COMPUTATION SHEET

(REINFORCED CONCRETE WORKS)


Project:
Owner:
Location:

MATERIALS AND ESTIMATED QUANTITIES


REQUIRED
GI Tie
Items to be
CALCULATION 10 mm 12 mm 16 mm Wires
estimated
Ø RSB Ø RSB Ø RSB #16
(pcs) (pcs) (pcs) (kg)

Net Length of 1 Bar


= 1.0m – (2 x 0.075) = 0.85m
Total # of Cut Bars in 1 Footing
= 10 x 2 = 20pcs
Total # of Bars for 9 Footing
= 20 x 9 = 180 pcs. @ 0.85 m. long
Total Length of Bars
Reinforcing = 180 x 0.85 = 153m
Bars for No. of Bars Req’d (12mmØ) 26 5.09
Column 153 m
Footing = = 25.5, say
6.0 m
……………………………………………………….26pcs

10 x 10 x 0.3 x 9
Tie Wires Req’d = =
53
…………………………………….5.09 kg

Reinforcing Number of Similar Beam = 5 pcs 29 36 6.79


Bars for
Continuous For Longitudinal Bars (16mm Ø):
Beam AC Bar Straight Length = 7.3m + 0.35 = 7.65m
(0.4m x 0.2m) 5 pcs x 7.65 x 4.4
# of F/L Bars Req’d: = = 28.05pcs, say
6.0 m
………….28pcs

For Short Bars (16mm Ø):


Length of Left Corner Short Bar
3.2
= +0.3+ 0.35 = 1.45m
4
Length of Right Corner Short Bars
3.2
= +0.3+ 0.35 = 1.45m
4
Length of First Bottom Bar:
= 3.2 x 0.6 = 1.92m
Length of Second Bottom Bar:
= 3.2 x 0.6 = 1.92m
Length of Middle Top Bar:
3.2+ 3.2
= +0.3 = 1.9m
4
Total Length of Short Bars = 8.64
5 pcs x 8.64
# of F/L Bars Req’d = = 7.2, say
6
……………………………..8pcs

For Stirrups (10mm Ø):


Number of Stirrups per Beam = 40pcs
Total Number of Stirrups = 40 x 5pcs = 200pcs
Using Table D-3:
200 pcs
Total F/L Req’d = = 28.57, say
7 pcs / ¯¿ ¿
……………………………….29pcs

40 stirrups x 6 bars x 5 beams x 0.3


For Tie Wires = =….…….
53
……….6.79kg
Reinforcing Number of Similar Beams = 1pc 6 8 1.36
Bars for
Continuous For Longitudinal Bars (16mm Ø):
Beam 4/AC Bar Straight Length = 7.3m + 0.35 = 7.65m
(0.3m x 0.2m) 1 pc x 7.65 x 4.4
# of F/L Bars Req’d: = = 5.5pcs, say
6.0 m
………………….6pcs

For Short Bars (16mm Ø):


Length of Left Corner Short Bar
3.2
= +0.3+ 0.35 = 1.45m
4
Length of Right Corner Short Bars
3.2
= +0.3+ 0.35 = 1.45m
4
Length of First Bottom Bar:
= 3.2 x 0.6 = 1.92m
Length of Second Bottom Bar:
= 3.2 x 0.6 = 1.92m
Length of Middle Top Bar:
3.2+ 3.2
= +0.3 = 1.9m
4
Total Length of Short Bars = 8.64
1 pc x 8.64
# of F/L Bars Req’d = = 1.44, say
6
……………………………..2pcs
For Stirrups:
For Stirrups (10mm Ø):
Number of Stirrups per Beam = 40pcs
Total Number of Stirrups = 40 x 1pcs = 40pcs
Using Table D-3:
40 pcs
Total F/L Req’d = = 5.71, say
7 pcs / ¯¿ ¿
…………………………………..6pcs

40 stirrups x 6 bars x 1 beam x 0.3


For Tie Wires = = …………………
53
1.36kg
Reinforcing Number of Similar Beams = 3pcs 18 27 1.83
Bars for
Continuous For Longitudinal Bars (16mm Ø):
Beams in Bar Straight Length = 9.15 + 0.35 = 9.5m
Column A 3 pcs x 9.5 x 4.4
# of F/L Req’d = = 20.9, say
(0.4m x 0.2m) 6.0 m
…………………………….21pcs

For Short Bars (16mm Ø):


Length of Left Corner Short Bar:
3.7
= + 0.3+0.35 = 1.58m
4
Length of Right Corner Short Bar:
0.65
= + 0.3+0.35 = 0.81m
4
Length of First Bottom Short Bar:
= 3.7 x 0.6 = 2.22m
Length of Second Bottom Bar:
= 3.7 x 0.6 = 2.22m
Length of Third Bottom Bar:
= 0.65 x 0.6 = 0.39m
Length of First Top Bar:
3.7+3.7
= +0.3 = 2.15m
4
Length of Second Top Bar:
3.7+0.65
= +0.3 = 1.39m
4
Total Length of Short Bars = 10.76m
10.76 m x 3 beams
# of F/L Req’d = = 5.38, say
6 m/ ¯¿ ¿
………………………….6pcs

For Stirrups (10mm Ø):


Number of Stirrups per Beam = 42pcs
Total Number of Stirrups = 42pcs x 3beams = 126pcs
Using Table D-3:
126 pcs
Total F/L Req’d = =
7 pcs / ¯¿ ¿
………………………………………………..18pcs

18 stirrups x 6 bars x 3 beams x 0.3


For Tie Wires = =
53
………………..1.83kg
Total Length of Wall Footing = 35m

For Straight Bars (12mm Ø):


35 x 3
# of F/L Req’d = = 17.5, say
6.0
……………………………………….18pcs
Reinforcing
Bars for Wall
For Cross Bars (12mm Ø): 23 0.51
Footing
35
(0.4m x 0.2m) # of F/L Req’d = = 4.86, say ………………………………………
0.30 x 24
5pcs

18 straightbars x 5 cross bars x 0.3


For Tie Wires = =
53
………………..0.51kg
3.5
Test for Slab = = 1.75, 2-way slab
2.0

By Area Method:
Reinforcing
Area of Slab = 7.00 sq.m
Bars for Roof
Number of Similar Slabs = 8 Slabs 162 12.43
Slab S2
Using Table 3-9:
(10mm Ø)
# of F/L 6.00m Bars @200mm Spacing
= 7.0 sq.m x 8 slabs x 2.880 = 161.28, say …………………..162pcs

For Tie Wires = 7.0 sq.m x 8 slabs x 0.222 = …………………….12.43kg


3.5
Test for Slab = = 3.5, 1-way slab
1.0

By Area Method:
Reinforcing
Area of Slab = 3.5 sq.m
Bars for Roof
Number of Similar Slabs = 2 slabs 16 0.85
Slab S1
Using Table 3-9:
(10mm Ø)
# of F/L 6.00m Bars @250mm Spacing
= 3.5 sq.m x 2 slabs x 2.225 = 15.58, say ……………………..16pcs

For Tie Wires = 3.5 sq.m x 2 slabs x 0.121 = ………………………0.85kg