Transport Connectivity and Asset Management Project Eastern Province
Transport Connectivity and Asset Management Project Eastern Province
Page 1 of 50
Monthly Progress Report August 2021
Table of Contents
TABLE OF CONTENT 2
LIST OF FIGURE 5
LIST OF TABLE 6
1. PROJECT DETAILS 7
2.2 Facilities 17
3. PROGRESS 20
4. QUALITY ASSURANCES 29
5. ESSH Progress 32
6. CONTRACTUAL SUBMISSIONS 35
7. WEATHER REPORT 37
8.1 Physical 38
8.2 Financial 42
10. ANNEXES 44
Page 3 of 50
Monthly Progress Report August 2021
Page 4 of 50
Monthly Progress Report August 2021
LIST OF FIGURES
Figure 1: Kokkuvil Saththurukondan Thannamunai Road, New Boundary Road.9
Figure 2: Vavunativu Ayithiyamalai Road & Komariya Mandur Road.9
Figure 3: Updated Physical S-Curve23
Figure 4: Updated Financial S-Curve26
Figure 5: Source Approved33
Figure 6: Weather Chart of May Month37
Figure 7: Base Failure Area Prime at Vavunathivu Ayiththiyamalayai Road CH 3+040 (Both Side)44
Figure 8: Asphalt Concrete Laying at Vavunathivu Ayiththiyamalayai Road CH 0+823 44
Figure 9: Checking Body Temperature before Start the Work45
Figure 10: Washig hand before the entering office45
LIST OF TABLES
Table 1.3.1: List of Roads.....................................................................................................................................10
Table 1.5.1 Quantities of Major works.................................................................................................................13
Table 2.2.1 Requirement vs. Appointed as at end of current month....................................................................15
Table 2.4.1 Labor distribution -May month.........................................................................................................17
Table 2.5.1 Summery of facilities provided.........................................................................................................17
Table 2.5.1 Details of Plants, Machineries and Vehicles availability..................................................................18
Table 2.6.1 monthly summery of materials in site...............................................................................................19
Table 3.2.2.1 Details of physical work progress- Quantities................................................................................25
Table 3.2.2.2 Details of physical work progress- Lengths...................................................................................25
Page 5 of 50
Monthly Progress Report August 2021
Page 6 of 50
Monthly Progress Report August 2021
1. PROJECT DETAILS
The Improvements of 21.625 Km length selected Provincial roads in Batticaloa District Transport Connectivity and Asset Management Project is funded by the World Bank (WB). The
area covered by the MPCLGS/PRDP/EP/02 road package consists of four numbers of roads that belong to the Road Development Department (RDD). Those roads surface consist of DBST
and concrete, as well as road surfaces, are moderate condition. In this project, all the DBST surfaces are going to improve as an asphalt surface and introduce some road furniture. Hence
the improvements of this road project will stimulate new economic opportunities while expanding industrial agricultural and commercial activities and other related services in the project
area. The benefits derived from this project will be multi-fold as the communities served by this project would benefit from improved, lower-cost, and easy transport services thereby
improving their access to economic opportunities and social services while preserving the nature. The Contractor’s site establishment has been almost completed, and the Engineer’s
facilities have been provided and are being maintained. The Residential Engineer’s office is being fully functioned at No-220, Hospital Road, Batticaloa.
