Professional Documents
Culture Documents
Appendix H - Geotechnical and Pavement Report
Appendix H - Geotechnical and Pavement Report
Appendix H
Geotechnical and Pavement Report
PRELIMINARY GEOTECHNICAL INVESTIGATION
CLASS ENVIRONMENTAL ASSESSMENT STUDY
ELGIN MILLS ROAD (Y.R. 49)
BATHURST STREET (Y.R. 38) TO YONGE STREET (Y.R. 1)
TOWN OF RICHMOND HILL, YORK REGION
.
103, 2010 Winston Park Drive, Oakville, ON L6H 5R7 T: 905 829 8666 F: 905 829 1166
thurber.ca
TABLE OF CONTENTS
SECTION PAGE
1.0 INTRODUCTION ............................................................................................................ 1
2.0 PROJECT AND SITE DESCRIPTION ............................................................................ 1
2.1 Background ................................................................................................................ 1
2.2 Physiography .............................................................................................................. 1
2.3 Existing Conditions ..................................................................................................... 2
3.0 INVESTIGATION METHODOLOGY ............................................................................... 2
4.0 FIELD INVESTIGATION ................................................................................................. 4
4.1 Existing Pavement Condition ...................................................................................... 4
4.2 Existing Pavement Structure....................................................................................... 4
4.3 Subgrade Soil ............................................................................................................. 5
4.4 Groundwater Levels.................................................................................................... 6
4.5 Chemical Analysis ...................................................................................................... 7
5.0 PAVEMENT EVALUATION AND DESIGN ..................................................................... 7
5.1 Traffic Analysis ........................................................................................................... 8
5.2 ESALs Calculations .................................................................................................... 8
5.3 AASHTO Pavement Design ........................................................................................ 8
5.4 New Flexible Pavement Design .................................................................................. 9
5.5 Pavement Rehabilitation Analysis ..............................................................................10
5.6 Pavement Rehabilitation Alternatives ........................................................................11
6.0 PRELIMINARY GEOTECHNICAL RECOMMENDATIONS............................................14
6.1 Pavement Rehabilitation ............................................................................................14
6.2 Pavement Widening Areas ........................................................................................14
6.3 New Pavement Materials ...........................................................................................15
6.4 Existing Pavement Materials......................................................................................15
6.5 Transition Treatments ................................................................................................16
6.6 Pavement Drainage ...................................................................................................16
6.7 Subgrade Preparation................................................................................................17
6.8 Culverts .....................................................................................................................17
6.9 Excavation and Groundwater Control ........................................................................21
6.10 Storm Sewer Installation ............................................................................................22
6.11 Corrosion Potential of Soils........................................................................................22
6.12 Management of Excess Materials ..............................................................................23
6.13 Construction Inspection and Testing ..........................................................................23
7.0 CLOSURE .....................................................................................................................23
Statement of Limitations and Conditions
This report presents the results of a geotechnical investigation carried out by Thurber
Engineering Ltd. (Thurber) for the improvement of Elgin Mills Road between Bathurst Street and
Yonge Street, located in the Town of Richmond Hill, Ontario. The work was undertaken by
Thurber Engineering Ltd. (Thurber) for Hatch Mott MacDonald (HMM) as part of a Schedule 'C'
Class Environmental Assessment (EA) for the Regional Municipality of York (York Region or the
Client).
The purpose of this investigation was to obtain existing pavement condition and geotechnical
subsurface information along the proposed improvements and based on the findings, to provide
preliminary pavement and geotechnical recommendations for the proposed improvements to the
existing roadway. The investigation was carried out in general accordance with Thurber’s
proposal letter No. 114-3856 to HMM.
It is a condition of this report that Thurber's performance of its professional services is subject to
the attached Statement of Limitations and Conditions.
2.1 Background
It is understood that the Region is undertaking this Environmental Assessment (EA) study to
improve the functional and structural capacity of the above noted section of Elgin Mills Road. The
project includes identification of alternative solutions for the improvement of the roadway. The
alternatives being considered for this pavement and geotechnical investigation will include:
2.2 Physiography
The Quaternary geologic mapping for the site (OGS Map P.2204, 1980) indicates that the soil
conditions in the project area mainly consist of glacial tills ranging in composition from clayey silt
to sandy silt till. The bedrock, which is greater than 30 m depth, in the area comprises Upper-
Ordovician shale, limestone, dolomite and sandstone of the Georgian Bay Formation (Map 2197,
The study area is located within a physiographic region known as the South Slope: the southern
slope of the Oak Ridges Moraine. The South Slope region is gently sloped and faintly
drumlinized, although no drumlins are present within the study area.
The topography within the study area is gently undulating from a ground surface elevation of
approximately 253 m to 240 m above sea level, with a gradual downwards slope eastwards
towards Yonge Street.
The typical foundation frost penetration depth expected within the project area is 1.5 m.
Elgin Mills Road currently comprises a three-lane cross section, constructed with a semi-urban
platform from Bathurst Street to Regent Street/Shaftsbury Avenue (Regent Street) with a curb
and gutter along the westbound pavement edge, and a gravel shoulder and a ditch along the
eastbound direction. From Regent Street to Yonge Street, Elgin Mills Road has an urban
platform, with curb and gutter on both sides of the roadway. At signalized intersections, Elgin
Mills Road widens to include turn lanes and/or a secondary driving lane. The centre median is
paved and serves as a left turn lane, providing access to residential properties on both sides of
the roadway.
Elgin Mills Road, within the project limits, has an asphalt pavement surface, and a posted speed
limit of 50 km/hr.
At various locations within the project area, three culverts containing two tributaries of the East
Don River and one tributary of German Mills Creek cross beneath Elgin Mills Road.
A field investigation was carried out in May 2015 and comprised of a pavement surface condition
survey, borehole drilling, and laboratory testing on recovered samples of granular base/subbase
and pavement subgrade soil.
The visual pavement surface condition survey was completed within the project limits on
May 6, 2015 to assess the condition of the existing pavement surface, and identify the type and
severity of the specific pavement distresses present at that time. Typical photographs of existing
conditions are provided in Appendix A, while pavement condition evaluation forms are provided
in Appendix B.
Prior to the start of the drilling investigation, utility clearances were obtained through Ontario-1-
Call. Boreholes were positioned in order to avoid conflicts with existing infrastructure, including a
watermain located beneath the westbound lane. Therefore all boreholes other than BH 15-18
(Station 2+110) were advanced in the EB lane and/or shoulder, and Borehole 15-09 (Station
1+205) was limited to only pavement core sampling due to an underground utility conflict.
A road occupancy permit was obtained prior to commencement of drilling. Traffic control was
provided by Direct Traffic Management, while the boreholes were advanced using track-mounted
CME-55 drill rigs supplied and operated by DBW Drilling Ltd.
A plan of the borehole locations is provided in Appendix C, and borehole logs are provided in
Appendix D. Boreholes logs for the shallow boreholes (2.1 m depth) are presented in tabular
format, while logs for deeper boreholes are provided on separate record of borehole sheets. The
borehole locations were established in the field, relative to existing site features. The
approximate ground elevations at the boreholes were established based on elevation contours
on a topographic survey drawing provided by HMM.
The field investigation was carried out under the full-time supervision of Thurber technical staff.
All boreholes were logged in the field. Soil samples were identified, placed in labelled containers
and transported back to Thurber’s laboratory for further examination and testing. Laboratory test
results are provided in Appendix E.
Selected soil samples were submitted to a qualified laboratory for analytical testing to assess
disposal requirements for excess excavated materials, corrosivity potential of soils, and potential
site contamination. The laboratory Certificates of Analysis are provided in Appendix F.
Groundwater conditions in the open boreholes were observed during drilling. Monitoring wells
were installed in both culvert location for hydrogeological purposes to measure/test groundwater
conditions.
