Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Technical Paper

Fernando Stucchi* DOI: 10.1002/suco.201600086


Marcelo Coelho Ungaretti
Gilson Fujii
Hugo Corres Peiretti
Sergio Doniak
José Soriano Martin

Corinthians Arena –
2014 World Cup, design and construction
This paper describes the design and construction of the concrete
structures of the Corinthians Arena built for the 2014 World Cup.
Due to many constraints, the structure was designed, essentially,
with prefabricated structural concrete members, some specific
elements were designed with structural concrete cast in situ, and
some areas, with special construction problems, were designed
with composite steel–concrete structures.
Keywords:  arena, precast concrete, design, construction, vibration,
connections

1 Introduction

The construction of the stadiums for the 2014 Brazil


World Cup was developed at a very fast rate. Some of
them had been completed and operational since the Con-
federations Cup in 2013. The financial system used for Fig. 1.  Corinthians Arena in São Paulo
each stadium is specific and aims to consider very differ-
ent conditions. The design projects of all these infrastruc- pending on the regional capacity to produce prefabricated
tures were developed to fulfil strict requirements imposed elements and assemble them (at the time of the construc-
by FIFA (Football Stadiums – Technical Recommenda- tion of the arenas, there was intensive development of
tions and Requirements [1, 2]) and, at the same time, to be buildings and infrastructure, and the availability of the
able to offer different and valuable uses after the event, appropriate equipment, such as cranes, was also a condi-
trying to avoid potential “white elephants” at the end of tioning factor), a major or minor percentage of industrial-
the competition. This important commitment has given ized elements were adopted. In some cases only the slabs
rise to multi-use buildings, which could be used as football were prefabricated, using hollow core slabs. In other cases
arenas during the World Cup, and as sport or cultural in- more than 90 % of the construction was prefabricated.
stallations, or, in certain cases, as shopping malls, after the This paper describes the Corinthians Arena in
event. It may be said that the great challenge of hosting a Itaquera (Fig. 1), São Paulo. In this example, piles, col-
World Cup is to secure economic benefits for the host na- umns, beams, slabs, grandstands and grandstand beams
tion. were prefabricated. Some elements were prefabricated in
Additionally, there were several other crucial con- factories, and others, the majority, were prefabricated on
straints: the construction schedule was very tight, the fact site. In fact, a prefabrication plant was actually installed
that FIFA has imposed the green guide certification for all on site. Additionally, some areas, with an irregular geom-
World Cup projects, and very strict cost-control condi- etry or with special structural requirements, such as the
tions were imposed due to the financial crisis and Brazil- shear walls, were cast in situ.
ian public opinion. Under these conditions, many of the The roof was designed in steel according to the
arenas have been designed considering prefabrication shape defined in the architectural design. The facade area
(according to Brazilian standard NRB9062:2006 [3]). De- of the east building is a huge LED screen of 2,950 m2 and
the facade area of the west building is composed of a large
glass puzzle with a surface of 5,136 m2.
* Corresponding author: frstucchi@gmail.com
2 General description of Corinthians Arena
Submitted for review: 03 May 2016; revision: 02 July 2016; accepted for
publication: 12 July 2016. Discussion on this paper must be submitted within
The Corinthians Arena, located in the eastern part of the
two months of the print publication. The discussion will then be published in
print, along with the authors’ closure, if any, approximately nine months after city of São Paulo in Itaquera, has a final seating capacity
the print publication. of 48,000 spectators (after all the necessary adjustments

