Professional Documents
Culture Documents
Sample 1 - High Performing
Sample 1 - High Performing
Sample 1 - High Performing
PROJECT REPORT
Submitted by
NANDHINI S 161EE159
PREETHI P 161EE168
VAISHNAVI E 161EE201
In partial fulfilment for the award of the degree
of
Bachelor of Engineering
in
AUGUST 2020
BONAFIDE CERTIFICATE
SIGNATURE SIGNATURE
Dr.J.Senthil Kumar Dr.P.Prem
SUPERVISOR HEAD OF THE DEPARTMENT
Assistant Professor
Department of Electrical and Department of Electrical and
Electronics Engineering, Electronics Engineering,
Bannari Amman Institute of Bannari Amman Institute of
Technology, Technology,
Sathyamangalam - 638401. Sathyamangalam - 638401.
(Signature of Guide)
Dr.J.SENTHIL KUMAR
ACKNOWLEDGMENT
We would like to thank our friends, faculty and non-teaching staff who have
directly and indirectly contributed to the success of this project.
S.NANDHINI
P.PREETHI
E.VAISHNAVI
i
ABSTRACT
ii
TABLE OF CONTENTS
ABSTRACT ii
LIST OF FIGURES vi
1 INTRODUCTION 1
1.1 OVERVIEW 1
1.2 MOTIVATION 4
1.4 OBJECTIVE 5
1.5 SCOPE 5
2 LITERATURE SURVEY 6
3 SYSTEM DESCRIPTION 11
3.1 DISTRIBUTION SYSTEM AND
11
DISTRIBUTED GENERATION
iii
4 PROBLEM FORMULATION 15
5.2 ALGORITHM 23
7 CONCLUSION 50
REFERENCES 51
iv
ANNEXURE - I 55
ANNEXURE - II 61
PUBLICATION CERTIFICATE 61
AANEXURE - III 63
PLAG SCAN 63
v
LIST OF FIGURES
FIGURE
LABEL PAGE NO
NO
Distribution line segment connected between two
4.1 15
nodes
vi
6.16 VSI graph with CS 39
vii
LIST OF TABLES
TABLE
LABEL PAGE NO
NO
viii
LIST OF SYMBOLS AND ABBRAVIATIONS
List of Symbols
Charging Station
Distributed Generation
List of Abbreviations
CS Charging Station
DG Distributed Generation
EV Electric Vehicle
ix
1
CHAPTER 1
INTRODUCTION
1.1 OVERVIEW
Type 1
This type of DG delivers only active power when combined to the grid with the
help of converters/inverters.
Fuel cell
Fuel cell is a type of power plant where electrical energy is produced from the
chemical energy by electrochemical process. The output of this plant DC. When it is
connected to the grid, it should be controlled by the converter and converted to
alternating current.
3
Type 2
Type 3
The distributed generation which only delivers reactive power come under this
category. E.g.: Synchronous compensators. gas turbines, operates at power factor zero.
Type 4
This type of DG consumes reactive power but delivers active power. Example:
Induction generators in wind farms. Similar to synchronous generators, Doubly Fed
Induction Generators (DFID) also delivers active power by consumption of reactive
power.
many impacts in power system protection, also causes power losses in the distribution
system (K.Vijeta & D.V.S.S.Siva Sarma 2012). The introduction of DG in the
distribution system with only PHEV not only enhances the system performance but
also enhance the reliability system.
Reliability means the ability of a power system to give adequate, stable and
reliable power given in distribution system. A general overview of power system
reliability and analytical method and simulation techniques for the evaluation of
power system reliability and their limitations are explained (Preet Lata & Shelly
Vadhera 2015) and reliability evaluation in power system along with a failure of
protection devices are discussed (Xingbin Yu & Chanan Singh 2002).
1.2 MOTIVATION
1.4 OBJECTIVE
This project has major scope in distribution side and load dispatch centre.
Reliability computation helps in designing the future distribution system.
1.6 INTENDED APPROACH
Chapter 1: It deals with the Introduction, Motivation, Objectives, Scope and Intended
approach.
CHAPTER 2
LITERATURE REVIEW
Alberto Escalera et al (2018) have discussed that the new technologies have
been introduced in modern distribution networks that gives new way of improving the
reliability. A survey of reliability assessment in distribution networks has been
8
presented in paper. An analysis and comparison are done for two different
technologies for the assessment of reliability for each technology along with their
application. For planning and modernisation of power system distribution, the
reliability assessmemt tools are essential.
A.Aljanad & Azad Mohamed (2016) described the impact of power quality for
integrating large scale PHEV in the distribution systems. Power quality issues such as
voltage profile, line loading and circuit losses are investigated by conducting time
series simulations. PHEV is designed as current harmonics source that introduce
harmonics to different buses.
CHAPTER 3
SYSTEM DESCRIPTION
Therefore, we are using here Radial Distribution system with Distributed Generation.
It is used in medium density load areas to provide the light in primary and
secondary circuits where they generally carried overhead on poles. Often the system is
radial only from the distribution substation to the transformers. In radial system, if any
failure occurs beyond the fault, the supply system can be protected. An alternate way
for power supply is provided in the faulted system when the system is protected or
fault rectified. The radial distribution system has an advantage of simplicity and lower
cost. It requires fewer amounts of cables and less maintenance.