A detailed pavement surface distress survey was completed for Elgin Mills Road (within the
project limit) in accordance with the MTO Document SP-022 (Flexible Pavement Condition
Rating Guidelines for Municipalities). The condition assessment of the Elgin Mills Road
pavement was sub-divided into two segments based on the pavement surface condition. The
condition of the pavement surface on Elgin Mills Road between Bathurst Street and Regent
Street was considered to be in fair to poor condition, while the pavement section from Regent
Street and Yonge Street was considered to be in fair condition.
Predominant distresses in the pavement section between Bathurst Street and Regent Street
included frequent to extensive moderate transverse cracking, frequent slight to moderate
longitudinal/construction joint cracking, and slight to moderate map cracking. The eastbound
lanes were generally considered to be in worse condition than the westbound lane, as this area
often included moderate to severe alligator cracking, with slight to moderate edge pavement
cracking. Overall the ride condition rating for this section of Elgin Mills was considered to be fair
to poor, as the ride was considered to be relatively uncomfortable, with frequent bumps and
depressions.
The segment between Regent Street and Yonge Street was found to be in fair condition, with
patches and cracking through most of the area. Pavement distresses in this segment typically
comprised frequent slight to moderate severity patches, intermittent slight to moderate
transverse cracking and longitudinal joint cracking. Localized distressed areas also included
slight to moderate map cracking. Overall the ride condition rating for this section of Elgin Mills
was considered to be fair, as the ride was somewhat comfortable with intermittent bumps or
depressions.
4.2.1 Asphalt
The asphalt thickness based on core samples in the travel lanes of Elgin Mills Road was
observed to be variable, with thicknesses ranging from 120 to 170 mm. Although the shoulder
adjacent to the eastbound lane generally comprised a gravel surface, a 75 mm layer of asphalt
was observed at Station 0+205 (BH 15-02).
Standard Penetration Test (SPT) ‘N’ values obtained in the granular base/subbase ranged from
16 to 68 blows per 0.3 m penetration, indicating that the granular material varies from compact to
very dense. The moisture content of the retrieved samples ranged from 2 to 7%.
Grain Size analysis was completed on selected samples of granular base/subbase material that
indicate that the granular material generally follows OPSS Gradation specifications for Granular
B, Type I though most of the samples were finer than specification requirements in passing the
75 µm sieve size. It should be noted that gradations slightly exceeding the percent passing on
the 75 µm sieve size are common for samples collected from existing roadways, and could be
the result of construction activities (i.e. compaction efforts) and/or the drilling operation. To
confirm the suitability of the reuse of existing granular base material, additional laboratory testing
is required during construction. The grain size analysis results are shown on Figure E1 in
Appendix E.
Below the frost penetration depth, the subgrade soils encountered at the foundation borehole
locations consisted of silty sand to silty clay till, with zones of silty sand to sandy silt or silt.
Descriptions of these subgrade soils are provided below:
A sandy, silty clay till deposit was encountered in Boreholes 15-01 to 15-04, 15-06 to 15-08, and
15-12 to 15-18. The till deposit extended to depths of 4.6 to 4.9 m, except at Borehole 15-02,
which was terminated in the till at 5.0 m deep. SPT ‘N’ values recorded in the till ranged from 8
to 56, indicating a stiff to hard consistency. Atterberg Limits test results on the silty clay indicated
that the deposit has low plasticity, with a group symbol of CL. The moisture content of the till
ranged from 10 to 18%. The results of gradation analyses conducted on selected samples of the
till are shown on Figure E4 in Appendix E, and the Atterberg Limits test results are shown on
Figures E6 and E7.
4.3.3 Silt
Beneath the silty clay till unit, a deposit of silt was encountered at Boreholes 15-05, 15-07, 15-12,
and 15-18. These boreholes were terminated at a depth of 5.0 m within the silt deposit, which
ranged in composition from silt with some sand and trace clay to sandy silt with trace clay. The
silt was very dense, based on SPT ‘N’ values from 50 to 86 blows per 0.3 m penetration. The
moisture content of the silt ranged from 18 to 25%. The results of gradation analyses conducted
on the silt samples are shown on Figure E5 in Appendix E.
All boreholes were dry upon completion of drilling, with the exception of BH 15-05, adjacent to a
culvert, at Station 0+580 (EB Lane) where groundwater was observed at a depth of 3.55 m.
Monitoring wells were installed in 5 boreholes in order to measure the groundwater level. The
water level measurements are summarized in Table 4.1.
Selected granular and soil samples were submitted to AGAT Laboratories for analytical testing to
assess disposal requirements for excess excavated materials, corrosivity potential of soils, and
potential site contamination. The laboratory Certificates of Analysis are provided in Appendix F.
Four samples of the fill and native soils were submitted for analysis of Metals and Inorganics.
The analytical results were compared to the O. Reg. 153 (as amended) Table 2 standards (Full
Depth Generic Site Condition Standards in a Potable Groundwater Condition). The
concentrations of all parameters tested met the standards established in Table 2 for Industrial,
Commercial and Community land use, with the exception of Electrical Conductivity and Sodium
Adsorption Ratio in a sample of granular fill from Borehole 15-07, which likely reflects the
localized effect of road de-icing salt.
Two samples of the fill and native soils were also subjected to toxicity characteristic leaching
procedures (TCLP) analysis of inorganic parameters in accordance with O. Reg. 558/00. The
concentrations of all parameters tested were below the leachate quality criteria presented in
Schedule 4 of O. Reg. 558/00.
Due to the presence of 2 gas stations at the intersection of Elgin Mills Road and Bathurst Street,
and historical evidence of former gas stations at the intersection of Elgin Mills Road and Yonge
Street, two samples of the fill soils (granular fill and silty clay fill) were submitted for analysis of
Petroleum Hydrocarbons F1-F4, including Benzene, Toluene, Ethylbenzene and Xylenes
(BTEX). Both samples met the O.Reg. 153 (as amended) Table 2 standards for Industrial
Commercial and Community land use for the petroleum hydrocarbon parameters tested.
The results of corrosivity testing on two samples are discussed in Section 6.11.
The recommendations are based on the subsurface soil and groundwater conditions
encountered during the investigation. The soil conditions may vary between and beyond the
borehole locations, and accordingly geotechnical inspection during construction is important to
assess any variation of subsurface conditions and to provide additional recommendations if
necessitated by such variations.
Traffic information used for this investigation was provided by HMM Technical Memo “AADT
Volumes for Elgin Mills Road Prepared for the Elgin Mills Road West Class EA - Bathurst Street
to Yonge Street” issued August 13, 2015. A summary of the collected 2014 Average Annual
Daily Traffic (AADT) on Elgin Mills Road have been provided in Table 5.1.
The provided traffic volumes were forecasted to 2018 traffic volumes when construction was
assumed to be completed. Forecasted 2018 AADT was 23,225.
For the purposes of developing 20-year pavement designs, Average Annual Daily Traffic (AADT)
between Creekview Avenue and Yonge Street was considered. Commercial truck traffic used in
the design analysis was 3.5%, as indicated in the report for the eastbound lane. A consistent
traffic growth rate of 3.0 percent was also applied.
The traffic data was used to determine the pavement damage caused by the anticipated traffic
volumes. Using axle load equivalency factors, the different axle loads and axle groups are
converted to a standard axle load known as an Equivalent Single Axle Loads (ESALs). The
ESALs calculation was completed in accordance with the MTO Procedures for Estimating Traffic
Loads for Pavement Designs. It has been assumed that the average truck factor for trucks using
Elgin Mills Road is expected to be 2.5.
Based on the provided traffic information, the calculated 20-year design ESALs for Elgin Mills
Road is 8.0 million. It is noted that the ESALs calculated for the purposes of developing
pavement designs assume widening of the platform on Elgin Mills Road to two lanes in each
direction.
