road
Water Level (m)
35 160
Discharge (m3/s)
Rail way
25 120
Road
15 80
5 40
Dolok Bypass Flood way
-5 0
500
0
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
5,500
6,000
6,500
7,000
7,500
8,000
8,500
9,000
9,500
10,000
10,500
16,000
16,500
17,000
17,500
18,000
18,500
19,000
19,500
20,000
24,500
25,000
11,000
11,500
12,000
12,500
13,000
13,500
14,000
14,500
15,000
15,500
20,500
21,000
21,500
22,000
22,500
23,000
23,500
24,000
Distance from river mouth (m)
5,000m
12,000m
16,500m
Bypass
:Hydrodynamic
model (MIKE11)
Dolok Dam 25,500m
250
Discharge (m3/s)
200
150
100
50
0
2:00
3:00
5:00
6:00
7:00
9:00
10:00
11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
0:00
1:00
4:00
8:00
0:00
9.6 Design Profile and Design Cross Sections of the Alternative Flood
Control Plans
9.6.1 Concepts for Setting Design Bed Profile and Design Cross
Sections
In order to flow down safely the design discharge of floods and to maintain dynamic equilibrium condition of the
river bed profile, followings are the concepts for setting design bed profile and design cross sections.
River Improvements
Bypass Floodway of
the Dolok River
Tractive Force
25.00
Majapahit Bridge Kedung Mundu R.
Candi River
20.00
HL
Bajak River
15.00 B
Elevation (El.m)
5.00
0.00
(1) KBT_Alt-1 and Alt-2: Design Profile, Cross Sections and HWL
BKT: Water Level of 100-Year Flood under the Design Profile and Design Cross Sections
30.00
BKT Gate
Design Discharge (100-year Return Period): 320m3/s 265m3/s 140m3/s
25.00
Majapahit Bridge Kedung Mundu R.
Candi River
20.00
HL
Bajak River
15.00
B
Elevation (El.m)
5.00
0.00
(2) KBT_Alt-1 and Alt-2: Water Level of 100-Year Flood under the Design Profile and
Design Cross Sections (Example of Excessive Flood)
Figure 9.6.17 KBT_Alt-1 and Alt-2: Design Profile, Cross Sections and HWL
9.6.3 Babon River: Design Profile and Typical Design Cross Sections
Design profile including typical design cross sections of the Alt-1 and Alt-2 of the Babon River are shown in Figure
9.6 .18 and Figure 9.6 .19, respectively. These figures also show the HWL and design top of dikes or river walls (if
necessary).
The design bed profile is set almost same as the present lowest riverbed profile. The bank height of low water channel
is set about 4m, which is almost same as the existing bank height except downstream reach.
B
15.00
Elevation (El.m)
Babon Bridge
of Pantura Road
10.00
5.00
0.00
Note:
Left Bank Lowest Bed DG: Design Bed Gradient
Right Bank Present Bed Profile PG: Present Bed Gradient
Ground (Left) Ground (Right)
Design Bed Design Bank of Low Water Channel B: Design Bed Width
Design Top of Dike Design HWL HL: Design Height of Low Water Channel
Design HWL
Figure 9.6.18 Babon River_Alt-1: Design Profile, Cross Sections and HWL
B
15.00
Elevation (El.m)
Babon Bridge
of Pantura Road
10.00
5.00
0.00
Note:
Left Bank Lowest Bed DG: Design Bed Gradient
Right Bank Present Bed Profile PG: Present Bed Gradient
Ground (Left) Ground (Right)
Design Bed Design Bank of Low Water Channel B: Design Bed Width
Design Top of Dike Design HWL HL: Design Height of Low Water Channel
Design HWL
Figure 9.6.19 Babon River_Alt-2: Design Profile, Cross Sections and HWL
30.00
Sayung Bridge of
Majapahit Road
25.00
HL
20.00
Railway Bridge
B
Elevation (El.m)
5.00
0.00
Figure 9.6.20 Dombo-Sayung River_Alt-1: Design Profile, Cross Sections and HWL
30.00
Sayung Bridge of
Majapahit Road
25.00
HL
20.00 Railway Bridge
B
Elevation (El.m)
10.00
5.00
0.00
Figure 9.6.21 Dombo-Sayung River_Alt-2: Design Profile, Cross Sections and HWL
9.6.5 Dolok River: Design Profile and Typical Design Cross Sections
Design profile including typical design cross sections of the Alt-1 to Alt-4 of the Dolok River are shown in Figure
9.6 .22 to Figure 9.6 .25, respectively. These figures also show the HWL and design top of dikes or river (if
necessary).
In the case of without Dolok Dam (Alt-1 and Alt-2), the design discharge of the Dolok River or Dolok River plus
Bypass Floodway is 380m3/s. In the case of with Dolok Dam (Alt-3 and Alt-4), the design discharge of the Dolok
River or Dolok River plus Bypass Floodway is 200m3/s.
For 380m3/s and 200m3/s, considering the existing height of single cross sections in the upstream to mid-stream
reaches of about 4m or more, the bank height of the improved low water channel is set at 4m for the Dolok River.
Dikes or river walls with height of minimum 1m are proposed to be constructed (if necessary) to keep allowance
above the HWL.
For the Bypass Floodway, in order to minimize modification of drainage systems around the Bypass Floodway,
single cross sections including allowance height of 1m above the HWL are set for the design cross sections of the
Bypass Floodway.
As the detailed topographic map is not available along the Bypass Floodway, it is recommendable to conduct
topographic survey along the Bypass Floodway for increasing accuracy of analysis in the feasibility study on the Alt-
2 or Alt-4 of the Dolok River.
