Accelerasi Pek STP Rev 2

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

WORK STEP ACCELERATED STUCTURE WORK

DIMENSION MAN POWER


NO. JOB DESCRIPTION VOL QTY MATERIAL QTY EQUIPMENT START FINISH DURATION
LENGTH WIDTH DEPTH SIFT1 SIFT2

1 PEKERJAAN SLAB LANTAI ZONE2


WATER PROOFING INSTALL DONE
REBAR INSTALL
CASTING CONCRETE

2 PEKERJAAN STP WALL ZONE 1


REBAR INSTALL DONE TADANO CRANE 12 6 11/11/2020 15/11/2020
FORM WORK INSTALL DONE TADANO CRANE 12 6 12/11/2020 16/11/2020
CASTING CONCRETE DONE TADANO CRANE 8 8 16/11/2020 17/11/2020

3 UN INSTALL STRUTTING LAYER 2 ZONE 1 TADANO CRANE 6 6 14/11/2020 16/11/2020

4 PEKERJAAN STP WALL ZONE 2


REBAR INSTALL DONE TADANO CRANE 18 12 16/11/2020 19/11/2020
FORM WORK INSTALL DONE TADANO CRANE 26 12 17/11/2020 20/11/2020
CASTING CONCRETE DONE TADANO CRANE 6 6 20/11/2020 21/11/2020

5 PEKERJAAN STP WALL BLOCK THE ROOM ZONE 1


REBAR INSTALL DONE TADANO CRANE 18 12 20/11/2020 21/11/2020
FORM WORK INSTALL DONE TADANO CRANE 26 12 22/11/2020 24/11/2020
CASTING CONCRETE DONE TADANO CRANE 6 6 25/11/2020 26/11/2020

UN INSTALL STRUTTING LAYER2 ZONE 2 TADANO CRANE 6 6 17/11/2020 21/11/2020

6 PEKERJAAN STP WALL BLOCK THE ROOM ZONE 2


REBAR INSTALL 20/11/2020 TADANO CRANE 18 12 25/11/2020 27/11/2020
FORM WORK INSTALL 19/11/2020 TADANO CRANE 26 12 26/11/2020 28/11/2020
CASTING CONCRETE TADANO CRANE 6 6 29/11/2020 30/11/2020

7 PEKERJAAN STP SLAB MEZZANINE ZONE 1


FORM WORK INSTALL 20/11/2020 TADANO CRANE 26 12 27/11/2020 29/11/2020
REBAR INSTALL 19/11/2020 TADANO CRANE 18 12 29/11/2020 30/11/2020
CASTING CONCRETE TADANO CRANE 6 6 30/11/2020 01/12/2020

8 INSTALLING WATER PROOFING FOR THE OUTER WALL -6.500 4 4 30/11/2020 02/12/2020

9 BACK FILL TO ELEVATION ( - 7.000 ) EXCAVATOR PC200 2 2 03/12/2020 10/12/2020

10 PEKERJAAN STP SLAB MEZZANINE ZONE 2


FORM WORK INSTALL 20/11/2020 TADANO CRANE 26 12 30/11/2020 02/12/2020
REBAR INSTALL 19/11/2020 TADANO CRANE 18 12 01/12/2020 03/12/2020
CASTING CONCRETE TADANO CRANE 6 6 03/12/2020 04/12/2020

UN INSTALL STRUTTING LAYER 1 ZONE 1 TADANO CRANE 6 6 02/12/2020 04/12/2020

11 PEKERJAAN STP WALL ZONE 1 STEP 2


REBAR INSTALL 20/11/2020 TADANO CRANE 26 12 04/12/2020 07/12/2020
FORM WORK INSTALL 19/11/2020 TADANO CRANE 18 12 06/12/2020 08/12/2020
CASTING CONCRETE TADANO CRANE 6 6 08/12/2020 09/12/2020

12 PEKERJAAN STP WALL ZONE 2 STEP 2


REBAR INSTALL 20/11/2020 TADANO CRANE 18 12 08/12/2020 11/12/2020
FORM WORK INSTALL 19/11/2020 TADANO CRANE 26 12 10/12/2020 12/12/2020
CASTING CONCRETE TADANO CRANE 6 6 12/12/2020 13/12/2020

UN INSTALL STRUTTING LAYER 1 ZONE 2 TADANO CRANE 6 6 07/12/2020 10/12/2020

13 PEKERJAAN STP TOP SLAB ZONE 1 AND 2


FORM WORK INSTALL 20/11/2020 TADANO CRANE 26 12 09/12/2020 20/12/2020
REBAR INSTALL 19/11/2020 TADANO CRANE 18 12 17/12/2020 22/12/2020
CASTING CONCRETE TADANO CRANE 6 6 22/12/2020 23/12/2020

14 INSTALLING WATER PROOFING FOR THE OUTER WALL -3.300 4 4 13/12/2020 17/12/2020
15 INSTALLING WATER PROOFING FOR THE OUTER TOP SLAB -3.300 6 4 26/12/2020 27/12/2020

16 DOG HOUSE 8 8 24/12/2020 30/12/2020

17 FINISHING 14 14 06/12/2020 30/12/2020

18 BACK FILL TO ELEVATION ( 00.000 ) EXCAVATOR PC200 2 2 28/12/2020 03/01/2021

NOTE
TOTAL STRUCTURE MAN POWER SHIFT 1 54 WORKERS Dibuat oleh,
TOTAL STRUCTURE MAN POWER SHIFT 2 30 WORKERS PT. TOTALINDO EKA PERSADA
TOTAL ARCHITECTURE MAN POWER SHIFT 1 14 WORKERS
TOTAL ARCHITECTURE MAN POWER SHIFT 2 14 WORKERS

( Haryo Nuswantoro )
Project Manager