The pavement design analysis was carried out using the methodology outlined in the 1993
AASHTO “Guide for the Design of Pavement Structures”, as modified by the Ministry’s
The AASHTO procedure for the design of flexible pavements determines a required Structural
Number that characterizes the structural capacity of the pavement layers, for a given set of
inputs. The following design inputs were used in the AASHTO design analysis.
Soils information obtained from the pavement investigation indicate that the native subgrade in
this area generally comprised of clayey silt to sandy clayey silt soils, with moist conditions. A
conservative 30 MPa was selected as the subgrade strength in the design analysis to represent
soil conditions within the project limits.
Based on design input parameters and the calculated ESALs, a required design structural
number (SNDes) of 134 mm required for the rehabilitation or reconstruction of the existing
pavement structure. The details of the pavement design analysis from the AASHTO DARWin 3.0
software is provided in Appendix G.
Based on the above structural requirements, site considerations, and input from the design team,
the following new pavement structure is required should full reconstruction be considered for
Elgin Mills Road.
The existing pavement on Elgin Mills Road within the project limits was evaluated to determine
their functional and structural capacity of supporting the anticipated future traffic volumes. The
understanding of these requirements is critical for the development of future rehabilitation
strategies.
As noted in previous sections, the pavement surface on Elgin Mills Road is generally considered
to be in fair to poor condition. In consideration of the poor to fair functional condition,
rehabilitation treatments for the improvement of the existing roadway will need to address these
functional distresses.
The rehabilitation design for the pavements within the project limits were determined using the
AASHTO 1993 overlay design methodology to assess the structural capacity of the existing
pavement, and determine the overlay thickness required to meet the structural design
requirements. Structural layer and drainage coefficients used to determine the existing
pavement strength include:
Structural Drainage
Pavement Layer
Coefficient Coefficient
New Hot Mix Asphalt 0.42 1.0
New Granular Base 0.14 1.0
Existing Asphalt Layer 0.28 1.0
Existing Granular Material 0.08 0.9
Based on the thickness and condition of the existing pavement, the structural design analysis
indicates that the existing roadway would require a structural strengthening of 51 mm (SN),
which correlated to 125 mm of new Hot Mix Asphalt (HMA) overlay to be placed over the existing
pavement structure.
Detailed results of the AASHTO overlay design analysis are provided in Appendix F.
Based on the AASHTO pavement design analysis, and the completed pavement evaluation of
the in-situ pavement structure on Elgin Mills Road, the existing roadway is considered
structurally and functionally deficient to support anticipated traffic levels for the next 20 years.
Therefore, rehabilitation alternatives of this roadway will be required to improve the functional
and structural capacity of this roadway.
Various rehabilitation options are considered for the improvements of Elgin Mills Road, with each
option assessed for the treatments ability to address the observed distress, the level of effort
required, and the amount of improvement expected. Other constraints, such as grade raise
limitations, were also considered in selecting the most appropriate rehabilitation strategy.
A common technique for the functional rehabilitation of flexible pavements is a mill and overlay
strategy. This strategy involves the partial depth removal of the existing HMA followed by an
overlay, of similar thickness, with new HMA. This strategy does not include remediation of
existing distress areas, although strengthening could be completed by increasing the thickness
of the asphalt overlay.
This rehabilitation alternative is often referred to as a ‘holding strategy’, and considering the
extent of structural deficiencies of the existing pavement; it would be expected that many of
This rehabilitation alternative is often considered when localized pavement repairs are within
20 percent of the entire roadway surface. In consideration of the extent of observed pavement
distresses throughout the project limits, it would be expected that a significant percentage of the
existing pavement would need full depth repairs. For this reason, this option is not considered
further in this analysis.
5.6.4 Pulverize with Expanded Asphalt Stabilization and New HMA Overlay
A suitable alternative to ‘Pulverize and Overlay’ option is to supplement the lower binder course
with an expanded asphalt stabilization layer. The expanded/foamed asphalt method is an in-
place recycling technique that uses foamed asphalt to stabilize a designed thickness of the
pulverized material.
For the CIP process to be most effective the existing asphalt thickness must be greater than
150 mm to prevent the equipment from breaking through the bottom of the asphalt layer. Based
on the results of the pavement investigation, the existing asphalt thickness was found to have a
variable thickness with a few areas with an asphalt thickness of 120 mm. Furthermore, this
process is also complicated with the presence of iron works within the roadway platform. For this
reason, the rehabilitation option of pulverize with expanded asphalt stabilization is not considered
a viable rehabilitation strategy and is not considered further in the design analysis.
Should this alternative be considered, the existing asphalt would be removed full depth, with the
underlying granular graded to accommodate the placement of a new pavement surface.
However, in consideration of the high content of fines within the existing granular material, it will
However, should the geometric design review of this roadway indicate that grade raises are to be
minimized (or reduced) as a result of the rehabilitation treatment, then full reconstruction of the
existing pavement will be required to accommodate the full granular base and subbase
thicknesses.
The recommended pavement rehabilitation strategy for the existing pavement on Elgin Mills
Road should consist of removing the existing asphalt, placing 150 mm of new granular base
material, followed by paving 160 mm of new asphalt. The new asphalt shall comprise of the
following material type and layer thicknesses:
50 mm HL1
110 mm HDBC (2 lifts)
The recommended new pavement structure in all pavement widening areas, shall consist of:
50 mm HL1
110 mm HDBC (2 lifts)
150 mm Granular 'A' Base
900 mm Granular 'B' Subbase
It is important to note that in all pavement widening areas, the thicknesses of the new pavement
structure must match, or exceed the thickness of the existing pavement.
Should the Region consider using Superpave asphalt mixes for this project, the recommended
HL1 material should be substituted with a Superpave 12.5FC1 asphalt mix, and the HDBC
asphalt material should be replaced with a Superpave 19 asphalt materials. As the 20-year
design ESALs for the intersection is estimated to be approximately 8 million, a Traffic Category C
designation should be used in preparing all Superpave asphalt mix designs
The existing pavement materials should be removed, full depth, to allow for the construction of
the new pavement platform.
Smooth transitions are required in all areas where the new pavement meets the existing asphalt
surface. All longitudinal and transverse joints should meet the requirements of OPSS 310. All
longitudinal joints should be staggered between the asphalt lifts. The staggering of the
longitudinal joints should be accomplished by offsetting the paving edge in the upper asphalt
course by a minimum of 150 mm.
At the paving limits, the transverse tie-in should be trimmed to a depth of the surface course, full
width, to provide a straight clean vertical surface so that the new asphalt material can be placed
flush with the top of the existing pavement surface. At all transverse tie-ins to existing
pavements, the top lift of asphalt should extend a minimum of 5 m in length beyond the
transverse joint in the upper binder lift.
In all areas, the new pavement structure should be constructed to provide positive cross lateral
drainage at the top of subgrade, as well as the pavement surface. The top of subgrade should be
sloped at a minimum 3 percent grade, while the pavement surface should be constructed with a
minimum 2 percent crossfall. Subgrade drainage should outlet to subdrains or open ditches.
Subdrains should be included and conform to Regional standards. Drainage ditches in rural
areas should be constructed in accordance with OPSD 200.010, and be suitable to provide
drainage of the subgrade.
In all areas of pavement widening, the surficial vegetation and topsoil should be removed, and
excavated or engineered fill placed to achieve stable, competent subgrade. The underlying
subgrade soils graded as required to accommodate the new pavement platform. The exposed
subgrade should be compacted and proof-rolled with a heavy roller and examined to identify
areas of unstable subgrade. Any soft/wet areas identified should be subexcavated and replaced
with approved material within 2 percent of Optimum Moisture Content (OMC), and compacted to
at least 98 percent of Standard Proctor Maximum Dry Density (SPMDD).