Distributed Generation system employs numerous and small plants can give
power onsite of less dependence on the distribution grid and transmission grid
particularly on large scale generating stations. Distributed Generation technologies
give in power ranging from 1 kilowatt [kW] to 100 megawatts [MW]. Power supplied
to various areas from Distributed Generation First, to solve local supply power
problem to remote regions and rural areas. Second, with high reliability in grid failure
gives back-up supply source for customers. Third, during the time of peak demand by
giving power supply, in supporting of levelling out peaks to reduce peak loads.
Fourth, to meet customer needs and efficiency improvement via a multi
generation system provides diverse energy products. Fifth, supports improvement of
power factor, reduces in power losses and modifying grid voltage.
operation for PHEVs are charge-depleting and charge-sustaining modes. Thus these
modes are together called blended mode.
In all electrical modes at low speeds or at all speeds, this vehicles are created to
run at an increased range. The operation of charge depletion mode is to allow a fully
charged PHEV until the charge of the battery is exhausted. At start-up condition, the
plug-in hybrid vehicle operates in a charge-depletion mode, but when a battery attains
a threshold state by charging, the vehicle converts to charge sustaining mode. Blended
mode is the charge depleting action in which the battery supplements from medium to
large loads. The advantage of blended mode is the option to use a smaller battery pack
and it may offer the vehicle designer.
A single unit consists of lead acid battery and supercapacitor which is the
hybrid car battery. The advantage of this battery is less cost, more powerful and longer
life. The PHEV have larger potential and more efficient than conventional hybrid
vehicles. PHEV allows the inner combustion engine system to achieve maximum
efficiency. Electricity generation, charging and discharging of battery, motor
controller are the factors for achieving the actual efficiency. The operating modes and
the driving amount of charges in all electric range give the actual fuel economy. With
the increase in usage of PHEV, pollution is expected to decrease.
are also used to energize. There are several advantages for PHEV such as noise is
reduced, air quality is improved and greenhouse emissions are decreased. The
charging and discharging of PHEV need deeper battery compared to conventional
hybrid vehicles. The PHEV in comparison with the conventional vehicles profits the
cost of energy from 40% to 60%.
Kona electric car drives over long distance with high acceleration and it is
versatile and powerful. Kona electric is fitted with a li- ion polymer battery. Instead of
using liquid electrolyte, polymer electrolyte is used in li- ion polymer battery and it is
rechargeable. Lithium ion and lithium metal batteries are called lithium polymer cells.
These cells are working on the concept of intercalation and de-intercalation of lithium
ions from positive and negative electrode materials. The motor type used in Kona
electric car was permanent magnet synchronous motor. There are two battery versions
used in Kona electric such as 39.2 kwh and 64 kwh. The battery capacity of lithium
battery used in Kona electric was identified as 39.2 kwh. The battery can either be
charged by ac or dc supply. When the car battery is charged with ac supply, it takes
approximately 6 hours 10 minutes for charging. But when it charges with supply of dc
at 50 kW, 57 minutes is needed for charging. The time needed for charging the battery
may differ based on the conditions of high voltage battery, specification of charger
and ambient temperature. The body of the Hyundai Kona is made up of high strength
of steel and it is bonded for adding rigidity with hot stampings.
15
CHAPTER 4
PROBLEM FORMULATION
Considering the distribution line segment attached in-between the two nodes i
and j are shown in figure 4.1. The Voltage Stability Index (VSI) at bus j is computed
as follows (M.Abdel-Akher et al 2011),
Node i Node j
R+jX
At the nodes of i and j, the current flows in the line segment are calculated as follows
( )
| | (1)
( )
| | (2)
Where,
The and are showed in terms of the current flowing in the line as follows:
( ) (3)
( ) (4)
( ) (5)
( ) (6)
Where, R and X are resistance and reactance of line connecting the nodes i and j.
( )
{[ ( ) ] [ ( ) ] }
(7)
(8)
Where,
( )
( )( )
√
(9)
[ ( ) ] [( )( )] (10)
[ ( ) ( ) ] (11)
[( ) ( )] (12)
( ) (13)
∑
(14)
Where
0 (DG size+Pin-Losses)-(EV Load+Std load) ≥ 0
€t=
1 (DG size+Pin-Losses)-(EV Load+Std load) < 0
G (t) = DG size+Pin-Losses
( )
∑ ( ) ∑ | | (15)
Where
∑ ∑ (16)
Where,
(17)
∑ (18)
Load flow analysis is the best approach to solve problems in power system
operation and planning. The steady state operating condition of the power system is
determined by Load flow studies. Throughout the network, load-flow studies helps to
determine whether the voltage profiles are expected to be in the limits range at the
design stage. In the operation stage, load flow study supports the voltage profile and to
reduce the system losses. Some basic load flow algorithms such as Newton Raphson
method, Gauss seidel method were developed and applied to the transmission
network. These algorithms are not efficient for distribution network because the
distribution network has radial structure, unbalanced load, high resistance per
reactance ratio etc., The special feature causes an evaluation of power flow in
distribution system more complex compared to transmission system. Different
methods for the computation of Load flow analysis for distribution system have
developed in the past. Among the different methodologies, ladder network theory and
forward / backward sweep algorithm are most efficient and accurate. Here backward
and forward sweep algorithm is used for the load flow analysis of radial distribution
system.
