Professional Documents
Culture Documents
Risk Assessment All Activities TLT HIRA
Risk Assessment All Activities TLT HIRA
Risk Assessment All Activities TLT HIRA
: OHSAS / RC / RA /
KM / DC 132 KV OHTL AND
ASSOCIATED SUBSTATION
PROJECT RISK ASSESSMENT DATE : 20-05-2017
23 Segregating of Routine Hit by material Injury to men 1 3 3 Low • Use forklifts and machinery, deploy
authorized operator.
• Ensure basic procedures for manual
Tower parts at
handling,
sore & site.
• Tool box talk, Hand & Foot protection,
PPE's
• Work must be started only after taking
proper shutdown and discharging both
the side & confirming with Induction
Electrocution/ Severe injury/ Tester, use additional earthing for
Routine 2 3 6 Low
Induction Fatality leakage current.
• Engineering control, tool box talk &
Erection of • Certified PPE's (according to the line
24 Tower near voltage.)
LT/HT line • Inspection of Tools &Tackles’ prior to
start of the job,
Injury to men • Engineering control &
Routine Defective tools or damage of 2 3 6 Low • Necessary PPE's,
material • Trainings should given for such type of
job and ensure usage of proper and
correct tools.
• Ensure competent riggers to precede
the job.
• All tools & Tackles must be checked
daily before the work starts.
• All lifting machineries should be
certified by third party.
• Only one person stands near the leg (3-
5 m away) from the base of the lifting
material. The person will stand away
Fall of men, Fall of Injury to men from the lifting direction of the load,
Erection of leg Routine Tower leg, Failure of or damage of 1 3 3 Low ensure proper PPE's
25 part of Tower tools & Tackles material • Tool box talk to be conducted before
the work starts,
• Competent workmen to be engaged
for special task.
• Full body safety harness must be
anchored with vertical life line.
• No lone worker to be allowed to
proceed the work,
• No work to be allowed without
supervisor control.
Stub damage (due to Material • Ensure Competent Supervisor /
Routine 1 3 3 Low
overload /Improper damage Engineer , only 2 leg joints are erected
initially,
arrangement )
• Mandatory PPE's.
• The path of the tractor is ensured plain
and no person shall stand in front of the
Hit (or) run over by vehicle, should be 3m away (beside) from
Injury to men
vehicle, (The jerk the tractor,
Routine or damage of 1 4 4 Low
caused due to • Engineering Control and High visibility
material
uneven surface). Jackets & Aprons and PPE's.
• Banks men to be appointed to clear the
passage.
• Checked Tools & Tackles before use.
Injury to men • Engineering Control,
Failure of Tools
Routine or damage of 1 4 4 Low • Third party certificates for all lifting
Erection of leg &Tackles
material tools, tackles & machineries.
part of Tower
• Tool box talk, and mandatory PPE's.
• Lift up & Guying arrangement of
derrick should be done in experienced
fitter.
• Supervisor control,
Routine Fall of Derrick Injury to men 2 3 6 Low
• Proper inspection of lifting tools and
tackles before start the work,
Tower erection • Competent Riggers and Necessary
26 through Derrick PPE's.
Pole.
• Before use inspect the derrick pole by
Experienced person.
Non- Damage/bend of Damage of • Hook welding must be inspected by
2 3 6 Low
Routine derrick Material welding inspector,
• Engineering controls,
• Supervisor control.
• Authorized and competent operator.
• Healthy condition of tractor should be
engage at site.
Hit, Run over, • Supervisor control,
Injury to • Housekeeping should maintain in
Using Tractor in Toppled & Fall of men. proper way,
27 Routine 1 3 3 Low
Erection activity materials Damage of • The path of the tractor is ensured plain
Material / and no person shall stand in front of the
Vehicle. vehicle, should be 3m away (beside) from
the tractor, and
• High visibility Jackets & Aprons and
PPE's.
• Competent workmen and fitter must
be engaged for the specialty task.
• Ensure competent supervision.
• No person shall stand beneath when
Fitter derrick is being hoisted.
ascending/ Injury to men • The person holding the bottom of the
28 Routine Fall from Height 2 3 6 Low
descending in / Fatality derrick must use fall arrestor or Hoisting
Tower of the derrick shall be carried Manually.
• Rope grab fall arrester must be used
during ascending or descending time.
• Daily tool box talk & ensure use of
mandatory PPE.
• Competent workmen and fitter must
be engaged for the specialty task.
Fitting of Fall of Person/ Fall of
29 Routine Injury to men 1 3 3 Low • Ensure competent supervision.
Diagonals Material
• Strict usage of double lanyard harness
& ensure use of necessary PPE
• Check for the maintenance of all Tools
Fall of material or
Erection of & Tackles’ before start of work.
30 Routine failure of tools & Injury to men 1 1 1 Low
Cross arms • Administrative control &
tackles
• PPE
• While hoisting small pieces, use ‘S
“hook and they should be removed in
Erection Of such a way that the lower part of the
31 Routine Fall of Material Injury to men 1 1 1 Low
Peak piece must be secured by a person & this
must not obstruct by tower body.
