7S92-06011-CO-TP-540 - MST - For - Re-Calibration of PSV-039
7S92-06011-CO-TP-540 - MST - For - Re-Calibration of PSV-039
: 7S92-06011-CO-TP-540
Method Statement Statement Rev. :0
for Re-Calibration of PSV-039 Date : 28 Dec. 2012
Page : 2 of 4
1. PURPOSE
The purpose of this procedure is to Re-calibration of the PSV-039. Related work will be on the
PTTLNG Jetty Development and LNG Receiving Terminal Project to be built at Map Ta Phut
Indutrial Estate, Rayong, Thailand.
2. DEFINITIONS
2.1 COMPANY” means PTTLNG Company Limited, its successors and assignees.
2.2 CONTRACTOR” means the GS Consortium that GS Engineering & Construction Corp. leads
under Process and Utility piping, for the PTTLNG Jetty Development and LNG
Receiving Terminal Project.
2.3 “SUBCONTRACTOR” means any company, firms or person with whom CONTRACTOR
enters into a subcontract.
2.4 “SITE” means the areas where the WORK shall be performed as indicated in the PROJECT
SPECIFICATION situated at Map Ta Phut Industrial Estate, Rayong Province, Thailand.
3. REFERENCES
3.1 Drawings
3.1.1 Piping & Instrument Diagram: 7S92-A1-06011-0100-PC-013 Rev.8.
3.1.2 Piping & Instrument Diagram: 7S92-A1-06011-0100-PC-016 Rev.8.
3.1.3 Piping & Instrument Diagram: 7S92-A1-06011-0900-PC-001 Rev.8.
4. PERSONNEL RESPONSIBILITIES
4.2 Field QA/QC Manager (FQM) is responsible for assuring the construction activities
and his personnel are responsible for inspection and reviewing the witness/holding points
and the activities to be monitored as surveillance. Quality control personnel give the
organizational freedom to identify and prevent quality problems.
PMC Doc. No.: 7S92-06011-CO-TP-540
Method Statement Statement Rev. :0
for Re-Calibration of PSV-039 Date : 28 Dec. 2012
Page : 3 of 4
4.3 Mechanical Superintendent is responsible for all orders and directions issued by the
Construction Manager. He is responsible for supervising his designated work, controlling
activities for Supervisors and Foremen, assignment of major equipment, ensuring works
executed safely, subcontractors execute works in safe manner and monitoring the work of
Subcontractors.
4.4 Safety Manager is responsible for monitoring and observing the safe execution of the work,
the safety work plan, compliance with project SHE requirements and procedures, works
conducted as mentioned in approved WMS / JSA and work permit.
5. WORK PROCEDURES
5.2 Re-Installation
5.2.1 Check pressure at VT-0177 and vent clear.
5.2.2 Remove out blind flange.
5.2.3 PSV-039 Reinstall and tightening.
5.2.4 LNG-0176, LNG-0178 Valve service for leak test.
PMC Doc. No.: 7S92-06011-CO-TP-540
Method Statement Statement Rev. :0
for Re-Calibration of PSV-039 Date : 28 Dec. 2012
Page : 4 of 4
6.1 All safety precautions shall be taken care as required as per JSA.
6.2 Testing area will be barricaded and warning signs for pressure testing shall be displayed.
6.3 All testing equipments and instruments shall be inspected prior to testing commencing.
6.4 During high pressure testing, if required, nearby area work will be suspended till test is
complete.
6.5 GSC supervisors and safety shall ensure all required work permits approved and JSA .
6.6 All testing personnel shall be provided with and use required PPE i.e. safety helmet,
safety glasses (clear & dark), safety shoes/boots, hearing protection, gloves, safety harness
for working at height etc. additional PPE shall be supplied as required.
6.7 Disciplinary action will be taken against personnel committing safety violations, action
taken will depend on the severity of the violation.
7. ATTACHMENTS