SOR Mirzapur
SOR Mirzapur
as per Labour/Material Rates Sanctioned by SE, 22nd Circle, U P Jal Nigam, Mirzapur
vide order no 2602/ Dar Saridi / 03 Dated-16/08/2019 (For Estimation-Rural) Inflation: 0 %
Description Code RATE Unit
LABOUR
MISTRY 101 460.00 DAY
MASON/STONE MASON 102 425.00 DAY
BELDAR/MAZDOOR/DIGGER/DRESSER 103 350.00 DAY
COOLIE 104 350.00 DAY
BLACK SMITH 105 425.00 DAY
BHISTI 106 350.00 DAY
CARPENTER 107 460.00 DAY
HAMMER MAN 108 350.00 DAY
PAINTER 109 460.00 DAY
WHITE WASHER 110 300.00 DAY
MECHANIC 111 425.00 DAY
HELPER 112 350.00 DAY
WATCHMAN 113 350.00 DAY
FITTER/PLUMBER 114 400.00 DAY
JUNIOR FITTER 115 350.00 DAY
SPECIAL LABOUR FOR ROCK CUTTING 116 400.00 DAY
CHISELLERS 117 400.00 DAY
SPECIAL MAZDOOR/COOLIE(FOR RUBBING AND POLISHING) 118 400.00 DAY
MATE 119 370.00 DAY
PESHRAJ 120 350.00 DAY
TILE LAYER 121 350.00 DAY
THATCHER 122 350.00 DAY
MASON(JUNIOR) 123 400.00 DAY
WOMAN COOLIE 124 350.00 DAY
CHOWKIDAR 125 350.00 DAY
WORK AGENT 126 350.00 DAY
DRIVER FOR CONCRETE MIXER 127 700.00 DAY
CLEANER 128 350.00 DAY
WELL SINKER 130 475.00 DAY
WORK MISTRI 131 475.00 DAY
TAR BOILER MAN/FIRE MAN 132 350.00 DAY
STONE DRESSER 133 400.00 DAY
BORER(BORING MECHANIC) 134 400.00 DAY
DIVER 136 350.00 DAY
ASSISTANT BORER 137 350.00 DAY
MATERIAL
BRICKS IST CLASS 235 7350.00 1000NO.
BRICK TILES IST CLASS 236 9000.00 1000NOS
BRICKS OVER BURNT 240 4000.00 1000NOS
BRICKS SUNDRIED 241 3800.00 1000NOS
DIFFERENCE IN RATES OF IST CLASS & SPECIALLY MOULDED BRICKS 243 350.00 1000NOS
BRICK BALLAST 40MM GAUGE 244 1300.00 CUM.
STONE BALLAST 40MM GAUGE 245 800.00 CUM.
STONE BALLAST 20MM GAUGE 246 750.00 CUM.
STONE GRIT 10-12MM 247 1090.00 CUM.
PEBBLES OR FINE GRAVEL 248 2400.00 CUM.
COARSE SAND(BADARPUR) 249 1395.00 CUM.
LOCAL SAND 250 860.00 CUM.
CEMENT 251 370.00 BAG
WHITE CEMENT 252 665.00 BAG
WHITE LIME(SLAKED) 253 750.00 CUM
WHITE LIME(UNSLAKED) 254 650.00 QTL
KANKAR LIME 255 2100.00 CUM
SURKHI 256 550.00 CUM
SHINGLE 257 860.00 CUM
EARTH 258 180.00 CUM
STONE 50MM THICK 259 500.00 SQM
STONE 40MM THICK 260 350.00 SQM
MARBLE DUST 261 335.00 CUM
MARBLE CHIPS 262 3200.00 CUM
WHITE MARBLE BAGS 263 665.00 BAG
09-Sep-19 16 Note: Rates of Cartage of different Pipes are for 8 Kms. Page 1 of 3
Page 410
LABOUR and MATERIAL RATES fot the Year 2019-20 Mirzapur
as per Labour/Material Rates Sanctioned by SE, 22nd Circle, U P Jal Nigam, Mirzapur
vide order no 2602/ Dar Saridi / 03 Dated-16/08/2019 (For Estimation-Rural) Inflation: 0 %
Description Code RATE Unit
FLAT TILES 264 385.00 100NOS
HALF ROUND TILES 265 594.00 100NOS
FLAT RIDGE 266 594.00 100NOS
LARGE COUNTRY TILES 267 1199.00 100NOS
SEGMENTAL TILES 268 494.00 100NOS
SMALL SIZE COUNTRY TILES 269 330.00 100NOS
SMALL SIZE SEGMENTAL TILES 270 330.00 100NOS
TILES 15*15CM GLAZED 271 27.00 NO.
