Professional Documents
Culture Documents
Week 14 CPM APC
Week 14 CPM APC
Medium range
Short range
Finite loading
Back end
Shop-floor Supplier
Input / output analysis
systems systems
Capacity
Planning
and Control
Capacity
Resource Profiles Requirements
Planning
Choice of specific techniques
Rough-cut methods Capacity APS Systems
requirements
planning
45 percent for assembly. Given the Leather 55% 1.2 hr = 0.66 45% 1.2 hr = 0.54 1.2
following schedule for the next six Fabric 55% 1.0 hr = 0.55 45% 1.0 hr = 0.45 1.0
weeks, calculate the labor hours 2. Calculate labor hours needed at each WC.
needed in each of the two work Week 1 2 3 4 5 6
centers: Sewing 45.65 46.2 45.98 46.31 45.65 45.43
Assembly 37.35 37.8 37.62 37.89 37.35 37.17
Week 1 2 3 4 5 6
i.e.
Leather 15 20 18 21 15 13
Sewing @wk 1: (15 x 0.66) + (65 x 0.55) = 45.65 hrs
Fabric 65 60 62 59 65 67
Assembly @wk 6: (13 x 0.54) + (67 x 0.45) = 37.17 hrs
Q7-9: A company with three S7-9: Given: WC A B C Working
product lines has estimated its 100 35 28 12 hours / week
weekly capacity requirements for 200 25 37 56 = 40
three work centers as follows. 300 46 35 33
Work Product Line
Center A B C Calculate:
1. Calculate the total hours WC Total hours
100 35 hours 28 hours 12 hours
for each WC 100 75
200 25 hours 37 hours 56 hours
200 118
300 46 hours 35 hours 33 hours
300 114
a. How many workers (and a. WC Workers Machines Workers @ WC100:
duplicate machines) are 100 2 2 Total hours required / weekly
needed in each work center if 200 3 3 working hours
300 3 3 = 75 ÷ 40 = 1.875 ~ 2
they are to work 40 hours per
week? Machine @ WC100: Workers required / shift = 2 ÷ 1 = 2
b. What is the difference if the b. Total workers required still the
firm decides to work two shifts WC Workers Machines same, however now shift = 2,
(80 hours per week)? 100 2 1 hence the number of machines
200 3 2 could be reduced. i.e. machine @
300 3 2 WC100 = workers/shift = 2/2=1
Production Activity Control (PAC) concerns the
execution of material plans.
plans
Production
Shop-floor scheduling Vendor scheduling and
and control (SFC) Activity follow-up
Control
Basic Shop-floor Control
Theory of
Priority Sequencing
Gantt Charts Constraints
Rules
Scheduling
a. If these jobs are rescheduled by earliest due date, can they be completed on time?
b. Can they be completed on time using the critical ratio technique?
c. Can the jobs be completed on time (using the earliest due date or critical ratio
techniques) if 20 hours of overtime are run in work center X each week?
d. Can the jobs be completed on time (using the earliest due date or critical ratio
techniques) if only one day is required between operations?
S8-3: Hours allowed for Hours allowed for Working
Job Day when due
Given: machine center X machine center Y hours / week
A 36 20 10 = 40
B 96 24 17 5d/wk
C 60 28 25 8hr/d
Calculate: Days allowed for Days allowed for
a. Using EDD Job machine center X* machine center Y**
A 4.5 2.5 8ℎ𝑜𝑢𝑟𝑠
Calculate the days needed 36ℎ𝑜𝑢𝑟𝑠 ÷ = 4.5 𝑑𝑎𝑦𝑠
B 12.0 3.0 𝑑𝑎𝑦
(hour allowed ÷ ℎ𝑜𝑢𝑟𝑠/𝑑𝑎𝑦) C 7.5 3.5
Move: 2d
MC X MC Y
Machine Center X Machine Center Y For EDD, job will start immediately
Move Due with job A, as it is the earliest due
Job Start Days* Done Start Days** Done (in 10 days). Job will be completed
by 9 days.
A 0 4.5 4.5 2 6.5 2.5 9 10
However, job B and C will be
B 4.5 12.0 16.5 2 18.5 3.0 21.5 17 delayed (i.e. job B done 21.5 days
while it is due on day 17)
C 16.5 7.5 24 2 26 3.5 29.5 25
S8-3: Days allowed for Days allowed for
Job machine center X* machine center Y** Day when due
A 4.5 2.5 10
B 12.0 3.0 17
C 7.5 3.5 25
Calculate:
10−0 10 17−0 17
b. Using Critical Ratio: 𝐶𝑅𝐴 = = = 1.11 ; 𝐶𝑅𝐵 = = = 1.00 ; 𝐶𝑅𝐶 =
4.5+2.0+2.5 9 12+2.0+3.0 17
25−0 25
= = 1.92 Using CR, Job B have to be completed first, then A, and C
7.5+2.0+3.5 13
Move: 2d
MC X MC Y
Calculate: c. With 20hrs/ wk OT at MCX, we have to revise the data for Days allowed for MCX
Days allowed for Days allowed for
Job machine center X* machine center Y** Day when due
A 3.0 2.5 10
B 8.0 3.0 17
C 5.0 3.5 25
Move: 2d
MC X MC Y
Move: 2d
MC X MC Y
Calculate:
d. Using EDD with move only 1day
Move: 1d
MC X MC Y