6.8 Culverts
As part of the proposed road widening of Elgin Mills Road, three culverts may require extension:
The existing 2.2 m diameter corrugated steel pipe (CSP) at approximate Sta. 0+200
(invert Elev. 242.9 to 242.4 m);
The existing 1.8 m diameter CSP at approximate Sta. 0+580 (invert Elev. 245.3 to
244.6 m); and
The existing approximately 3 m wide concrete box culvert at approximate Sta. 2+120
(approximate invert Elev. 238 m).
We understand from HMM that the culvert at Sta. 2+120 may not be included in the current
phase of road improvements, however recommendations are provided in this report for reference
purposes.
The stratigraphy encountered in Borehole 15-02 near the culvert near Sta. 0+200 consisted of
asphalt, granular fill and silty clay fill to a depth of 1.5 m, underlain by native stiff silty clay till.
At the culvert near Sta. 0+580, the stratigraphy in Borehole 15-05 near the culvert consisted of
asphalt and granular fill to a depth of 0.8 m, overlying native loose to very loose silty sand to
4.0 m deep, underlain by very dense silt.
At the culvert near Sta. 2+120, the stratigraphy in Borehole 15-18 consisted of asphalt, granular
fill and sand fill to a depth of 2.1 m, underlain by hard silty clay till and very dense silt.
The culvert invert level at Sta. 0+200 is below the depth investigated in Borehole 15-02, which
was terminated at 5.0 m deep in silty clay till. It is anticipated that the silty clay may be underlain
by very dense silt, which was encountered below the till and silty sand deposits in Boreholes
15-05, 15-07, 15-12 and 15-15. However, if the ultimate design of the project includes extension
of this culvert, an additional borehole should be advanced at this culvert extension location
during detailed design to confirm the founding soil conditions.
All existing fill, topsoil, organic/streambed deposits and soft/loose soils should be removed from
the culvert subgrade prior to placement of the culvert bedding material. Inspection and approval
of the exposed base by a geotechnical engineer is recommended. In order to maintain the
culvert extensions at the same or lower elevation as the existing culverts, the grade should be
raised if necessary using Granular A backfill, compacted to 100% of SPMDD. Accordingly, an
engineered fill pad will likely be required to raise the grade for the culvert at Sta. 0+580, where
the soil conditions in Borehole 15-05 consist of very loose silty sand at the invert level.
The anticipated culvert subgrade conditions and recommended design bearing resistances at the
concrete culvert at Sta. 2+120 are presented in Table 6.1, based on minimum footing widths of
0.6 m.
Table 6.1 – Recommended Culvert Bearing Resistances
Depth Below Factored
Bearing
Culvert Reference Final Grade at Anticipated Bearing
Resistance
Location Boreholes Borehole Subgrade Resistance
at SLS (kPa)
Location (m) at ULS (kPa)
Sta. 2+120 15-18 3.0 Hard silty clay till 375 250
The bearing values provided are for vertical, concentric loads only. Effects of load inclination
and eccentricity must be considered.
Horizontal resistance against sliding may be developed by frictional resistance between the
concrete culvert base and the underlying soil. For cast-in-place concrete, an ultimate friction
Applicable comments regarding excavation and groundwater control during culvert installation
are presented in Section 6.9.
The depth of frost penetration at this site is approximately 1.2 m. Any culvert extensions to be
constructed within the frost penetration depth should include frost tapers as per OPSD 803.031,
constructed suing OPS Granular B Type II, with a 10H:1V slope.
Widened embankment slopes beyond the culverts should be constructed at the same slope
inclination as the existing embankment, but not steeper than 2H:1V.
The lateral earth pressures acting on the culvert (and any headwalls), assuming full drainage
from behind the walls, may be computed using the following pressure distribution:
p = K (H + q)
Table 6.2 lists the unfactored parameters recommended for design, for an essentially level
ground surface or for sloping backfill (2H:1V) behind and in front of the culvert and walls:
If lateral movement is not permissible and/or the wall is restrained from lateral yielding, the
at-rest pressure coefficient, Ko, should be used. If the wall design allows lateral yielding (non-
rigid structure), the active earth pressure coefficient, Ka, may be used.
The earth pressure coefficients in the table above do not include potential compaction effects
that must be included in the design. Compaction effects should be considered as per the
Canadian Highway Bridge Design Code (CHBDC).
Wall backfill should be placed in maximum 200 mm loose lifts and compacted to 95% of the
material’s SPMDD. The backfill should be placed and compacted in simultaneous equal lifts on
both sides of the culvert, and the top of the backfill elevation should be the same on both sides of
the culvert at all times. Heavy compaction equipment should not be used adjacent to the walls
and roof of the culvert or headwalls.
Design of the culvert headwalls must incorporate measures such as weepholes as per OPSD
3190.100 to permit drainage of the backfill and avoid potential build-up of hydrostatic pressures
behind the walls.
A concrete/steel cut-off wall or clay seal should be installed at the culvert inlet to minimize the
potential for seepage through the granular bedding and backfill material and avoid consequent
Frost treatment for the concrete culvert should be done as per OPSD 803.010.
Excavations for culvert foundations and open cut installation of sewers will primarily extend
through the existing roadway pavement structure and into native silty sand, silty clay till, and silt
deposits. Use of a hydraulic excavator should be suitable for excavation within these materials.
Provision should be made for handling and removal of possible obstructions in the fill and
cobbles or boulders in the till soils.
All temporary excavations must be carried out in accordance with the current Occupational
Health and Safety Act (OHSA) of Ontario and local regulations. In general, the pavement
structure and subgrade soils are classified as Type 3 soils, with the exception of silty sand below
the water table near culverts, which is classified as Type 4 soil.
Where space restrictions preclude excavation of inclined slopes, sewer installation may be
carried out using a trench box or temporary shoring. If the trench depth exceeds 6 m, the support
system must be designed specifically for this project.
The design of all members of the support system should include the effects of surcharge loads
such as those imposed by construction equipment and highway traffic. Soil should not be
stockpiled within a horizontal distance from the excavation wall equal to the depth of excavation.
Groundwater was measured at depths of 1.8 to 4.4 m below the ground surface in four of the
boreholes and was at shallower depth (1.8 to 3.1 m deep) near the creek crossings. Considering
the observations during drilling and the consistency of the soils on site, dewatering of shallow
excavations will be required. Concentrated seepage and instability of the trench walls and base
may be experienced where cohesionless layers are encountered below the groundwater level,
including at the culvert locations. Further, localized zones of perched water may be encountered
in the fill. Sumps and pumps or suitable well point systems may be required dependent on the
conditions at a particular location. Borehole 15-05 near the culvert at Station 0+580 encountered
water-bearing, cohesionless silty sand, and therefore may require additional groundwater control
measures, such as carrying out the foundation excavations within a water-tight, sheetpile
enclosure, or utilizing well point systems for dewatering.
New storm sewers may be installed along Elgin Mills Road as part of the roadway improvements.
Excavations and control of groundwater for sewer installations should follow the
recommendations provided in Section 6.9.
Prior to placement of the pipe bedding, the base of the sewer trench should be maintained in a
dry condition, free of loose or disturbed material. The pipe must be placed on a uniformly
competent subgrade. Pipe bedding materials, compaction and cover should follow OPSD
802.030 to 803.034, and/or York Region specifications.
In areas where a less competent subgrade is encountered, it may be necessary to increase the
sewer bedding thickness. Any excessively soft, loose or compressible materials at the pipe
subgrade should be subexcavated and replaced with OPS Granular A material compacted to at
least 95 percent of SPMDD.
Trench backfill materials should be placed and compacted as per OPSS 401. Where the sewer
trench is located beneath the roadway, OPSS Granular A or B material, or unshrinkable fill
should be employed as backfill.
Where the sewer trench is located outside of the roadway, the portion of the trench above the
pipe cover can be backfilled with excavated till provided it is unfrozen and free of organics, debris
and other deleterious materials. The placement moisture content should be within about
2 percent of the OMC for efficient compaction, and the till must be adequately broken down and
compacted in the trench.