Dolok River_Alt-1 (Original River with Short-cuts): Longitudinal Profile, Cross Sections and HWL
55
40 Dolok Bridge of
Majapahit Road
35
HL
30
Railway Bridge
Elevation (El.m)
25 B
20
15 New Bridge of
Pantura Road
10
5 Stretch_5 Stretch_6
DG=1/385 DG=1/323
0 PG=1/385 PG=1/323
B=20m, HL=4m B=15m, HL=4m
-5 Stretch_1 Stretch_4
Stretch_2 Stretch_3
DG=1/5,000 DG=1/2,500 DG=1/1,000 DG=1/630
-10 PG=1/10,000 PG=1/2,500 PG=1/1,000 PG=1/714
B=150m, HL=4m B=50m, HL=4m B=30m, HL=4m B=25m, HL=4m
-15
0 5,000 10,000 15,000 20,000 25,000 30,000
Acc. Distance (m) Note:
Left Bank Lowest Bed DG: Design Bed Gradient
Right Bank Ground (Left) PG: Present Bed Gradient
Ground (Right) Bed Profile B: Design Bed Width
Design Bed Design Bank of Low Water Channel HL: Design Height of Low Water Channel
Design HWL Design Top of Dike
Figure 9.6.22 Dolok River_Alt-1: Design Profile, Cross Sections and HWL
20.00
5.00
0.00
-5.00
Stretch_1 Stretch_2 Stretch_3 Bypass_St.1 Bypass_St.2 Bypass_St.3
DG=1/5,000 DG=1/2,500 DG=1/1,000 DG=1/1,000 DG=1/450 DG=1/190
-10.00 PG=1/10,000 PG=1/2,500 PG=1/1,000
B=150m, HL=4m B=50m, HL=4m B=40m, HL=4m B=50m, HL=4mB=35m, HL=4m B=20m, HL=4m
-15.00
0 5,000 10,000 15,000 20,000 25,000 30,000
Acc. Distance (m) Note:
Lowest Bed Right Bank Ground (Left)
DG: Design Bed Gradient
Ground (Right) Present Bed Profile Design BedPG: Present Bed Gradient
Left Bank Bank of Low Water Channel Dike Top B: Design Bed Width
Design HWL Majaphit 系列39 HL: Design Height of Low Water Channel
Figure 9.6.23 Dolok River_Alt-2: Design Profile, Cross Sections and HWL
Dolok River_Alt-3 (Original River with Short-cuts): Longitudinal Profile, Cross Sections and HWL
55
40 Dolok Bridge of
Majapahit Road
35
HL
30
Railway Bridge
Elevation (El.m)
25 B
20
15 New Bridge of
Pantura Road
10
5 Stretch_5 Stretch_6
DG=1/385 DG=1/323
0 PG=1/385 PG=1/323
B=10m, HL=4m B=8m, HL=4m
-5 Stretch_1 Stretch_4
Stretch_2 Stretch_3
DG=1/5,000 DG=1/2,500 DG=1/1,000 DG=1/630
-10 PG=1/10,000 PG=1/2,500 PG=1/1,000 PG=1/714
B=85m, HL=4m B=30m, HL=4m B=17m, HL=4m B=12m, HL=4m
-15
0 5,000 10,000 15,000 20,000 25,000 30,000
Acc. Distance (m) Note:
Left Bank Lowest Bed DG: Design Bed Gradient
Right Bank Ground (Left) PG: Present Bed Gradient
Ground (Right) Bed Profile B: Design Bed Width
Design Bed Design Bank of Low Water Channel HL: Design Height of Low Water Channel
Design HWL Design Top of Dike
Figure 9.6.24 Dolok River_Alt-3: Design Profile, Cross Sections and HWL
20.00
5.00
0.00
-5.00
Stretch_1 Stretch_2 Stretch_3 Bypass_St.1 Bypass_St.2 Bypass_St.3
DG=1/5,000 DG=1/2,500 DG=1/1,000 DG=1/1,000 DG=1/450 DG=1/190
-10.00 PG=1/10,000 PG=1/2,500 PG=1/1,000
B=30m, HL=4m B=17m, HL=4m
B=85m, HL=4m B=30m, HL=4mB=20m, HL=4m B=11m, HL=4m
-15.00
0 5,000 10,000 15,000 20,000 25,000 30,000
Acc. Distance (m) Note:
Lowest Bed Right Bank Ground (Left)
DG: Design Bed Gradient
Ground (Right) Present Bed Profile Design BedPG: Present Bed Gradient
Left Bank Bank of Low Water Channel Dike Top B: Design Bed Width
Design HWL Majaphit 系列39 HL: Design Height of Low Water Channel
Figure 9.6.25 Dolok River_Alt-4: Design Profile, Cross Sections and HWL
Bypass Floodway of the Dolok River (Alt-2 and Alt-4): Control Weir and Overflow Weir
(1) Course, Length and Typical Cross Sections of the Bypass Floodway
Following figure shows course, length and typical cross sections of the Bypass Floodway.
Bypass Floodway:
Alt-2 (Q=380m3/s):
HL=4m
B=20 to 50m
B’=42m to72m
Area=61ha
Alt-4 (Q=200m3/s):
HL=4m
Dolok River B=11 to 30m
B’=33m to 52m
Area=53ha
Length = 8.72km
Bypass Floodway
Overflow Weir
B’
Control Weir
Table 9.6.3 Comparison of the Costs of the Options of the Control Weir for the
Bypass Floodway of the Dolok River
(Unit: Million Rp.)
Option of the Control
Alt-3 (Q=380m3/s) Alt-4 (Q=200m3/s)
Weir
1. Option-1
1) Overflow Weir 13,189 9,216
(L30m x H1.5m) (L16m x H1.5m)
2) Gated weir 9,171 9,171
2.5m
Overflow Weir:
Concrete Pile
1) Q380m3 /s: W30m x H1.5m
2) Q200m3 /s: W16m x H1.5m
C C Impermeable Wall
(Steel Sheet Pile)
Upstream Surface
Layout
Control Weir (Gated Weir)
30m 15m
Bed Protection
Note:
Concrete Pile Impermeable Wall Automatic operation of the Gated
(Steel Sheet Pile)
Weir based of telemetric monitoring
of water level at the site and
upstream together with manual
operation for emergency cases is
Longitudinal Profile recommended to be applied.