Page 7 of 50
Monthly Progress Report August 2021
PARTICULERS INFORMATION
Project - Transport Connectivity & Asset Management Project - (TCAMP) - Provincial Road Development Project
Contract No - MPCLGS/PRDP/EP/02
Location - Batticaloa District in the Eastern Province
Total Length of rehabilitation - 21.3 km
No of Roads - 04 Nos
Funded by - World Bank (WB)
Employer - Ministry of Public Administration, Home Affairs, Provincial Councils
and Local governments
Engineer - Project Implementation Consultation (PIC) – Eastern Province
Contractor - Nawaloka Construction Company (Pvt) Ltd
Contractor’s Representative - W.A. Premaratne, No 10-12, Main Street. Ambalantota, 0740431538, nccep2pm@gmail.com
Page 8 of 50
Monthly Progress Report August 2021
Minimum Amount of IPC - 2% of the Accepted Contract Amount for Initial 3 Months period of the contract & 8%of the accepted Contract Amount thereafter
Figure 1: Kokuvil Sathurukondan Thannamunai Road, New Boundary Road. Figure 2: Vavunativu Ayithiyamalayai Road & Komariya Mandur Road
Page 9 of 50
Monthly Progress Report August 2021
4.5
2 Kokuvil Sathurukondan Thannamunai Road 4.625 0+000 – 4+625
0+000 – 6+999.4
3 Vavunativu Ayithiyamalayai Road 7.5 4.5
9+079.5 – 9.839.4
4 Komariya Mandur Road 7.0 0+000 – 7+000 4.5
Page 10 of 50
Monthly Progress Report August 2021
1. Providing and maintaining facilities for the Engineer consisting of but not necessarily limited to housing, offices, laboratory, transport vehicles, survey equipment, and
support staff etc. as per contract provisions.
1. Carry out cross-section surveys and submit drawings as directed by the Engineer.
2. Establish Benchmarks as directed by the Engineer.
3. Carry out site surveys as required and as requested by the Engineer.
1. Preparation and submission of Construction drawings for the approval of the Engineer as specified below,
Road Works
The bidder shall recognize the varied nature of the road, culvert and drainage rehabilitation works to be performed under the Contract and that the bid
Drawings PART 2- SECTION VII- (d) give typical details only of the rehabilitation scope of work. The proposed works will be based on the established center
line of the roads. For highway alignment, drainage and structures works, the Contractor shall undertake all necessary investigations and carry out the
design works conforming to Provincial Road Development Project standards and design guidelines provided by the Engineer.
All Construction Drawings shall be prepared by the Contractor based on the cross-section data, survey and design works carried out as per the standards and
guidelines given in PART 2- SECTION VII-( c) Appendix 11 of Special Specifications and as instructed by the Engineer. Construction Drawings will be approved
by the Engineer, in stages, based on the submission of same by the Contractor. The actual details of the road and drainage works and structures to be constructed and
any site instructions issued by the Engineer during the execution of the Contract shall be included in Construction Drawings to be prepared by the Contractor
Rehabilitation and improvement of Project Roads including but not limited to the following:
4. Strengthening of the carriageway and widening to the standard width where necessary and possible within the existing right-of-way.
5. Correcting pavement failures and construction of pavement overlays.
6. Correcting surface irregularities and cross fall with dense graded aggregate and surface treatment with Asphalt Concrete material or aggregate and hot bitumen treatments to
an acceptable standard.
7. Repairing, extending or constructing new cross drainage culverts and other drainage structures.
8. Installation of project name board, road signs and markings.
9. Provide necessary Krebs at the edge of paved road surface.
1. Construction of culvert and other structures and carrying out repair and rehabilitation of existing structures as directed by the Engineer.
1. Grade and generally maintain the road sections covered by the Contract during construction of the Works to ensure the safety of the public and residents along the roads and
minimum disruption to flow of traffic as agreed by the Engineer.
1. As may be required to be carried out for proper completion of the Works in all respects in accordance with the provisions of the Contract.
Page 12 of 50
Monthly Progress Report August 2021
sq.m
4 Solid Sodding 1000
sq.m.
5 Clearing and Grubbing for culverts 406
Nos.
6 Clearing & De silting and Repairing of Culverts 62
cu.m.
7 Concrete class B (grade 25/20) including formwork 160
Nos.
8 Precast concrete cover slabs 890
Nos.
9 Provide and erect Direction boards 105
Road marking continuous line, 100mm wide with reflectorized thermoplastic sq.m.
10 4650
material
cu.m.
