Professional Documents
Culture Documents
Structural Procedure UGFC-PQCP-52, Rev00
Structural Procedure UGFC-PQCP-52, Rev00
DOCUMENT TITLE
Page 1 of 6
UPGRADE GAS FLOW CAPACITY
BIN QURAYA EST.
(UGFC)
CONTRACT NO : 6600033800 PREPARATION DATE : 01 FEB 2016
BI NO : 10-00903 DOCUMENT NO & REVISION : UGFC-PQCP-052, REV: 00
Table of Contents
SL NO DESCRIPTION PAGE
1.0. SCOPE 3 of 12
2.0. PURPOSE
3.0. DEFINIATION
5.0. RESPONSIBILITY 3 of 12
Page 2 of 6
UPGRADE GAS FLOW CAPACITY
BIN QURAYA EST.
(UGFC)
CONTRACT NO : 6600033800 PREPARATION DATE : 01 FEB 2016
BI NO : 10-00903 DOCUMENT NO & REVISION : UGFC-PQCP-052, REV: 00
1.0. SCOPE:
- This Quality procedure covers all the Work Related to Preparation and Erection
procedure for Structural Steel and Bolt tightening.
- This procedure has been used for BI 10-00903 project scope of work covers all of
Structural Steel Erection and bolt tightening activities.
2.0. PURPOSE:
- The purpose of this Procedure is to obtain a quality erection throughout identifying
the job responsibility to who are involved in the erection process.
3.0. DEFINITIONS
QCP : QUALITY CONTROL PROCEDURE
ITP : INSPECTION AND TEST PLAN.
CLIENT : SAUDI ARAMCO
CONTRACTOR : BIN QURAYA EST (BQE)
SAPMT : SAUDI ARAMCO PROJECT MANAGEMENT TEAM
SAPID : SAUDI ARAMCO INSPECTION DEPARTMENT.
5.4. The Structural Quality Control Inspector shall be responsible to carry out
inspections and release hold points by signing various inspection requests as
proof record of inspection conforming to specifications.
Page 4 of 6
UPGRADE GAS FLOW CAPACITY
BIN QURAYA EST.
(UGFC)
CONTRACT NO : 6600033800 PREPARATION DATE : 01 FEB 2016
BI NO : 10-00903 DOCUMENT NO & REVISION : UGFC-PQCP-052, REV: 00
and side girt are installed. The bolts are to be tightened to the
required torque. All the bracing horizontal and cross bracing are
to be installed prior to remove the temporary bracing.
6.3.4. Before any further proceeding the first bay shall be made plumb and
square.
6.3.5. Similarly all other structurals shall be erected and must be braced during
erection.
6.3.6. Erection shall not be commenced if weather conditions are unsettled or strong
winds imminent.
6.3.7. Flame cutting of the steel base plates will not be allowed. Reaming of not more
than 1mm is allowed.
6.4. INSTALLATION AND TIGHTINING OF STEEL FASTENERS
6.4.1. Handling and storage of fasteners: shall be protected from dirt and
moistures at jobsite. Fasteners shall not be cleaned of lubricant that is
present in as delivered conditions.
6.4.2. Calibrated wrench tightening: when calibrated wrench is used for
installation, they shall be set to provide a tension not less than 5 percent
in excess of the minimum tension specified.
6.4.3. The torque wrench shall be calibrated at least once each working day for
each bolt diameter length and grade using fastener assemblies that are
being installed in the work.
6.5. QA/QC CHECK LIST: After completing the entire Erection works (Structure wise) the
final inspection of the Structure shall be conducted.
6.5.1. All bracing in position and tightened.
6.5.2. All bolts in place and high-straight bolts strengthen to correct tension.
6.5.3. Any missing bolts.
6.5.4. Touch up or any damaged paints.
6.6. ADDITIONAL POINTS
6.6.1. Erection or site civil engineer / supervisor to ensure the foundation has
been released for erection.
6.6.2. Secure access ladders to steel columns while still on the ground.
6.6.3. Begin erection of steel structure, piece, by piece on the ground,
preliminary tightening of structure component.
6.6.4. Surveyor to submit alignment survey report to site engineer / QC
inspector prior to releasing the structure for final alignment/tightening.
6.6.5. Bolt tightening shall be as per AISC Part 6 using one of the following
methods:
A-Load indicator washer.
B-Turn of the nut.
6.6.6. QA/QC access to tightened joints will remain in place until bolt tightening
is completed.
Page 5 of 6
UPGRADE GAS FLOW CAPACITY
BIN QURAYA EST.
(UGFC)
CONTRACT NO : 6600033800 PREPARATION DATE : 01 FEB 2016
BI NO : 10-00903 DOCUMENT NO & REVISION : UGFC-PQCP-052, REV: 00
Page 6 of 6