Overflow Weir
Dolok River
Revetment
Closing Dike (Reinforced Concrete)
1) L35m, W33m, H5m
2) Earthfill with Surface
Protection by Boulders
(Downstream Surface) and
Reinforced Concrete (Upstream River Outlet
Surface)) (Q=30m3 /s) Bypass Floodway
Surface Protection
(Concrete Block)
Concrete Facing (t=0.5m)
Bed Protection
Trash rack (Concrete Block)
Overflow Weir:
1) Q380m3 /s: W30m x H1.5m Note:
2) Q200m3 /s: W16m x H1.5m
Overflow Weir is same as the
Layout Option-1
Closing Dike with River Outlet River Outlet (Culvert)
1) L35m x W25m x H5m 1) W2.2m x H2.2m
Surface Protection 1) Earthfill and Surface Protection by 2) Q=30m3/s
(Concrete Block) Boulders
5m
2m
1m Concrete Pile
Impermeable Wall
(Steel Sheet Pile)
Downstream Surface
Table 9.7.4 Number of the River Crossing Structures and Related Structures
River KBT KBT KBT Babon Dombo- Dolok Total
Structure Downstre Mid to Total Sayung
am Upstream
(River (Majapahi
Mouth to t Bridge
Majapahit to Inlet
Bridge) Gate)
(No.) (No.) (No.) (No.) (No.) (No.) (No.)
1. Road Bridge 7 7 14 16 39 55 138
1-1 Medium to 5 5 10 4 9 5 38
Major Bridge
1-2 Pedestrian and 2 2 4 12 30 50 100
Small Bridge
2. Railway Bridge 1 0 1 1 1 3 7
3. Water Pipe Bridge 1 2 3 3 0 0 9
4. Telecom. Bridge 2 0 2 0 0 0 4
5. Gas Pipe 2 0 2 1 1 0 6
6. Sluice Gate (Weir) 0 1 1 1 0 3 6
7. Water Pump 3 0 3 1 0 0 7
8. Drainage Outlet/ 2 5 7 0 10 2 26
Shipon
Total 18 15 33 23 51 63 203
Data Source: Preliminary Inventory Survey of the Study
(1) KBT
Table 9.7 .5 shows the number of the river crossing structures along the KBT for reconstruction. In addition to
these there are some bridges etc., which need strengthening of foundation such as piers. List of the bridges to be
reconstructed are also shown in Table 9.7 .8.
Among the bridges in the downstream reach of the KBT, the following bridges, two
pedestrian bridges (see Figure 10.1.6 and Figure 10.1.7), one water pipe bridge and one
telecommunication cable bridge are proposed to be reconstructed by the river improvement
in the downstream reach.
In addition to the above, the following bridges have also problems such as insufficient
freeboard above the design high water level.
Data source: PU
Figure 9.7.30 Clogging in the Upstream Side of Kaligawe Bridge by Floating Debris
(after January 2016 Flood)
Railway Bridge (Upstream Side: Existing Length 70m):
Freeboard of the Railway Bridge (upstream side) is very small. It is understood that this
bridge will be heightened by the Perum Kereta Api (Railway Company), which is also to
be confirmed. It is necessary to design heightening of this Bridge based on the proposed
design cross section for the KBT.
Table 9.7.6 Babon River and Dombo-Sayung River: Number of River Crossing Structures
for Reconstruction
Alternative Alt-1 Alt-2
River Babon Dombo- Total Babon Dombo- Total
Structure Sayung Sayung
(No.) (No.) (No.) (No.) (No.) (No.)
1. Road Bridge 12 27 39 10 24 34
1-1 Medium to 1 2 3 0 1 1
Major Bridge
1-2 Pedestrian and 11 25 36 10 23 33
Small Bridge
2. Railway Bridge 0 0 0 0 0 0
3. Water Pipe Bridge 3 0 3 3 0 3
4. Telecom. Bridge 0 0 0 0 0 0
5. Gas Pipe 1 1 2 1 1 2
6. Sluice Gate (Weir) 1 0 1 1 0 1
7. Water Pump 0 0 0 0 0 0
8. Drainage Outlet/ 0 0 0 0 0 0
Shipon
Total 17 28 45 15 25 40
Alt-1: River improvements with the Natural Retarding Basin in the Penggaron River
Alt-2: River improvements with Strengthening of the Retarding Basin in the Penggaron River
To be Reconstructed with
BKT: Existing River Crossing Structures/ Bridges bridge length or
ID No. Name River Station Kind of Structure Material Length Width Depth Status Condition Road/Railway Related Structure/ Remarks Stretch Reinforce the Substructure
4 PDAM Bridge BKT 2+480 Water Pipe Bridge Steel Truss 66.0 - - Permanent str. Good Water Supply 2 68
5 Telecomunication Cable Bridge BKT 2+480 Telecommunication Steel Truss 66.0 - - Permanent str. Good Telecom Pier broken. 2 68
6 Pedestrian Bridge BKT 3+086 Pedestrian Bridge Steel 135.0 3.0 2.5 Temporaty str. Bad Small road Feeboard low 2 114
7 Pedestrian Bridge BKT 3+900 Pedestrian Bridge Steel 122.0 3.0 3.0 Temporaty str. Bad Small road Freeboard low 0 114
No reconst. (Reinforce
8 Citarum Bridge BKT 3+984 Road Bridge Concrete 268.0 17.0 4.5 Permanent str. Good Medium Road 2
substructure)
No reconst. (Reinforce
9 Kartini Bridge BKT 5+425 Road Bridge Concrete 213.0 9.0 7.8 Permanent str. Good Medium Road 2
substructure)
No reconst. (Reinforce
10 Telecomunication Cable Bridge BKT 5+450 Water Pipe Bridge Steel 135.0 - 4.5 Permanent str. Good Water Supply 2
substructure)
No reconstruct. Apply
11 Majapahit Bridge BKT 6+700 Road Bridge Concrete 71.5 15.0 6.0 Permanent str. Good Main Road 2
steeper revetment slope.
