Professional Documents
Culture Documents
Q and A PMP 013
Q and A PMP 013
Q and A PMP 013
processes required to develop and administer contracts for you project. What is this
B: Close Procurements
Question 358: All of the following are examples of legally binding agreements
except?
A: Agreement
B: Subcontract
D: Purchase order
www.it-ebooks.info
CHAPTER 1 ■ QUESTIONS
91
Question 359: You are just about to begin the process of procuring services from
external providers and you think there may be a standard set of rules governing this
A: Lessons learned
Question 360: You have completed the work described in the contract as per the
required specifications but the customer is complaining that the product is not what they
B: Restart the project and complete the work the way the
Question 361: Which of the following is not a term used to describe the buyer in a
contract?
A: Client
B: Entrepreneur
C: Service requestor
D: Prime contractor
Question 362: Which of the following is not a term used to describe the seller in a
contract?
A: Service provider
B: Vendor
C: Dealer
D: Contractor
Question 363: You and your project team are completing the process of producing
your procurement management plan and want to make sure that you have completed a
robust process and used all possible and appropriate inputs. Which of the following is not
A: Requirements documentation
C: Stakeholder register
D: Make-or-buy decisions
www.it-ebooks.info
CHAPTER 1 ■ QUESTIONS
92
Question 364: You are carrying out the procurement of services necessary for
your project. After consulting with your Organizational Process Assets, specifically the
procurement guidelines, which specify that you are to use the most commonly used
B: Firm-fixed-price
C: Fixed-price-incentive-fee
D: Cost-plus-incentive-fee
Question 365: You discover that there is a part of the project that contains some risk.
Your strategy to deal with this risk is to subcontract the work to an outside supplier by
the activity of the supplier to make sure that the supplier deals
B: You should make every effort to make sure that the supplier
C: You should make certain that the project team does not
Question 366: You are the project manager for a project that is well underway. You
are using a contractor that has agreed to a fixed-price contract that calls for a single, lump
sum payment on completion of the contract. The contractor’s project manager contacts
you and informs you that cash flow problems are making it difficult for the contractor to
pay employees and subcontractors. The contractor then asks you for a partial payment for
contractor.
part of a project. Which of the following contract types would your organization most
A: Fixed-price-incentive-fee contract
C: Firm-fixed-price
D: Cost-plus-incentive-fee