Professional Documents
Culture Documents
Cost Center Accounting
Cost Center Accounting
Cost Center Accounting
I Configuration
1) Standard Hierarchy
2) Cost center category
3) Cost center spilt
4) Allocation methods
A) Assessment B) Distribution
5) Planning profile & layout
II Master Data
1) Cost center
2) Cost center group
3) Statistical key figure
4) Statistical key figure group
5) Activity type
6) Activity type group
III Planning
IV Actuals
V Information systems
I.1 Cost center Standard Hierarchy
Alternative STD hierarchy: we can have N no of alternative STD hierarchies to address the reporting
requirements and configuration purpose
Ex: Labor activity (If you give Cctr category in activity master then it will only use for specified
Cctr)
Cctr currency
Case 1: if the cocode & co area currency type are different then always Cctr currency is the
cocode currency
Case 2: where the co area having the cocode currency type 10 in such case we can assign any
currency in the Cctr master
Control tab
What are the factors to be consider while finalizing the cost center
Reporting criteria-at what level you want to monitor and view the cost
Planning level-plan vs actual
Profit centers
-Values from OH Exp (Cctr)/goods movement data (MM) (SD) like mat consumption, stock, sales
COGM, COGS to profit centers
-we can assign single profit center to more than on Cctr.
-not possible to assign more than one profit center to single Cctr
Work centers
-it represents the place where the work performs and WC can be group of
machines/place/group of the employees/group of any
-limitation is not possible to assign more than 6 activity types for single WC
-BOM is nothing but list of the components & planned quantities which are required to
manufacture the product
-Routing it contains the list of sequence of process steps (operations) and each operation
specifies which work center to be performed and what are the activities to be performed at the
work center. And planned quantities are required for each activity or resource wise.
Activity type and activity price
-activity types are used as base to allocate the OH from Cctr to the product
-activity price maintained with combination of Cctr & activity type
Allocation criteria
II.2 Cost center group: We can have N no of Cctr groups to address the reporting requirements and
configuration purpose
SKF can be used on base in allocation method to allocate the cost b/w cost objects (Cctr to Cctr)
o Canteen dept cost need to allocate to the other dept’s based on no employees
In this ex SKF is no of employees & allocation base is the SKF no of employees
o SAP license fee to be allocated to other dept’s based on SAP users
In this ex SKF=No of systems
o Power expenditure to be allocated to the other dept’s based on the power units
consumed in the dept’s
In this ex SKF=no of units
SKF needed only if you are using the cost allocating based on SKF otherwise no need.
1) Fixed category:
o not required to enter the values every period ex: no of systems
o Fixed SKF values are not only for the entered period, it is valid for the next following
month till the next change or till the next fiscal year
o Need to be select those key figures having the constant values for the entire fiscal year
2) Total category
o These key figures wont update for the following periods
o Which are the key figures not constant and varies period to period for those key figures
need to change the fixed category for their hierarchy
o In total category need to update or enter the vales every period
II.4 Statistical key figures Group: Group of similar nature (category) of key figures either based on
reporting criteria or configuration purpose
To convert the RM to another stage we need to perform some activities are called as activity
types
RM -------> FG
Machine setup
Labor
Sharpening
Painting
Assemble
Printing
Packing
To record and track the activities which are spent on job (order) and also measure/track the
output of the dept’s or activities of dept’s
Plan activities
Actual activities
To allocate the OH based on resource used (activities spent) from Cctr (Dept) to Order (job)
Activities can be used to allocate the OH both Direct (MFG) & Indirect (Service)
To calculate plan activity price (plan resource price) or actual activity price
To get the cost breakup in the product costing
The below factors need to be consider during the finalization of activity type
1) Work center
We can assign maximum 6 activity types per work center
Single activity type can be assigned to multiple work centers
We can assign maximum one Cctr to single work center, and the same Cctr can be assigned
to multiple work centers
2) Activity type & Activity price
We can maintain the activity price for each combination of Cctr & work center
Assume if you want to change or if you want to maintain the different price for the same
activity & same dept (Cctr), in such case either we need to increase the no of activity types
or no of Cctrs
Ex:
o Where you want to maintain (Change) different price for the skill labor and unskilled
labor in such case we need to define two activity types or two cost centers