12 Lamper Sari Bridge BKT 7+600 Road Bridge Concrete 57.0 8.0 5.0 Permanent str. Good Medium Road 2 72
13 Guther Bridge for Ir igation BKT 8+300 Pedestrian Bridge Steel 44.0 2.0 4.0 Permanent str. Good Small road Drain outlet 3 No
Sendong Guo Bridge (Under-
14 BKT 9+100 Road Bridge Concrete 67.0 2.0 6.6 Permanent str. - - Under-construction 3 No
construction)
15 Sendong Guo Bridge BKT 9+100 Water Pipe Bridge Steel 33.0 - 6.2 Permanent str. Good Water Supply 3 45
16 Pedestrian Bridge BKT 10+214 Pedestrian Bridge Steel (Suspension) 35.0 1.5 7.0 Permanent str. Bad Small road 3 45
17 Gemah Permai Bridge BKT 10+500 Road Bridge Concrete 13.0 5.0 5.5 Permanent str. Good Medium Road Bridge slab is not good. 3 45
18 Ampo Sari Bridge BKT 10+700 Road Bridge Concrete 24.0 5.5 5.5 Permanent str. Good Medium Road Drain outlet 3 52
19 PDAM Steel Bridge BKT 11+300 Water Pipe Bridge Steel Cable Bridge 52.0 - 5.7 Permanent str. Good Water Supply 4 No
20 Pucang gading Bridge BKT 14+105 Road Bridge Concrete 56.0 10.0 10.0 Permanent str. Good Medium Road 5 No
21 Inlet Gate of BKT BKT 14+600 Gate Brick - - - Permanent str. Good Gate 5 No
Alt-1 Alt-2
To be Reconstructed To be Reconstructed
Babon River: Existing River Cros ing Structures/ Bridges with bridge length or with bridge length or
Alt-1 Alt-2
To be Reconstructed To be Reconstructed
Dombo-Sayung River: Existing River Crossing Structures/ Bridges with bridge length or with bridge length or
Alt-1 Alt-3
To be Reconstructed To be Reconstructed
Dolok River: Existing River Crossing Structures/ Bridges with bridge length or with bridge length or
3 Tugu 2 Bridge Dolok 4+140 Road Bridge Concrete 13.2 2.6 2.5 Permanent str. Good Small road 1 182 117
4 Tugu 1 Bridge Dolok 4+150 Road Bridge Concrete 11.6 3.5 2.5 Permanent str. Good Small road 1 182 117
5 Bridge Dolok Road Bridge Concrete 9.3 2.3 2.0 Permanent str. Good Small road 1 182 117
6 Bridge Dolok Road Bridge Concrete 11.8 2.1 1.9 Permanent str. Bad Small road 1 182 117
7 Bridge Dolok Pedestrian Bridge Concrete 9.8 1.3 1.4 Permanent str. Bad Small road 1 182 117
8 Bridge Dolok 5+250 Road Bridge Concrete 14.9 2.1 1.3 Permanent str. Good Small road 2 82 62
9 Bridge Dolok 5+460 Road Bridge Concrete 11.6 2.1 1.5 Permanent str. Good Small road 2 82 62
10 Karang Malang Bridge Dolok 5+570 Road Bridge Concrete 17.3 2.3 1.5 Permanent str. Good Small road 2 82 62
11 Jogo 4 Bridge Dolok 5+720 Road Bridge Concrete 13.8 3.0 1.6 Permanent str. Good Small road 2 82 62
12 Jogo 3 Bridge Dolok 5+790 Road Bridge Concrete 15.6 2.1 2.5 Permanent str. Good Small road 2 82 62
13 Jogo 2 Bridge Dolok 5+900 Road Bridge Concrete 16.0 2.1 1.4 Permanent str. Good Small road 2 82 62
14 Jogo 1 Bridge Dolok 6+300 Road Bridge Concrete 11.8 4.1 1.5 Permanent str. Good Small road 2 82 62
15 Bridge Dolok 6+500 Road Bridge Concrete 13.1 2.7 2.5 Permanent str. Good Small road 2 82 62
16 Onggorawe Bridge Dolok 6+650 Road Bridge Concrete 7.2 5.3 1.3 Permanent str. Good Medium road 2 sluice gates 2 82 62
17 Pantura(Onggorawe) Bridge Dolok 7+550 Road Bridge Concrete 12.1 20.0 3.5 Permanent str. Good Pantura Road 2 82 62
18 Sukasari Bridge Dolok 9+105 Road Bridge Concrete 10.5 3.6 3.5 Permanent str. Good Small road 2 82 62
19 Pilangsari 8 Bridge Dolok 9+270 Road Bridge Concrete 9.3 3.2 4.0 Permanent str. Good Small road 2 82 62
20 Pilangsari 7 Bridge Dolok 9+400 Road Bridge Concrete 9.0 3.9 3.0 Permanent str. Good Small road 3 62 49
21 Pilangsari 6 Bridge Dolok 9+480 Road Bridge Concrete 14.6 3.0 3.5 Permanent str. Good Small road 3 62 49
22 Pilangsari 5 Bridge Dolok 9+580 Road Bridge Concrete 8.2 3.4 4.0 Permanent str. Good Small road 3 62 49
23 Pilangsari 4 Bridge Dolok 9+620 Road Bridge Concrete 9.1 3.8 3.0 Permanent str. Good Small road 3 62 49
24 Pilangsari 3 Bridge Dolok 9+692 Road Bridge Concrete 8.4 3.2 3.1 Permanent str. Good Small road 3 62 49
25 Pilangsari 2 Bridge Dolok 10+390 Road Bridge Concrete 11.1 3.7 2.4 Permanent str. Good Small road 3 62 49
26 Pilangsari Bridge Dolok 10+680 Road Bridge Concrete 9.4 3.5 3.0 Permanent str. Good Small road 3 62 49
27 Blerong 4 Bridge Dolok 11+990 Pedestrian Bridge Concre Pier & Wood Slub 15.0 1.3 3.0 Semi Permanent str. Dangerous Small road Drop structure 3 62 49