• Engineering control & PPE.
Injury to • Ensure proper co-ordination and team
Fall of materials,
Erection men, work, nominate separate signal man.
32 Routine dangerous 2 2 4 Low
procedures damage to • Maintain good communication all the
occurrences
materials time.
• In case of high winds work should post
Incidence fall of pone until wind speed is normal, before
Non- progressive stop the work ensure no suspended
33 Tower erection Fatal / Injury 5 1 5 Low
routine assembly structure loads left on tower structure,
due high winds • Clear all persons from possible hazard
zone for fall of material
Due to lightening or • Prior to start with any work at any
Non- induction effect of location ensures that two legs of the
34 Tower erection Fatal / Injury 5 1 5 Low
routine any adjacent live line tower must be connected to the
passing near by provided earth wire.
1) Vehicle must be checked by a
competent person before leaving the
Store.
2) Allow only authorize drivers with
Statutory documents.
Injury to 3) Driver should not be under any
Transportation men, alcoholic affect
of insulators Non - Road Accident, Fall Material 4) Administrative control & PPE
1 2 2 4 Low
from store to Routine Of materials damage, 5) Solar Blinkers and red flag should be
site. legal placed at transportation vehicle.
proceedings 6) Tool box talk to be conducted before
the work starts
7)Competent drivers must engaged for
the trnasportation work.
8) Good & adequate packing must be
provided for transporting of Insulators.
Insulator
6 fittings in 1) Follow the safe work method of Lifting
Injury to men
Cross arms Non - arrangement of insulator & aerial roller.
Fall of Material & damage to 2 2 4 Low
Routine 2) Guying arrangement &fix the arc
material.
clip,Aerial roller properly.
1 The puller and Non- Damage to Injury to 1 3 3 Low 1) Ensure proper braking system of both
Tensioner are Routine material,Fall of men,Fatality machines & back stay arrangements.
kept at machinery at worst case, 2) Administrative control
predetermined Damaged to 3) Protect the area by fensing to control
place. The the unauthorized entry. 4)
tensioner & materials. PPE
puller are placed
such a way that
the load doesn’t
act on
suspension
tower. Generally
the tensioner &
puller are placed
at each Dead
end point. (The
tensioner /
puller must be
kept at a
minimum
distance of 200
m from
suspension
tower).
The back stay (2
no) is provided
at distance of
4.5m from the
machine. The
depth of the pit
for back stay
1) The wooden deadment (wooden log)
must be 1.5 m or
used must be above 600 mm dia and of
more. The
good quality wood (teak/red
length of the
wood/neem/babur).
wooden log Failure of the Tools &
Injury to 2) The anchoring point shall be in-
must be 1.5m or Tackles (Slings,
Non- men & between 20 to 30° 3)
2 more. The back- D’Shackles, Wire 2 4 8 Medium
Routine damage of Engineering control &
stay is provided rope etc.), Failure of
material 4) Check the physical damage of tools &
using a 16/18 the wooden log
tackles 5) All lifiting
mm wire rope
tools & tackles must be certified by
sling attached
competent thirdparty.
to a 10 ton turn
6) PPE
buckle. The turn
buckle is
connected to
the machine &
wire rope using
D-Shackle (10
ton)
The conductor is
first passed
through the
Tensioner
manually. The 1) Once the conductor is inserted, the
two ends of the sock is held firmly with the help of
conductor are binding wire to ensure that the
Hit by material
connected to conductor doesn’t get released from the
Non- (release of the
4 the head board Injury to men 1 4 4 Low socks.
Routine conductor from
through 2) Engineering Control
socks)
conductor 3) Administrative control
holding socks. 4) Supervisor Control
The pilot wire is 5)PPE
joined to the
head board with
an articulated
joint.
PRESSING &
FIXING THE
DEAD END
CONE :
•After the dead 1) No person is allowed to stand in the
end press is vicinity of 10 m from suspended load.
Injury to
completed, the 2) Strict usage of double lanyard & usage
Non- Fall of material & Fall men,
6 conductor is 1 3 3 Low of retractable fall arrestor by all persons
Routine of person Material
hoisted by using working on the tower.
damage
a PP rope. 3) Administrative control
•The dead end 4) PPE
cone D shackle
is fixed to the
yoke plate of
the insulator.
7 RELEASING Routine Hit to the persons. Injury to men 1 3 3 Low 1) No one shall stand in the vicinity area.
THE - 2) Sorrounding area must be cleared
ARRANGEMEN before releasing the rotating sagg.
T: •After 3) Administrative control PPE
fixing the dead
end cones the
wire rope of the
“lefty”
connecting the
conductors is
slowly released
by rotating the
sagging winch
handle in
opposite
direction.
•At the same
time the lefty
end connecting
the conductor is
pulled so that
the lefty is
extended.