698 © 2016 Ernst & Sohn Verlag für Architektur und technische Wissenschaften GmbH & Co. KG, Berlin · Structural Concrete 17 (2016), No. 5
F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

um should be able to adequately receive the 32 heads of


state who were representing the countries participating in
the 2014 World Cup, as well as housing more than 5,000
journalists.
The stadium is a long-time dream come true for the
Sports Club Corinthians Paulista. For several years, one of
the most popular football teams in Brazil, it needed its
own home. The project was built through a private con-
tract between Corinthians and Odebrecht (the contrac-
tor). The works began on 30 May 2011 and finished in
May 2014.
The architect Anibal Coutinho, from CDCA Archi-
tects, designed the arena. One of the key points of the ar-
chitectural design was its adaptation of the ground area in
such a way as to accommodate the differences in levels
Fig. 2.  Internal view of the arena and therefore minimize earthworks.
The football pitch is set in a north–south direction.
are implemented – see Fig. 2). For the opening ceremony In the east wing, two levels of grandstands are placed. In
of the 2014 Brazil World Cup, the stadium had to increase the north and south parts (Fig. 3), there is only one level
its current seating capacity by 17,000 seats. This increase of grandstands (during the World Cup a second level of
in seating capacity was provisional and its removal began temporary seats was provided). The major grandstands are
following the end of the World Cup. These provisional placed in the east and west wings (Fig. 4). In the west
seats were supported by a steel structure to facilitate their wing, two levels of grandstands and two levels of cabins
assembly and subsequent disassembly. Thus, the final ca- are placed. For practical purposes, all the necessary ser-
pacity of the stadium during the World Cup was that of vices for the stadium are located in the west wing.
65,000 spectators. EGT Engenharia and Fhecor Consulting Engineers
The complex covers an area of approximately (concrete and steel design of the buildings) and Werner
200,000 m2 and has more than 2,800 parking spaces Sobek Structural Engineers (steel design of the roof) car-
(about 1,000 inside the stadium and 1,800 located around ried out the structural design of the stadium. Each con-
the arena). Additionally, it was established that the stadi- sultant tried to achieve the best solution in accordance

Fig. 3.  North-south cross section

Fig. 4.  East-west cross section

Structural Concrete 17 (2016), No. 5 699


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 5.  Pile driving Fig. 7.  Cast in situ pile caps

with the main constraints of cost and time. Furthermore, 3 Foundations and retaining walls
in order to meet all the FIFA requirements, several meet-
ings were necessary to satisfy all parties involved in the According to the geotechnical conditions, it was decided
project: contractor, structural designers, architects and, of that the best solution for foundations consisted of precast
course, the final client: Sports Club Corinthians Paulista. driven piles (Fig.  5). Precast piles of ∅ 0.50 m and
The structure below the roof level is made mainly of ∅ 0.70 m diameter were used to support vertical loads of
structural concrete. Practically 80 % of this structure is 1500 kN and 2500 kN, respectively. In some cases, for
precast whereas the remaining parts are cast in situ or example when a tension support is necessary, other types
made of composite elements, with steel girders and top of excavated piles were applied. More than 4,000 founda-
concrete slabs. Composite construction was used only tion piles were executed with a total length of 55,500 m
when construction conditions prevented a concrete solu- over a period of six months (the initial estimate was nine
tion (for example, when architectural design demanded months).
longer spans without columns). The roof consists of a The foundation system comprises not only vertical
membrane supported by a steel structure. The facades piles, as can be seen in Fig. 6, but also inclined piles that
were designed as important characteristics of this arena. were placed in order to support horizontal forces. These

Fig. 6.  Foundation layout of core piles (arrows indicate inclined piles according to the respective orientation)

700 Structural Concrete 17 (2016), No. 5


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 8.  Plan view and cross section of pile cap for six piles