11 Re-gravelling of existing shoulders 3550
Page 13 of 50
Monthly Progress Report August 2021
Page 14 of 50
Monthly Progress Report August 2021
CONTACT CONTACT
NO POSITION NO REQUIRED NO APPOINTED NAME OF THE PERSON
PHONE E-MAIL
W.A. Premaratne
1 Project Manager / CR 01 01 0740431538 nccep2pm@gmail.com
K.U.P.P.S. Jayanath
2 Site Engineers 02 01 0765674537 jayanathncc@gmail.com
Page 15 of 50
Monthly Progress Report August 2021
Total
No DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Working
Name Days
1 W.A.Premarathne 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 20
2 B.M.N.T.Jayathilaka 1 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 1 1 1 1 21
3 S.Thilak 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 16
4 U.Danushka 1 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 1 18
5 K.U.P.P.S.Jayanath 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 27
6 Y.A.Thilanka 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 22
7 J.A.Firnas 1 1 1 1 1 0 1 1 1 1 1 1 0 1 0 1 1 1 1 0 1 1 1 1 0 1 0 0 1 1 1 24
8 S.Nilakshana 1 1 1 1 1 0 1 1 1 1 1 1 0 1 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 1 1 15
9 V.Rohini 1 1 1 1 1 0 1 1 0 0 0 0 0 0 0 0 0 1 0 0 1 1 1 1 1 1 1 0 0 0 0 15
10 P.P.T.Anuradha 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 26
Page 16 of 50
Monthly Progress Report August 2021
NO CATEGORY TOTAL REQUIRED TOTAL ATTENDED FOR THE MONTH TOTAL % AGAINST
FOR THE MONTH REUIRED
MALE FEMALE
01 Skilled Labor
540 99 - 18.33 %
02 Semi-Skilled Labor
0 0 - 0.0 %
03 Helpers
0 0 - 0.0%
04 Unskilled Labor
600 315 - 52.5 %
05 TOTAL
1140 414 - 36.32 %
2.5 Facilities
2.5.1 Table Summery of facilities provided
1 Office Type A RE 1 0 0
Type B ARE 1 0 0
2 Vehicle Double cab D.P. D 1 1 1 Under Variation
Car CRE 1 1 1 Under Variation
3 Accommodation RE RE 1 0 0
ARE ARE 1 0 0 Not yet Requested
Page 17 of 50
Monthly Progress Report August 2021
Poya day
Month
Sun day
Sun day
Sun day
Sun day
July 2021
(A). LABOUR
Total
DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Unit
Quantity
Skilled 2 3 2 0 2 1 0 1 1 10 9 12 0 1 2 2 11 9 9 9 1 1 0 1 1 9 0 0 0 0 0 M. Days 99
Un Skilled 5 7 9 0 8 8 9 8 9 17 17 17 9 8 9 7 21 22 22 22 8 8 0 8 8 21 0 7 5 8 8 M. Days 315
Poya day
Sun day
Sun day
Sun day
Sun day
(B). Equipment
Total
DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 29 30 Unit
Quantity
Bolero Cab 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 Days 28
JCB 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Truck (3 Cube) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Truck (1 Cube) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Excavator 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Roller (1 Ton) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Roller (4 Ton) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Roller (10 Ton) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Roller (Static) 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 0
Compressor 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 8
Hand Rammer 1 1 1 0 1 1 0 1 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 Days 10
Water bowser 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 8