28 Blerong 3 Bridge Dolok 12+700 Pedestrian Bridge Concrete 18.0 1.5 3.5 Permanent str. Good Small road 3 62 49
29 Blerong 2 Bridge Dolok 12+820 Pedestrian Bridge Concrete 17.0 1.2 4.0 Permanent str. Bad Small road 3 62 49
30 Blerong Bridge Dolok 14+880 Road Bridge Concrete 26.2 4.8 4.7 Permanent str. Good Small road 4 57 44
31 Dolok Bridge Dolok 15+620 Road Bridge Concrete 27.3 4.5 6.0 Permanent str. Good Small road 4 57 44
32 Bridge Dolok 15+950 Pedestrian Bridge Concrete 17.3 1.2 4.5 Permanent str. Good Small road 4 57 44
33 Ngumpul Bridge Dolok 16+120 Pedestrian Bridge Concrete 18.6 2.0 4.7 Permanent str. Good Small road 4 57 44
34 Bridge Dolok 16+500 Pedestrian Bridge Concrete 12.2 1.5 4.6 Permanent str. Good Small road 4 57 44
35 Jetis Bridge Dolok 16+920 Pedestrian Bridge Concrete 11.2 0.9 3.2 Permanent str. Good Small road 4 57 44
36 Tamansari 2 Bridge Dolok 17+100 Pedestrian Bridge Concrete 19.0 2.0 5.0 Permanent str. Good Small road 4 57 44
37 Tamansari Bridge Dolok 18+160 Pedestrian Bridge Concrete 12.0 2.0 5.0 Permanent str. Good Small road 4 57 44
38 Kembangan 3 Dolok 18+420 Pedestrian Bridge Concrete 12.0 2.0 5.0 Permanent str. Good Small road 4 57 44
39 Kembangan 2 Bridge Dolok 18+560 Pedestrian Bridge Concrete 18.0 1.8 5.0 Permanent str. Good Small road 4 57 44
40 Kembangan 1 Bridge Dolok 19+000 Pedestrian Bridge Concrete 15.0 1.5 4.0 Permanent str. Good Small road 5 52 42
41 Semarang-Purwodadi Bridge Dolok 19+080 Road Bridge Concrete 21.0 11.0 4.0 Permanent str. Good Main road 5 52 42
42 Railway Bridge (down line) Dolok 19+080 Railway Bridge Steel 16.0 6.5 5.0 Permanent str. Good Railway 5 52 42
43 Railway Bridge (up line) Dolok 19+080 Railway Bridge Steel 14.0 4.0 5.0 Permanent str. Good Railway 5 52 42
44 Growong 2 Bridge Dolok 19+480 Road Bridge Concrete 15.0 2.8 4.0 Permanent str. Good Small road 5 52 42
45 Railway Bridge Dolok 19+500 Railway Bridge Steel 11.7 2.0 4.0 Permanent str. Good Railway 5 52 42
46 Growong Bridge Dolok 20+050 Road Bridge Concrete 17.0 3.5 4.5 Permanent str. Good Small road 5 52 42
47 Senggrong 2 Bridge Dolok 20+760 Road Bridge Concrete 12.0 2.8 5.0 Permanent str. Good Small road 5 52 42
48 New Bridge Dolok 22+010 Road Bridge Concrete 12.0 3.4 5.0 Under construction - Small road 5 52 42
49 Senggrong Bridge Dolok 22+960 Pedestrian Bridge Concrete pier and wood slub 27.2 2.0 7.0 Permanent str. Bad Small road 5 52 42
50 Krajan Bridge Dolok 23+640 Road Bridge Concrete 26.0 3.0 7.0 Permanent str. Good Small road 6 47 40
No reconstruct.
51 Dolok Bridge Dolok 24+220 Road Bridge Concrete 26.3 7.5 8.0 Permanent str. Good Medium road 6 47 Apply steeper
revetment slope.
52 Bridge Dolok 25+850 Pedestrian Bridge Concrete pier and wood slub 18.6 1.8 6.5 Permanent str. Good Small road 6 47 40
53 Kangkung Krajan Bridge Dolok 26+700 Road Bridge Concrete 21.0 2.5 7.0 Permanent str. Good Small road 6 47 40
54 Batur 2 Bridge Dolok 27+200 Pedestrian Bridge Concrete 25.0 1.0 7.0 Permanent str. Bad Small road 6 47 40
55 Batur Bridge Dolok 27+780 Road Bridge Concrete pier and wood slub 23.0 3.0 6.0 Permanent str. Good Small road 6 47 40
56 Dempel Bridge Dolok 28+620 Road Bridge Concrete 24.5 3.2 7.0 Permanent str. Good Small road 6 47 40
57 Dempel Bridge Dolok 30+400 Pedestrian Bridge Concrete 18.0 2.0 4.0 Permanent str. Good Small road 6 47 40
No reconstruct. No reconstruct.
58 Banyumeneng Bridge Dolok 30+580 Road Bridge Concrete 36.0 4.0 7.0 Permanent str. Good Medium road 6 Apply steeper Apply steeper
revetment slope. revetment slope.
Table 9.7.12 Dolok River with Bypass Floodway: Bridges for Reconstruction and New
Construction
Alt-2 Alt-4
To be Reconstructed To be Reconstructed
Dolok River: Existing River Crossing Structures/ Bridges with bridge length or with bridge length or
Number of the houses to be relocated by the proposed river improvements of the KBT, Babon, Dombo-Sayung and
Dolok Rivers is estimated as described below.
Table 9.8.14 KBT Mid-stream to Upstream Reach: Rough Estimation of the Number of
Houses to be relocated
Table 9.8.16 Dombo-Sayung River: Rough Estimation of Number of Houses for Relocation
Alt-1 Alt-2
Kecamantan/ District Kelurahan
(No.) (No.)