Fig. 9.  Execution of pile caps

horizontal forces come from shear walls, which have two


main functions: to provide static stability to the building
when subjected to horizontal forces from roof, wind, tem-
perature and shrinkage effects; and to provide sufficient Fig. 10.  West wing section – crane position beside the wall
horizontal stiffness to control the dynamic effects mainly
due to the movement of the crowd (bobbing or jumping). (other solutions, such as a slab over piles, were studied,
In addition, the tie beams between the pile caps of but were found to be not as efficient). The wall is 650 m
one or two piles were always cast in situ, as well as the long, and a construction period of six months was neces-
pile caps themselves (see Figs. 7, 8 and 9). sary to complete it. During the assembly of this retaining
Due to the exceptionally poor soil conditions in cer- wall, several layers of a polyester mesh were applied (this
tain zones in the west wing, it was necessary to substitute system is named “terramesh”, see Figs. 11 and 12).
the grade slab with a slab supported directly on piles.
In the west wing there was a 15.00 m long gap be- 4 Structural solution
tween the lower level of the underground and the en- 4.1 Main structural challenges
trance level of the arena. Furthermore, the cranes that as-
sembled the roof needed to be positioned next to the edge Several issues were considered to decide the structural
of the wall (see Fig. 10); causing a huge horizontal pres- solution and the construction method. However, the main
sure against it (the heaviest crane was able to raise constraints were the short deadline to deliver the stadium
13,500 kN and had a vertical pressure on the soil of and the comfort of the users. On the one hand, precast
0.5 MPa). In order to address this problem, a retaining concrete was the solution adopted to accelerate the con-
wall (see Figs. 11, 12 and 13) 15.00 m high was adopted struction works. On the other hand, monolithic connec-

Structural Concrete 17 (2016), No. 5 701


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 11.  View of Terramesh execution Fig. 13.  Precast grandstands’ prefabricated beams on site

composed of hollow core precast slabs of 20 cm thickness


+ 6 cm of topping for the normal spans of 7.00 m, and
25 cm thickness of hollow core slabs + 6 cm of topping for
the larger spans.
In specific areas, where the structural behavior de-
mands a more monolithic solution, such as close to the
cores, or where due to specific constraints it was not pos-
sible to use precast slabs, in situ concrete slabs or compo­
site solutions were employed.
Cast in situ cores were implemented to resist hori-
zontal forces, for example due to wind loads, to improve
the dynamic behavior (according to recommendations in
“Vibrations Problems in Structures – Practical Guide-
lines” [5]) of the entire structure and to stabilize the steel
roof, which covers the four stands of the arena.
Fig. 12.  View of Terramesh execution The cores were executed using climbing formworks.
The connection between the core and the slabs, at the dif-
ferent levels, was solved using special reinforcement details.
tions were used to satisfy several dynamic analyses carried
out to guarantee the comfort of the spectators considering 4.1.2 Dynamic analysis
vibration (following ISO 2632-1 [4] recommendations).
The crowd action in a multi-use stadium may consist of
4.1.1 Structural solution dancing, running, jumping and clapping. These activities
are enhanced when accompanied by music, due to a
Considering the important amount of prefabricated ele- greater synchronization among people. The structural de-
ments required, CPI, the prefabricator, installed a 7,500 m2 sign should carefully consider these aspects, because the
prefabrication plant on site. This company regularly em- facility is also expected to be used for rock concerts.
ployed 45 people during the day shift, and 15 for the night In order to perform the dynamic analysis, the dy-
shift. In the peak periods, this workshop produced around namic loading of spectators (that excites the structure) is
3,500 elements and hired up to 150 workers. Columns, defined by a function Fp(t), represented by a Fourier series
beams, grandstands and grandstand beams were produced composed of the sum of three harmonic components as
on site (see Fig. 13). This on-site plant saved money and follows:
time, because outside factories would have encountered
∑i=1 G ∝i sen(2π fpt − ∅i)
n
problems in transporting all these concrete elements Fp(t) = G +
through the congested highways of São Paulo to reach
Corinthians Arena. where: G is the standard weight of the crowd; ∝i is the ith
In addition, other precast elements were supplied by “generated load factor” defining the load generated by ac-
local prefabricators, such as piles and hollow core slabs. tivity of the crowd; fp is the fundamental frequency of the
The structural solution (see Fig. 14) is composed of crowd activity in Hz; t is the time in seconds; and ∅i is the
frames, in the east-west direction, made of precast col- phase difference of the ith harmonic.
umns and beams. The frames are separated every 7.50 m, The recommended values G ∝i used, according to the
except at the edges on which they are placed every activity represented, are shown in Table 1. IStructE Guide
10.50 m. In the north-south direction, the structure is [6] and a Brazilian researcher, Rodrigues [7], suggest differ-

702 Structural Concrete 17 (2016), No. 5


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 14.  Layout of frames, slabs and cast in situ cores