Distribution networks have high resistance per reactance ratio when compared
to transmission network which cause the more voltage drop and more power or energy
loss in the distribution networks. The higher value of resistance per reactance ratio
causes ill-condition of the radial networks and traditional load flow method like
Newton Raphson Load Flow (NRLF) and Fast Decouple load flow (FDLF) are
inefficient for the load flow analysis of radial networks. Thus forward/backward load
flow analysis was developed for the evaluation of more accurate radial network
parameters.
Listed below are the major steps involved in forward and backward sweep algorithm:
STEP 1
For first iteration, consider rated voltages at end nodes and update a voltage values
calculated in forward sweep for subsequent iterations.
STEP 2
Starting from the farthest node, calculate the node current by equation (19). Now,
apply Kirchoff’s current law to compute current flow from node to node
using equation (20).
( ) (19)
( ) ∑ (20)
STEP 3
By using this current, voltage at node can be calculated by equation (21). Continue
this step till the junction node is attained. Computed voltage is stored at the junction
node.
( ) ( ) (21)
STEP 4
Starting with other end node, voltage and current are calculated as same as that of in
step (2) and (3).
STEP 5
The voltage at the junction node is computed and current is calculated by equation
(19).
STEP 6
STEP 7
Specified source voltage is compared with the computed rated voltage magnitude at
the reference node.
STEP 8
STEP 1
STEP 2
In forward direction calculate the node voltage from the reference node to the end
node by equation (22).
( ) ( ) (22)
STEP 3
Bu using the updated bus voltage calculated in forward sweep, again initiate the
backward sweep. Using standard forward and backward sweep algorithm line current
and node voltages are calculated and then line losses are computed. The complex
power from j bus to i bus and from i bus to j bus are computed by equation (23)
and (24)
(23)
(24)
22
CHAPTER 5
METHODOLOGY
START
t=1
NO
G(t)-L(t)>=0 €t=1
YES
€t=0
LOLP=LOLP+(€t/NT)
t=t+1
NO
t ≤ NT
YES
END
5.2 ALGORITHM
STEP 1
STEP 2
Bus data is collected and it consist of bus number, real power and reactive power.
STEP 3
Line Data is collected and it comprises of line number, ‘from bus’ and ‘to bus’,
resistance and reactance of transmission lines.
STEP 4
After collecting the required data, load flow analysis is performed. Here, backward/
forward sweep algorithm is used for load flow analysis.
STEP 5
In backward sweep, current is calculated with help of Kirchoff’s current law and in
forward sweep, voltage is calculated by Kirchoff’s voltage law.
STEP 6
As a result of load flow analysis, voltage, real power, reactive power, real power
losses and reactive losses are evaluated.
STEP 7
For the optimal allocation of CS and DG in the distribution system, voltage stability
index technique is used.
STEP 8
For the integration of CS in the distribution system, index values are calculated by the
VSI technique. The charging station is placed at the bus with minimum index value
i.e. in the bus with higher stability.
24
STEP 9
After the integration of CS in the distribution system, again index values for the
system with CS is calculated for the optimal allocation of DG. The DG should be
placed at the bus where the index value is maximum.
STEP 10
For the optimal allocation of DG in the system, the size of DG is calculated using
analytical method.
STEP 11
STEP 12
Reliability is assessed for 24 hour load variation for the system with only CS and both
CS and DG.
STEP 13
The net reliability of the system with only CS is compared with net reliability of the
system with both CS and DG. Reliability of the system is good when the net LOLP
value is maximum.
STEP 14
The voltage, real power, reactive power, real power losses, reactive losses are
evaluated and compared for the system without both CS and DG, with only CS and
with both CS and DG.
STEP 15
STEP 16
The above steps are performed again for different distribution system models.
26
CHAPTER 6
1 2 3 4 5 6 7 8 9 10 11 12
SS
0.012
0.01
0.008
VSI (p.u)
0.006
0.004
0.002
0
1 2 3 4 5 6 7 8 9 10 11 12
Bus number
VSI CS
The above figure 6.2 shows the variation of Voltage Stability Index at each bus. An
unit of VSI is p.u. The placement of Charging Station is identified by VSI technique.
The charging station is fixed at the bus VSI is minimum i.e. at the bus12.
5
Number of vehicles
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hour)
The above figure 6.3 shows the variation of load for 24 hour. Hyundai Kona requires
6 hours for complete charging as it allows to travel a distance of 312 Km. The load is
varied based on the usage of vehicles (load) for a day.
28
The table 6.1 shows the variation of load percentage for 24 hours. During peak hours
the usage of vehicles is more so the number of vehicles decreases while charging i.e.
less consumption of load. Except the peak hours, the consumption of load is high i.e.
the number of vehicles for charging is more.
29
40
35
Real power loss (kW)
30
25
20
15
10
5
0
DG Size (kW)
The above figure 6.4 shows the variation of real power loss regarding Distributed
Generation size. Real power loss decreases with increase in Distributed Generation
size. At certain point, real power loss begins to increase with increase in Distributed
generation size. The point where the real power loss drops at last is fixed as optimal
DG size. Hence, 400 kW is concluded as DG size for this 12 bus system.