Mranggen 1. Batursari 2 2
Mranggen 2. Plamongansari 2 1
Mranggen 3. Bandungrejo 12 5
Pedurungan 4. Penggaron Kidul 7 0
Mranggen 5. Menur 2 0
Mranggen 6. Waru 0 0
Mranggen 7. Wringinjajar 0 0
Sayung 8. Dombo 101 51
Sayung 9. Karangasem 16 10
Sayung 10. Prampelan 0 0
Sayung 11. Loireng 0 0
Sayung 12. Kalisari 0 0
Sayung 13. Sayung 182 57
Sayung 14. Purwosari 331 83
Sayung 15. Bedono 141 36
Total 796 245
Notes;
1) Number of houses to be relocated is counted by the Consultant Team based on the Google Earth.
2) Alt-1: River Improvement with the Natural Retarding Basin in the Penggaron River.
3) Alt-2: River Improvement with the Strengthening of the Retarding Basin in the Penggaron River.
Table 9.8.17 Babon and Dombo-Sayung River: Rough Eatimation of Number of Houses
for Relocation
Alt-1 Alt-2
River
(No.) (No.)
Babon 76 58
Dombo-Sayung 796 245
Total 872 303
Notes;
1) Number of houses to be relocated is counted by the Consultant Team based on the Google Earth.
2) Alt-1: River Improvement with the Natural Retarding Basin in the Penggaron River.
3) Alt-2: River Improvement with the Strengthening of the Retarding Basin in the Penggaron River.
Table 9.8.18 Dolok River (Alt-1 and Alt-3): Rough Estimation of Number of Houses for
Relocation
Alt-1 Alt-3
Kecamantan/ District Kelurahan
(No.) (No.)
Sayung 1. Tugu 43 29
Sayung 2. Surodadi 0 0
Sayung 3. Timbulsloko 0 0
Sayung 4. Gemulak 116 85
Sayung 5. Loireng 58 42
Sayung 6. Prampelan 0 0
Sayung 7. Tambakroto 79 64
Sayung 8. Pilangsari 59 39
Mranggen 9. Blorong 31 27
Mranggen 10. Tegalarum 2 1
Mranggen 11. Tamansari 6 6
Mranggen 12. Kembangarum 89 67
Mranggen 13. Kangkung 36 22
Mranggen 14. Kebonbatur 60 46
Mranggen 15. Banyumeneng 10 6
Mranggen 16. Rowosari 13 8
Total 602 442
Notes;
1) Number of houses to be relocated is counted by the Consultant Team based on the Google Earth.
2) Alt-1: River Improvement of the Dolok River without Dolok Dam.
3) Alt-2: River Improvement of the Dolok River with Dolok Dam.
Table 9.8.19 Dolok River with Bypass Floodway(Alt-2 and Alt-4): Rough Estimation of
Number of Houses for Relocation
Alt-2 Alt-4
Kecamantan/ District Kelurahan
(No.) (No.)
Dolok River:
Sayung 1. Tugu 43 29
Sayung 2. Surodadi 0 0
Sayung 3. Timbulsloko 0 0
Sayung 4. Gemulak 116 85
Sayung 5. Loireng 58 42
Sayung 6. Prampelan 0 0
Sayung 7. Tambakroto 79 64
Sayung 8. Pilangsari 59 39
Mranggen 9. Blorong 31 27
Mranggen 10. Tegalarum 2 1
Mranggen 11. Tamansari 1 6
Sub-total 389 293
Bypass Floodway:
Mranggen Karangsono 0 0
Mranggen Kembangarum 58 58
Mranggen Kalitengah 0 0
Mranggen Kangkung 0 0
Mranggen Sumberejo 0 0
Mranggen Kebonbatur 0 0
Mranggen Banyumeneng 30 3
Sub-total 88 61
Total 477 354
Notes;
1) Number of houses to be relocated is counted by the Consultant Team based on the Google Earth.
2) Alt-2: River Improvement of the Dolok River with Bypass Floodway and without Dolok Dam.
3) Alt-4: River Improvement of the Dolok River with Bypass Floodway and with Dolok Dam.
Table 9.9.20 Estimated Land Acquisition of Mid-stream to Upstream Reaches of the KBT
Land Acuisition
Kecamantan/ District Kelurahan
(m2)
Semarang Selatan 1. Petrongan 4,965
Gayamsari 2. Pandean Lamper 8,501
Gayamsari 3. Gayamsari 7,903
Semarang Selatan 4. Lamper Lor 4,340
Semarang Selatan 5. Lamper Tengah 7,884
Tembalang 6. Sendangguwo 28,270
Tembalang 7. Kedungmundu 27,020
Pedurungan 8. Gemah 5,915
Pedurungan 9. Pendurungan Kidul 30,940
Tembalang 10. Sendangmulyo 5,688
Total 131,426
Note:
1) Land acquisition area was estimated by the Consultant Team based on Google Earth.
2) Above land acquisition area is the minimum required area for the proposed river improvement.
Table 9.9.23 Babon and Dombo-Sayung Rivers: Estimated Land Acquisition Area
Alt-1 Alt-2
River
(m2) (m2)
Babon 600,750 517,610
Dombo-Sayung 968,916 828,420
Retarding Basin in the - 550,000
Penggaron River
Total 1,569,666 1,896,030
Notes;
1) Land acquisition area was estimated by the Consultant Team based on the Google Earth.
2) Land acquisition area is the minimum required area for the above alternatives.
2) Alt-1: River Improvement with the Natural Retarding Basin in the Penggaron River.
3) Alt-2: River Improvement with the Strengthening of the Retarding Basin in the Penggaron River.