Fig. 15.  Finite element model of the western part of the stadium

ent parameters for the harmonic numbers (activity crowds). Figure 16 shows a table with the difference between
Rodrigues’ [7] research was based upon local measure- the dynamic results (acceleration on determined points)
ments in Brazilian stadiums (with no seats in grandstands). considering the IStructE Guide [6] and Rodrigues [7].
A 3D finite element model (see Fig. 15) was devel- The  difference between the results obtained with IS-
oped to evaluate the acceleration on critical points of the tructE Guide and Rodrigues is quite evident. This differ-
structure. ence could be based on the fact that the arenas studied
According to this model and taking into account by Rodrigues [7] in Brazil had no seats whereas the Euro-
the dynamic behavior of the crowd, it was possible to pean ones, studied in [6], did. With the presence of num-
define the dimensions of main structural elements bered seats, and according to the distance between seats
(cores, shear walls, columns and beams), in order to re- [1, 2], the available space to crowd movements is re-
spect the limits of comfort imposed by ISO standards. duced, not allowing larger excitations. Studies performed
Due to architectural impositions, the upper grandstand by Rodrigues [7] in Brazilian arenas were always in
located in the west wing presented a lower vertical stiff- grandstands with no seats, setting people free to move
ness. Consequently, this area was significantly excited (bobbing, jumping, etc.), and consequently larger excita-
by the vertical mode with minimum frequency in the tions were obtained. In the near future, the authors plan
grandstands, 6.013 Hz. to retro-analyse soccer matches held in the Corinthians

Structural Concrete 17 (2016), No. 5 703


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Table 1.  Fourier coefficients adopted in dynamic analysis

Fourier coefficients (IStructE Guide, 2008)

Table A2.2 Recommended values of the generated load factors, G ∝i, for use in calculations of performance for design or
assessment.

Scenario Harmonic number Typical activity represented Effectiveness factor

i=1 i=2 I=3

1 – – – Not required. Not required.


Route 1 only, but with discretion available by listed engineer
(recommendations Table I)

2 0.12 0.015 Zero Predominantly seated with occasional coordinated rhythmic Eqn. A2.3
movement from standing people

3 0.188 0.047 0.013 All crowd considered active. Moderate bobbing at three Eqn. A2.3
quarters Parkhouse and Ewin’s’ 50 person level

4 0.375 0.095 0.026 The whole crowd active. Eqn. A2.2


Loading taken to be twice that for the commonly occurring
events of Scenario 3

Fourier coefficients (Rodrigues, 2003)

Stadium Number of people First harmonic Second harmonic Third harmonic


(N/m2) (N/m2) (N/m2)

Morumbi I 4200 1184 473.6 118.4

II 3780 1376 550.4 137.6 a1 1.146

III 2940 704 281.6 70.4 a2 0.4587


a3 0.1147
IV 2100 736 294.4 73.6

V 840 1040 416.0 104.0

Ibirapuera 15 919.4 367.8 91.9

Maracanã 5000 850 340.0 85.0

Castelão 2860 328 131.2 32.8

Arena with chairs installed, and compare the results with


the ones obtained with [6]. If there are still differences,
then they may be caused by the behavior of the public. It
is possible that the dynamic excitation due to Brazilian
crowds is more intense (regardless of the fact that many
Brazilian arenas have no seats) than in Europe. In that
case, the Fourier values should be revised for the Brazil-
ian arenas.
In the event, Corinthians was notified that chairs
should be maintained. If necessary, they could be taken
out only in the lower stand of the east wing, with very stiff
structures as shown in Figure 4. To date (during World
Cup games or National games), uncomfortable situations
due to crowd actions have not been reported.