Two samples of the fill and native soils (sand fill and clayey silt) were submitted to AGAT
Laboratories for corrosivity analysis to evaluate the potential for corrosion to metal pipes and
fittings, as well as sulphate attack on concrete. The results of the testing are included in
Appendix F. The test results indicate the following:
The potential for sulphate attack on concrete pipes and foundations from the surrounding
soil is considered to be low due to the low concentration of sulphate in the samples
tested.
If metal structural elements are used on the project, appropriate corrosion protection
measures must be provided.
Based on the available subsurface information and the analytical results of selected samples,
excess materials from the site may generally be classified as a “non-subject waste” in
accordance with O.Reg. 558/00 and disposed of at a suitable receiving site or reused on-site.
Tested materials recovered from the geotechnical investigation were found to meet the
standards established in Table 2 of the Regulation for Industrial, Commercial and Community
land use, with the exception of Electrical Conductivity and Sodium Adsorption Ratio in one
sample, which likely reflects the effects of road de-icing salt, and may impact vegetation growth if
placed near the surface of a receiving site.
Should materials require off-site disposal, the acceptance criteria stipulated by individual fill
receivers may vary, and some receivers may require that all results meet the stringent Table 1
background standards of O.Reg. 511/09 or other specified criteria.
Excavated asphalt and roadway granular material may be reused as described in Section 6.4
above or disposed of appropriately off-site. If disposed of off-site, asphalt should not be mixed
with excess excavated soil; some fill receivers may not accept excess excavated soils if they
contain asphalt.
Excavated native soils free from deleterious material and organics may be reused on site for
general fill purposes subject to geotechnical approval.
7.0 CLOSURE
Full time supervision of the field activities including obtaining utility clearances and direction of
the drilling operations was provided by experienced Thurber personnel, while drilling and
We note any changes in materials, or construction procedures, may have a significant impact on
assumptions made for the purposes of developing the recommended pavement designs. It is
strongly suggested that all materials and construction practices be completed in accordance with
York Region and Ontario standards and specifications.
Typical Photograph #1
Eastbound Lane at Station 0+360
(Looking Wessterly at Tennery Ct)
Typical Photograph #2
Eastbound Lane at Station 0+760
(Looking Wessterly)
Appendix A
Elgin Mills Road Class EA Study
Photographs of Typical Conditions
Typical Photograph #3
Eastbound Lane at Station 1+260
(Looking Easterly)
Typical Photograph #4
Westbound Lane at Station 1+845
(Looking Westerly)
APPENDIX B
Road No. (Street): Elgin Mills Road W. Location from: Bathurst St To: Regent St
Section Length: 1.25 (Km) Survey Date: 06-May-15 Traffic Direction: B B (Both Directions); N (North); S (South);
(East); W (West)
E
Pavement Condition Rating: 55 Riding Condition Rating: 5 Evaluated by: Riyad Islam
Density of
Severity of Density of Distress
Distress (Extent of Shoulder Distress Manifestion Severity of Distress
Distress (Extent of Occurrence, %)
Occurrence, %)
Right Left Right Left
Dominant Type Distress
10 8 6 4 2 0 Slight Moderate Severe Slight Moderate Severe <20 20-50 >50 <20 20-50 >50
Intermittent
Fair
Extensive
Excellent Good Poor Very Poor Pavement Edge
X
Frequent
Paved Full
Weighting
Paved Shoulder
Moderate
Severe Separation
Slight
Paved Cracking
<20 20-50 >50 Partial Breakup and
Pavement Distress Manifestion Potholes
(wi) 1 2 3 1 2 3 DMI Surface
Ravelling 1 3.0 0.00 Treated Distortion
Flushing 2 0.5 0.00 Pavement Edge
Primed
Surface Defects Potholes 3 1.0 x x 4.00 Curb Separation
Distress comments (Items not covered above): Other Comments (e.g. subsections, additional contracts):
FLEXIBLE PAVEMENT CONDITION EVALUATION FORM (MUNICIPALITIES)
Road No. (Street): Elgin Mills Road W. Location from: Bathurst St To: Regent St
Section Length: 0.9 (Km) Survey Date: 06-May-15 Traffic Direction: B B (Both Directions); N (North); S (South);
(East); W (West)
E
Pavement Condition Rating: 65 Riding Condition Rating: 6 Evaluated by: Riyad Islam
Density of
Severity of Density of Distress
Distress (Extent of Shoulder Distress Manifestion Severity of Distress
Distress (Extent of Occurrence, %)
Occurrence, %)
Right Left Right Left
Dominant Type Distress
10 8 6 4 2 0 Slight Moderate Severe Slight Moderate Severe <20 20-50 >50 <20 20-50 >50
Intermittent
Fair
Extensive
Excellent Good Poor Very Poor Pavement Edge
Frequent
X Paved Full
Weighting
Paved Shoulder
Moderate
Severe Separation
Slight
Paved Cracking
<20 20-50 >50 Partial Breakup and
Pavement Distress Manifestion Potholes
(wi) 1 2 3 1 2 3 DMI Surface
Ravelling 1 3.0 0.00 Treated Distortion
Flushing 2 0.5 0.00 Pavement Edge
Primed
Surface Defects Potholes 3 1.0 x x 2.00 Curb Separation
Distress comments (Items not covered above): Other Comments (e.g. subsections, additional contracts):
APPENDIX C
0+200
0+150
0+100
0+050
0+000
x
x
x x x
x
x
x x
x
x x x x x
0+200
0+250
0+300
0+350
0+400
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
x x
x
x
x
x
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
0+600
0+550
0+500
0+450
x
x
x
x
x x
0+800
0+750
0+700
0+650
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
PLOTDATE: Sep 17, 2015 - 3:31 PM
HATCH MOTT MACDONALD
LEGEND
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
0+950
1+000
0+900
0+850
x
x
x x
1+150
1+100
1+200
1+050
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
PLOTDATE: Sep 17, 2015 - 3:31 PM
HATCH MOTT MACDONALD
LEGEND
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
x
x x
x x
1+400
1+300
1+350
1+250
x
x x
x
x
x
x
x
x
x
x x x x
1+450
1+500
1+600
1+550
x x x
x
x
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
PLOTDATE: Sep 17, 2015 - 3:31 PM
HATCH MOTT MACDONALD
LEGEND
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
1+700
1+750
1+800
2+000
1+900
1+950
1+850
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
x
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
FILENAME: H:\Drafting\19\1605\184\ted5184-BoreholePlans.dwg
PLOTDATE: Sep 17, 2015 - 3:31 PM
HATCH MOTT MACDONALD
LEGEND
ELGIN MILLS
CLASS EA STUDY ENGINEER : DRAWN : APPROVED :
TERMINOLOGY PROPORTION
Trace or Occasional Less than 10%
Some 10 to 20%
Adjective (e.g. silty or sandy) 20 to 35%
And (e.g. sand and gravel) 35 to 50%
SYMBOLS AND SS Split Spoon Sample WS Wash Sample AS Auger (Grab) Sample
ABBREVIATIONS TW Thin Wall Shelby Tube Sample TP Thin Wall Piston Sample
FOR PH Sampler Advanced by Hydraulic Pressure PM Sampler Advanced by Manual Pressure
SAMPLE TYPE WH Sampler Advanced by Self Static Weight RC Rock Core SC Soil Core
(1) SPT ‘N’ Value Standard Penetration Test ‘N’ Value – refers to the number of blows from a 63.5kg hammer free falling a
height of 0.76m to advance a standard 50 mm outside diameter split spoon sampler for 0.3 m depth into undisturbed ground.
