PROJECT DESCRIPTION: VCS Version 3

Wind Power Project by NACL in


Tamil Nadu
M/s. Nagarjuna Agrichem Limited. (NACL) (entity)

Project Title Wind Power Project by NACL in Tamil Nadu

Version 01

Date of Issue 07-10-2013

Prepared By M/s. Nagarjuna Agrichem Limited. (NACL)

Contact Mr. R. K. S. Prasad


M/s. Nagarjuna Agrichem Limited
Plot No.12-A, “C” Block, Laxmi Towers,
,Nagarjuna Hills, Panjagutta,
Hyderabad-500 082
Andhra Pradesh, India
91 040-66510050
rkprasasd@nagarjunaagrichem.com

1
v3.1
PROJECT DESCRIPTION: VCS Version 3

Table of Contents

S.N Contents Page no

1 Project Details 3

2 Application of Methodology 8

3 Quantification of GHG Emission reduction and 8


removals

4 Monitoring 9

5 Environmental Impact Assessment 9

6 Stakeholder 9

2
v3.1
PROJECT DESCRIPTION: VCS Version 3

1 PROJECT DETAILS

1.1 Summary Description of the Project


The project activity is a wind power project having total capacity 6.3MW (2.1 MW x 03 nos.) The
project activity involves the implementation of 3 nos. of SUZLON make S-88 WTGs of capacity 2.1
MW each. The project activity utilizes the kinetic energy of wind, for generation of electrical energy
through wind electric generator. In wind power generation, kinetic energy of wind is converted into
mechanical energy by using wind turbine and subsequently into electrical energy.

The generated electricity from the project activity will be sold to the state grid of Tamil Nadu which
comes under Southern grid of India. The project activity can generate electricity to the order of
12.792 Million kWh annually which otherwise been generated by existing power plants or addition of
new power plants in the Southern grid. The renewable electricity generation will displace electricity
and associated GHG emissions approximately 11,733 tonnes of CO 2 equivalent from the Southern
grid

The project activity is implemented by M/s. Nagarjuna Agrichem Limited. (NACL) and is selling the
generated electricity to state electricity utility. The project activity details are as follow:

Project Promoter Nagarjuna Agrichem Limited


Capacity (MW) 2.1 2.1 2.1
WTG HT.SC. No. 3337 3338 3339
Commissioning Date 28/09/2010 28/09/2010 28/09/2010
Technology Used Suzlon Energy Limited
Village Sayamalai Keelaneelithanallur Melaneelithanallur

Taluka Sankarankoil
District Tirunelveli
State Tamil Nadu

1.2 Sectoral Scope and Project Type


Wind Power Project by NACL in Tamil Nadu is not AFOLU project.

Sectoral Scope : 1 (Energy industries (renewable - / non-renewable sources)


Project type: i. Renewable energy projects
Project category: D. Electricity generation for a system.

1.3 Project Proponent

Organization: M/s Nagarjuna Agrichem Limited


Street/P.O.Box: Plot No. 12-A, “C” Block, , Laxmi Towers, Panjagutta
Building: Nagarjuna Hills
City: Hyderabad
State/Region: Andhra Pradesh
Postfix/ZIP: 500 082
Country: India
Telephone: 91-40-23358217/ 23351742

3
v3.1
PROJECT DESCRIPTION: VCS Version 3

FAX: 91-40-23350234
E-Mail:
URL:
Represented by:
Title: Chief Financial Officer
Salutation: Mr.
Last Name: Prasad
Middle Name:
First Name: R. K. S.
Department:
Mobile: 91 9701301919
Direct FAX: 91 040-23350234, 23358062
Direct tel: 91 040-66510050
Personal E-Mail: rkprasasd@nagarjunaagrichem.com

1.4 Other Entities Involved in the Project

Refer Section A.3. of the Registered PDD Ref no 5096.

1.5 Project Start Date

28/09/2010.

1.6 Project Crediting Period


28/09/2010 to 01/12/2011 (inclusive of both days)

1.7 Project Scale and Estimated GHG Emission Reductions or Removals

The project capacity is 6.3 MW, which is less than 15 MW for prescribed small scale limit. Hence
the present project falls under small scale.

As per CDM Registered PDD1

4
Years Annual estimation of emission reductions in
tonnes of CO2 e
2011-12 11,733
2012-13 11,733
2013-14 11,733
2014-15 11,733
2015-16 11,733
2016-17 11,733

http://cdm.unfccc.int/filestorage/H/7/E/H7E0ZNYR6IGO5LMQDPTVW1S92K8XBJ/PDD_NACL%20version%204.p
df?t=ZlF8bXVhY3phfDBnFq-8Z0QXSHpsxh3S-uhw
4
v3.1
PROJECT DESCRIPTION: VCS Version 3

2017-18 11,733
2018-19 11,733
2019-20 11,733
2020-21 11,733
Total estimated reductions (tonnes of CO2 e) 1,17,330
Total number of crediting years 10
Annual average over the crediting period of 11,733
estimated reductions (tonnes of CO2 e)

1.8 Description of the Project Activity

Refer Section A.4.2 of the Registered PDD Ref no 5096. For life time of the project activity refer
section C of the Registered PDD.