4.2 Roof

Werner Sobek Structural Engineers (see Figs. 17 and 18)


designed the roof. A steel frame structure was designed to Fig. 16.  Vertical acceleration (m/s2) of the grandstand due to crowd action
cover a total area of 32,300 m2. Initially, the roof was as-
sembled as cantilevers in the east and the west wings. Af- 5 Construction data
terwards, temporary supports were placed in the south
and north wings to finally connect the east and west can- In total, 20,430 elements (excluding foundation piles)
tilevers. The maximum span is 170 m long. were assembled, distributed as follows:

704 Structural Concrete 17 (2016), No. 5


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 17.  Roof sketch

– 4,000 grandstand elements; – 950 precast columns;


– 430 grandstand beams; – 1,600 other elements (stairs, slabs, plates, etc.).
– 11,450 hollow core precast slabs;
– 2,000 precast beams; The concrete volume of precast elements was 31,500 m3.
The peak of production was 160 pieces assembled in one day.
The maximum daily fabrication was 4  columns,
8 units of single beams, 2 units of grandstand beams,
15 units of grandstand elements, and 36 units of slabs. The
maximum assembly was 4 columns, 6 units of single
beams, 3 units of grandstand beams, 16 units of grand-
stand elements, and 32 units of slabs.

6 Connection detailing

The definition of the precast connection details was made


in such a way as to minimize and facilitate the erection
process and the crew operations, because the unit costs of
Fig. 18.  General overview of the roof crane time and the erection crew time were relatively high.

Fig. 19.  Typical joint detail between two prefab column segments in the west wing

Structural Concrete 17 (2016), No. 5 705


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 20.  Typical columns, beam and slab joint detail

Fig. 21.  Connection between alligator beams

706 Structural Concrete 17 (2016), No. 5


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

In the east wing, where the building is not so high, cast beams, the small gap between the back face of the beam
single precast columns were employed. In the highest ar- and the front face of the column is filled with grout. The con-
eas of the west wing, the columns were split (see Fig. 19), tinuity to the top reinforcement of the beam, through the col-
at least into two elements, which were assembled using umn, is guaranteed by coupled reinforcement that crosses the
couplers to establish continuity to the main vertical rein- precast column after the installation of the beam (see Fig. 20).
forcement. The type of coupler adopted in the construc- This figure also shows corbels all along the side of
tion of this arena was a screwed splice. It consists of the the beams, with continuity through the columns, to make
following procedure. At the end of the bottom part of the constant the length of the precast slabs.
columns, a screwed bolt is welded to the reinforcement To establish a monolithic connection between pre-
bars. These bars splice to the main reinforcement of the cast grandstand beams, welded steel bars are used to
column. These screwed bolts remain outside the concrete transfer tension forces (see Fig. 21).
column. The top part of the column has a system of weld- For the connection between precast stands, bolts are
ed plates connected to the reinforcement bars of the col- used to transfer tension forces. These bolts are designed to
umn. The horizontal plate has a hole to fit the screwed allow a group movement of the stands. These stands are
bolt of the bottom column. Then, after a crane raises the pinned to the alligator beams (see Fig. 22).
upper part of the column and positions it over the bottom As it had been initially proposed, all the connections
column, a worker screws each nut, usually only in the four were optimized to achieve the best possible cost-time rela-
corners, for provisional stability of the column. After that, tionship. Even in cantilevered beams, (see Fig. 23) a pre-
the crane releases the column to move on to the next one cast solution was applied.
and the other necessary connections can be screwed. In In some zones, due to the strict clearance-height re-
comparison to a welded connection, the saved time is strictions, it was deemed necessary to substitute the pre-
about 80 minutes for each column. A welded connection cast concrete beams with slender composite beams or cast
would take about 130 minutes, while this screwed splice in situ post-tensioned girders (see Figs. 24, 25 and 26).
takes only about 50 minutes. After having connected all Alternative connection details can be found in Lu [8]
nuts, the connection is grouted to provide continuity to and Yekrangnia [9].
the structure and protect the reinforcement.
The prefabrication plant was able to produce 4 col- 7 Conclusions
umns per day. And the contractor usually assembled 4 col-
umns per day. A total volume of 5,200 m3 of concrete was Many and very different constraints, in particular the
used to produce the precast columns. time available for the design and construction of the
The joints of the frames are monolithic. To maintain this structure of the Corinthians Arena, determined the use
continuity, corbels located at different levels on the precast of structural concrete as the main material used in this
columns support the beams. After the installation of the pre- project.

