RC443 DS 000 2542 0001 Rev2 LNG Storage Tank
RC443 DS 000 2542 0001 Rev2 LNG Storage Tank
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 3/13
Amend. Date N° FJLNG-DATA-TS-MA-009
CONTENTS
1 GENERAL DATA
4 FLOW RATES
5 SITE DATA
5.1 CLIMATIC DATA
5.2 SEISMIC DATA
6 LOADINGS
6.1 IMPACT LOADING
6.2 BLAST LOADING
6.3 FIRE HAZARD
7 LEAKAGE AND SPILL
8 INSULATION CRITERIA
9 HYDROTEST
11 MISCELLANEOUS
11.1 FIRE FIGHTING
11.2 PUMP HANDLING DEVICE
11.3 LIFT
12 GUARANTEE
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 4/13
Amend. Date N° FJLNG-DATA-TS-MA-009
1 GENERAL DATA
Item number TS-T-02 01 & TS-T-02 02
Quantity 2
Storage tank type Full containment tank, with 9% nickel
inner tank and concrete outer tank and
roof. Membrane tank may be proposed
as alternate.
Net working capacity 155 000 m3
Gross capacity By Subcontractor *
Nominal diameter of inner tank By Subcontractor *
Height of inner tank By Subcontractor *
Internal diameter of outer tank By Subcontractor *
Foundation type Elevated slab (without heating system)
* : For sizing criteria, see appendix 1
4 FLOW RATES
Maximum liquid filling rate 13 200 m3/h
Maximum liquid pump-out rate 1350 m3/h
Maximum air flow to tank vacuum breakers See RC443.NT.000.P050.0003
Relief calculation note
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 5/13
Amend. Date N° FJLNG-DATA-TS-MA-009
Maximum vapour flow to tank relief valves See RC443.NT.000.P050.0003
Relief calculation note
5 SITE DATA
6 LOADINGS
The relief valves tail pipes shall be designed such that heat radiation, in case of
relief valve fire, is not greater than 32 kW/m².
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 6/13
Amend. Date N° FJLNG-DATA-TS-MA-009
7 LEAKAGE AND SPILL
The tank shall be designed to withstand the following external leaks and spills :
- Minor leak on tank top equipment (e.g. flange leak) shall not produce any
damage
- Runoff from a major spill on the tank top shall not impair the tank integrity
8 INSULATION CRITERIA
The maximum boil-off rate shall not exceed 0.05% per day of the gross tank liquid
content, based on pure methane, constant pressure, maximum ambient
temperature and maximum solar radiation.
9 HYDROTEST
Inner tank shall be hydrotested with fresh water.
11 MISCELLANEOUS
11.3 LIFT
The Subcontractor shall provide a 500 kg payload lift. It shall give access from the
grade level, to the peripheral gangway at the top of the wall and to the pump
platform. The lift shall be explosion proof, and approved for personal use.
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 7/13
Amend. Date N° FJLNG-DATA-TS-MA-009
12 GUARANTEE
Subcontractor shall guarantee :
- The maximum boil-off rate
- The net tank capacity at operating conditions
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 8/13
Amend. Date N° FJLNG-DATA-TS-MA-009
APPENDIX 1
LEVELS AND VOLUMES DEFINITION
Top of shell
LAHH
Net
Working
Capacity
LALL
Net working capacity = volume between normal maximum operating level and
normal minimum operating level at operating temperature.
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 9/13
Amend. Date N° FJLNG-DATA-TS-MA-009
Gross capacity = volume between maximum design level and top of annular
bottom plate level at operating temperature.
Height between top of shell and maximum design level is determined by the
minimum freeboard according to code or the accommodation of the sloshing wave
height in OBE and SSE.
The volume between LAH and LAHH corresponds to 5 minutes at maximum filling
rate.
The volume between LAL and LALL corresponds to 5 minutes at maximum send
out rate.
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 10/13
Amend. Date N° FJLNG-DATA-TS-MA-009
APPENDIX 2
SUMMARY OF TANK OPERATING PRESSURES
(mbarg)
270 PAHH
255 PAH
30 PAL
15 PALL
0 Atmospheric pressure
Notes :
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 11/13
Amend. Date N° FJLNG-DATA-TS-MA-009
APPENDIX 3
NOZZLE LIST
N° RC443.DS.000.2542.001
2 08/04/05 Page : 12/13
Amend. Date N° FJLNG-DATA-TS-MA-009
N11 2 100 N Annular purge With 2 risers and ring DN 80
N12 1 50 N Bottom purge With 1 radial line DN 25 per cellular
glass layer and1 common riser
N13 1 50 N Bottom purge With 1 radial line DN 25 per cellular
glass layer and1 common riser
N14 4 50 N Pressure balance With 4 risers DN 25
N15 1 600 Y Pressure relief valve
N16 1 50 N Pressure relief valve
pilot
N17 1 600 N Vacuum breaker valve (b)
N18 * 150 N Perlite nozzle (b)
N19 * * N Suspended deck vent (b)
K1 2 150 N Level gauge With stilling well DN 300
K2 2 50 N Multi-element With well DN 50 (c)
temperature sensor
K3 1 150 N LTD Level / temperature / density
measurement
K4 1 150 N Level switch (c)
K5 1 50 N Temperature
K6 1 50 N Temperature
K7 1 50 N Pressure
K8 1 50 N Pressure
K9 1 300 N Spare For camera installation
K10 2 400 N Temperature sensors (b)
outlet
M1 1 900 N Personnel manhole
M2 1 1300 N Equipment manhole
M3 1 900 N Personnel passage
M4 1 1300 N Equipment passage
(a) : Nozzle provided with heatbreak (Y) or not (N)
(b) : By tank Contractor
(c) : To be confirmed
Rév. Date
01.02
N° RC443.DS.000.2542.001
2 08/04/05 Page : 13/13
Amend. Date N° FJLNG-DATA-TS-MA-009