STONE SLAB STANDARD 40MM THICK 272 1012.00 SQM
STONE SLAB NON STANDARD 40MM THICK 273 726.00 SQM
SPUN YARN 274 60.50 KG.
PIG LEAD 275 130.00 KG.
FUEL(WOOD) 276 700.00 QTL.
GUR 277 60.00 KG.
WATER PROOFING COMPOUND 278 105.00 KG.
STEEL 279 37.50 KG.
COAL TARRING 280 24.00 SQM.
LINSEED OIL 281 115.00 LTR.
COLOUR 282 88.00 KG.
PRIMER 283 182.00 LTR.
VARNISH 284 225.00 LTR.
PAINT(ENAMEL) 285 295.00 LTR.
WHITING 286 8.00 KG.
DISTEMPER OIL 287 80.00 LTR.
COAL TAR 288 35.00 LTR.
SOLIGNUM 289 125.00 LTR.
CAUSTIC SODA 290 63.00 KG.
WAX POLISH 291 245.00 KG.
ENAMEL(SYNTHETIC) 292 225.00 LTR.
COLOURING MATERIAL 293 55.00 KG.
DRY DISTEMPER 294 105.00 KG.
MUSTARD OIL 295 200.00 KG.
COTTON CORD 296 115.50 KG.
SAL BALLIES(EUCALYPTUS)100MM 297 165.00 RM.
SAL BALLIES(EUCALYPTUS)125MM 298 192.50 RM.
SAL BALLIES(EUCALYPTUS)150MM 299 220.00 RM.
SAL WOOD WALLERS 300 57200.00 CUM.
TEAK WOOD(C.P.) 301 101500.00 CUM.
SHISHAM WOOD 302 45600.00 CUM.
SAL WOOD 303 57200.00 CUM.
DEODAR WOOD 304 71500.00 CUM.
KAIL WOOD 305 45000.00 CUM.
COUNTRY WOOD 306 52800.00 CUM.
CHIR WOOD 307 41800.00 CUM.
PLY WOOD 9MM 308 1320.00 SQM.
PLANKS(COUNTRY WOOD) 309 16500.00 CUM.
C.P. TEAK WOOD CLEAT 310 18.00 NO.
TEAK WOOD BLOCK 75*75*120MM 311 30.00 NO.
TEAK WOOD PLATE 100*100*10MM 312 20.00 NO.
C.P. TEAK WOOD PEG RACK 313 22.00 NO.
BAMBOOS 25MM DIA. 314 80.00 NO.
CHATAI 315 125.00 SQM.
BAN 316 16.50 KG.
BASKETS 317 100.00 NO.
EMPTY BAGS 318 8.00 NO.
M.S.SHEETS 319 3760.00 QTL.
ANGLE IRON 320 3700.00 QTL.
SHEET IRON 1MM THICK 321 65.00 KG.
G.C. SHEETS 0.63MM 322 10450.00 QTL.
G.I. PLAIN SHEETS 2.5*1.0MM 323 6050.00 QTL.
MASONITE OR CALOTAX 6MM THICK 324 495.00 SQM.
EXPANDED METAL 325 121.00 SQM.
M.S. BARS 16MM DIA. 326 3775.00 QTL.