Bitumen Distributor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Days 0
Asphlat Paver 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 8
Compactor PTR 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 8
Finishing PTR 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 1 1 1 1 0 0 0 0 0 1 0 0 0 0 0 Days 8
Page 18 of 50
Monthly Progress Report August 2021
OPENING
RECEIVED BALANCE AS
REQUIRED BALANCE AS AT USED DURING TOTAL
TYPE OF DURING AT END OF
UNIT MATERIAL FOR 1ST OF REPORTING RECEIVED TO
MATERIAL REPORTING REPORTING
REPORTING MONTH REPORTING MONTH DATE
MONTH MONTH
MONTH
3 CSS 1 L 0 0 0 0 0 400
Page 19 of 50
Monthly Progress Report August 2021
3 PROGRESS
3.1 Updated Master plan
Page 20 of 50
Monthly Progress Report August 2021
Page 21 of 50
Monthly Progress Report August 2021
Page 22 of 50
Monthly Progress Report August 2021
Page 23 of 50
Monthly Progress Report August 2021
Page 25 of 50
Monthly Progress Report August 2021
Submission of
Length Approval of
Road Center Line Initial LS /CS design Cross Approval Given
(Km) Vertical Profile
sections
Kokkuvil Saththurukondan
4.625 Completed Submitted Granted Submitted Approved
Thannamunai Road
Komariya Mandur Road 7.0 Completed Submitted Granted Submitted Partially Approved
ITEM
Planned Complete Complete
Length Planned Length Planned Planned
Weightage Length length Progress Weightage length Progress
(Km) Progress (Km) Length (Km) Progress
(Km) (Km) (Km)
Asphalt 2.5 0.67 1.1 44 % 2.5 100 % 4.590 0.67 2.5 54.5 % 4.59 100%
Culverts
1 0.05 0 100 % 1 60% 0 0.05 0 0% 0 0%
(Nos)
Page 26 of 50
Monthly Progress Report August 2021
ITEM
Planned Planned Complete
Length Planned Complete Length Planned
Weightage Length Progress Weightage Length length Progress
(Km) Progress length (Km) (Km) Progress
(Km) (Km) (Km)
Page 27 of 50
Monthly Progress Report August 2021
ACTUAL BILL
EXPENDITURE
SUBMISSION ACTUAL PAID DISBURSEMENT ACTUAL BILLS ACTUAL BILLS PAID
PLANNED FOR
FOR THIS THIS MONTH PLANNED TODATE SUBMITED TODATE TODATE REMARKS
THIS MONTH
MONTH (Rs) (Rs) (Rs) (Rs)
(Rs)
(Rs)
LIST OF BILLS
DATE APPLLIED AMOUNT DATE CHECK
NO SUBMITED AS AT REMARKS
SUBMITED AMOUNT (Rs) RECEIVED (Rs) RECIVED
TODATE
1 IPA -1 26/12/2019 15,970,517.55 15,970,517.55 31/12/2019 -
2 IPA -2 22/06/2020 33,687,040.25 25,746,169.88 22/07/2020 -
3 IPA -3 07/10/2020 30,618,288.53 7,930,837.61 10/11/2020 -
4 IPA -4 08/12/2020 41,419,503.70 36,487,205.40 22/12/2020 -
5 IPA -5 26/03/2021 42,872,116.61 37,463,636.01 07/04/2021 -
6 IPA -6 27/05/2021 38,729,160.64 22,867,520.16 01/06/2021 -
7 IPA -7 08/07/2021 25,201,603.23 Retained due to IPC Minimum Amount
8 IPA -8 15/08/2021 29,860,849.05 - - On Processing
ENGINEER’S ENGINEER’S
RATE AMOUNT ENGINEER’S
DATE DATE PAY PAY RECOMMEND REMARK
NO DESCRITION QUANTITY APPLIED APPLIED RECOMMEND
SUBMITED RECOMEND ITEM UNIT ED AMOUNT S
(Rs) (Rs) ED RATE (Rs)
ED (Rs)
03 Name Board 05/03/2020 29/04/2020 1.32 Rs 51,000.00 55,000.00 440,000.00 51,000.00 408,000.00 -
4 QUALITY ASSURANCES
Page 30 of 50
Monthly Progress Report August 2021
NCR raised 1
Page 31 of 50
Monthly Progress Report August 2021
Page 32 of 50
