Production Monitoring Week - 4

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

Productivity Monitoring

Activity: Steel (Ton)


Location Box unit 1 and 2 - Foundation
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader 1 1 1 1
Skilled 5 5 4 5
Unskilled 0 0 0 0
Hired Skilled 21 23 8 17
Hired Unskilled 0 0 0 0
107,427.08

Crane (including Diesel) 0.75 0.75 0.75 0.75


High up 0 0 0 0
Generator 100KV 0.75 0.75 0.75 0.75
Compressor 0.75 0.75 0.75 0.75
Month Feb-19
Week no. 4

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
1 1 0 6 1,668.00
5 5 0 29 3,103.00
0 0 0 0 - 305
17 17 0 103 13,905.00
0 0 0 0 -

0.75 0.75 0 4.5 6,750.00


0 0 0 0 -
0.75 0.75 0 4.5 1,384.62
0.75 0.75 0 4.5 1,384.62

Current 28,195.23 305.00


Previous 107,427.08
Total 135,622.31
Rate Steel (Ton) 444.66
Unit

Steel (Ton)
Productivity Monitoring

Activity: Formwork (m2)


Location Box Foundation (1 and 2)
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader 1 1 1 0
Skilled 2 2 1 0
Unskilled 21,938.00 0 0 0 0
Hired Skilled 9 7 7 0
Hired Unskilled 0 0 0 0
Month Feb-19
Week no. 4

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
0 1 0 4 1,112.00
0 1 0 6 642.00
0 0 0 0 - 330
0 4 0 27 3,645.00
0 0 0 0 -

Current 5,399.00 330.00


Previous 21,938.00
Total 27,337.00

Rate Formwork (m2) 82.84


Unit

Formwork
(m2)
Productivity Monitoring

Activity: Concrete (m3)


Location Box Foundation 1 and 2
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader 0 0 0 0
Skilled 0 0 0 0
Unskilled 8,735.00 0 0 0 0
Hired Skilled 0 5 6 12
Hired Unskilled 0 0 0 0
Month Feb-19
Week no. 4

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
0 1 0 1 278.00
0 2 0 2 214.00
0 0 0 0 - 1210
12 7 0 42 5,670.00
0 0 0 0 -

Current 6,162.00 1,210.00


Previous 8,735.00
Total 14,897.00

Rate Concrete (m3) 12.31


Unit

Concrete (m3)
Productivity Monitoring

Activity: Steel (Ton)


Location Box unit 1 and 2
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader 0 0 1 0
Skilled 0 0 1 0
Unskilled 0 0 0 0
Hired Skilled 0 0 4 4
Hired Unskilled 0 0 0 0
-

Crane (including Diesel) 0.25 0.25 0.25 0.25


High up 0 0 0 0
Generator 100KV 0.25 0.25 0.25 0.25
Compressor 0.25 0.25 0.25 0.25
Month Feb-19
Week no. 4

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
0 0 0 1 278.00
0 0 0 1 107.00
0 0 0 0 - 50
4 4 0 16 2,160.00
0 0 0 0 -

0.25 0.25 0 1.5 2,250.00


0 0 0 0 -
0.25 0.25 0 1.5 461.54
0.25 0.25 0 1.5 461.54

Current 5,718.08 50.00


Previous -
Total 5,718.08
Rate Steel (Ton) 114.36
Unit

Steel (Ton)
Productivity Monitoring

Activity: Formwork (m2)


Location Box Foundation 1
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader 0 0 1 1
Skilled 0 0 1 2
Unskilled - 0 0 0 0
Hired Skilled 0 0 3 6
Hired Unskilled 0 0 0 0
Month Feb-19
Week no. 3

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
1 1 0 4 1,112.00
2 1 0 6 642.00
0 0 0 0 - 120
6 3 0 18 2,430.00
0 0 0 0 -

Current 4,184.00 120.00


Previous -
Total 4,184.00

Rate Formwork (m2) 34.87


Unit

Formwork
(m2)
Productivity Monitoring

Activity: Concrete (m3)


Location Box Foundation 1
No. Of

Trade Previous Week Cost Saturday Sunday Monday Tuesday

(To be Filled By Site team on Daily Basis)


Gang Leader
Skilled
Unskilled -
Hired Skilled
Hired Unskilled
Month Feb-19
Week no. 3

No. Of
Estimated Weekly Cost
Cumulative Location
Wednesday Thursday Friday Total (including Allowance, visas, 2
production
Hours Overtime…)

To be filled by Site
y Site team on Daily Basis) Team
0 -
0 -
0 - 0
0 -
0 -

Current - -
Previous -
Total -

Rate Concrete (m3) #DIV/0!


Unit

Concrete (m3)

You might also like