09-Sep-19 16 Note: Rates of Cartage of different Pipes are for 8 Kms. Page 2 of 3
Page 411
LABOUR and MATERIAL RATES fot the Year 2019-20 Mirzapur
as per Labour/Material Rates Sanctioned by SE, 22nd Circle, U P Jal Nigam, Mirzapur
vide order no 2602/ Dar Saridi / 03 Dated-16/08/2019 (For Estimation-Rural) Inflation: 0 %
Description Code RATE Unit
M.S. CLAMP 327 270.00 NO.
NAILS 328 75.00 KG.
IRON CLEAT 329 75.00 NO.
SCREW 30/40MM 330 95.00 100NO.
IRON SCREW 65*25MM. 331 105.00 100NO.
G.I. BOLTS 25*6MM. 332 95.00 10NO.
G.I. BOLTS 150MM. 333 125.00 10NO.
NUT WITH BOLT 16*65MM. 334 92.00 KG.
NUT WITH BOLT 20*65MM 335 92.00 KG.
NUT WITH BOLT 20*75MM 336 92.00 KG.
NUT WITH BOLT 20*90MM 337 92.00 KG.
NUT WITH BOLT 24*90MM. 338 92.00 KG.
NUT WITH BOLT 27*100MM 339 92.00 KG.
NUT WITH BOLT 27*110MM 340 92.00 KG.
NUT WITH BOLT 30*110MM 341 92.00 KG.
NUT WITH BOLT 33*120MM 342 92.00 KG.
G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 343 400.00 SQM.
BRASS CLEAT 344 150.00 NO.
BRASS SCREW 345 35.00 100NO.
BRASS HINGES 50MM. 346 185.00 NO.
BRASS HAT PEG 347 75.00 NO.
C.I. FOOT STEPS 348 150.00 NO.
GLASS PANE 24*36CM(2.5MM THICK) 349 250.00 NO.
GLASS PANE(18*34CM)2.5MM THICK 350 275.00 NO.
GLASS PANE 2.5MM THICK 351 330.00 SQM.
C.I.DOWN PIPE 100MM DIA. 2M LONG 352 302.50 RM.
A.C.DOWN PIPE 100 MM DIA.2M LONG 353 220.00 RM.
LUMPET WASHER 354 104.50 10NO.
BITUMEN WASHER 355 12.65 10NO.
A.C.SHEET 6MM THICK 356 38.50 SQM.
STEAM COAL 357 440.00 QTL.
3MM THICK RUBBER INSERTION 358 99.00 KG.
ROSE BOWL 359 115.50 NO.
HEAD 360 110.00 NO.
SHOE SPLASH PROOF 361 110.00 NO.
BEND WITH EYE HOLE 362 82.50 NO.
HIRING OF ROAD ROLLER 363 8000.00 DAY
DIFFERENCE IN RATES OF IST & 2ND CLASS BRICKS 364 650.00 1000NO.
DIFFERENCE IN RATES OF SHINGLE AND STONE GRIT 365 230.00 CUM.
DIFFERENCE IN RATES OF IST & 3RD CLASS BRICKS 366 2850.00 1000NO.
CARTAGE OF C.I.PIPE 80-300MM DIA. 367 39.93 QTL.
CARTAGE OF C.I.PIPE 350-750MM DIA. 368 42.60 QTL.
CARTAGE OF C.I.PIPE 800-1000MM DIA. 369 50.58 QTL.
CARTAGE OF C.I.PIPE 1100-1200MM DIA. 370 55.90 QTL.
CARTAGE OF A.C.CLASSI&II PIPE 50-300MM DIA. 371 41.26 QTL.
CARTAGE OF A.C.CLASS I&II PIPE 350-600MM DIA. 372 57.20 QTL.
CARTAGE OF M.S.G.I.SCREWED/SOCKETED PIPE 15-150MM DIA. 373 41.25 QTL.
CARTAGE OF STONEWARE GLAZED PIPE 40-400MM DIA. 374 46.58 QTL.
CARTAGE OF R.C.C. P1 QUALITY PIPE 80-300MM DIA. 375 41.93 QTL.
CARTAGE OF R.C.C. P2 PIPE 80-300MM DIA. 376 39.93 QTL.
