PGA MIRI Perunding Timur Sdn Bhd

Project: Cadangan Merekabentuk, Membina, Menyiapkan Dan Menguji Tauliah Projek Pembangunan
Semula Kem Batalion 12, Pasukan Gerak Am (Pga) Miri Dan Balai Polis Trafik Miri,
Di Atas Lot 633, 2363, 141 Dan 314 Miri Concession Land, Miri Sarawak

rical Defects and Outstanding Works List


Location Service(s) Remark(s) Date Action By

Bangunan Electrical 1) All lighting fittings are to be installed with wire to prevent sagging 18.03.10 ATHSB
Batalion
All Floors

Bangunan Electrical 1) Power Point not provided for Bain Marie 18.03.10 ATHSB
Batalion 2) Switches and ppts are to be adjusted to be the same level as wall 18.03.10 ATHSB
tiling (shift up)
Kantin 3) Trunking in ceiling void not earthed 18.03.10 ATHSB
4) Trunking through wall opening not properly sealed 18.03.10 ATHSB

Bangunan Electrical 1) Earthing not installed 18.03.10 ATHSB


Batalion 2) Cable tray to PABX room not installed. Cable Tray to start from 18.03.10 ATHSB
Manhole in MDF room through to PABX Room
MDF/PABX Telephone 1) Internal Cabling not installed 18.03.10 ATHSB

Bangunan Electrical/ICT 1) Trunking tee off from main trunking not earthed 18.03.10 ATHSB/GTSB
ATHSB/
Batalion 2) Trunking through walls/beams openings not sealed 18.03.10 GTSB
Ground Floor
Corridor

Bangunan ELV 1) PA Speakers not installed (Generally) 18.03.10 ATHSB


Batalion
Ground Floor

Substation SS5 Electrical 1) Genset and AMF Board not installed 18.03.10 ATHSB
2) Trenches not cleaned up 18.03.10 CEES
3) Trenches not filled with sand 18.03.10 CEES
4) Checker Plate cover not installed at trenches 18.03.10 CEES

Water Tower Lightning 1) Lightning Protection (Non Conventional) at Water Tower not 18.03.10 ATHSB
installed

Protection 2) Conduits from Water Tower Pump room are not installed with G.I., 18.03.10
instead with PVC

Balai Polis Electrical 1) All lighting fittings are to be installed with wire to prevent sagging 18.03.10 ATHSB
Trafik Electrical/ICT/ELV 1) Trunking tee off from main trunking not earthed 18.03.10 ATHSB/GTSB
ATHSB/
General 2) Trunking through walls/beams openings not sealed 18.03.10 GTSB
Comments

Balai Polis Electrical 1) Trenches not cleaned up 18.03.10 CEES


Trafik 2) Trenches not filled with sand 18.03.10 CEES
SSB Room 3) Checker Plate cover not installed at trenches 18.03.10 CEES
4) Earthing not connected to Switchboard (SSB/POL) 18.03.10 ATHSB

Balai Polis Builder 1) Louver installed at Server Room (Airconditioned Room) 18.03.10 Builder
Trafik
Server Room

Balai Polis Builder 1) Ceiling suspended from M&E Services 18.03.10 Builder
Trafik
PGA MIRI Perunding Timur Sdn Bhd

All Floors

Project: Cadangan Merekabentuk, Membina, Menyiapkan Dan Menguji Tauliah Projek Pembangunan
Semula Kem Batalion 12, Pasukan Gerak Am (Pga) Miri Dan Balai Polis Trafik Miri,
Di Atas Lot 633, 2363, 141 Dan 314 Miri Concession Land, Miri Sarawak

rical Defects and Outstanding Works List


Location Service(s) Remark(s) Date Action By
Balai Polis Electrical 1) 13A ppt not installed at Main entrance for Sliding door 18.03.10 ATHSB
Trafik
Ground Floor

