Financial offer for steel building of proposed two storied chemical store

Frame House Footwear Ltd, Dhamrai, Savar. Date:23-10-2021


Unit Amount
No Description Unit Quantity Remarks
Rate in Tk.
A.1 Civil & Steel Structure Design, Including Desin Report L.S 0.00 150000 0
Layout/Setting Out: Providing layout and carry over
Bench-mark (BM) at site from nearby BM pillar, existing
ground level (FGL), plinth levels (PL), setting and
2 marking for all footings, columns including marker, pegs, L.S 0.00 35000 0
etc. and protecting all public utilities within the premise of
work. Use digital instruments for layout.

Earth excavation for foundation trenches at required


depth as per design including levelling, ramming etc all
3 complete with cleaning of excavated earth at a safe m3 65.00 450 29250
distance by direction of engineer in charge.

Sand filling for foundation trenches with local vitty sand


having FM 0.8 to 1.2 in 150 mm layers including levelling,
watering and compaction to achieve minimum dry density
4 of 90% with optimum moisture content by ramming each m3 55.00 616 33880
layer upto finished level as per design and etc. all complete
accepted by the engineer in charge.

One layer Brick flat soling below ground floor with first
class bricks including preparation of bed and filling
5 interstices with local sand, levelling etc. all complete and m2 56.00 387 21672
accepted by the engineer incharge.

6 Lean Cocrete m3 1.60 9000 14400

7 Shutter m2 0.00 850 0


Reinforced cement concrete works with minimum
cement content relates to mix ratio 1:1.5:3 having
minimum compressive strength f’c = 24 Mpa at 28 days on
standard cylinders as per standard practice of Code
ACI/BNBC/ASTM & cement conforming to CEM II-
AM/OPC, best quality coarse sand (F.M.2.3 min.), 20 mm
down well graded stone chips conforming to ASTM C-33,
mixing in standard mixture machine and fed by standard
measuring boxes, screening through proper sieves,
cleaning and washing, placing of reinforcement cage in
position, casting, compacting by vibrators, curing for 28
days etc. including cost of water, electricity and other
charges of all equipments including hire charge of
vibrator, mixture machineetc, labour, shampering, test of
materials and concrete etc. all complete as per design,
8 drawing and accepted by the Engineer. In case RMC m3 32 15500 496000
strength will be 500 psi more.

Note: Cement have to be


tested by BUET as per randomly selected cement bags
by engineer in-charge from site. Stone chips will be
clean, sound boulder crushed stone, no dead stone or
vuttu vanga is allowable. Coarse sand should be well
cleaned. All materials including stone and sand must be
tested by BUET as per randomly selected by engineer
in-charge from site at any time.

M.S. Reinforcement Works : Fabricating and fixing to


details of minimum 60 Grade deformed bar confirming
ASTM A; 615 M with minimum, fy= 415 Mpa as per
design in concrete in accordance with BSTI standard
including cutting, straightening, cleaning rusts, if any,
bending & putting in position by wires, providing spacer
blocks of approved type in required number, supply and
carriage of labours, tools, plants, incidentals, cost of
9 testing etc. all complete as per drawing, specification and Ton 6.5 56000 364000
direction of the engineer.The rate includes fabrication,
welding, local carrying, delivering, lifting, placing and all
kinds of welding for spirals and splices as per drawing all
complete.

125mm Brick works with first class machine made


bricks with sand (F.M 1.2) cement mortar (1:4) including
filling the interstices with mortar, raking out joints,
cleaning, soaking of bricks for atleast 24 hours before
10 using, washing of sand, necessary scafolding, curing m2 0 1125 0
atleast for 7 days etc. all complete including cost of water,
electricity and other charges accepted by the Engineers in-
charge.
250mm Brick works with first class machine made
bricks with sand (F.M 1.2) cement mortar (1:4) including
filling the interstices with mortar, raking out joints,
cleaning, soaking of bricks for atleast 24 hours before
11 using, washing of sand, necessary scafolding, curing m3 15 8500 127500
atleast for 7 days etc. all complete including cost of water,
electricity and other charges accepted by the Engineers in-
charge.
12mm to 20mm Cement Plastering work (1:4) with
good quality cement and sand (FM 1.2) including
12 screening, washing of sand and all other requirements as m2 65 1350 87750
per design and direction of engineer incharge.

Tota Amount For Civil Work 1174452

Supply ,Fabrication & Erection of Base Plate, Top


B.1 Plate,Connection Plate ,Column, Rafter, Beam, etc.as kg 12,900 130 1677000
per supplied drawing & specification.

Supply ,Fabrication & Erection of 1.6 mm thic M.S


2 Purlin for roof & wall as per supplied drawing & kg 1,900 120 228000
specification.

Supply ,Fabrication & Erection of Galvanized Nut


3 Bolts and Washer for Joint (92 grade) as per supplied kg 300 230 69000
drawing & specification.

Supply ,Fabrication & Erection of Anchor Bolt 25


4 kg 200 150 30000
mm dia as per supplied drawing & specification.