0.018
0.016
0.014
0.012
VSI (p.u)
0.01
0.008
0.006
0.004
0.002
0
1 2 3 4 5 6 7 8 9 10 11 12
Bus number
VSI CS DG
The figure 6.5 shows VSI of the distribution system with CS and DG. After the
allocation of Charging Station, the size of Distributed Generation is calculated and it
is placed where the VSI of Distribution System with charging station is maximum.
DG CS
1 2 3 4 5 6 7 8 9 10 11 12
SS
The figure 6.6 shows the 12 bus radial distribution system with CS and DG. The
placement of DG and CS is fixated by Voltage Stability Index technique. DG is
allocated at bus9 and CS is allocated at bus12. The losses from real and reactive
power after the allocation of DG and CS is 18.922 kW and 6.4721 kW respectively.
1.02
1
0.98
Voltage magnitude (p.u)
0.96
0.94
0.92
0.9
0.88
0.86
0.84
1 2 3 4 5 6 7 8 9 10 11 12
Bus number
The above figure 6.7 shows variation of voltage at each bus in 12 bus distribution
system without both distributed generation and charging station, with only charging
station, and with both distributed generation and charging station. It is shown from the
graph that after the allocation of charging station the voltage drops when compared to
31
the voltage in distribution system without both CS and DG. The introduction of
Distributed Generation in the distribution system with CS, enhances voltage by
compensating the losses caused by the backward power flow. Thus, the voltage is
improved after the allocation of both charging station and distributed generation.
Allocation of DG at bus9 causes the maximum voltage at bus9 and increase in voltage
at nearest buses.
9
8
7
6
Real power loss (kW)
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 10 11
Branch number
3.5
3
Reactive power loss (kVAr)
2.5
2
1.5
1
0.5
0
1 2 3 4 5 6 7 8 9 10 11
Branch number
Reactive power loss graph is similar to real power loss graph. Losses in the
distribution system are increased by integrating it with Charging Station. These losses
are reduced by the installation of Distributed Generation.
Without With
With CS
CS & DG CS & DG
DG Location - 5 9
DG Size (kW) - - 400
CS Location - 12 12
CS capacity (kW) - 156.8 156.8
From the table 6.2, real power from the substation for distribution system with
Charging Station is increased by 39.30% and real power loss is increased by 51.9%
when compared to real power and real power losses in distribution system without
charging station and distributed generation. But after the installation of distributed
generation the real power from substation and real power losses are decreased by
86.5% and 56.1% respectively. The minimum voltages are identified at bus9 for
distribution system without charging station and distributed generation and system
with charging station and bus4 for distribution system with charging station and
distributed generation.
The below figure 6.10 shows the load profile graph of 12 bus system. The generation
capacity of the distribution system is identified as 435 kW for 24hours. Bar graph
shows the variation of standard load and Electric Vehicle load with respect to time.
33
The point where the bar graph touches the generation capacity line and at that time the
LOLP is 1 and LOLP for rest of the time is 0.
700
600
500
Load (kW)
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hour)
120
100
80
Load (%)
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hour)
The above figure 6.11 shows the load percentage variation for 24 hours. This graph
reaches peak when the number of vehicles for charging increases.
34
Total
STD DG Generation G(T)-
Time EV Pin Loss load
Load Size capacity L(T)
(hour) (kW) (kW) (kW) L(T) LOLP
(kW) (kW) G(T) (kW) (kW)
(kW)
1 196 435 0 455.71 20.713 435 631 -196 1
Total
STD DG Generation G(T)-
Time EV Pin Loss load
Load Size capacity L(T)
(hour) (kW) (kW) (kW) L(T) LOLP
(kW) (kW) G(T) (kW) (kW)
(kW)
1 196 435 400 90.67 28.364 462.30 631 -168.6 1
From table 6.3, LOLP for a system is calculated by the summation of LOLP for
24 hours divided by 24. Here, the LOLP of this system is calculated as 0.75.
Table 6.4 shows that after the allocation of Distributed Generation in 12 bus
system, the generation capacity, input power, losses are changed. With respect to the
changes, the LOLP is calculated for every hour. The net LOLP of this system after the
allocation of Distributed Generation is calculated as 0.54167.
On comparing the table 6.3 and 6.4, the LOLP of a system with CS is larger
when compared to system with CS and DG. Reliability is good when LOLP is low.
Thus, reliability is enhanced in the system with CS and DG.
250
200
150
100
G(T)-L(T) (kW)
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-50
-100
-150
-200
-250
Time(hour)
The above figure 6.12 shows the reliability analysis of a distribution system
with only CS for every 24 hours. If the value of G(t)-L(t) is greater than or equal to 0
37
then LOLP at that time will be 0. Suppose G(t)-L(t) is less than 0 then LOLP at that
time will be 1. Thus the LOLP value depends on generation capacity and total load.
300
250
200
150
G(T)-L(T) (kW)
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-50
-100
-150
-200
Time (hour)
The figure 6.13 shows the reliability analysis of the distribution system with
both DG and CS. The LOLP of a time is 0 when the value of G(t)-L(t) is greater than
or equal to 0 and LOLP will be 1 when G(t)-L(t) is less than 0. The above shows that
the reliability is improved in the system with both CS and DG compared to the system
with only CS.
0.007
0.006
0.005
Power flow (kW)
0.004
0.003
0.002
0.001
0
1 2 3 4 5 6 7 8 9 10 11
-0.001
-0.002
Branch number
Figure 6.14 shows the power flow in the distribution system. When distributed
generation is added to the distribution system, the backward power will flow towards
the substation. Here, in 12 bus system distributed generation is installed at bus9. From
bus9 reverse power will flow on the basis of DG size.
23 24 25
26 27 28 29 30 31 32 33
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
SS
19 20 21 22
The proposed work is carried out using 33 bus radial distribution system
connected to a 12.66 kV substation.
Figure 6.15 consists of 32 load buses connected via main and lateral feeders.
The load data’s and line data’s are collected (M. M. Aman et al 2013). It has a real
power load of 3715 kW and reactive power load of 2300 kW.
The real and reactive power supplied from the substation is 3884.5 kW and
2414.8 kW respectively.
39
Real and reactive power loss from the base case load flow is 169.5135 kW and
114.8382 kW respectively.
0.016
0.014
0.012
0.01
VSI (p.u)
0.008
0.006
0.004
0.002
0
1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233
Bus number
VSI CS
Figure 6.16 shows VSI graph with CS. VSI technique is used for the optimal
allocation of Distributed Generation and Charging Station. The Charging Station is
placed at the bus where VSI is minimum. In this proposed system, Charging Station is
placed at bus33.
200
180
160
140
Real power loss (kW)
120
100
80
60
40
20
0
DG Size (kW)
In this above graph 6.17, the real power loss value decreases by increasing the size of
DG. But after some point real power loss values starts to increase. Thus, the minimum
value of real power loss is fixated as DG size.
0.016
0.014
0.012
0.01
VSI (p.u)
0.008
0.006
0.004
0.002
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33
Bus number
VSI CS DG
Figure 6.18 shows the Voltage Stability Index graph with Charging Station and
Distributed Generation for 33 bus Distribution System. VSI technique is used to find
the weakest branch in Distribution System and this method is used to determine the
optimal sizing and siting for the installation of Distributed Generation. VSI is
calculated for the distribution system with Charging Station. Distributed Generation is
placed at bus6 because DG should be placed at a bus where VSI is minimum. Thus,
the Charging Station is placed at bus33 and Distributed Generation at bus6.
The below figure 6.19 shows the 33 bus radial distribution system with CS and
DG. The VSI technique is used for the allocation of Charging Station and Distributed
Generation.
41
23 24 25
CS
26 27 28 29 30 31 32 33
DG
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
SS
19 20 21 22
1.02
1
0.98
Voltage magniitude (p.u)
0.96
0.94
0.92
0.9
0.88
0.86
1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233
Bus number
The voltage profile graph 6.20 shows the variation of voltage in the
Distribution System without Charging Station and Distributed Generation, without
Distributed Generation and with Charging Station and Distributed Generation. The
42
maximum voltage in this system without Charging Station and Distributed Generation
is 0.997133 p.u, without Distributed Generation is 0.997048 p.u and with Charging
Station and Distributed Generation is 0.998412 p.u.
50
45
40
35
Real power loss (kW)
30
25
20
15
10
5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Branch number
The above Figure 6.21 shows the real power loss in 33 bus radial distribution
system. Because of increasing number of PHEV, losses in distribution system are
further increased. These losses can be minimized by the allocation of Distributed
Generation at suitable bus. Considerable decrease in power loss is noticed in
distribution system with Charging Station after the introduction of Distributed
Generation in it.
35
30
Reactive power loss (kW)
25
20
15
10
5
0
1 2 3 4 5 6 7 8 9 1011121314151617181920212223242526272829303132
Branch number
Reactive power loss graph is similar to real power loss graph. Losses in
distribution system are reduced by the optimal allocation of distributed generation.
The total reactive power loss in this system without charging station and distributed
generation is 114.8382 kW, with charging station is 126.541 kW and with charging
station and distributed generation is 71.0985 kW. Thus the graph 6.22 shows the
losses are reduced after the allocation of distributed generation.
Without With
With CS
CS & DG CS & DG
DG Location - 6 6
DG Size (kW) - - 2750
CS Location - 33 33
CS capacity (kW) - 156.8 156.8
Real power from substation (kW) 3884.5 4058.2 1217.9
Reactive power from substation
2414.8 2426.5 2371.1
(kVAr)
Real power loss (kW) 169.5135 186.3839 96.0627
Reactive power loss (kVAr) 114.8382 126.541 71.0985
Minimum voltage (p.u) @ bus 0.9217@18 0.9259@18 0.9589@18
From the table 6.5, it is shown that the real power from substation for system
without Distributed Generation and Charging Station is 3884.5 kW and with Charging
Station is 4058.2 kW i.e. 4.47 % increase.
4500
4000
3500
3000
2500
Load (kW)
2000
1500
1000
500
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hour)
Load profile graph 6.23 shows the variation of load (standard and Electric
Vehicle) for 24 hours. The generation capacity of this system is identified as 3714.9
kW. When the load graph touches the generation capacity line the LOLP is 1
otherwise LOLP will be 0.
Table 6.6 shows that the generation capacity of the system is calculated by size
of distributed generation, input power and losses. Thus, the value of generation
capacity is 3714.9 kW. The total load is evaluated by the summation of standard load
and EV load. LOLP of the system is calculated as 0.458333.
The generation capacity of the distribution system with both charging station
and distributed generation is found to be 3870.19 kW. The net LOLP of the system is
0.166667 is shown from the table 6.7.
Total
STD DG Generation G(T)-
Time EV Pin Loss load
Load Size capacity L(T) LOLP
(hour) (kW) (kW) (kW) L(T)
(kW) (kW) G(T) (kW) (kW)
(kW)
1
1 196 3715 0 3884.5 169.5 3714.9 3911 -196.0
1
2 196 3715 0 3884.5 169.5 3714.9 3911 -196.0
0
3 196 3343.5 0 3884.5 169.5 3714.9 3539.5 175.48
1
4 196 3715 0 3884.5 169.5 3714.9 3911 -196.0
0
5 196 3157.7 0 3884.5 169.5 3714.9 3353.7 361.23
0
6 235.2 2972 0 3884.5 169.5 3714.9 3207.2 507.78
0
7 39.2 2600.5 0 3884.5 169.5 3714.9 2639.7 1075.2
0
8 39.2 1671.7 0 3884.5 169.5 3714.9 1710.9 2004.0
1
9 39.2 3715 0 3884.5 169.5 3714.9 3754.2 -39.21
1
10 39.2 3715 0 3884.5 169.5 3714.9 3754.2 -39.21
0
11 39.2 3604.7 0 3884.5 169.5 3714.9 3643.9 71.086
0
12 78.4 3529.2 0 3884.5 169.5 3714.9 3607.6 107.33
1
13 78.4 3715 0 3884.5 169.5 3714.9 3793.4 -78.41
1
14 78.4 3715 0 3884.5 169.5 3714.9 3793.4 -78.41
0
15 78.4 2786.2 0 3884.5 169.5 3714.9 2864.6 850.33
0
16 78.4 2600.5 0 3884.5 169.5 3714.9 2678.9 1036.0
0
17 156.8 2414.7 0 3884.5 169.5 3714.9 2571.5 1143.4
0
18 78.4 2043.2 0 3884.5 169.5 3714.9 2121.6 1593.3
0
19 196 1875.5 0 3884.5 169.5 3714.9 2071.5 1643.4
0
20 196 2229 0 3884.5 169.5 3714.9 2425 1289.9
1
21 196 3715 0 3884.5 169.5 3714.9 3911 -196.0
1
22 196 3566.4 0 3884.5 169.5 3714.9 3762.4 -47.41
1
23 117.6 3603.5 0 3884.5 169.5 3714.9 3721.1 -6.164
1
24 117.6 3715 0 3884.5 169.5 3714.9 3832.6 -117.6
46
Total
STD DG Generation G(T)-
Time EV Pin Loss load
Load Size capacity L(T)
(hour) (kW) (kW) (kW) L(T) LOLP
(kW) (kW) G(T) (kW) (kW)
(kW)
2500
1500
1000
500
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-500
Time (hour)
G(T)-L(T)
The above figure 6.24 shows the reliability analysis of the distribution system with
only CS for every 24 hours. If the value of G(t)-L(t) is greater than or equal to 0 then
LOLP at that time will be 0. Suppose G(t)-L(t) is less than 0 then LOLP at that time
will be 1. Thus the LOLP value depends on generation capacity and total load.
4000
3500
3000
G(T)-L(T) (kW)
2500
2000
1500
1000
500
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-500
Time (hour)
G(T)-L(T)
The figure 6.25 shows the reliability analysis of the distribution system with both CS
and DG. The LOLP of a time is 0 when the value of G(t)-L(t) is greater than or equal
to 0 and LOLP will be 1 when G(t)-L(t) is less than 0. The above shows that the
48
reliability is improved in the system with both CS and DG compared to the system
with only CS.
0.045
0.04
0.035
0.03
Power flow(kW)
0.025
0.02
0.015
0.01
0.005
0
-0.005 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
-0.01 Branch number
The above figure 6.26 shows that the reverse current from the bus6 shows that
the distributed generation is placed at bus6. The current will flow backward until it is
compensated by the power from the substation. Thus, the distributed generation
supplies power to rest of the branches.
12 bus 33 bus
DG location 9 6
CS location 12 33
CHAPTER 7
CONCLUSION
This project proposes the effectiveness of the introduction of charging station and
distributed generation in the distribution system. The proposed method is tested on 12
and 33 bus radial distribution system. Distributed Generation is integrated with
charging station to decrease the impact on distribution system. By the introduction of
new technologies such as distributed generation, electric vehicle, microgrid and
automated protection devices gives an opportunity for improving the reliability.
Distributed Generation should be placed at the farthest bus from the source to reduce
the transmission losses. Backward and Forward sweep algorithm gives the value of
voltages at each bus, real and reactive power losses of the system. VSI technique is
implemented for finding the optimal allocation of distributed generation and exact loss
formulas are implemented for finding the optimal size of distributed generation. The
results have been developed for without both charging station and distributed
generation, with only charging station and with both charging station and distributed
generation. The result graph shows that after the integration of charging station and
distributed generation, the voltage profile and reliability is significantly enhanced,
losses and stresses are reduced in the distribution system.