CARTAGE OF R.C.C.P2 PIPE 350-600MM DIA. 377 54.06 QTL.
CARTAGE OF R.C.C.P3 PIPE 200-300MM DIA. 378 41.26 QTL.
CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 379 45.26 QTL.
CARTAGE OF R.C.C.P3 PIPE 900-1200MM DIA. 380 95.86 QTL.
CARTAGE OF R.C.C.NP2 PIPE 100-300MM DIA. 381 20.62 QTL.
CARTAGE OF R.C.C. NP2 PIPE 350-700MM DIA. 382 30.02 QTL.
CARTAGE OF R.C.C.NP2 PIPE 800-1800MM DIA. 383 36.08 QTL.
BITUMEN 384 22500.00 TONNE
BRICK BALLAST 25MM GAUGE 385 1350.00 CUM.
100MM DIA.A.C.BEND 386 80.00 NO.
CARTAGE OF R.C.C.NP3 PIPE 350-700MM DIA. 387 35.94 QTL.
CARTAGE OF R.C.C.NP3 PIPE 800-1200MM DIA. 388 63.43 QTL.
HOLDER FOR A.C. DOWN PIPE 100MM SIZE. 389 64.57 NO.
09-Sep-19 16 Note: Rates of Cartage of different Pipes are for 8 Kms. Page 3 of 3
Page 412
Schedule of Rates (2019-20) for Building Works District: Mirzapur
as per Labour/Material Rates Sanctioned by SE, 22nd Circle, U P Jal Nigam, Mirzapur Inflation: 0%
vide order no 2602/ Dar Saridi / 03 Dated-16/08/2019 (For Estimation-Rural) Item Rate Item Rate
without with 10%
ItemCode Description Quantity Unit UnitRate Cost Con.Profit Con.Profit
1001 EXCAVATION 0-1.5M. DEEP IN ORDINARY SOIL. 153.87 169.26 /CUM.
Details of cost for 100 /CUM.
101 MISTRY 0.25 DAY 460.00 115.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
104 COOLIE 23 DAY 350.00 8050.00
105 BLACK SMITH 0.25 DAY 425.00 106.25
Sundries.. L.S. 116.06
15387.31
Add for contractor's profit @ 10 % 1538.73
16926.04
1002 EXCAVATION 0-1.5M. DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, KANKAR. 179.95 197.95 /CUM.
Details of cost for 100 /CUM.
101 MISTRY 0.25 DAY 460.00 115.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 27 DAY 350.00 9450.00
104 COOLIE 23 DAY 350.00 8050.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 167.58
17995.08
Add for contractor's profit @ 10 % 1799.51
19794.59
1005 FILLING, DRESSING AND RAMMING EARTH OR SAND OR BAJRI OR BALLAST 100.20 110.21 /CUM
OR KANKAR OR SHINGLE.
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
104 COOLIE 15 DAY 350.00 5250.00
106 BHISTI 3 DAY 350.00 1050.00
Sundries.. L.S. 219.52
10019.52
Add for contractor's profit @ 10 % 1001.95
11021.47
1007 CONC. 40 MM BRICK BALLAST, WHITE LIME & SAND MORTAR (1:2) IN 2591.47 2850.62 /CUM
FOUNDATIONS AND FLOORS.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
104 COOLIE 12 DAY 350.00 4200.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 1.5 DAY 350.00 525.00
244 BRICK BALLAST 40MM GAUGE 9.5 CUM. 1300.00 12350.00
250 LOCAL SAND 3 CUM. 860.00 2580.00
253 WHITE LIME(SLAKED) 1.5 CUM 750.00 1125.00
Sundries.. L.S. 67.20
25914.70
Add for contractor's profit @ 10 % 2591.47
28506.17
1008 CONC. 40 MM BRICK BALLAST, WHITE LIME & SURKHI IN FOUNDATIONS AND 2497.98 2747.78 /CUM
FLOORS(100:16:32).
