TESTING AND COMMISSIONING PLAN

SUBSTATION Starting Date


Item MAIN ACTIVITY SUB ACTIVITY
Insulation resistance of Core and windings
Winding resistance test for HV and MV side
Ratio / vector group
Automatic voltage regulator test (AVR)
Neutral CTs (refer to CT tests)
1 Main Power Transformers Complete functional tests of cooling equipment
and tap-change equipment, including
manual/automatic sequences, indications, alarms
and interlocks

secondary wiring shall be checked for tightness


Cable termination point to point check (continuity test)
G PLAN
Starting Date ( )
DETAILS
to be performed
to be performed
to be performed
shall be performed with a package
to be performed
shall be performed with a package

shall be performed with a package


shall be performed with a package