Professional Documents
Culture Documents
Rosu Marius - Golden Gate Bridge
Rosu Marius - Golden Gate Bridge
Rosu Marius-Alexandru
UTCB-FILS-SE year II
INTRODUCTION
The Golden Gate Bridge is a
suspension bridge spanning the Golden
Gate, the one-mile-wide (1.6 km)
strait connecting San Francisco Bay
and the Pacific Ocean. The structure
links the U.S. city of San Francisco,
California—the northern tip of the San
Francisco Peninsula—to Marin County,
carrying both U.S. Route 101 and
California State Route 1 across the
strait. It also carries pedestrian and
bicycle traffic and is designated as
part of U.S. Bicycle Route 95. Being
declared one of the Wonders of the
Modern World by the American
Society of Civil Engineers, the bridge
is one of the most internationally
recognized symbols of San Francisco
and California. It was initially
designed by engineer Joseph Strauss
in 1917.
The Frommer's travel guide describes
the Golden Gate Bridge as "possibly
the most beautiful, certainly the most
photographed, bridge in the world."
At the time of its opening in 1937, it
was both the longest and the tallest
suspension bridge in the world, with a
main span of 1,280 m and a total
height of 227 m.
SUSPENSION BRIDGE
A suspension bridge is a type of bridge
in which the deck is hung below
suspension cables on vertical suspenders.
The first modern examples of this type of
bridge were built in the early 1800s.
Simple suspension bridges, which lack
vertical suspenders, have a long history
in many mountainous parts of the world.
The Golden Gate Bridge has cables
suspended between towers, with vertical
suspender cables that transfer the live
and dead loads of the deck below, upon
which traffic crosses. This arrangement
allows the deck to be level or to arc
upward for additional clearance.
Typically, this type of bridge is
constructed without a falsework.
The suspension cables must be anchored
at each end of the bridge, since any
load applied to the bridge is
transformed into a tension in these main
cables. The main cables continue beyond
the pillars to deck-level supports, and
further continue to connections with
anchors in the ground. The roadway is
supported by vertical suspender cables
or rods, called hangers.
ADVANTAGES
• A suspension bridge can be made out of simple materials such as wood and common wire rope.
• Longer main spans are achievable than with any other type of bridge.
• Less material may be required than other bridge types, even at spans they can achieve, leading to a
reduced construction cost.
• Except for installation of the initial temporary cables, little or no access from below is required during
construction and so a waterway can remain open while the bridge is built above.
• They may be better able to withstand earthquake movements than heavier and more rigid bridges.
• Bridge decks can have deck sections replaced in order to widen traffic lanes for larger vehicles or add
additional width for separated cycling/pedestrian paths.
DISADVANTAGES
• Considerable stiffness or aerodynamic profiling may be required to prevent the bridge deck vibrating
under high winds.
• The relatively low deck stiffness compared to other (non-suspension) types of bridges makes it more difficult
to carry heavy rail traffic in which high concentrated live loads occur.
• Some access below may be required during construction to lift the initial cables or to lift deck units. That
access can often be avoided in cable-stayed bridge construction.
HISTORY
Before the bridge was built, the only
practical short route between San Francisco
and what is now Marin County was by boat
across a section of San Francisco Bay. A
ferry service began as early as 1820, with
a regularly scheduled service beginning in
the 1840s for the purpose of transporting
water to San Francisco.
VIDEO: https://www.pbs.org/video/american-
experience-building-bridge-ocean/
THE TOWERS OF GOLDEN
GATE BRIDGE
The first 227 m tower began to rise in
Nov. 1933. Prefabricated sections were
fit into place and then joined together by
four-man rivet gangs. The heater was the
boss; he brought rivets to the right
temperature on a small forge, then tossed
them to catchers with metal cans.
VIDEO: https://www.pbs.org/video/american -
experience-towers-golden-gate-bridge/
STATISTICS & DATA
LENGTH, WIDTH, HEIGHT, WEIGHT
• Total length of Bridge including approaches from abutment to abutment is 2,737 m.
• Total length of Bridge including approaches from abutment to abutment, plus the distance to the Toll Plaza, is 2,788 m.
• Length of suspension span including main span and side spans is 1,966 m.
• Length of main span portion of suspended structure (distance between towers) is 1,280 m. Until 1964, the Golden Gate Bridge had the longest suspension
bridge main span in the world.