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
104 COOLIE 12 DAY 350.00 4200.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 1.5 DAY 350.00 525.00
244 BRICK BALLAST 40MM GAUGE 9.5 CUM. 1300.00 12350.00
253 WHITE LIME(SLAKED) 1.5 CUM 750.00 1125.00
256 SURKHI 3 CUM 550.00 1650.00
Sundries.. L.S. 62.29
24979.79
Add for contractor's profit @ 10 % 2497.98
27477.77
1009 CONC. 40 MM BRICK BALLAST, LOCAL SAND AND CEMENT (12:6:1) IN 3464.83 3811.31 /CUM
FOUNDATIONS AND FLOORS.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
104 COOLIE 12 DAY 350.00 4200.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 1.5 DAY 350.00 525.00
244 BRICK BALLAST 40MM GAUGE 9.5 CUM. 1300.00 12350.00
250 LOCAL SAND 4.75 CUM. 860.00 4085.00
251 CEMENT 22.6 BAG 370.00 8362.00
Sundries.. L.S. 58.80
34648.30
Add for contractor's profit @ 10 % 3464.83
38113.13
1011 SAME AS ITEM 1009 BUT FOR 8:4:1. 3886.96 4275.66 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
104 COOLIE 12 DAY 350.00 4200.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 1.5 DAY 350.00 525.00
244 BRICK BALLAST 40MM GAUGE 9.5 CUM. 1300.00 12350.00
250 LOCAL SAND 4.75 CUM. 860.00 4085.00
251 CEMENT 34 BAG 370.00 12580.00
Sundries.. L.S. 62.09
38869.59
Add for contractor's profit @ 10 % 3886.96
42756.55
1012 CONC.40 MM BRICK BALLAST, WHITE LIME AND SAND MORTAR (1:2) IN 3226.00 3548.60 /CUM
HAUNCH FILLING.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15.5 DAY 350.00 5425.00
104 COOLIE 26 DAY 350.00 9100.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 2 DAY 350.00 700.00
244 BRICK BALLAST 40MM GAUGE 9.5 CUM. 1300.00 12350.00
250 LOCAL SAND 3 CUM. 860.00 2580.00
253 WHITE LIME(SLAKED) 1.5 CUM 750.00 1125.00
Sundries.. L.S. 112.52
32260.02
Add for contractor's profit @ 10 % 3226.00
35486.02
1014 CONC. 25 MM BRICK BALLAST, WHITE LIME AND SURKHI (100:18:36) IN ROOF 3669.99 4036.98 /CUM
TERRACING.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.5 DAY 350.00 6125.00
104 COOLIE 35 DAY 350.00 12250.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 2.5 DAY 350.00 875.00
253 WHITE LIME(SLAKED) 1.5 CUM 750.00 1125.00
256 SURKHI 3 CUM 550.00 1650.00
277 GUR 12 KG. 60.00 720.00
385 BRICK BALLAST 25MM GAUGE 9.5 CUM. 1350.00 12825.00
Sundries.. L.S. 262.35
36699.85
Add for contractor's profit @ 10 % 3669.98
40369.83
1015 C.C. 20 MM STONE BALLAST, COARSE SAND AND CEMENT 4:2:1. 5062.43 5568.67 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9 CUM. 750.00 6750.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 64.5 BAG 370.00 23865.00
Sundries.. L.S. 401.78
50624.28
Add for contractor's profit @ 10 % 5062.43
55686.71
1017 SAME AS ITEM 1015 BUT FOR 8:4:1. 4023.14 4425.46 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9.4 CUM. 750.00 7050.00
249 COARSE SAND(BADARPUR) 4.8 CUM. 1395.00 6696.00
251 CEMENT 34.5 BAG 370.00 12765.00
Sundries.. L.S. 390.44
40231.44