o Where you want to charge the different price based on the high value machine & low
value machine in this case also either we need to increase the Cctrs or activity types
3) Reporting criteria (Product costing reports)
Activity type category: It specifies how the planned activity units are recorded / maintained against
the activity type
Direct activity allocation:- Manual maintain 1 & 4
Indirect activity allocation: - we are depending on the other dept’s ex power 2,3 & 5
Activity price indicator: - (how the price to be calculated) system calculated price
Activity type category (5) ------ Actual activity rate/price=actual cost/actual activity qty’s or units
Allocation Cost element: the allocation cost element require allocating the cost from Cctr to other
objects like Cctrs/orders/WBS element
Lock indicator: if you activate then it cannot be use for activity (Cannot post)
III Planning
Purpose: - to compare between plan & actual, to analyze the variance & to calculate plan activity
(Resource) rate
Input planning
Output planning
SKF planning
Cost element planning with reference to activity is called as activity dependent planning
Prerequisite
o Output planning
o Cost element planning
Activity dependent planning not required splitting
Manual planning
Excel Upload
-New layouts
Where the cocode & co area currencies are difference in this case where you want to plan in
cocode currency
Where you want to upload the excel planning
Distribution key
File description
keep the blank, it updates automatically after attaching the layout to the planner profile at the
time of saving the planner profile
It specifies how and what base cost/amount to be allocated to the activity types. This
conditions are specified in the spitting rule
The main purpose of splitting rule is split the amount to the activity type for the purpose of
sys calculated activity price
It required only in case of activity independent planning
Cost center split can be done by splitting structure, splitting structure contains the
assignments, each assignment specifies the rules and also relationship between source CE—
Acty type—Splitting rules, splitting rules specifies splitting method, splitting method specifies
on what base the amount to be split & allocated to the activity types.
Splitting structure linked to the Cctr, need to assign splitting structure to the Cctr which
Cctrs having both expenditure & activities. Assign the splitting structure to the Cctr where
you want to allocate the cost to the activity type based on the splitting rules.
o Salaries + staff welfare------- labor Acty and cleaning Acty one splitting rule
o MISC cost------cleaning Acty +labor Acty +machine Acty one splitting rule
One splitting structure can have n no of splitting rules
Unallocated method:- which are the cost elements not allocated in splitting structure, those
can be assigned to the this method
‘12’ splitting method used for both plan & actual
o In case of planning the amount will be splitted based on plan activity units
o In case of actual the amount will be spitted based on actual activity units
‘0’ splitting method is for unallocated amount
During the execution of splitting program it splits the amount based on splitting rule ,
splitted amount allocated to the activity types for the purpose of activity price calculation
o KSS4 During this step it won’t calculate the price, just it allocate the amount to the
activity types
Not required spitting structure, the reason is that during the planning itself the amount is
allocated to with reference to activity type wise hence the splitting structure or splitting rules
are not required
Both input & output planning is required
Cost element planning with reference to activity type wise
CE vs Acty type vs Cctr
Prerequisites are input planning & output planning
Not required to perform any splitting
Perform the plan activity price calculation KSPI
If any cost element not done planning with activity type wise in case of activity dependent
planning the cost equally distributed to the activity types
IV Actuals
FI-OH Exp, MM-Consumable price diff & revaluation of inventory, Asset acct- Depreciation, HR-
Salaries, CO-Internal orders, Project WBS element, Service orders, Maintenance orders, etc…
FI-During the data entry need to enter the Cctr manually or can be set the default Cctr against
the CE in configuration OKB9
MM-During the GI to the Cctr can be enter manually or can be se the default Cctr against the
CE in configuration OKB9
FI-Asset acct every Asset master linked with the Cctr and at the month end while executing the
Dep program that Dep updates to the other Cctr
FI(FCR & Ex rate diff)-Automatic transactions and default Cctrs can be set against the CE in
configuration
Internal Order-At the time of internal order settlement and we can give the Cctr in IO master
CS/PM/QM/Projects(WBS)-if the settlement rule is Cctr then at the time of orders settlement
the values are transferred to the Cctrs
Cctr to Cctr-During the execution of allocation we can distribute the values to Cctr
Cctr to PP- At the time of activities confirmation against the order system allocates the cost
from the Cctr to production