51
REFERENCES
[10] Bamdad Falahati, Masood Shahverdi, Poria Fajri and Amin Kargarian, Loss
of Load Probability of Power Systems Considering the High PHEV
Penetration Rates, IEEE Conference on Technologies for Sustainability, 2018.
[11] Beenish Sultana, M.W. Mustafa, U. Sultana, Abdul Rauf Bhatti, Review on
reliability improvement and power loss reduction in distribution system via
network reconfiguration, reconfiguration, Renewable and Sustainable Energy,
2016.
[12] Curtis Roe, Farantatos Evangelos, Dr.Jerome Meisel, Dr.A.P.Meliopoulos,
Dr.Thomas Overbye, Power System Level Impacts of PHEVs, International
Conference on System Sciences, 2009.
[13] Daniel Fioresi Botelho, Leonardo Willer de Oliveira, Bruno Henriques Dias,
Camile Aredes Moraes, Edimar Jose de Oliveira, Distributed Generation
Planning in Distribution System With Focus on Reliability, International
Conference on distribution networks, 2018.
[14] Fazelpour F, Vafaeipour M, Rahbari O, Rosen MA, Intelligent optimization to
integrate a plug-in hybrid electric vehicle smart parking lot with renewable
energy resources and enhance grid characteristics. Article in Energy
Conversion and Management, vol.77, pp-250-261, 2014.
[15] G. A. Quiroga, H. Kagan, J. C. C. Amasifen, N. Kagan, C. F. M. Almeida, E.
Vicentini, Study of the Distributed Generation Impact on Distributed
Networks, Focused on Quality of Power, International conference on
Harmonics and Quality of power, 2016.
[16] Galiveeti Hemakumar Reddy, Arup Kumar Goswami, Nalin B. Dev
Choudhury, Impact of plug-in hybrid electric vehicles and distributed
generation on reliability of distribution systems, Engineering Science and
Technology, an International Journal, vol.21,pp-50-59, 2018.
[17] Galiveeti Hemakumar Reddy, Pranju Chakrapani, Arup Kumar Goswami,
Nalin B. Dev Choudhury, Optimal distributed generation placement in
distribution system to improve reliability and critical loads pick up after
natural disasters, Engineering Science and Technology, an International
Journal, 2017.
53
[18] Jaser A. Saed, Mohammad Amer, Ahmed Bodair, Ahmad Baransi, Salvatore
Favuzza, Gaetano Zizzo, A Simplified Analytical Approach for Optimal
Planning of Distributed Generation in Electrical Distribution Networks,
Journal of Applied sciences, Volume 9, 2019.
[19] J. Senthil Kumar, S. Charles Raja, Dipti Srinivasan, P. Venkatesh, Hybrid
renewable energy-based distribution system for seasonal load variations,
International Journal of Energy Research, 2017.
[20] K. Kirubarani & A. Peer Fathima, Distribution system reliability assessment
for improved feeder configurations, International Journal of Engineering and
Advanced Technology, Volume 8, 2019.
[21] K.Vijeta, D.V.S.S Siva Sarma, Protection of Distributed Generation
connected Distribution system, International Conference on Advances in
Power Conversion and Energy, 2012.
[22] M. M. Aman, G. B. Jasmon, K. H. Solangi, A. H. A. Bakar, and H. Mokhlis,
Optimum Simultaneous DG and Capacitor Placement on the Basis of
Minimization of Power Losses, International Journal of Computer and
Electrical Engineering, Vol. 5, No. 5, 2013.
[23] M.Abdel-Akher, A.A.Ali, A.M.Eid, H.El-Kishky, Optimal Size and Location
of Distributed Generation Unit for Voltage Stability Enhancement,
International Conference on Distributed generation, 2011.
[24] Mahmud Fotuhi-Firuzabad, Reliability assessment of distribution system with
distributed generation, International Conference on Power and Energy, 2008.
[25] Mamdouh Abdel-Akher, Ahmad Eid, Abdelfatah Ali, Effective Demand Side
Scheme for PHEVs Operation Considering Voltage Stability of Power
Distribution Systems. International Journal of Emerging Electric Power
Systems, 2017.
[26] Omid Sadeghian, Morteza Nazari-Heris, Mehdi Abapour, S. Saeid TAHERI,
Improving reliability of distribution networks using plug-in electric vehicles
and demand response, Journal of Modern Power Systems and Clean Energy,
2019.
54
[27] Preet Lata, Shelly Vadhera, Issues of concerns in power system reliability,
International conference on power, Instrumentation, control and computing,
2015.
[28] Rajmund Drenyovszki, Kovacs L, Pinter I, Olah A, Tornai K, Levendovszky
J, Power system reliability assessment based on Large Deviation Theory
bounds, IEEE International Energy Conference, 2016.
[29] S.Subramanya Sarma, Dr.V.Madhusudhan, Dr.V.Ganesh, Evaluation and
Enhancement of Reliability of Electrical Distribution System in the presence
of Dispersed Generation, International conference on Signal Processing,
Communication, Power and Embedded System, 2016.
[30] Seyed Morteza Alizadeh, Cagil Ozansoy, Tansu Alpcan, The Impact of X/R
ratio on Voltage Stability in a Distribution Network Penetrated by Wind
Farms, Australasian Universities Power Engineering Conference, 2016.
