Professional Documents
Culture Documents
PM Glossary of Terms
PM Glossary of Terms
Activity An operation on a network which takes time (or other resources) and is indicated by an arrow.
Actual cost of work performed (ACWP) Cumulative actual cost (in money or man hours) of work
booked in a specific period.
Actual hours The man hours actually expended on an activity or contract over a defined period.
Advance payment bond Bond given in return for advanced payment by client.
Analytical estimates Accurate estimate based on build up of all material and labour requirements of
the project.
Backward pass A process for subtracting durations from previous events, working backwards from the
last event.
Banding The subdivision of a network into horizontal and vertical sections or bands to aid identification
of activities and responsibilities.
Beta (b) distribution Standard distribution giving the expected time, te=(a+4m+b)/6.
Budgeted cost of work scheduled (BCWS) Quantified cost (in money or man hours) of work scheduled
(planned) in a set time.
Budget hours The hours allocated to an activity or contract at the estimate or proposal stage.
Business case The document setting out the information and financial plan to enable decision makers
to approve and authorize the project.
1
Calendar Time scale of programme using dates.
Change control The process of recording, evaluating and authorizing project changes.
Change management The management of project variations (changes) in time, cost and scope.
Close out procedure The actions implemented and documents produced at the end of a project.
Close-out report The report prepared by the project manager after project close-out.
using a computer.
Conciliation The first stage of dispute resolution using a conciliator to improve communications and
understanding.
Contingency plan Alternative action plan to be implemented when a perceived risk materializes.
Counter-trade Payment made of goods or services with materials or products which can be sold to pay
for the items supplied.
Cost/benefit analysis Analysis of the relationship between the cost and anticipated benefit of a task or
project.
Cost breakdown structure (CBS) The hierarchical breakdown of costs when allocated to the work
packages of a WBS.
Cost code Identity code given to a work element for cost control purposes.
Cost control The ability to monitor, compare and adjust expenditures and costs at regular and
sufficiently frequent intervals to keep the costs within budget.
Cost performance index The ratio of the earned value (useful) cost and the actual cost.
Cost reporting The act of recording and reporting commitments and costs on a regular basis.
Cost variance The arithmetical difference between the earned value cost and the actual cost. This could
be positive or negative.
2
CPA Critical path analysis. The technique for finding the critical path and hence the minimum project
duration.
Critical activity An activity on the critical path which has zero float.
Critical path A chain of critical activities, i.e. the longest path of a project.
Dangle An activity which has a beginning node but is not connected at its end to a node which is part of
the network.
Discounted Cash Flow (DCF) Technique for comparing future cash flows by discounting by a specific
rate.
Distribution schedule A tabular record showing by whom and to whom the documents of a project are
distributed.
Dummy activity A timeless activity used as a logical link or restraint between real activities in a
network.
Event The beginning and end node of an activity, forming the intersection point with other activities.
Expediting Action taken to ensure ordered goods are delivered on time. Also known a progress chasing.
Feasibility study Analysis of one or more courses of action to establish their feasibility or viability.
Free float The time by which an activity can be delayed without affecting a following activity.
3
Forward pass A process for adding durations to previous event times starting at the beginning of a
project.
Front end the design and procurement stage of a project. This may or may not include the
manufacturing period of equipment.
Functional organization Management structure of specialist groups carrying out specific functions or
services.
Gantt chart A programming technique in which activities are represented by bars drawn to a time scale
and against a time base.
Graphical analysis A method for calculating the critical path and floats using a linked bar chart
technique.
Hammock An activity covering a number of activities between its starting and end node.
Herzberg’s theory the hygiene factors and motivators which drive human beings.
Histogram A series of vertical columns whose height is proportional to a particular resource or number
of resources in any time period.
Independent float the difference between free float and the slack of a beginning event.
Indirect cost Cost attributable to a project, but not directly related to an activity or group within the
project.
Input The information and data fed into a computer. Also required process information for a PM
Process
Interfering float the difference between the total float and the free float. Also the slack of the end
event.
Internal Rate of Return (IRR) the discount rate at which the Net Present Value is zero.
Key performance indicators (KPI) Major criteria against which the project performance is measured.
Lag the delay period between the end of one activity and the start of another.
Latest finish the latest time at which an activity can be finished without affecting subsequent activities.
4
Latest start the latest time at which an activity can be started without delaying the project.
Lead the time between the start of one activity and the start of another.
Leadership The ability to inspire and motivate others to follow a course of action.
Lester diagram Network diagram which combines the advantages of arrow and precedence diagrams.
Line of balance Planning technique used for repetitive projects, subprojects or operations.
Litigation Act of taking a dispute to a court of law for a hearing before a judge.
Logic links The link line connecting the activities of a precedence diagram.
Manual analysis The method for calculating floats and the critical path without the use of a computer.
Matrix The table of activities, durations and floats used in arithmetical analysis.
Matrix organization Management structure where functional departments allocate selected resources
to a project.
Method statement Narrative or graphical description of the methods envisaged to construct or carry
out selected operations.
Milestone slip chart Graph showing and predicting the slippage of milestones over the project period.