1.9 Project Location


0 0 0
The project activity ranges between 9 03’38.3” N to 9 05’31.3” N latitude and 77 36’24.8” E
0
to 77 37’23.5” E longitude. The detailed geo-coordinates for each WTG location
mentioned in below table.
2
Survey No. HT. WTG ID Village Dist. State Latitude Longitude
SC.No. No.
0 0
1227/2C 3337 TDA211 Sayamalai Tirunelveli Tamil Nadu 9 05’31.3” N 77 36’ 37.4”E
0 0
1090/1(P), 3338 TDA171 Keelaneelithanallur Tirunelveli Tamil Nadu 9 04’45.0” N 77 36’ 24.8”E
2(P)
0 0
161(P) 3339 VL330 Melaneelithanallur Tirunelveli Tamil Nadu 9 03’38.3” N 77 37’ 23.5”E

5
v3.1
PROJECT DESCRIPTION: VCS Version 3

Tirunelveli Junction Railway Station is a major railhead of the Southern Railways. Nellai Express
runs daily between Chennai and Tirunelveli. Nearest airports are the Madurai Airport (151 km)
and Trivandrum International Airport (160 km).

1.10 Conditions Prior to Project Initiation


In the absence of the project activity, the equivalent amount of electricity would have been
generated from the connected / new power plants in the Southern Region grid, which are / will be
predominantly based on fossil fuels. The main emission source in the pre-project scenario is the
power plants connected to the Southern grid and main greenhouse gas involved is CO2.
The project activity is a renewable source of electricity generation and will supply the electricity to
the Southern Region grid. The project activity is a wind power plant of capacity 6.3 MW. The
project activity uses wind energy in producing electricity and no other input is being used,
therefore, it will not produce any GHG emission during its lifetime

v3.1 6
PROJECT DESCRIPTION: VCS Version 3
1.11 Compliance with Laws, Statutes and Other Regulatory Frameworks

Refer Section B.5. of the Registered PDD Ref no 5096

1.12 Ownership and Other Programs

1.12.1 Right of Use

Provide evidence of right of use.


For the ownership details of the project any of the following may be referred to:
1. Power Purchase Agreement between the project promoters and State Utility.
2. Commissioning certificates
3. Purchase order of WTGs

1.12.2 Emissions Trading Programs and Other Binding Limits


Not Applicable. The project is registered under CDM and UNFCCC (Registration ID -5096).

1.12.3 Participation under Other GHG Programs

Project has been registration with UNFCCC under Clean Development Mechanism program,.

Registration reference number is 5096.

Web link: http://cdm.unfccc.int/Projects/DB/SGS-UKL1327062017.82/view

1.12.4 Other Forms of Environmental Credit

The project has been purely taken up as CDM project and has not been applied for any form of
2
environmental credit. The project is registered in UNFCCC as reference number 5096 at
UNFCCC

1.12.5 Projects Rejected by Other GHG Programs

The project has neither been applied nor rejected under any other program. The project is
registered with reference number 5096 at UNFCCC.

1.13 Additional Information Relevant to the Project

Eligibility Criteria
Wind Power Project by NACL in Tamil Nadu is not grouped project

2
http://cdm.unfccc.int/Projects/DB/SGS-UKL1312814456.75/view

v3.1 7
PROJECT DESCRIPTION: VCS Version 3
Leakage Management

NA

Commercially Sensitive Information

NA.

Further Information

NA

2 APPLICATION OF METHODOLOGY

2.1 Title and Reference of Methodology


Refer Section B.1. of the Registered PDD Ref no 5096

2.2 Applicability of Methodology


Refer Section B.2. of the Registered PDD Ref no 5096

2.3 Project Boundary


Refer Section B.3. of the Registered PDD Ref no 5096

2.4 Baseline Scenario


Refer Section B.4. of the Registered PDD Ref no 5096

2.5 Additionality
Refer Section B.5. of the Registered PDD Ref no 5096

2.6 Methodology Deviations

.NA

3 QUANTIFICATION OF GHG EMISSION REDUCTIONS AND REMOVALS

3.1 Baseline Emissions

Refer Section B.6.1 of the Registered PDD Ref no 5096.

3.2 Project Emissions

NA.

v3.1 8
PROJECT DESCRIPTION: VCS Version 3
3.3 Leakage

NA

3.4 Summary of GHG Emission Reductions and Removals


Refer Section B.6.4 of the Registered PDD Ref no 5096

4 MONITORING

4.1 Data and Parameters Available at Validation


Refer Section B.6.2 of the Registered PDD Ref no 5096

4.2 Data and Parameters Monitored


Refer Section B.7.1 of the Registered PDD Ref no 5096

4.3 Description of the Monitoring Plan


Refer Section B.7.2 of the Registered PDD Ref no 5096

5 ENVIRONMENTAL IMPACT
Refer Section B.7.2 of the Registered PDD Ref no 5096

6 STAKEHOLDER COMMENTS
Refer Section E of the Registered PDD Ref no 5096