• Width of Bridge is 27 m.
• Width of sidewalk is 3 m.
• Original combined weight of Bridge, anchorages, and approaches is 894,500 tons (811,500,000 kg).
• Total weight of Bridge, anchorages, and approaches (1937) is 894,500 tons (811,500,000 kg).
• Total weight of Bridge, anchorages, and approaches (1986)* is 887,000 tons (804,700,00 kg*).
• Weight of Bridge, excluding anchorages and approaches, and including the suspended structure, main towers, piers and fenders, bottom lateral system and
orthotropic redecking (1986) is 419,800 tons (380,800,000 kg *).
* The total bridge weight listed for 1986 includes the reduction in weight due to the redecking in 1986. The weight of the original reinforced concrete deck and its
supporting stringers was 166,397 tons (150,952,000 kg). The weight of the new orthotropic steel plate deck, its two inches of epoxy asphalt surfacing, and its
supporting pedestals is now 154,093 tons (139,790,700 kg). This is a total reduction in weight of the deck of 12,300 tons (11,158,400 kg), or 1.37 tons (1133 kg)
per lineal foot of deck.
BRIDGE DEFLECTION, LOAD CAPACITY
• At midspan, the maximum downward deflection (or the distance the Bridge was built to move downward) is 3.3 m. The maximum upward deflection is 1.8 m.
• Live load capacity per lineal foot is 4,000 lbs (1,814.4 kg).
• As an example of how the Bridge is built to move, during the winter storms in 1982, the main span bowed approximately 1.8 to 2.1 m.
• The three maximum deflections noted above at the center of the suspension bridge are due to the following loading conditions:
1. The transverse deflection is due to a sustained transverse wind load. The maximum transverse movement of 8.4 m is based on the maximum allowable longitudinal
movement of the wind locks at the support towers;
2. The maximum downward deflection is due to a condition with maximum live load on the center span, no live load on the side spans and maximum design temperature
to elongate the main cables;
3. The maximum upward deflection is due to a condition opposite to condition 2 above, with maximum live load on side spans, no live load on center span and minimum
design temperature to shorten the cable length.
MAIN TOWER STATS
• The Golden Gate Bridge has two main towers that support the two main cables.
• The height of a tower above water is 227 m, were the world's tallest on a suspension bridge until 1993.
• The load on each tower from main cables is 61,500 tons (56,000,000 kg).
• To build south tower pier to support the south tower, construction workers pumped 35.6 million liters of water out of the fender that was constructed first.
MAIN CABLE STATS
• The Golden Gate Bridge has two main cables which pass over the tops of the two towers and are secured at either end in giant anchorages. The galvanized carbon steel wire
comprising each main cable was laid by spinning the wire, using a loom-type shuttle that moved back and forth as it laid the wire in place to form the cables. The spinning of
the main cable wires was completed in 6 months and 9 days.
• The main cables rest on top of the 227 m main towers in huge steel castings called saddles.
• Total length of galvanized steel wire used in both main cables is 129,000 km.
• Number of galvanized steel wires in one main cable that are 5 mm in diameter is 27,572.
• Number of bundles or strands of galvanized steel wire in one main cable is 61.
• Weight of both main cables, suspender cables, and accessories is 24,500 tons (22,200,000 kg).
• The Golden Gate Bridge has 250 pairs of vertical suspender ropes that are spaced 15 m apart across both sides of the Bridge.
Each suspender rope is 40 cm in diameter. All of the ropes were replaced between 1972 and 1976, with the last rope replacement completed on May 4, 1976.
CONCRETE QUANTITIES
• On December 1, 1951, a windstorm revealed swaying and rolling instabilities of the bridge. In 1953 and 1954, the bridge was retrofitted with lateral and diagonal
bracing that connected the lower chords of the two side trusses. This bracing stiffened the bridge deck in torsion so that it would better resist the types of twisting that had
destroyed the Tacoma Narrows Bridge in 1940.
• The original bridge used a concrete deck. Salt carried by fog or mist reached the rebar, causing corrosion and concrete spalling. From 1982 to 1986, the original bridge
deck, in 747 sections, was systematically replaced with a 40% lighter, and stronger, steel orthotropic deck panels, over 401 nights without closing the roadway
completely to traffic. The roadway was also widened by two feet, resulting in outside curb lane width of 11 feet, instead of 10 feet for the inside lanes. This deck
replacement was the bridge's greatest engineering project since it was built and cost over $68 million.