Negative float The time by which an activity is late in relation to its required time for meeting the
programme.
Network analysis The method used for calculating the floats and critical path of a network.
5
Organization breakdown structure (OBS) Diagrammatic representation of the hierarchical breakdown
of management levels for a project.
Output The information and data produced by a computer. Also result/deliverable of a PM process
Parametric estimates Estimates based on empirical formulae or ratios from historical data.
Pareto’s law Doctrine which shows that approx. 20% of causes create 80% of problems. Also known as
80/20 rule.
Performance bond Bond which can be called by client if contractor fails to perform.
PERT Programme Evaluation and Review Technique. Another name for CPA.
Post project review History and analysis of successes and failures of project.
Precedence network A method of network programming in which the activities are written in the node
boxes and connected by lines to show their interrelationship.
Product Breakdown Structure (PBS) Hierarchical decomposition of a project into various levels of
products.
Progress report A report which shows the time and cost status of a project, giving explanations for any
deviations from the programme or cost plan.
6
Project A unique set of co-ordinated and controlled activities to introduce change within defined time,
cost and quality/performance parameters.
Project life cycle All the processes and phases between the conception and termination of a project.
Project management The planning, monitoring and controlling of all aspects of a project.
Project management plan (PMP) A document which summarizes of all the main features encapsulating
the Why, What, When, How, Where and Who of a project.
Project manager The individual who has the authority, responsibility and accountability to achieve the
project objectives.
Project organization Organization structure in which the project manager has full authority and
responsibility of the project team.
Quality assurance Systematic actions required to provide confidence of quality being met.
Quality audit Periodic check that quality procedures have been carried out Quality control Actions to
control and measure the quality requirements.
Quality management The management of all aspects of quality criteria, control, documentation and
assurance.
Quality manual Document containing all the procedures and quality requirements.
Quality plan A plan that sets out the quality standards and criteria of the various tasks of a project.
Quality policy Quality intentions and directions set out by top management.
Quality programme Project specific document which defines the requirements and procedures for the
various stages.
Quality systems Procedures and processes and resources required to implement quality management.
Random numbering The numbering method used to identify events (or nodes) in which the numbers
follow no set sequence.
7
Resource smoothing The act of spreading the resources over a project to use the minimum resources at
any one time and yet not delay the project.
Responsibility matrix A tabular presentation showing who or which department is responsible for set
work items or packages.
Retention bond Bond given in return for early payment of retention monies.
Return on capital employed Profit (before interest and tax) divided by the capital employed given as a
%.
Return on Investment (ROI) Average return over a specified period divided by the investment given as a
%.
Risk The combination of the consequences and likelihood of occurrence of an adverse event or threat.
Risk analysis The systematic procedures used to determine the consequences or assess the likelihood
of occurrence of an adverse event or threat.
Risk identification Process for finding and determining what could pose a risk.
Risk management Structured application of policies, procedures and practices for evaluating,
monitoring and mitigating risks.
Risk management plan Document setting out strategic requirements for risk assessment and
procedures.
Risk register Table showing the all identified risks, their owners, degree of P/I, and mitigation strategy.
Schedule Performance Index The ratio of earned value cost (or time) and the planned cost (or time).
Schedule variance The arithmetical difference between the earned value cost (or time) and the planned
cost (or time).
Sequential numbering The numbering method in which the numbers follow a pattern to assist in
identifying the activities.
Situational leadership Adaptation of management style to suit the actual situation the leader finds
him/herself in.
Slack The period between the earliest and latest times of an event.
SMAC Site man hour and cost. The name of the computer program for controlling man hours in the
field.
8
Sponsor The individual or body who has primary responsibility for the project and is the primary risk
taker.
Statement of Work (SOW) Description of a work package which defines the project performance criteria
and resources.
Subcontract Contract between a main contractor and specialist subsidiary contractor (subcontractor).
Subjective estimates Approximate estimates based on ‘feel’ or ‘hunch’ Subnetwork A small network
which shows a part of the activities of a main network in greater detail.
Task The smallest work unit shown on a network programme (see also Activity).
Task data The attributes of a task such as duration, start and end date, resource requirement.
Task force Project organization consisting of a project team which includes all the disciplines and
support services under the direction of a project manager.
Teamwork The act of working harmoniously together in a team to produce a desired result.
Topological numbering A numbering system where the beginning event of an activity must always have
a higher number than the events of any activity preceding it.
Total float The spare time between the earliest and latest times of an activity.
Total quality management (TQM) Company wide approach to quality beyond prescriptive
requirements.
Updating The process of changing a network or programme to take into account progress and logic
variations.
Value engineering The systems used to ensure the functional requirements of value management are
met.
Value hours The useful work hours spent on an activity. This figure is the product of the budget hours
and the percentage complete of an activity or the whole contract.
9
Weightings The percentage of an activity in terms of man hours or cost of an activity in relation to the
contract as a whole, based on the budget values.
Work breakdown structure (WBS) Hierarchical decomposition of a project into various levels of
management and work packages.
Work package Group of activities within a specified level of a work breakdown structure.
10