This inspection and test plan outlines procedures for field density testing using the sandcone test for a power plant project in Asam Asam, Indonesia. Key steps include:
1) Reviewing technical specifications and ensuring all documentation is the latest revision
2) Preparing the work area through activities like clearing, grubbing, stripping, and excavation
3) Testing fill and backfill material based on specifications, including tests for moisture content, gradation, and compaction frequency
4) Documenting test results and equipment calibration certificates and reviewing quality control documents.
This inspection and test plan outlines procedures for field density testing using the sandcone test for a power plant project in Asam Asam, Indonesia. Key steps include:
1) Reviewing technical specifications and ensuring all documentation is the latest revision
2) Preparing the work area through activities like clearing, grubbing, stripping, and excavation
3) Testing fill and backfill material based on specifications, including tests for moisture content, gradation, and compaction frequency
4) Documenting test results and equipment calibration certificates and reviewing quality control documents.
This inspection and test plan outlines procedures for field density testing using the sandcone test for a power plant project in Asam Asam, Indonesia. Key steps include:
1) Reviewing technical specifications and ensuring all documentation is the latest revision
2) Preparing the work area through activities like clearing, grubbing, stripping, and excavation
3) Testing fill and backfill material based on specifications, including tests for moisture content, gradation, and compaction frequency
4) Documenting test results and equipment calibration certificates and reviewing quality control documents.
PROCEDURE FIELD DENSITY TEST WITH SANDCONE TEST Contract doc No : IKCP0-YYB-G-05-… Subcon: TEKNIKO DESCRIPTION PLTU CFSPP ( 2 x 100 MW ) PAGE : 2 PROJECT ASAM ASAM KASELTENG 2 REV : 0 Inspection Activity Inspection NO Item Activity Referance Document Verifying Document CONTRAC- Owner Remarks Location SUBCON TOR PLN Technical Specification & Procedure Review all technical specifications, drawing, procedures & work instructions 1.1 1.1.1 All Tech. Spec., Drawings, Proc. are latest revision Management System Manual, Standard All tech. spec., drawing, procedures, work instruction shall be clarified, Approved General Instruction, Technical P/R R/A R/A 1.0. 1.2 Operating Procedure, Document Contract - understood and implemented accordingly Specification & Procedures, drawings, etc. Agreement, Standard & Code 1.3 Finalise deviation, generate new procedure and work instruction if required 1.4 Handover work area document W W R Surface Preparation 2.1 Site clearance condition (Clearing, Grubbing And Stripping) Clearing includes removal and disposal of trees and downed timber, bush, hedges, bushes and other 2.2 vegetation or organic materials; and rubbish, debris or other foreign or objectionable materials at grade, except the removal of topsoil. Grubbing includes removal and disposal of stumps, large roots, buried logs and other objectionable 2.3 Tech. Spec., Drawing, Proc., Gen. Applicable Specification, Official Certificate Subcontractor 2.0 materials to 1,000 mm below ground surface. H W RW Instruction & Material Inspection Report Workshop 2.4 Measurement of existing ground profile before excavation 2.5 Routing of dewatering discharge lines Removing of all rubbish , humus, vegetable matter and all or part of the organic topsoil in the 2.6 respective areas, which can be removed by simple excavation methods. All materials excavated during clearing, grubbing and stripping operations shall be wasted in disposal 2.7 areas Excavation Excavation including construction of temporary diversion ditches, culverts, temporary access road 3.1 etc. Applicable Specification Approved Drawing, 3.2 Coordinate and leveling must be check with refer to benchmark Tech. Spec., Drawing, , Proc., Gen. 3.0 Applicable Specification & Report FIELD (ON SITE) H W RW 3.3 Bottoms of all excavations must be trimmed to line and grade. Instruction, Standard & Code. Fabrication Protection and Support shall be arranged for minimum interference with Electrical, mechanical, 3.4 Piping etc if any. 3.5 Minimum excavation from pipelines, conduits, and the side of trench. Fill / Backfill Material General fill material shall be well graded, no more than 15 % passing 4.1 4.0 No. 200 screen, maximum particle size 75 mm 4.2 Type structural fill material 4.3 Optimum moisture content 4.4 Trench Fill material Sand material Applicable Specification Approved Drawing, Tech. Spec., Drawing, , Proc., Gen. 4.5 Field Compacted around Structures Applicable Specification & Report FIELD (ON SITE) H W W Instruction, Standard & Code. 4.6 Field Compacted Backfill around pipe trench Fabrication 4.7 Field Compacted Backfill around Fiberglass Reinforced Pipe (FRP) 4.8 Height of backfill 4.9 Maximum size of stone in the backfill material 4.10 Lab test for General backfill materials with gradations / Sieve analisys Test 4.11 Heavy Equipment compacted rolling around structure Fill/Back Fill Test Frequency Tech. Spec., Drawing, , Proc., Gen. Applicable Specification Approved Drawing, 5,0 FIELD (ON SITE) 5.1 Bearing test interval frequency Instruction, Standard & Code. Applicable Specification H W W Documentation 6.1 Summary monitoring or Quality Inspection report activity Approved Drawing ,Applicable R&A R&A 6,0 6.2 Calibration Certificate of equipment test Contract, Tech. Spec., Proc. Specification,All Quality Document as per R 6.3 QAQC review of site generated document Contract (Inspection Reports, NCR, R R 6.4 Mill certificate material & manufacture certificate MDR,Warranty, Punch List, Etc.) Legend : P = Preparation, W = Witness, SW = Spot Witness, RW = Random Witness, R = Document Review, H = Hold Points, A=Approved Standard and code : ASTM Mechanical Test : Destructive Test : DIN : Non Destructive Test : AS/NZS