Supply ,Fabrication & Erection of0.47 mm thick


5 profile sheets for Roof as per supplied drawing & m2 186 675 125550
specification.
Supply ,Fabrication & Erection of 0.47 mm thick
6 profile sheets for Wall as per supplied drawing & m2 195 675 131625
specification.
Supply ,Fabrication & Erection of Decking Sheet for
7 mezzanine floor (0.8mm thick) as per supplied m2 95 1075 102125
drawing & specification.
Supply ,Fabrication & Erection of L-Capping as per
8 Rm 19 590 11210
supplied drawing & specification.

Supply ,Fabrication & Erection of External Corner


9 Rm 20 590 11800
Cappingas per supplied drawing & specification.

Supply ,Fabrication & Erection of Bottom Flashing


10 Rm 55 540 29700
as per supplied drawing & specification.

Supply ,Fabrication & Erection of Top Capping as per


11 Rm 19 590 11210
supplied drawing & specification.
Supply ,Fabrication & Erection of Front & Side
12 Rm 37 590 21830
Capping as per supplied drawing & specification.

Supply ,Fabrication & Erection of Rain Gutteras per


13 Rm 19 592 11248
supplied drawing & specification.

Supply ,Fabrication & Erection of Down Pipeas per


14 Rm 37 495 18315
supplied drawing & specification.

Supply ,Fabrication & Erection of U-Channel as per


15 Rm 40 263 10520
supplied drawing & specification.

Supply ,Fabrication & Erection of standard quality of


16 Nos 1800 4.5 8100
Screw.

Supply ,Fabrication & Erection of 01 no steel STAIR


17 Nos 1 250000 250000
as per supplied drawing & specification.

Supply ,Fabrication & Erection of standard quality of


18 m2 172 215 36980
roof Insulation with 8 mm thic pe. Foam
Supply & Painting with red oxide for all steel
19 m2 240 180 43200
members

20 Labour Cos for Erection m3 240 520 124800

Total Amount for Steel Structure 2952213


Gr.Total (A+B)= 4126665

Taka Forty One Lacs Twenty Six Thousand Six Hundred Sixty Five and Zero Paisa Only

Note: VAT, Tax, and Others fee are not included with the price proposal.
Financial offer for steel building of proposed two storied chemical store
Frame House Footwear Ltd, Dhamrai, Savar. Date:13-10-2022
Unit Amount
No Description Unit Quantity Remarks
Rate in Tk.
A.1 Civil & Steel Structure Design, Including Desin Report L.S 1.00 150000 150000
Layout/Setting Out: Providing layout and carry over Ground
Bench-mark (BM) at site from nearby BM pillar, existing Floor=(17x8
ground level (FGL), plinth levels (PL), setting and m) 136m2,
marking for all footings, columns including marker, pegs, + 1st
2 etc. and protecting all public utilities within the premise of L.S 1.00 35000 35000 floor=104m2
,Total
work. Use digital instruments for layout. Area=240m2

Earth excavation for foundation trenches at required


depth as per design including levelling, ramming etc all
3 complete with cleaning of excavated earth at a safe m3 85.00 450 38250
distance by direction of engineer in charge.

Sand filling for foundation trenches with local vitty sand


having FM 0.8 to 1.2 in 150 mm layers including levelling,
watering and compaction to achieve minimum dry density
of 90% with optimum moisture content by ramming each
4 layer upto finished level as per design and etc. all complete m3 120.00 616 73920
accepted by the engineer in charge.

One layer Brick flat soling below ground floor with first
class bricks including preparation of bed and filling
5 interstices with local sand, levelling etc. all complete and m2 210.00 387 81270
accepted by the engineer incharge.

6 Lean Cocrete m3 5.00 0


7 Shutter
Reinforced cement concrete works with minimum
cement content relates to mix ratio 1:1.5:3 having
minimum compressive strength f’c = 24 Mpa at 28 days on
standard cylinders as per standard practice of Code
ACI/BNBC/ASTM & cement conforming to CEM II-
AM/OPC, best quality coarse sand (F.M.2.3 min.), 20 mm
down well graded stone chips conforming to ASTM C-33,
mixing in standard mixture machine and fed by standard
measuring boxes, screening through proper sieves,
cleaning and washing, placing of reinforcement cage in
position, casting, compacting by vibrators, curing for 28
days etc. including cost of water, electricity and other
charges of all equipments including hire charge of
vibrator, mixture machineetc, labour, shampering, test of
materials and concrete etc. all complete as per design,
drawing and accepted by the Engineer. In case RMC
7 strength will be 500 psi more. m3 61 14490 883890

Note: Cement have to be


tested by BUET as per randomly selected cement bags
by engineer in-charge from site. Stone chips will be
clean, sound boulder crushed stone, no dead stone or
vuttu vanga is allowable. Coarse sand should be well
cleaned. All materials including stone and sand must be
tested by BUET as per randomly selected by engineer
in-charge from site at any time.