(2) DCPT Dynamic Cone Penetration Test – Continuous penetration of a 50 mm outside diameter, 60 conical
steel point attached to “A” size rods driven by a 63.5 kg hammer free falling a height of 0.76 m. The resistance to cone
penetration is the number of hammer blows required for each 0.3 m advance of the conical point into undisturbed ground.
UNIFIED SOILS CLASSIFICATION
GROUP
MAJOR DIVISIONS SYMBOL TYPICAL DESCRIPTION
GW Well-graded gravels or gravel-sand mixtures, little or
GRAVEL no fines.
AND GP Poorly-graded gravels or gravel-sand mixtures, little
GRAVELLY or no fines.
COARSE SOILS GM Silty gravels, gravel-sand-silt mixtures.
GRAINED GC Clayey gravels, gravel-sand-clay mixtures.
SOILS SW Well-graded sands or gravelly sands, little or no
SAND AND fines.
SANDY SP Poorly-graded sands or gravelly sands, little or no
SOILS fines.
SM Silty sands, sand-silt mixtures.
SC Clayey sands, sand-clay mixtures.
ML Inorganic silts and very fine sands, rock flour, silty or
clayey fine sands or clayey silts with slight plasticity.
CL Inorganic clays of low to medium plasticity, gravelly
SILTS AND clays, sandy clays, silty clays, lean clays.
FINE CLAYS (WL < 30%).
GRAINED WL < 50% CI Inorganic clays of medium plasticity, silty clays.
SOILS (30% < WL < 50%).
OL Organic silts and organic silty-clays of low plasticity.
MH Inorganic silts, micaceous or diatomaceous fine
SILTS AND sandy or silty soils, elastic silts.
CLAYS CH Inorganic clays of high plasticity, fat clays.
WL > 50% OH Organic clays of medium to high plasticity, organic
silts.
HIGHLY Pt Peat and other highly organic soils.
ORGANIC
SOILS
CLAY SHALE
SANDSTONE
SILTSTONE
CLAYSTONE
COAL
Appendix D
Elgin Mills Road Class EA
Bathurst Street to Yonge Street
Pavement Borehole Logs Sept 11, 2015
LAB. TESTING
ADDITIONAL
rem V - Cpen
STRATA PLOT
PIEZOMETER
BLOWS/0.3m
(metres)
40 80 120 160
DYNAMIC CONE PENETRATION
NUMBER
OR
RESISTANCE PLOT
TYPE
ELEV. WATER CONTENT, PERCENT STANDPIPE
DESCRIPTION INSTALLATION
DEPTH w
wp wl
(m) 20 40 60 80 100 10 20 30 40
247.54
CLAY, silty, with sand, trace gravel, stiff, 0.76
grey, moist: (FILL)
1 2 SS 14
246.78 Bentonite
CLAY, silty, sandy, trace gravel, stiff, grey, 1.52
moist: (TILL) 3 SS 12
2
Solid Stem Augers
4 SS 14
Filter Sand
3
5 SS 14
Slotted
Screen
4
6 SS 8
5 243.27
END OF BOREHOLE AT 5.03m. 5.03
Well installation consists of 50mm diameter
Schedule 40 PVC pipe with a 1.52m slotted
screen.
8
THURBER2S 19-1605-184.GPJ 9/17/15
GROUNDWATER ELEVATIONS
WATER LEVEL UPON COMPLETION WATER LEVEL IN WELL/PIEZOMETER LOGGED : AN
June 22, 2015 CHECKED : MEF
RECORD OF BOREHOLE BH 15-05
PROJECT : Elgin Mills Class EA Study Project No. 19-1605-184
LOCATION : Sta. 0+580 EB Lane
STARTED : May 25, 2015 SHEET 1 OF 1
COMPLETED : May 25, 2015 DATUM Geodetic
SHEAR STRENGTH: Cu, KPa
BORING METHOD
LAB. TESTING
ADDITIONAL
rem V - Cpen
STRATA PLOT
PIEZOMETER
BLOWS/0.3m
(metres)
40 80 120 160
DYNAMIC CONE PENETRATION
NUMBER
OR
RESISTANCE PLOT
TYPE
ELEV. WATER CONTENT, PERCENT STANDPIPE
DESCRIPTION INSTALLATION
DEPTH w
wp wl
(m) 20 40 60 80 100 10 20 30 40
246.84
SAND, silty, some clay, loose to very 0.76
loose, dark brown, moist
1 2 SS 10
Bentonite
3 SS 6
2
Solid Stem Augers
4 SS 2
Filter Sand
3
5 SS 3 Grain Size Analysis:
Gr 0%/ Sa 68%/ Si 21%/ Cl 11%
Slotted
243.64
Screen
4 SILT, some sand, trace clay, very dense, 3.96
brown, moist
5 242.57
END OF BOREHOLE AT 5.03m. 5.03
Piezometer installation consists of 50mm
diameter Schedule 40 PVC pipe with a
1.52m slotted screen.
8
THURBER2S 19-1605-184.GPJ 9/17/15
GROUNDWATER ELEVATIONS
WATER LEVEL UPON COMPLETION WATER LEVEL IN WELL/PIEZOMETER LOGGED : AN
June 22, 2015 CHECKED : MEF
RECORD OF BOREHOLE BH 15-07
PROJECT : Elgin Mills Class EA Study Project No. 19-1605-184
LOCATION : Sta. 0+975 EB Lane
STARTED : May 26, 2015 SHEET 1 OF 1
COMPLETED : May 26, 0215 DATUM Geodetic
SHEAR STRENGTH: Cu, KPa
BORING METHOD
LAB. TESTING
ADDITIONAL
rem V - Cpen
STRATA PLOT
PIEZOMETER
BLOWS/0.3m
(metres)
40 80 120 160
DYNAMIC CONE PENETRATION
NUMBER
OR
RESISTANCE PLOT
TYPE
ELEV. WATER CONTENT, PERCENT STANDPIPE
DESCRIPTION INSTALLATION
DEPTH w
wp wl
(m) 20 40 60 80 100 10 20 30 40
2
Solid Stem Augers
4 SS 50 >>
Filter Sand
3
Grain Size Analysis:
5 SS 47 Gr 0%/ Sa 34%/ Si 37%/ Cl 29% >>
Slotted
Screen
4
248.53
SILT, some sand, very dense, grey, wet 4.72 6 SS 86
5 248.22
END OF BOREHOLE AT 5.03m. 5.03
Piezometer installation consists of 50mm
diameter Schedule 40 PVC pipe with a
1.52m slotted screen.
8
THURBER2S 19-1605-184.GPJ 9/17/15
GROUNDWATER ELEVATIONS
WATER LEVEL UPON COMPLETION WATER LEVEL IN WELL/PIEZOMETER LOGGED : AN
June 22, 2015 CHECKED : MEF
RECORD OF BOREHOLE BH 15-12
PROJECT : Elgin Mills Class EA Study Project No. 19-1605-184
LOCATION : Sta. 1+490 EB Lane
STARTED : May 26, 2015 SHEET 1 OF 1
COMPLETED : May 26, 2015 DATUM Geodetic
SHEAR STRENGTH: Cu, KPa
BORING METHOD
LAB. TESTING
ADDITIONAL
rem V - Cpen
STRATA PLOT
PIEZOMETER
BLOWS/0.3m
(metres)
40 80 120 160
DYNAMIC CONE PENETRATION
NUMBER
OR
RESISTANCE PLOT
TYPE
ELEV. WATER CONTENT, PERCENT STANDPIPE
DESCRIPTION INSTALLATION
DEPTH w
wp wl
(m) 20 40 60 80 100 10 20 30 40
248.34
SILT, clayey, sandy, very stiff, brown, dry 0.76
to moist
1 2 SS 19
247.73 Bentonite
CLAY, silty, sandy, hard, brown: (TILL) 1.37
2
Solid Stem Augers
4 SS 38
Filter Sand
3
Grain Size Analysis:
5 SS 56 Gr 0%/ Sa 27%/ Si 55%/ Cl 18%
Slotted
Screen
4
244.53
SILT, sandy, trace clay, very dense, grey, 4.57
Grain Size Analysis:
moist to wet 6 SS 73 Gr 0%/ Sa 28%/ Si 67%/ Cl 5%
5 244.07
END OF BOREHOLE AT 5.03m. 5.03
Piezometer installation consists of 50mm
diameter Schedule 40 PVC pipe with a
1.52m slotted screen.