Cctr to COPA-During the month end executing the COPA assessment the values are transfer
from Cctr to COPA
The default different CO objects can be maintain for the same cost element based on plant
o Ex: CE 100045 Bank chargesPlant 1010E_ASSM (Cctr)
o CE 100045 Bank chargesPlant 2010S_MFG (Cctr)
The default Cctrs can be overwrite manually
if the CO object is maintained both in OKB9 Automatic account assignment and KA02 Cost
element, this scenario always give the priority for OKB9 setting
AS02 Change asset masterTime defendant tabmore intervalAdd intervalfrom the date
of new interval we can maintain the new Cctr
It’s not possible to change the Cctr STD hierarchy in the master based on the time interval, that
means the STD hierarchy allow to change the entire period interval in the Cctr
We need to consider the below factors while changing the functional area in Cctr master
o Always prefer to change at the starting of the period before posting the transactions
o It the transactions already posted in to the Cctr in such case you need to ask the user to
transfer the balances to other Cctr or reverse the transactions then change the
functional area in the Cctr master
o After updating the FA in the Cctr then transfer the balances back
Actual SKF
when you enter the actual SKF in KB31N
o The total SKFs are not updated in the following month and the entered key figures are
only valid for the specific entered period Ex: Power units
o In case of the fixed SKF the values are updated in to the following months till the next
change of SKF units
We can repost the values from one Cctr to other CO object with reference to FI Doc & specific
line item
Advantage
Disadvantage
It is called as variant
One single cycle we can maintain n no of segments
By cycle segment method we can maintain rules between sender & receiver, and also we are
specifying relationship between send & receiver
Each segment contains the who is sender and who is receiver & what cost to be allocated
(Which cost element cost) and also it contains the sender and receiver rules
Sender rules
Posted Amount of %
Fixed amount
Fixed rate
Receiver rules
Variable portion
Fixed %
Fixed amount
Fixed portion
Each sender having the different sender rules even though all receivers having same receiver
rule
Where the different receiver rules for each sender wise
Where the receiver again it becomes the sender in such cases we need to define different
segments
Iterative indicator
The purpose is sys will consider the independent segment with cycle
And also the iterative repeated until each sender fully credited
Where you having the more than one segment in the single cycle
Where the independent relationship between the two segments that means one segment
receiver becomes the another segment sender
Cumulative indicator:
Case 1: The purpose is if this indicator is activated then the sender amount posted/allocated up to
the current period based on the cumulative tracing factor (cumulates from the Period 1 to current
period)
Case 2: In the current period the allocated amount (Sender amount) determines or posted less than
the amount allocated in the previous periods (total amount till period-already allocated amount)
The below are the prerequisites or the cumulative indicator can be used in below business cases
The sender or receiver relationship should be stable with the fiscal year (that means no sender
or receiver shouldn’t be deleted in the fiscal year)
The cumulative indicator should be applicable only in case of sender rule is (Posted amount),
receiver rule is (Variable Portion)
Field Groups: which amount currency values are transferred that is objective currency or transaction
currency (Doc currency)
Consumption: If you want to allocate the consumption Qty then select this check box
Sender rule share in %: what % of the posted amount to be allocated, it is applicable only when
sender rule is posted amount
Functional area: FA only use if you want to allocate the specific FA values
Ex: allocate the values only relevant to FA R29
Sender values tab: the sender values by default its copied form sender rules which are specified in the
segment header tab
Receiver tracing factor tab: we need to specify the receiver %, but the receiver % should not be cross
100% from less than 10%
Ex: sender is fixed rate & receiver is fixed amount in this case, it ignores the sender rule and
always highest priority is receiver rule fixed amount method
Note: the consumption Qty not possible to transfer through assessment method
Segment header tab: The purpose to enter the Secondary cost element in the segment header
tab during the assessment in the sender side the allocated amount is credit under the
specified assessment cost element and debits in receiver side
Sender values: version ‘0’ also not required for actuals, if in case of plan its required
Note: in the sender side all the allocated amount are totaled (Sum-up) & it is credited under the
separate cost assessment cost element, in the receiver side it is debited as a separate
assessment cost element
In the receiver side we can't get the breakup of allocated amount
Allocation Structure: