Mubadala Petroleum Indonesia (MPI) planned to conduct lifting of luffing cylinder (crane component)
from PQP to WHP through the platform bridge. Due to the unavailability of PQP Crane, the lifting (laying
down) process from PQP topdeck to PQP bridge will use beam clamp that will be attached at the beam,
used for anchor point with a load around 4 Tons, consisted of piston rod and cylinder (barrel).
3rd party contractor will analyze and simulate load in the beam clamps location as shown in the image
below. Besides that, the contractor also conducts load simulation in the bridge to calculate maximum
bridge load capacity to ensure the luffing cylinder (consists of 2 lifting activity for cylinder tube and piston
rod) is able to safely transported to WHP.
Figure 1 Lifting plan route (as per etail step transfer luffing crane PQP to WHP)
2 Scope of Work
The scope of work are listed below:
5 Detail Load
Load that will be applied in the analysis covers:
Lifting Location
4 D.1
SCTN 11 of FRMWORK 1 of STRUCTURE RB-WPI-PLT-ST-DR-2401-10 PQP Topside
1
/PSDMB-SP-EL(+)33000.NEW Module P2 Top Deck Primary Framing Plan
5 D.2