[31] T.Adefarati, R.C.Bansal, Integration of renewable distributed generators into
the distribution system: a review, IET Renewable Power Generation, Volume:
10, 2016.
[32] Xingbin Yu, Chanan Singh, Power System Reliability Analysis Considering
Protection Failures, IEEE power engineering society summer meeting, 2002.
[33] Xue Wang, Rajesh Karki, Exploiting PHEV to Augment Power System
Reliability, IEEE transactions on smart grid, 2016.
[34] Y. M. Atwa, E. F. El-Saadany, M. M. A. Salama, R.Seethapathy, Optimal
Renewable Resources Mix for Distribution System Energy Loss
Minimization, IEEE transactions on power systems, Vol. 25, 2010.
[35] Yimin Gao and Mehrdad Ehsani, Design and control Methodology of Plug-in
Hybrid Electric Vehicles, IEEE transactions on Industrial Electronics, Vol.57,
2010.
55
ANNEXURE - I
S. NANDHINI 161EE159
In our project Distributed Generation and Charging station are integrated in the
Distribution System for the assessment of reliability. Distributed Generation is
integrated with charging station to decrease the impact on distribution system. The
project is done by using Matlab coding. I have studied the base coding for load flow
analysis and literature survey based on Distributed Generation. The literature survey
was completed and found different types of Distributed Generation. The proposed
methodology was prepared for our project by using 12 and 33 bus distribution system.
I have studied Voltage Stability Index and performed analysis for the evaluation of the
index. This index is used for the allocation of Distributed Generation. The optimal
size and location of distributed generation is identified by using voltage stability index
technique. The integration technique is implemented in the coding. By running the
code, the suitable bus is identified for the allocation of Distributed Generation and the
variation of the voltage and losses are found.
increasing the size of Distributed Generation. But after some point real power loss
values starts to increase. Thus, the minimum value of real power loss is fixated as DG
size. The distributed generation size for 12 bus system is 400 kW. From the result, the
voltage profile shows that the voltage level increases and losses are reduced after the
allocation of distributed generation.
[S.NANDHINI]
57
P.PREETHI 161EE168
In the first week, I have done Literature survey in Distribution system. From
that survey I got an overview of Distribution system. After the completion of
Literature survey I have decided to work on radial Distribution System and referred
many papers on radial distribution system. Then I have studied MATLAB base coding
and implementation of operating functions. Literature survey on Load flow analysis is
done. From that study, I have identified the effective method to perform Load flow
analysis. Forward and Backward sweep algorithm is identified as effective method to
perform Load flow analysis. Then base code for Load flow analysis is analyzed and
studied. After the completion of Load flow analysis, literature survey is done on
reliability and reliability assessment techniques. Loss Of Load Probability technique is
identified as effective method for the evaluation of reliability and it is introduced in
the MATLAB coding. Literature survey on Loss Of Load Probability is done. From
that I have prepared flow chart for Loss Of Load Probability. Then Loss Of Load
Probability equation is formulated. Loss Of Load Probability equation is introduced in
the MATLAB coding. I have selected PHEV Hyundai KONA electric car as load. I
have varied the load based on the usage of vehicles. Then load graph is prepared. The
load graph shows the variation of load with respect to time. Load percentage variation
tabulation is prepared. The tabulation shows the variation of load percentage for 24
hours.
Load profile graph is prepared for 12 bus radial distribution system. This graph
shows the variation of total load with respect to time and generation capacity line is
also included in this graph. Reliability evaluation tabulation is made for 12 bus radial
distribution system with only charging station and with both charging station and
distributed generation. Reliability evaluation tabulation comprises of time, electric
vehicle load, standard load, distributed generation size, input power, losses, generation
capacity, total load and LOLP. EV load values are noted from the load graph and
58
standard load values are noted by referring load percentage variation tabulation. For
the distribution system with only CS Pin, losses are taken from the base case load
flow and for the system with both CS and DG Pin and losses are varied because of the
integration of DG. Thus, reliability assessment is done for the 12 bus radial
distribution system. I have identified that the reliability is enhanced in the system with
both CS and DG compared to the system with only CS. Then I have decided to apply
this reliability evaluation methodology in 33 bus distribution system. Load graph,
Load percentage variation tabulation, load profile graph, reliability evaluation
tabulation are prepared for 33 bus radial distribution system. Reliability is evaluated
for 33 bus radial distribution system. The result shows that the reliability is enhanced
in 33 bus radial distribution system similar to that of 12 bus radial distribution system.
Finally, I have included all the obtained results in our project report.
[P.PREETHI]
59
E.VAISHNAVI 161EE201
Then, calculated the Real power and Reactive power losses without the
placement of charging station and with placing of charging station for 12 and 33 bus
radial distribution system and graph is made on them. Then calculated all the values
and tabulated. While placing of charging station, I analysed that voltage becomes less
in placing of charging station when compared to without placing of charging station
and similarly real and reactive power losses becomes high when placing of charging
station compared to non-placing of charging station in the distribution system. Finally,
the obtained results are VSI graph after placing of charging station, voltage profile
graph without placing of charging station and with placement of charging station and
also similar graph about real and reactive power losses in 12 bus and 33 bus radial
distribution system.
[E.VAISHNAVI]
61
ANNEXURE – II
PUBLICATION CERTIFICATE
62
63
ANNEXURE – III
PLAG SCAN