Add for contractor's profit @ 10 % 4023.14
44254.58
1018 R.C.C. DOOR SILLS, CHAUKHATS ETC. WITH CEMENT, COARSE SAND AND 20 7036.81 7740.49 /CUM
MM STONE BALLAST 1:1.5:3
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 14.5 DAY 425.00 6162.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9 CUM. 750.00 6750.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 85.75 BAG 370.00 31727.50
Sundries.. L.S. 6333.06
70368.06
Add for contractor's profit @ 10 % 7036.81
77404.87
1020 SAME AS ITEM 1019 BUT FOR SLABS. 7796.90 8576.59 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 14.5 DAY 425.00 6162.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9 CUM. 750.00 6750.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 85.75 BAG 370.00 31727.50
Sundries.. L.S. 13934.02
77969.02
Add for contractor's profit @ 10 % 7796.90
85765.92
1021 SAME AS ITEM 1019 BUT IN LIGHTER BEAMS. 8035.11 8838.62 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 14.5 DAY 425.00 6162.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9 CUM. 750.00 6750.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 85.75 BAG 370.00 31727.50
Sundries.. L.S. 16316.12
80351.12
Add for contractor's profit @ 10 % 8035.11
88386.23
1023 R.C.C. WITH CEMENT, COARSE SAND AND 40 MM STONE BALLAST 1:1.5:3 IN 6833.48 7516.82 /CUM
RAFT FOUNDATIONS & FOOTING.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 14.5 DAY 425.00 6162.50
106 BHISTI 7 DAY 350.00 2450.00
245 STONE BALLAST 40MM GAUGE 9 CUM. 800.00 7200.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 85.75 BAG 370.00 31727.50
Sundries.. L.S. 3849.75
68334.75
Add for contractor's profit @ 10 % 6833.48
75168.23
1024 R.C.C. WITH CEMENT, COARSE SAND AND 20 MM STONE BALLAST 1:1.5:3 IN T 8469.27 9316.20 /CUM
BEAMS, SLABS, COLUMNS.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
104 COOLIE 14 DAY 350.00 4900.00
105 BLACK SMITH 14.5 DAY 425.00 6162.50
106 BHISTI 7 DAY 350.00 2450.00
246 STONE BALLAST 20MM GAUGE 9 CUM. 750.00 6750.00
249 COARSE SAND(BADARPUR) 4.5 CUM. 1395.00 6277.50
251 CEMENT 85.75 BAG 370.00 31727.50
Sundries.. L.S. 20657.69
84692.69
Add for contractor's profit @ 10 % 8469.27
93161.96
1026 SAME AS ITEMS 1018 TO 1024 BUT WITH SHINGLES (DEDUCT FROM ITEMS 476.02 523.62 /CUM
1018 TO 1024).
Details of cost for 10 /CUM
249 COARSE SAND(BADARPUR) 0.32 CUM. 1395.00 446.40
251 CEMENT 4.6 BAG 370.00 1702.00
257 SHINGLE 0.63 CUM 860.00 541.80
365 DIFFERENCE IN RATES OF SHINGLE AND 9 CUM. 230.00 2070.00
STONE GRIT
Sundries.. L.S. 0.00
4760.20
Add for contractor's profit @ 10 % 476.02
5236.22
1027 1ST CLASS BRICK-WORK IN KANKAR-LIME IN FOUNDATION & PLINTH. 5115.07 5626.58 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
255 KANKAR LIME 3 CUM 2100.00 6300.00
Sundries.. L.S. 375.74
51150.74
Add for contractor's profit @ 10 % 5115.07
56265.81
1028 1ST CLASS BRICK-WORK IN WHITE-LIME & SURKHI 1:2, IN FOUNDATION & 4709.19 5180.11 /CUM
PLINTH.