8
THURBER2S 19-1605-184.GPJ 9/17/15
GROUNDWATER ELEVATIONS
WATER LEVEL UPON COMPLETION WATER LEVEL IN WELL/PIEZOMETER LOGGED : AN
CHECKED : MEF
RECORD OF BOREHOLE BH 15-18
PROJECT : Elgin Mills Class EA Study Project No. 19-1605-184
LOCATION : Sta. 2+110 WB Lane 2
STARTED : May 26, 2015 SHEET 1 OF 1
COMPLETED : May 26, 2015 DATUM Geodetic
SHEAR STRENGTH: Cu, KPa
BORING METHOD
LAB. TESTING
ADDITIONAL
rem V - Cpen
STRATA PLOT
PIEZOMETER
BLOWS/0.3m
(metres)
40 80 120 160
DYNAMIC CONE PENETRATION
NUMBER
OR
RESISTANCE PLOT
TYPE
ELEV. WATER CONTENT, PERCENT STANDPIPE
DESCRIPTION INSTALLATION
DEPTH w
wp wl
(m) 20 40 60 80 100 10 20 30 40
2
Hollow Stem Augers
238.97
CLAY, silty, sandy, hard, grey, moist to 2.13
dry: (TILL)(CL) Filter Sand
4 SS 48 >>
3
Grain Size Analysis:
5 SS 46 Gr 0%/ Sa 32%/ Si 43%/ Cl 25%
Slotted
Screen
8
THURBER2S 19-1605-184.GPJ 9/17/15
GROUNDWATER ELEVATIONS
WATER LEVEL UPON COMPLETION WATER LEVEL IN WELL/PIEZOMETER LOGGED : AN
June 22, 2015 CHECKED : MEF
APPENDIX E
GRANUALR BASE/SUBBASE
80
70
PERCENT FINER THAN
60
50
GRANULAR A
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10 100
GRAIN SIZE, mm
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-03 0.66 249.64
BH 15-07 0.99 252.26
BH 15-14 0.67 244.93
GRAIN SIZE DISTRIBUTION - THURBER 19-1605-184.GPJ 9/17/15
90
80
70
PERCENT FINER THAN
60
50
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10 100
GRAIN SIZE, mm
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-03 1.58 248.72
BH 15-14 1.58 244.02
GRAIN SIZE DISTRIBUTION - THURBER 19-1605-184.GPJ 9/17/15
90
80
70
PERCENT FINER THAN
60
50
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10 100
GRAIN SIZE, mm
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-05 3.35 244.25
BH 15-10 1.31 248.99
BH 15-18 1.75 239.35
GRAIN SIZE DISTRIBUTION - THURBER 19-1605-184.GPJ 9/17/15
90
80
70
PERCENT FINER THAN
60
50
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10 100
GRAIN SIZE, mm
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-07 1.75 251.50
BH 15-07 3.28 249.97
BH 15-12 1.75 247.35
GRAIN SIZE DISTRIBUTION - THURBER 19-1605-184.GPJ 9/17/15
SILT
90
80
70
PERCENT FINER THAN
60
50
40
30
20
10
0
0.0001 0.001 0.01 0.1 1 10 100
GRAIN SIZE, mm
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-05 4.80 242.80
BH 15-12 4.80 244.30
BH 15-18 4.80 236.30
GRAIN SIZE DISTRIBUTION - THURBER 19-1605-184.GPJ 9/17/15
60
CH
50
40
PLASTICITY INDEX
CI
30
CL
20
10
CL
CL-ML MI-OI MH-OH
ML OL
0
0 10 20 30 40 50 60 70 80
LIQUID LIMIT
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-03 1.58 248.72
BH 15-07 1.75 251.50
BH 15-07 3.28 249.97
BH 15-14 1.58 244.02
BH 15-16 1.65 241.55
BH 15-18 1.75 239.35
THURBALT 19-1605-184.GPJ 9/17/15
60
CH
50
40
PLASTICITY INDEX
CI
30
CL
20
10
CL
CL-ML MI-OI MH-OH
ML OL
0
0 10 20 30 40 50 60 70 80
LIQUID LIMIT
LEGEND
SYMBOL BOREHOLE DEPTH (m) ELEV. (m)
BH 15-18 3.28 237.82
THURBALT 19-1605-184.GPJ 9/17/15
EC/Resistivity, pH, Chloride, Sulphate and Redox Potential were determined on the extract obtained from the 2:1 leaching procedure (2 parts DI water: 1 part soil).
Elevated RDL indicates the degree of sample dilution prior to the analysis to keep analytes within the calibration range, reduce matrix interference and/or to avoid contaminating the instrument.
6623238 * Sulphide analysis was performed at AGAT Laboratories Vancouver.
EC/Resistivity, pH, Chloride, Sulphate and Redox Potential were determined on the extract obtained from the 2:1 leaching procedure (2 parts DI water: 1 part soil).
Certified By:
CERTIFICATE OF ANALYSIS (V1) Page 1 of 5
Results relate only to the items tested and to all the items tested
5835 COOPERS AVENUE
Certificate of Analysis MISSISSAUGA, ONTARIO
CANADA L4Z 1Y2
AGAT WORK ORDER: 15T981109 TEL (905)712-5100
FAX (905)712-5122
PROJECT: 19-1605-184 http://www.agatlabs.com
CLIENT NAME: THURBER ENGINEERING LTD ATTENTION TO: MARK FARRANT
SAMPLING SITE: SAMPLED BY:Deanna Przycki
O. Reg. 153(511) - Metals & Inorganics (Soil)
DATE RECEIVED: 2015-06-04 DATE REPORTED: 2015-06-12
BH15-7, SS#2, BH15-7, BH15-13, BH15-2, SS#4,
SAMPLE DESCRIPTION: 2'6"-4'0" 150-1200 1200-1950 7'6"-9'6"
SAMPLE TYPE: Soil Soil Soil Soil
DATE SAMPLED: 5/26/2015 5/26/2015 5/26/2015 5/25/2015
Parameter Unit G/S RDL 6623184 6623237 6623238 6623242
Antimony µg/g 40 0.8 <0.8 <0.8 <0.8 <0.8
Arsenic µg/g 18 1 2 2 2 2
Barium µg/g 670 2 29 18 65 65
Beryllium µg/g 8 0.5 <0.5 <0.5 0.5 0.5
Boron µg/g 120 5 <5 <5 7 <5
Boron (Hot Water Soluble) µg/g 2 0.10 <0.10 0.33 <0.10 0.23
Cadmium µg/g 1.9 0.5 <0.5 <0.5 <0.5 <0.5
Chromium µg/g 160 2 9 14 17 16
Cobalt µg/g 80 0.5 3.9 2.3 7.2 6.2
Copper µg/g 230 1 8 6 13 12
Lead µg/g 120 1 5 5 7 13
Molybdenum µg/g 40 0.5 <0.5 <0.5 <0.5 <0.5
Nickel µg/g 270 1 8 5 15 13
Selenium µg/g 5.5 0.4 <0.4 <0.4 <0.4 <0.4
Silver µg/g 40 0.2 <0.2 <0.2 <0.2 <0.2
Thallium µg/g 3.3 0.4 <0.4 <0.4 <0.4 <0.4
Uranium µg/g 33 0.5 <0.5 <0.5 <0.5 <0.5
Vanadium µg/g 86 1 16 15 24 26
Zinc µg/g 340 5 24 21 32 48
Chromium VI µg/g 8 0.2 <0.2 <0.2 <0.2 <0.2
Cyanide µg/g 0.051 0.040 <0.040 <0.040 <0.040 <0.040