M.S. Reinforcement Works : Fabricating and fixing to


details of minimum 60 Grade deformed bar confirming
ASTM A; 615 M with minimum, fy= 415 Mpa as per
design in concrete in accordance with BSTI standard
including cutting, straightening, cleaning rusts, if any,
bending & putting in position by wires, providing spacer
blocks of approved type in required number, supply and
carriage of labours, tools, plants, incidentals, cost of
8 testing etc. all complete as per drawing, specification and Ton 7 72000 504000
direction of the engineer.The rate includes fabrication,
welding, local carrying, delivering, lifting, placing and all
kinds of welding for spirals and splices as per drawing all
complete.

125mm Brick works with first class machine made


bricks with sand (F.M 1.2) cement mortar (1:4) including
filling the interstices with mortar, raking out joints,
cleaning, soaking of bricks for atleast 24 hours before
9 using, washing of sand, necessary scafolding, curing m2 0 1125 0
atleast for 7 days etc. all complete including cost of water,
electricity and other charges accepted by the Engineers in-
charge.
250mm Brick works with first class machine made
bricks with sand (F.M 1.2) cement mortar (1:4) including
filling the interstices with mortar, raking out joints,
cleaning, soaking of bricks for atleast 24 hours before
10 using, washing of sand, necessary scafolding, curing m3 45 7200 324000
atleast for 7 days etc. all complete including cost of water,
electricity and other charges accepted by the Engineers in-
charge.

12mm to 20mm Cement Plastering work (1:4) with


good quality cement and sand (FM 1.2) including
11 screening, washing of sand and all other requirements as m2 400 1125 450000
per design and direction of engineer incharge.

Tota Amount For Civil Work 2540330


Supply ,Fabrication & Erection of Base Plate, Top
B.1 Plate,Connection Plate ,Column, Rafter, Beam, etc.as kg 12,500 120 1500000
per supplied drawing & specification.
Supply ,Fabrication & Erection of 1.6 mm thic M.S
2 Purlin for roof & wall as per supplied drawing & kg 1,900 100 190000
specification.
Supply ,Fabrication & Erection of Galvanized Nut
3 Bolts and Washer for Joint (92 grade) as per supplied kg 300 220 66000
drawing & specification.
Supply ,Fabrication & Erection of Anchor Bolt 25
4 kg 200 110 22000
mm dia as per supplied drawing & specification.
Supply ,Fabrication & Erection of0.47 mm thick
5 profile sheets for Roof as per supplied drawing & m2 186 646 120156
specification.
Supply ,Fabrication & Erection of 0.47 mm thick
6 profile sheets for Wall as per supplied drawing & m2 195 646 125970
specification.
Supply ,Fabrication & Erection of Decking Sheet for
7 mezzanine floor (0.8mm thick) as per supplied m2 95 1075 102125
drawing & specification.
Supply ,Fabrication & Erection of L-Capping as per
8 Rm 19 590 11210
supplied drawing & specification.
Supply ,Fabrication & Erection of External Corner
9 Rm 20 590 11800
Cappingas per supplied drawing & specification.
Supply ,Fabrication & Erection of Bottom Flashing
10 Rm 55 540 29700
as per supplied drawing & specification.
Supply ,Fabrication & Erection of Top Capping as per
11 Rm 19 590 11210
supplied drawing & specification.
Supply ,Fabrication & Erection of Front & Side
12 Rm 37 590 21830
Capping as per supplied drawing & specification.
Supply ,Fabrication & Erection of Rain Gutteras per
13 Rm 19 592 11248
supplied drawing & specification.
Supply ,Fabrication & Erection of Down Pipeas per
14 Rm 37 495 18315
supplied drawing & specification.
Supply ,Fabrication & Erection of U-Channel as per
15 Rm 40 263 10520
supplied drawing & specification.
Supply ,Fabrication & Erection of standard quality of
16 Nos 1800 4.5 8100
Screw.
Supply ,Fabrication & Erection of 01 no steel STAIR
17 Nos 1 250000 250000
as per supplied drawing & specification.
Supply ,Fabrication & Erection of standard quality of
18 m2 172 215 36980
roof Insulation with 8 mm thic pe. Foam
Supply & Painting with red oxide for all steel
19 m2 240 180 43200
members
20 Labour Cos for Erection m3 240 480 115200
Total Amount for Steel Structure 2705564
Gr.Total (A+B)= 5245894
Note: VAT, Tax, and Others fee are not included with the price proposal.