FIRE DETECTION AND ALARM SYSTEM ACTIVITY SCHEDULE

May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-21 Feb-21
Activity week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4

mobilization
tempacil and fabrication set up
painting works(primer paint)
lay outs
ADMIN BUILDING week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
SSP BUILDING(MAIN BUILDING) week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
IWL,BAGGING,UTILITY,MDB,&MCC BUILDING week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
RPET&MODIFICATION of Wh# week 1&2 week 3&4 Week 1&2 Week 3&4 Week 1&2 week 3&4 week 1&2 week 3&4 Week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 Week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
BALE STORAGE,FINISH GO DOWN ,ROAD week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
ETP BUILDING week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
Roughing installation of emt pipe
chipping works for manual pull station,bell and annunciator panel
wiring
PERIMETER LAY OUT week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 Week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4 week 1&2 week 3&4
CHIPPING, AND LAY OUT OF EMT PIPE FOR FDAS HOME RUN AT PERIMETER
INSTALLATION OF ALL FDAS DEVICES AND WIRE TERMINATION
INSTALLATION OF FACP AND ANNUNCIATOR PANEL
PROGRAMMING & INITIAL TESTING
FINAL TESTING AND COMMISSIONING
manpower loading May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-21 Feb-21
foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
electrician 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
helper 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
mason 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

equipment loading/tools
pipe bender 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Speed Cutter 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Grinder 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
rotary hammer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
chipping gun 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2
0 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9

work schedule