Table 9.9.24 River Improvement of the Dolok River_Alt-1 and Alt-3: Estimated Land
Acquisition Area
Alt-1 Alt-3
Kecamantan/ District Kelurahan
(m2) (m2)
Sayung 1. Tugu 375,100 243,500
Sayung 2. Surodadi 179,300 125,900
Sayung 3. Timbulsloko 202,900 105,800
Sayung 4. Gemulak 195,700 129,900
Sayung 5. Loireng 89,690 67,380
Sayung 6. Prampelan 13,800 10,400
Sayung 7. Tambakroto 177,700 126,000
Sayung 8. Pilangsari 94,290 75,580
Mranggen 9. Blorong 175,800 142,000
Mranggen 10. Tegalarum 150,800 115,900
Mranggen 11. Tamansari 107,000 83,220
Mranggen 12. Kembangarum 189,800 148,600
Mranggen 13. Kangkung 100,700 86,970
Mranggen 14. Kebonbatur 209,100 178,300
Mranggen 15. Banyumeneng 190,300 146,600
Mranggen 16. Rowosari 74,030 59,050
Total 2,526,010 1,845,100
Notes;
1) Land acquisition area was estimated by the Consultant Team based on the Google Earth.
2) Land acquisition area is the minimum required area for the above alternatives.
3) Alt-1: River Improvement of the Dolok River without Dolok Dam.
4) Alt-3: River Improvement of the Dolok River with Dolok Dam.
Table 9.9.25 River Improvement of the Dolok River with Bypass Floodway: Estimated
Land Acquisition Area
Alt-2 Alt-4
Kecamantan/ District Kelurahan
(m2) (m2)
Dolok River:
Sayung 1. Tugu 375,100 243,500
Sayung 2. Surodadi 179,300 125,900
Sayung 3. Timbulsloko 202,900 105,800
Sayung 4. Gemulak 195,700 129,900
Sayung 5. Loireng 89,690 67,380
Sayung 6. Prampelan 13,800 10,400
Sayung 7. Tambakroto 177,700 126,000
Sayung 8. Pilangsari 94,290 75,570
Mranggen 9. Blorong 175,800 142,000
Mranggen 10. Tegalarum 150,800 115,900
Mranggen 11. Tamansari 87,170 69,150
Sub-total 1,742,250 1,211,500
Bypass Floodway:
Mranggen Karangsono 75,730 64,790
Mranggen Kembangarum 123,800 124,600
Mranggen Kalitengah 40,230 45,290
Mranggen Kangkung 101,000 77,270
Mranggen Sumberejo 75,720 72,750
Mranggen Kebonbatur 62,560 60,420
Mranggen Banyumeneng 127,800 83,930
Sub-total 606,840 529,050
Total 2,349,090 1,740,550
Notes;
1) Land acquisition area was estimated by the Consultant Team based on the Google Earth.
2) Land acquisition area is the minimum required area for the above alternatives.
3) Alt-2: River Improvement of the Dolok River with Bypass Floodway and without Dolok Dam.
4) Alt-4: River Improvement of the Dolok River with Bypass Floodway and with Dolok Dam.
Tenggang R.
(D-7-1)
D-9-3
Siringin R.
(D-7-2)
D-8-1
D-8-3
D-8-1
D-9-1
D-8-4
Note:
D-9-1 D-X-Y is the drainage basin
name set in this Study.
Figure 9.11.33 Major Drainage Systems between the KBT and Dolok River
Tenggang River and the Siringin River with their secondary and tertiary drainage channels form the major drainage
systems between right bank of the KBT and left bank of the Babon River (drainage basins: D-7-1 and D-7-2
respectively). These two (2) Drainage systems discharge rainfall runoff directly into the sea through the Tenggan
River and the Siringin River. It can be observed that there is serious problem of reducing discharge capacities of the
drainage channels by deposition of debris including garbage (example: the Tenggang River shown in Figure 9.11.2).
It seems that more than 70% of the cross section of the Tenggang River at the Railway Bridge is filled-up with debris
including garbage.
There are four (4) major drainage systems (drainage basis: D-8-1 to D-8-4) between right bank of the Babon River
and left bank of the Dombo-Sayung River. These drainage channels join with the mid-stream to downstream reaches
of the Dombo-Sayung River.
There are three (3) major drainage systems between right bank of the Dombo-Sayung River and left bank of the
Dolok River (drainage basins: D-9-1 to D-9-3). The drainage system of D-9-1 originates from the irrigation canal,
which starts from the irrigation intake at right side of Gergaji Weir of the Dombo-Sayung River at Pucanggading. The
drainage system of D-9-2 seems to be joined with the Dolok River before the construction of the existing dike on the
left bank of the Dolok River. Then, probably the flow direction of the drainage channel of D-9-2 was artificially
changed to west and joined with the drainage channel of D-9-1. Currently, the runoff discharge from the D-9-1 and
D-9-2 jointly flows through the drainage channel, and flows into the right bank side of Dombo-Sayung River (see
Figure 9.11 .36).
Figure 9.11.34 Tenggang River (Drainage Basin: D-7-1) at the Railway Crossing Point
Dombo-Sayung River
(a) Joint Drainage Channel of the (b) Sluice (Flap) Gate at the Inflow
Drainage Channels of D-9-1 and Point of the Joint Drainage
D-9-2 (to West Direction to the Channel of D-9-1 and D-9-2 to the
Dombo-Sayung River) Dombo-Sayung River
Figure 9.11.35 Joint Drainage Channel of the Drainage Basins of D-9-1 and D-9-2 at the
Right Bank Side of the Dombo-Sayung River
Dolok R.
Dombo-Sayng R.
Babon R.
KBT
Mecanism/ Category of Inland
Flooding
Category-1:
Inland flood areas by drainage
problem due to insufficient
discharge capacity of drainage
systems
Category-2:
Inland flood areas by drainage
problem due to high tide
together with insufficient
discharge capacity of drainage
systems
Category-3:
Flood areas by the Rivers
together with insufficient
capacity of drainage systems
Discharge capacity of the existing drainage channels, especially in the urban areas, are very much
reduced by the deposition of debris including garbage. Therefore, firstly, it is necessary to clean up the
existing drainage channels to recover their original discharge capacity. This will contribute for
mitigating the condition of inland floods very much.
(2) To improve the Drainage Channels
Inland floods are generally caused by insufficient discharge capacity of the drainage systems including
drainage channels against storm runoff. Therefore, it is necessary to improve drainage channels, so that
the drainage channels will have sufficient discharge capacity for flowing down design storm runoff.
