Embankment Attention on Construction method

Type

1.Widnning Required Adequate bonding between old and new filling Removing top soil and scarify the sloping faces of
existing material embankment.
embankment
If slopes steeper than 2 horizontal to 1 vertical, subject to
decision on Engineer.
Benching of the slopes carried out at regular intervals.

2.Embankment on If slopes steeper than 2 horizontal to 1 vertical, subject to


hill slopes decision on Engineer.
Benching of the slopes carried out at regular intervals.

3.Embankment on
existing paved 1. Embankment height < 1.0 m Existing surface scarify prior to placing the material.
surface 2. Embankment height > 1.0 m Existing surface scarify, subject to decision on Engineer.

4.Embankment  Precaution to see the structure is not disturbed by the  Filling surround structure - By using suitable material
around structures embankment filling. and equipment as mechanically operated Hand
 Filling near to structure shall not be carried out till the rammers to reach compacted densities. As on
concrete or masonry work in position at least for7day Paragraph - 4.5
unless otherwise directed by engineer.  Fill up simultaneously on each side to avoid unequal
pressure acting it.

5. Embankment Unable to bear load of compacted equipment. Compaction of


over soft ground initial layer carried as given in contract document or directed
by the Engineer.
6.Construction of
drainage (filter
layer behind
structure)
5. Embankment construction under special condition