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
253 WHITE LIME(SLAKED) 1.2 CUM 750.00 900.00
256 SURKHI 2.4 CUM 550.00 1320.00
Sundries.. L.S. 396.91
47091.91
Add for contractor's profit @ 10 % 4709.19
51801.10
1030 SAME AS ITEM 1029 BUT IN 1:5 CEMENT & LOCAL-SAND MORTAR. 5242.02 5766.22 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
250 LOCAL SAND 2.5 CUM. 860.00 2150.00
251 CEMENT 15 BAG 370.00 5550.00
Sundries.. L.S. 245.22
52420.22
Add for contractor's profit @ 10 % 5242.02
57662.24
1031 SAME AS ITEM 1029 BUT IN 1:4 CEMENT & LOCAL-SAND MORTAR. 5343.84 5878.22 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
250 LOCAL SAND 2.4 CUM. 860.00 2064.00
251 CEMENT 18 BAG 370.00 6660.00
Sundries.. L.S. 239.40
53438.40
Add for contractor's profit @ 10 % 5343.84
58782.24
1033 SAME AS ITEM 1029 BUT IN 1:3 CEMENT & COARSE-SAND MORTAR. 5614.57 6176.03 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
249 COARSE SAND(BADARPUR) 2.25 CUM. 1395.00 3138.75
251 CEMENT 22.5 BAG 370.00 8325.00
Sundries.. L.S. 206.97
56145.72
Add for contractor's profit @ 10 % 5614.57
61760.29
1034 1ST CLASS BRICK-WORK IN MUD-MORTAR IN FOUNDATION & PLINTH. 4535.28 4988.81 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
104 COOLIE 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
235 BRICKS IST CLASS 4700 1000NO. 7350.00 34545.00
258 EARTH 3.2 CUM 180.00 576.00
Sundries.. L.S. 301.84
45352.84
Add for contractor's profit @ 10 % 4535.28
49888.12
1035 SAME AS ITEMS 1027 TO 1034 BUT IN SUPERSTRUCTURE 1.5 BRICK THICK 273.47 300.82 /CUM
WALL (EXTRA ON ITEMS 1027 TO 1034).
Details of cost for 10 /CUM
102 MASON/STONE MASON 3.5 DAY 425.00 1487.50
104 COOLIE 3.5 DAY 350.00 1225.00
Sundries.. L.S. 22.24
2734.74
Add for contractor's profit @ 10 % 273.47
3008.21
1037 SAME AS ITEMS 1027 TO 1034 BUT FOR HALF-BRICK THICK WALL (EXTRA ON 273.47 300.82 /CUM
ITEMS 1027 TO 1034).
Details of cost for 10 /CUM
102 MASON/STONE MASON 3.5 DAY 425.00 1487.50
104 COOLIE 3.5 DAY 350.00 1225.00
Sundries.. L.S. 22.24
2734.74
Add for contractor's profit @ 10 % 273.47
3008.21
1038 FOR II CLASS BRICK-WORK (DEDUCT FROM ITEMS 1027 TO 1036). 305.50 336.05 /CUM
Details of cost for 10 /CUM
364 DIFFERENCE IN RATES OF IST & 2ND 4700 1000NO. 650.00 3055.00
CLASS BRICKS
Sundries.. L.S. 0.00
3055.00
Add for contractor's profit @ 10 % 305.50
3360.50
1039 FOR III CLASS BRICK-WORK (DEDUCT FROM ITEMS 1034 TO 1036). 1339.50 1473.45 /CUM
Details of cost for 10 /CUM
366 DIFFERENCE IN RATES OF IST & 3RD 4700 1000NO. 2850.00 13395.00
CLASS BRICKS
Sundries.. L.S. 0.00
13395.00
Add for contractor's profit @ 10 % 1339.50
14734.50
1040 SUNDRIED BRICK-WORK IN MUD-MORTAR IN FOUNDATION & PLINTH. 2718.89 2990.78 /CUM
Details of cost for 10 /CUM
101 MISTRY 0.5 DAY 460.00 230.00
102 MASON/STONE MASON 7 DAY 425.00 2975.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
104 COOLIE 7 DAY 350.00 2450.00
106 BHISTI 0.5 DAY 350.00 175.00
241 BRICKS SUNDRIED 4700 1000NOS 3800.00 17860.00
258 EARTH 3.2 CUM 180.00 576.00
Sundries.. L.S. 472.87
27188.87
Add for contractor's profit @ 10 % 2718.89
29907.76
1042 SAME AS ITEM 1041 BUT IN JACK-ARCHES (EXTRA ON ITEMS 1027 TO 1033). 737.94 811.73 /CUM
Details of cost for 10 /CUM
102 MASON/STONE MASON 7 DAY 425.00 2975.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
104 COOLIE 9 DAY 350.00 3150.00
Sundries.. L.S. 29.40
7379.40
Add for contractor's profit @ 10 % 737.94
8117.34
1043 SAME AS ITEM 1041 BUT IN WELL-STEINING WITH ORDINARY BRICKS (EXTRA 875.38 962.92 /CUM
ON ITEMS 1027 TO 1033).