This is also proposed by the JICA Master Plan and Feasibility Study in 1993 for the Tenggang River
and the Siringin River with their drainage channels (JICA study: “The Master Plan on Water Resources
Development and Feasibility Study for Urgent Flood Control and Urban Drainage in Semarang City
and Suburbs”, 1993).
This method can be generally applied for the southern areas from Pantura Road. However, among these
areas, there are also low-lying lands where high tide affects condition of inland floods. For these areas,
it is necessary to conduct step-wise land raising as well as land use management for not permitting new
building houses on the low-lying lands, or in case of approving development of land, it is necessary to
raise lands with enough height against floods.
In addition, it is recommended to keep ponds or wet land or paddy fields as much as possible for
keeping retention capacity in these areas, which will make smaller the necessary size of the drainage
channels.
(3) To treat separately the drainage channels between the Dombo-Sayung River and the Dolok River
In the present conditions, the drainage channels between right bank of the Dombo-Sayung River and the
left bank of the Dolok River (the drainage basins of D-9-1 and D-9-2) are jointly flow into the right
bank of the Dombo-Sayung River by changing their flow direction from north to west. The inflow
discharge from these drainage basins is heavy burden to the Dombo-Sayung River, which makes worse
the condition of flooding including overflow from the Dombo-Sayung River. Considering the
topography in-between the Dombo-Sayung River and the Dolok River, instead of flowing runoff of the
drainage basins into the Dombo-Sayung River, it is natural and also proposed to drain the runoff from
the above two drainage basins directly to the sea together with the runoff from the drainage basin of D-
9-3.
(4) To conduct land raising of the areas, where high tide affect inland flooding, together with improvement
of the drainage channels
Currently, in the land where inland floods are occurred by high tide together with insufficient discharge
capacity of drainage channels, small scale pump drainage or raising land of houses or installing small
low height blocking for stopping inflow water into houses can be seen. Considering sustainability of
solving the problem of inland floods in these areas, instead of providing large or medium scale of pump
drainage systems by surrounding the areas by polder dikes, it is better to conduct area by area step-wise
raising of the lands, which will make possible gravity drainage from these areas. People will be
temporary relocated during the construction of raising land and can return to the original areas after
completion of land raising one by one.
In addition, together with the land raising, improvement of the drainage channels is also to be
conducted.
Furthermore, in terms of new request for approving land development in these areas, it is necessary to
manage land use so that the requested land for development will be raised with sufficient height against
floods.
Normally, drainage improvement is planned with design scale of 5 to 10-year return period of storm rainfall. Suppose
that the design scale of the drainage improvement is set at 10-year return period, design peak discharges for the
improvement of the drainage channels are shown in Figure 9.11 .39 (refer to Figure 6.2.3 to 6.2.5) as an example.
It is recommended to conduct further study for drainage improvement based on the above conceptual drainage
improvement plan.
Improvement of
KBT
the Drainage Legend:
Channels River
Babon (including
Candi Main Drainage Channel
River dredging,
River
excavation and Major Road
Bajak enlargement) is
River Railway
necessary to be
Kudung Close gate Existing Overflow Weir
during conducted.
Mundu
floods Existing Gated Weir
River
Natural Retarding
Pucanggading
Basin
Penggaron River Improvement (As
River Kebon- a supposition)
Batur Canal Barang Weir Drainage Improvement
内容
Chapter 9. flood control plans 9–1
9.1 Basic Concepts for Formulating Flood Control Plans 9–1
9.2 Conditions of Setting Design Discharge 9–1
9.3 Alternatives of Flood Control Plans 9–2
9.3.1 Alternatives of the Penggaron River System 9–2
9.3.2 Alternatives of the Dolok River System (Dolok River) 9–4
9.4 Design Discharge of the Alternatives 9–7
9.4.1 Design Discharge of the Alternatives of Penggaron River System 9–7
9.4.2 Design Discharge of the Alternatives of the Dolok River 9–7
9.5 Hydrological and Hydraulic Study on the Alternative Flood Control Plans 9–7
9.5.1 Penggaron RS_Alternative-1 9–7
9.5.2 Penggaron RS_Alternative-2 9–7
9.5.3 Dolok RS_Alternative-1 9–7
9.5.4 Dolok RS_Alternative-2 9–7
9.5.5 Set of Dolok Dam Outflow 9–7
9.5.6 Dolok RS_Alternative-3 (With Dolok Dam) 9–7
9.5.7 Dolok RS_Alternative-4 (With Dolok Dam) 9–7
9.6 Design Profile and Design Cross Sections of the Alternative Flood Control Plans9–7
9.6.1 Concepts for Setting Design Bed Profile and Design Cross Sections 9–7
9.6.2 KBT: Design Profile and Typical Design Cross Sections 9–7
9.6.3 Babon River: Design Profile and Typical Design Cross Sections 9–7
9.6.4 Dombo-Sayung River: Design Profile and Typical Design Cross Sections 9–7
9.6.5 Dolok River: Design Profile and Typical Design Cross Sections 9–7
9.7 Reconstruction of Bridges (etc.) 9–7
9.7.1 Existing River Crossing Structures 9–7
9.7.2 River Crossing Structures for Reconstruction 9–7
9.8 Relocation of Houses 9–7
9.8.1 KBT: Relocation of Houses 9–7
9.8.2 Babon River and the Dombo-Sayung River: Relocation of Houses 9–7
9.8.3 Dolok River: Relocation of Houses 9–7
9.9 Land Acquisition 9–7
9.9.1 KBT: Land Acquisition 9–7
9.9.2 Babon River and the Dombo-Sayung River: Land Acquisition 9–7
9.9.3 Dolok River: Land Acquisition 9–7
9.10 Consideration of Climate Change and Land Subsidence 9–7
9.11 Conceptual Plan of Drainage Improvement 9–7
9.11.1 Drainage Systems and Drainage Problems 9–7
9.11.2 Condition and Mechanism of Inland Floods 9–7
9.11.3 Conceptual Plan of Drainage Improvement 9–7