SPECIAL MEETING
14 August 2019, ABT Office Conference Room
Action
Due Date
Officer
The meeting was called to order at exactly 09:17 AM
1. DELIMONDO PROJECT
1.1. Project Status Report
IMA stated that the other party has not yet taken an action
regarding the Claim of Extended Prelims. IMA addressed FCC FCC
for a follow up letter for the claims.
IMA reported that the Change Order No. 4 for Recon
(Php.507,809.18) shall offset in the Anticipated Deletion
(Php.353,104.19) as per Contract.
1.1.1. Status and Concerns on Balance of Works
Offices
IMA reported that turn over for this item shall be done after
installation of wooden baseboard, however the baseboard are
OSM and PMT is currently waiting for delivery. Due to the
need to vacate the premises by the end of August, PMT was
given permission to leave if the wooden baseboard doesn’t
come on time and other contractor would take over the
installation instead.
Painting Works
IMA reported the withdrawal of the subcon for painting works, RCL 16Aug’19
three of the subcon’s manpower stayed and PMT absorbed
them as admin and made their payment on daily basis. Due
to the withdrawal, the site is in need of painters as they have
a lot of remaining painting works. RCL agreed to look for
painters for the site.
IMA raised the issue with peeling and bloating of paints along IMA 15Aug’19
the hallways. FGY suggested asking the supplier (BOYSEN)
to check it on site, to determine who’s at fault FODC or
BOYSEN.
IMA reported the following briefly: done with Gate 1, Gate 2 is for
application of putty. Regarding reblocking of road, base course
was delivered yesterday but it’s not yet suitable to install due to
weather condition. Perimeter wall is ongoing, DLJ to transfer
location of their container van. Ponding near utility building is the
last remaining work and is on-going. Epoxy injection is done.
Leveling of soil, waiting for operation of MMIC.
Plumbing materials IMA
IMA reported that plumbing materials are needed by end of FE
August. ABDM clarified if these materials are available locally
and if so, can PMT take care of the procurement to expedite
the process. IMA told ABDM that some of it are not available
locally. ABDM instructed that for the materials that cannot be
sourced out in the area, HO will take care of those, but for the
rest, PMT is responsible to process its procurement and
delivery.
Issue with Sealant Application for Exterior Zocallo
IMA reported that the BOSTICK sealant applied between the
PU Wall Panels and Zocallo failed. They also tried LANCO IMA 15Aug’19
and it failed too.
RCL and FGY suggested that before applying sealant
between the gaps, they should fill it first with cement then
apply the sealant on top of cement. FGY instructed to look for
sealant used in car windshields for a cheaper alternative. IMA
Meralco
IMA reported that the inauguration is scheduled by end of CHM 19Aug’19
August, and will process the disconnection.
IMA asked for a Secretary Certificate authorizing that they will
be the one to process the disconnection.
Regarding the security deposit, ABDM cleared with IMA that
IMA 16Aug’19
as per contract, it is 100% refundable.
PLDT
IMA reported that JAKKA will use the temporary connection
for 1 to 2 months, they don’t intend to change account name
though they will be the one to pay it after FODC is done with
the project. ABDM instructed IMA to write JAKKA a letter
about this for documentation.
1.2. Other Matters
ABDM informed IMA that she will be transferred to S-UMMO
project on the first week of September to assist ARVIN.
Regarding office structure, ABDM instructed to leave the
structure behind by the end of August as it would cost more time,
effort, and money if we shoulder its dismantling. RCL added to
leave the aircon as well.
73. COVENT PROJECT
73.1. Project Status Report
73.1.1. Status and Concerns on Balance of Works
Deductive – Wall at Stair 3 and Stair 4
JAA informed that EELHI asked verbally for a deductive cost
for the wall at stair 3 and 4 because as per EELHI, PMT failed
to construct it. She discussed that it was reflected on the PMT
elevations on both construction and bid plans, but it doesn’t
have a marking, schedule, and details. FGY added that they 15Sep’19
assumed that it was just a drafting mistake. Furthermore, the
other party did not send out a formal letter regarding this.
FOD and ABDM agreed to not construct it with the given
circumstances and instructed PMT that if ever EELHI send
out a letter, they should reply with conviction as to why FODC
should not comply with their request. JUN
Site Development – Retaining Wall & Concrete Pavement
JAA presented the site development plan and pointed out the
JUN
scope of FODC’s site development work. SLU verified that
the extent of this scope is all hardscapes only.
ABDM questioned PMT when is the start of concreting for the
site development. FGY informed that they cannot move due LPA
to other contractors’ container vans occupying the work area, CHM
their schedule to vacate the area is this August and PMT will
start after they do so. PMT
CAP reported that according to EELHI, the retaining wall in
Santol St. will be changed into curb stone in thickened slab.
CAP added that this would be recorded as additive/deductive. FERDIE
FOD instructed to finish all site development works that can
be done, and for the items that cannot be done due to other
contractor’s liability PMT would file it as deductive.
73.1.2. Project Control Report
Change Orders
JAA presented the change orders
JUN
LPA
LPA
FCC
PMT
PMT
FE
FE
JUN
SONNY 17Aug’19
SONNY
JUN
SLU
JUN
SLU
JUN