Monthly Progress Report August 2021
Page 33 of 50
Monthly Progress Report August 2021
5 ESSH progress
Table 5.1 Detail of ESSH plan implementation
%
ESSH ITEM % PLANNED
ESSH ITEM PARTICULERS OF TOTAL WORK COMPLET % PLANNED % COMPLETED
REFERENCE AS PER THIS REMARKS
CATEGORY ACTIVITY QUANTITY ED THIS TODATE TODATE
AGREEMENT MONTH
MONTH
Recruitment of ESSH Officer 15 Months 6.67 6.67 100 100 -
Submission of ESRM Plan 1 0 0 100 100 -
Submission of Traffic management plan 1 0 0 100 100 -
Site office establishment 15 Months 6.67 6.67 100 100 -
BEFORE
Approval for sources of material
CONSTRUCTION
a. Gravel / borrow pits/ sand 1 0 0 100 100 -
b. Rubble and aggregates / ABC 1 0 0 100 100 -
c. Bitumix, Asphalt 1 0 0 100 100 -
d. Water for construction 1 0 0 100 100 -
Site approval for Disposal of
3 0 0 100 100 -
debris/construction wastes
Mitigation of soil erosion 15 Months 6.67 6.67 100 100 -
Action against Contamination of water
15 Months 6.67 6.67 100 100 -
and water bodies with fuel and oil etc.
Action against Siltation into water bodies 15 Months 6.67 6.67 100 100 -
Actions for Alteration of Drainage paths/
DURING ENVIRONMENTAL 15 Months 6.67 6.67 100 100 -
Flooding
CONSTRUCTION COMPLIANCE Actions against Loss or Damage to Trees
15 Months 6.67 6.67 100 100 -
and Vegetation
Air Pollution 100 100
a. Actions against Mitigation of dust 15 Months 6.67 6.67 100 100 -
b. Actions against Emission from
construction Vehicles, Equipment and 15 Months 6.67 6.67 100 100 -
Machinery
Page 34 of 50
Monthly Progress Report August 2021
Page 35 of 50
Monthly Progress Report August 2021
NUMBER OF
NOMBER OF NOMBER OF NUMBER OF
COMPLAINS BRIEF DESCRIPTION
TYPE OF COMPLAIN COMPAINS ACTION TAKEN COMPLAINS RECEIVED COMPLAINS SOLVED
RECIEVED THIS OF COMPLAINS
SOLVED TODATE TODATE
MONTH
0 0 - - - -
Environmental
0 0 - - - -
Social Safeguard
0 0 - - - -
Health
0 0 - - - -
Livelihood
Page 36 of 50
Monthly Progress Report August 2021
6 CONTRACTUAL SUBMISSIONS
Table 6.1 Contractual submission for June Month.
Page 37 of 50
Monthly Progress Report August 2021
Page 38 of 50
Monthly Progress Report August 2021
7 WEATHER REPORT
Page 39 of 50
Monthly Progress Report August 2021
Page 40 of 50
Monthly Progress Report August 2021
Page 41 of 50
Monthly Progress Report August 2021
Page 42 of 50
Monthly Progress Report August 2021
Page 43 of 50
Monthly Progress Report August 2021
Page 44 of 50
Monthly Progress Report August 2021
8.2 Financial
Financial forecast for planned work for next month = 45.5 Million
Page 45 of 50
Monthly Progress Report August 2021
Figure 7: Base Failure Area Prime at Vavunathivu ………… Figure 8: Asphalt Concrete Laying at Vavunathivu …………
Ayiththiyamalayai Road CH 3+040 (Both Side) Ayiththiyamalayai Road CH 0+823
Page 46 of 50
Monthly Progress Report August 2021
10 ANNEXES
10.1 Copies of approved test reports
Asphalt Core Testing and report of preparation is ongoing
Page 47 of 50
Monthly Progress Report August 2021
Figure 9: Checking Body Temperature before Start the Work. Figure 10: Washing hand before the entering Office.
Page 48 of 50
Monthly Progress Report August 2021
Page 49 of 50
Monthly Progress Report August 2021
Page 50 of 50