Fig. 22.  Connection between stands

Fig. 23.  Typical joint detail applied to cantilever beams in the west wing

Structural Concrete 17 (2016), No. 5 707


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Fig. 26.  Cast in situ post-tensioned girder (22.5 m span)

References

  1. Caderno de Eneargos das FIFA: Football stadiums – Techni-


cal recommendations and requirements, 4th Edition, 2007.
  2. Department of Culture, Media and Sport: Guide to safety at
sports grounds, Crown Copyright, United Kingdom, 2008.
  3. NBR 9062:2006 Brazilian Standard; “Projeto e Execução de
Estruturas de Concreto Pré-Moldado”.
 4. ISO 2632-1 INTERNATIONAL STANDARD: Mechanical
Fig. 24.  Sketch of cast in situ post-tensioned girders vibration and shock – Evaluation of human exposure to
whole-body vibration – Part 1, General requirements, 1997.
  5. CEB: Bulletin d’information no. 209; Vibration problems in
structures. Practical Guidelines, 1991.
Prefabrication has been a special characteristic of  6. The Institution of Structural Engineers: Recommendations
this project. More than 20,000 elements were prefabricat- for management design and assessment; Dynamic perfor-
ed, both in established industrial plants and in plants built mance requirements for permanent grandstands subject to
on site. These elements (for the solution of the structure crowd actions, London, 2008.
under the roof) were executed and assembled in a reduced  7. Rodrigues, J. F. S.: Modelo das Ações Induzidas por Multi-
timescale. dões em Estruturas de Arquibancadas – PhD Thesis, Escola
Globally, the adopted solution combines specific ele- Politécnica da Universidade de São Paulo, 2003.
 8. Lu, X., Wang, L., Wang, D. and Jiang, H.: An innovative joint
ments cast in situ, prefabricated elements for most of the
connecting beam for precast concrete shear wall structures.
project, with stiff joints and composite elements as the
Structural Concrete. Accepted Author Manuscript.
solution for special areas. doi:10.1002/suco.201500193
The adopted solution has been a correct choice to  9. Yekrangnia, M., Taheri, A. and Zahrai, S. M.: Experimental
satisfy the structural demands of a project of this kind and, and numerical evaluation of proposed precast concrete con-
particularly, those related to vibration control, a character- nections. Structural Concrete. Accepted Author Manuscript.
istic and very important aspect in a building of this nature. doi:10.1002/suco.201500168

Fig. 25.  Sketch of slender composite beams

708 Structural Concrete 17 (2016), No. 5


F. Stucchi/M. Coelho Ungaretti/G. Fujii/H. Corres Peiretti/S. Doniak/J. Soriano Martin · Corinthians Arena – 2014 World Cup, design and construction

Prof. Dr. Eng. Fernando Stucchi


Professor at Escola Politécnica da Universidade
de São Paulo Hugo Corres Peiretti
Director at EGT Engenharia Ltda Prof. at Technical University of Madrid
ZIP Code: 05051-030 Director FHECOR Ingenieros Consultores
R: Fabia, 442 Calle del Barquillo, 23,
São Paulo, Brazil 28004 Madrid, Spain
fernando.stucchi@egtengenharia.com.br hcp@fhecor.es

Eng. Marcelo Coelho Ungaretti


Director at EGT Engenharia Ltda José Soriano Martin
ZIP Code: 05051-030 FHECOR Ingenieros Consultores
R: Fabia, 442 Calle del Barquillo, 23,
São Paulo, Brazil 28004 Madrid, Spain
marcelo.ungaretti@egtengenharia.com.br jsm@fhecor.es

Eng. Gilson Fujii Eng. Sérgio Doniak


EGT Engenharia Ltda CEO – FHECOR DO BRASIL
ZIP Code: 05051-030 ZIP Code 80610-260
R: Fabia, 442 República Argentina, 2403
São Paulo, Brazil Curitiba-Paraná-Brazil
gilson.fujii@egtengenharia.com.br sdk@fhecordobrasil.com

Structural Concrete 17 (2016), No. 5 709

You might also like