Mercury µg/g 3.9 0.10 <0.10 <0.10 <0.10 <0.10
Electrical Conductivity mS/cm 1.4 0.005 2.57 0.839 0.601 1.28
Sodium Adsorption Ratio NA 12 NA 36.3 3.65 6.34 9.53
pH, 2:1 CaCl2 Extraction pH Units NA 7.85 7.92 10.6 8.25
Certified By:
CERTIFICATE OF ANALYSIS (V1) Page 2 of 5
Results relate only to the items tested and to all the items tested
5835 COOPERS AVENUE
Certificate of Analysis MISSISSAUGA, ONTARIO
CANADA L4Z 1Y2
AGAT WORK ORDER: 15T981109 TEL (905)712-5100
FAX (905)712-5122
PROJECT: 19-1605-184 http://www.agatlabs.com
CLIENT NAME: THURBER ENGINEERING LTD ATTENTION TO: MARK FARRANT
SAMPLING SITE: SAMPLED BY:Deanna Przycki
O. Reg. 558 Metals and Inorganics
DATE RECEIVED: 2015-06-04 DATE REPORTED: 2015-06-12
BH15-2, SS#5, BH15-16,
SAMPLE DESCRIPTION: 10'-11'6" 120-1200
SAMPLE TYPE: Soil Soil
DATE SAMPLED: 5/25/2015 5/26/2015
Parameter Unit G/S RDL 6623240 6623241
Arsenic Leachate mg/L 2.5 0.010 <0.010 <0.010
Barium Leachate mg/L 100 0.100 0.608 0.347
Boron Leachate mg/L 500 0.050 <0.050 0.103
Cadmium Leachate mg/L 0.5 0.010 <0.010 <0.010
Chromium Leachate mg/L 5.0 0.010 <0.010 <0.010
Lead Leachate mg/L 5.0 0.010 <0.010 <0.010
Mercury Leachate mg/L 0.1 0.01 <0.01 <0.01
Selenium Leachate mg/L 1.0 0.010 <0.010 <0.010
Silver Leachate mg/L 5.0 0.010 <0.010 <0.010
Uranium Leachate mg/L 10.0 0.050 <0.050 <0.050
Fluoride Leachate mg/L 150 0.05 0.10 0.33
Cyanide Leachate mg/L 20.0 0.05 <0.05 <0.05
(Nitrate + Nitrite) as N Leachate mg/L 1000 0.70 <0.70 <0.70
Comments: RDL - Reported Detection Limit; G / S - Guideline / Standard: Refers to Regulation 558
Certified By:
CERTIFICATE OF ANALYSIS (V1) Page 3 of 4
Results relate only to the items tested and to all the items tested
5835 COOPERS AVENUE
Certificate of Analysis MISSISSAUGA, ONTARIO
CANADA L4Z 1Y2
AGAT WORK ORDER: 15T981109 TEL (905)712-5100
FAX (905)712-5122
PROJECT: 19-1605-184 http://www.agatlabs.com
CLIENT NAME: THURBER ENGINEERING LTD ATTENTION TO: MARK FARRANT
SAMPLING SITE: SAMPLED BY:Deanna Przycki
O. Reg. 153(511) - PHCs F1 - F4 (Soil)
DATE RECEIVED: 2015-06-04 DATE REPORTED: 2015-06-12
BH15-18, SS#2, BH15-01,
SAMPLE DESCRIPTION: 2'6"-4'0" 1500-2100
SAMPLE TYPE: Soil Soil
DATE SAMPLED: 5/26/2015 5/25/2015
Parameter Unit G/S RDL 6623243 6623245
Benzene µg/g 0.32 0.02 <0.02 <0.02
Toluene µg/g 6.4 0.08 <0.08 <0.08
Ethylbenzene µg/g 1.1 0.05 <0.05 <0.05
Xylene Mixture µg/g 26 0.05 <0.05 <0.05
F1 (C6 to C10) µg/g 5 <5 <5
F1 (C6 to C10) minus BTEX µg/g 55 5 <5 <5
F2 (C10 to C16) µg/g 230 10 <10 <10
F3 (C16 to C34) µg/g 1700 50 75 <50
F4 (C34 to C50) µg/g 3300 50 89 <50
Gravimetric Heavy Hydrocarbons µg/g 3300 50 NA NA
Moisture Content % 0.1 4.5 10.8
Surrogate Unit Acceptable Limits
Terphenyl % 60-140 110 111
Certified By:
CERTIFICATE OF ANALYSIS (V1) Page 4 of 5
Results relate only to the items tested and to all the items tested
5835 COOPERS AVENUE
Guideline Violation MISSISSAUGA, ONTARIO
CANADA L4Z 1Y2
AGAT WORK ORDER: 15T981109 TEL (905)712-5100
FAX (905)712-5122
PROJECT: 19-1605-184 http://www.agatlabs.com
CLIENT NAME: THURBER ENGINEERING LTD ATTENTION TO: MARK FARRANT
SAMPLEID SAMPLE TITLE GUIDELINE ANALYSIS PACKAGE PARAMETER GUIDEVALUE RESULT
6623184 BH15-7, SS#2, 2'6"-4'0" ON T2 S ICC CT Corrosivity Package Electrical Conductivity (2:1) 1.4 2.57
6623184 BH15-7, SS#2, 2'6"-4'0" ON T2 S ICC CT O. Reg. 153(511) - Metals & Inorganics (Soil) Electrical Conductivity 1.4 2.57
6623184 BH15-7, SS#2, 2'6"-4'0" ON T2 S ICC CT O. Reg. 153(511) - Metals & Inorganics (Soil) Sodium Adsorption Ratio 12 36.3
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 HMA 0.42 1 160 3.6 67
2 Granular A 0.14 1 150 3.6 21
3 Granular B 0.09 1 525 3.6 47
Total - - - 835 - 135
Page 1
Layered Thickness Design
Page 2
1997 AASHTO Pavement Design
AC Overlay of AC Pavement
Milling Thickness 40 mm
Calculated Results
Page 1
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 New HMA 0.42 1 150 3.7 63
Total - - - 150 - 63
Page 2
1997 AASHTO Pavement Design
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 New Asphalt Surface 0.42 1 160 3.7 67
2 Pulverized Material 0.14 1 300 3.7 42
3 Existing Granular 0.08 0.9 600 3.7 43
Total - - - 1,060 - 152
Page 1
Layered Thickness Design
Page 2
1997 AASHTO Pavement Design
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 New Asphalt Surface 0.42 1 90 3.7 38
2 Expanded Asphalt Stab 0.25 1 150 3.7 38
3 Pulverized Material 0.14 1 150 3.7 21
4 Existing Granular 0.08 0.9 600 3.7 43
Total - - - 990 - 140
Page 1
Layered Thickness Design
Page 2
1997 AASHTO Pavement Design
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 New Asphalt Surface 0.42 1 120 3.7 50
2 Cold-in-Place Recycling 0.35 1 120 3.7 42
3 Existing Granular 0.08 0.9 600 3.7 43
Total - - - 840 - 136
Page 1
Layered Thickness Design
Page 2
1997 AASHTO Pavement Design
Struct Drain
Coef. Coef. Thickness Width Calculated
Layer Material Description (Ai) (Mi) (Di)(mm) (m) SN (mm)
1 New Asphalt Surface 0.42 1 160 3.7 67
2 New Granular Base 0.14 1 150 3.7 21
3 Existing Granular Base/Subbase 0.08 0.9 650 3.7 47
Total - - - 960 - 135
Page 1
Layered Thickness Design
Page 2