• Although the Golden Gate Bridge suffered no observed damage from the 7.1 magnitude Loma Prieta earthquake, in 1989, since the epicenter was located some 60
miles to the south, the earthquake became a catalyst for the extensive seismic retrofit program. In 1996, the three construction phases were established as follows:
Phase 2 (2001-2008): Retrofit the San Francisco (south) Approach Viaduct, San Francisco (south) Anchorage Housing, Fort Point Arch, and Pylons S1 and S2
Phase 3A and 3B (2008-2013): Retrofit the Main Suspension Bridge and Marin (north) Anchorage Housing
BRIDGE MAINTENANCE
The caretakers of the Golden Gate Bridge include engineers and architects who had a vision to create such an incredible landm ark, rugged individuals
who built this one-of-a kind masterpiece, and skilled crafts people and engineers who have cared for the Bridge since opening da y in 1937. This
revered and rugged group of workers battle wind, sea air and fog, often suspended high above the Golden Gate Strait, to repai r corroding steel.
Ironworkers replace corroding steel and rivets, make small fabrications for use on the Bridge, and assist painters with their rigging. Ir onworkers also
remove plates and bars to provide access for painters to the interiors of the columns and chords that make up the Bridge.
Painters prepare all Bridge surfaces and repaint corroded areas. Painting the Golden Gate Bridge is an ongoing task and the primary ma intenance
job. The paint protects the Bridge from the high salt content in the air which rusts and corrodes the steel components.
Operating engineers and mechanics ensure that all equipment and vehicles are in good repair.
Electricians maintain toll equipment and all electrical components of the Bridge and operate the fog horns.
The Streets and Grounds team keeps the surrounding areas of the Bridge in proper repair and attractive for the over 10 million visitors each year.
Laneworkers assist Roadway Service Operators by configuring yellow roadway cones for various lane configurations.
Roadway Service Technicians assist disabled vehicles on the Bridge and its approaches, respond to all vehicle accidents and vehicle fires, and
operate the Barrier Machine to ensure the Bridge is in the proper configuration for morning and afternoon commutes.
Service operators assist disabled vehicles on the Bridge and its approaches. Tow service trucks are on site 24 -hours a day, ready to respond to any
emergency.
The Bridge Captain oversees the activities of the toll office and roadway operations, coordinating an around -the-clock workforce to ensure the smoo th
flow of traffic. There have been 10 Bridge Captains since the Bridge opened in 1937.
Bridge Sergeants and Bridge Lieutenants respond to inquiries, accidents, and emergencies. In fact, to date, two babies have been born at the toll
plaza! A team of Bridge Patrol Officers, who also report to the Bridge captain, are responsible for Bridge security.
PRESENTATION TITLE 29
REFERENCES
h t t p s : / / e n . w i k i p e d i a . o r g / w i k i / G o l d e n _ G a t e _ B r i d ge
h t t p s : / / e n . w i k i p e d i a . o r g / w i k i / S u s p e n s i o n _ b r i d ge
h t t p s : / / w w w. g o l d e n ga t e. o r g / b r i d ge / b r i d ge - m a i n t e n a n c e /
h t t p s : / / w w w. g o l d e n ga t e. o r g / b r i d ge / h i s t o r y - r e s e a r c h / b r i d ge - c o n s t r u c t i o n / c o n c e p t - fo r- a - b r i d ge /
h t t p s : / / w w w. g o l d e n ga t e. o r g / b r i d ge / h i s t o r y - r e s e a r c h / b r i d ge - c o n s t r u c t i o n / b r i d ge - d e s i g n /
h t t p s : / / w w w. g o l d e n ga t e. o r g / b r i d ge / h i s t o r y - r e s e a r c h / s t a t i s t i c s - d a t a / d e s i g n - c o n s t r u c t i o n - s t a t s /
h t t p s : / / w w w. g o l d e n ga t e. o r g / d i s t r i c t / d i s t r i c t - p ro j e c t s / s e i s m i c - r e t ro f i t /
VIDEO:
https://www.youtube.com/watch?v=OC5C9a2udjo
https://www.youtube.com/watch?v=FKU1PTyHtbM
PRESENTATION TITLE 30
THANK YOU