1) 13A Metal Clad ppt not installed at Black Maria Entrance (for Roller
Balai Polis Electrical 18.03.10 ATHSB
Shutter)
Trafik
Black Maria

Balai Polis Electrical 1) Switch level incorrect 18.03.10 ATHSB


Trafik
Lockup

Subsation Electrical 1) Supporting Bracket at MSB not installed (Trench) 18.03.10 ATHSB
SSTrafik 2) Trenches not cleaned up 18.03.10 CEES
3) Trenches not filled with sand 18.03.10 CEES
4) Checker Plate cover not installed at trenches 18.03.10 CEES

Dewan Makan Electrical 1) Switches and ppts not the same level 18.03.10 ATHSB
Kantin 2) All lighting fittings are to be installed with wire to prevent sagging 18.03.10 ATHSB

Kuarters Kelas Electrical 1) Lighting not installed 18.03.10 ATHSB


F 19A
Plant room
(Top Floor)

Kuarters Kelas Telephone 1) Trunking from SDF Room to Telephone Riser not installed 18.03.10 ATHSB
F 19A
Plant room
(Ground Floor)

External St Lighting 1) Verticality of street lighting poles are not adjusted 18.03.10 CEES

Ext. Telephone 1) JC9C at Pengangkutan Drop off porch not level to road level 18.03.10 CEES

Subsation Electrical 1) Supporting Bracket at MSB not installed (Trench) 24.03.10 ATHSB
SSTrafik 2) Trenches not cleaned up 24.03.10 CEES
3) Trenches not filled with sand 24.03.10 CEES
4) Checker Plate cover not installed at trenches 24.03.10 CEES
5) Lighting not installed 24.03.10 ATHSB
6) MCB at DB not installed 24.03.10 ATHSB
7) Switches and PPT not installed 24.03.10 ATHSB
8) Genset and AMF Board not installed 24.03.10 ATHSB

Substation SS5 Electrical 1) Genset and AMF Board not installed 24.03.10 ATHSB
2) Trenches not cleaned up and dewatered 24.03.10 CEES
3) Trenches not filled with sand 24.03.10 CEES
PGA MIRI Perunding Timur Sdn Bhd

4) Checker Plate cover not installed at trenches 24.03.10 CEES


5) MCB at DB not installed 24.03.10 ATHSB

Project: Cadangan Merekabentuk, Membina, Menyiapkan Dan Menguji Tauliah Projek Pembangunan
Semula Kem Batalion 12, Pasukan Gerak Am (Pga) Miri Dan Balai Polis Trafik Miri,
Di Atas Lot 633, 2363, 141 Dan 314 Miri Concession Land, Miri Sarawak

rical Defects and Outstanding Works List


Location Service(s) Remark(s) Date Action By

Bengkel Electrical 1) Trunking improperly installed 24.03.10 ATHSB


Kenderaan 2) Openings not sealed 24.03.10 ATHSB
Staircase 3) Ceiling points not properly sealed 24.03.10 ATHSB
4) Switches not patched up well 24.03.10 ATHSB
5) Isolator not patched up 24.03.10 ATHSB

Bengkel Electrical 1) Improper jointing of conduit/flexible pipe 24.03.10 ATHSB


Komunikasi

Stesen PMP Builder 1) No space to install light fitting due to omission of ceiling boards 24.03.10 Builder
(2 no.s of 2x2 Recessed light fittings outside of Pejabat)

Cawangan Builder 1) Shift of Ceiling grid caused lighting to be off centered 24.03.10 Builder
Pengangkutan
Lobby

1) Change of Mineral Fiber Board to UAC Ceiling caused lighting to be


Dewan Builder installed 24.03.10 Builder
Serbaguna on the surface (perimeter Prismatic lighting)
Electrical 2) Middle row of Medium Bay lighting to be shifted up one space (All) 24.03.10 ATHSB

External Electrical 1) Verticality of Street Lighting not rectified 24.03.10 CEES