Once the load
on lefty is
1) The persons working at height must
reduced, the
always harness their full body harness.
sling passing Fall of person & Fall
2) Before opening the D-Shackle
through the of material
Non- connected to the sling, a PP-Rope must
8 equalizer pulley (Detachment of sling Injury to men 1 4 4 Low
Routine be tied to the sling for lowering the
connecting the from the hook of the
arrangement. 3)
sling of the lefty while lowering)
Administrative control
come-along
4) PPE
clamps is
removed.
Once the D
shackle is
opened the lefty
is released from
conductor. For
1) No person is allowed to stand in the
releasing the
vicinity of 10 m from suspended load.
“lefty” the wire
2) No body is allowed to stand near the
rope is made Hit by material(due
Non- tower and the person releasing the wire
9 into loops near to releasing loop of Injury to men 1 4 4 Low
Routine rope must position himself inside the leg
the leg of the the lefty)
of the tower.
tower.
3) Administrative control
• For releasing
4) PPE
the “lefty” the
wire rope
passed through
the sag winch is
released.
10 •The person Non- Fall of material & Fall Injury to men 1 4 4 Low 1) Before detaching the come-along
detaches the Routine of person clamps, a PP-Rope must be tied to the
come along sling for preventing fall of material.
clamp and 2) The person should be wearing full
attaches it with body harness and should have rope grab
a PP rope. fall arresters on it.
•Two persons 3) Administrative control
on ground 4) PPE
slowly releases
down the PP
rope so that the
come along
clamp is
lowered to the
ground.
Now the person
on the top also
fastens one rope 1) Person must be wearing a full body
grab fall arrestor harness with a rope grab arrester
Non-
11 on either side of Fall of person Injury to men 1 3 3 Low anchored to the lifeline.
Routine
the rope and 2) Administrative control
descends 3) PPE
through the
rope
1) Under no circumstances is a worker
allowed to be working alone at height.
2) Supervisor to make sure they have
enough climbers on site to work at
heights
3) Supervisor to plan his workload to
ensure that a worker will never be
working alone at heights
4) No horseplay whiles you working at
1)Inexperienced
heights.
climbers doing
5)Only employees with certificates to
crossings Serious
work at heights should work
Working at 2) Production injuries or
1 Routine 2 3 6 Low 6) At all times two climbers per work
heights pressure fatality can
station.
3) Not having occur.
7)Supervisor to be on site at all times and
enough trained
supervising .
climbers on site.
8)Drop zones to be maintained on all the
work that is performed at height.( visible
cones to be used)
1)Rescue to be conducted within 7
minutes
2) Supervisor to remind climber to move
his legs as if he is cycling this will help to
1) Hanging in a full ensure blood flow to the brain
Serious
Body Harness for too 3) Supervisor to plan his work load to
injuries or
long and not having ensure that at least two rescuers are
fatality can
enough blood available in each team
occur .Panic,
Non- circulate to the brain 4) Inspection on the rescue kit to be
2 Rescue uncontrolled 1 3 3 Low
Routine 2) Not moving body conducted
emotions,
parts when 5) Two rescuers per team
anxiety,
suspended 6) 1 rescue kit per team
unconsciousl
3) Not enough 7) Emergency numbers and plan to be
y or death
rescuers available available and communicated to workers
8) Rescue drills and procedure to be
practiced
9) SCBA to be provided along with each
rescue kit.
1) Scaffolding hand over certificates to
be available at all times.
2) No work allowed commencing
without certificates.
3) Only approved scaffolding to be used.
4) Supervisor to insure correct placing
and back staying of the of the poles is
practiced
1) Equipment failure. 5) Only registered and certified
2) Falling of the equipment will be used
Erecting Serious
rugby poles, 6) Daily inspections by Supervisor of
Towers/Nets/sc injuries or
3 Routine 3) Collapsing of the 2 4 8 Medium scaffolding to be conducted.
affolding fatality can
scaffolding 7) Cross bracing of scaffolding to be
erection occur
4) Use of wrong practiced.
equipment 8) Drop zone to be practiced.
9) The MS to be followed at all times and
this has to be maintain when doing the
work on the crossing
1) Supervision
2) Tools to be stored properly
3) All the nets to be properly secured to
the poles used for crossing
The towers to be secured and properly
1) Getting struck by Minor to planted
2) Falling objects Serious 4) Supervisor to inspect working areas
Routine 1 2 2 Low
example: tools and, injuries can before leaving site.
falling poles nets occur 5) The drop zone should be maintained
at all the times.( the visible cones to be
used at all times)
Loading / Hit by falling Use of PPE like hand gloves, safety shoe,
Serious
unloading of material, Mechanical helmet; Continuous training to
physical
1 tower material Routine failure,Falling 5 2 10 Medium personnel involved in lifting operations;
Injury,
at store / site object / Stuck with Trained operator; Use fo Rigger &
Fatality
mechanically object Banksman during lifting operations