Details of cost for 10 /CUM
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
104 COOLIE 10.5 DAY 350.00 3675.00
Sundries.. L.S. 28.79
8753.79
Add for contractor's profit @ 10 % 875.38
9629.17
1044 SAME AS ITEM 1043 BUT WITH SPECIALLY MOULDED BRICKS (EXTRA ON 494.50 543.95 /CUM
ITEM 1043).
Details of cost for 10 /CUM
102 MASON/STONE MASON 2 DAY 425.00 850.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
243 DIFFERENCE IN RATES OF IST CLASS & 4700 1000NOS 350.00 1645.00
SPECIALLY MOULDED BRICKS
Sundries.. L.S. 0.00
4945.00
Add for contractor's profit @ 10 % 494.50
5439.50
1045 11.5 CM STRING OR DRIP-COURSE OF 1ST CLASS-BRICK IN KANKAR-LIME. 346.42 381.06 /RM
Details of cost for 10 /RM
101 MISTRY 0.25 DAY 460.00 115.00
102 MASON/STONE MASON 2 DAY 425.00 850.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
104 COOLIE 1.33 DAY 350.00 465.50
106 BHISTI 0.05 DAY 350.00 17.50
235 BRICKS IST CLASS 110 1000NO. 7350.00 808.50
255 KANKAR LIME 0.18 CUM 2100.00 378.00
Sundries.. L.S. 129.71
3464.21
Add for contractor's profit @ 10 % 346.42
3810.63
1047 SAME AS ITEM 1045 BUT IN 23 CM CORNICE IN KANKAR-LIME WITH LIME- 246.38 271.02 /RM
PLASTER.
Details of cost for 10 /RM
101 MISTRY 0.2 DAY 460.00 92.00
102 MASON/STONE MASON 2.25 DAY 425.00 956.25
104 COOLIE 1.33 DAY 350.00 465.50
106 BHISTI 0.05 DAY 350.00 17.50
236 BRICK TILES IST CLASS 55 1000NOS 9000.00 495.00
255 KANKAR LIME 0.16 CUM 2100.00 336.00
Sundries.. L.S. 101.58
2463.83
Add for contractor's profit @ 10 % 246.38
2710.21
1048 SAME AS ITEM 1047 BUT IN 1:6 CEMENT & LOCAL-SAND WITH PLASTERING 257.70 283.47 /RM
1:6.
Details of cost for 10 /RM
101 MISTRY 0.2 DAY 460.00 92.00
102 MASON/STONE MASON 2.25 DAY 425.00 956.25
104 COOLIE 1.33 DAY 350.00 465.50
106 BHISTI 0.1 DAY 350.00 35.00
236 BRICK TILES IST CLASS 55 1000NOS 9000.00 495.00
250 LOCAL SAND 0.17 CUM. 860.00 146.20
251 CEMENT 0.78 BAG 370.00 288.60
Sundries.. L.S. 98.40
2576.95
Add for contractor's profit @ 10 % 257.70
2834.65
1049 EXTRA FOR CUTTING OF BRICK FOR MOULDING. 91.53 100.68 /RM
Details of cost for 10 /RM
102 MASON/STONE MASON 1.33 DAY 425.00 565.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
Sundries.. L.S. 0.00
915.25
Add for contractor's profit @ 10 % 91.52
1006.77
1051 R.B. WORK IN SUN-SHADE WITH 1ST CLASS BRICK, CEMENT & COARSE- 7631.65 8394.82 /CUM
SAND MORTAR 1:3.
Details of cost for 10 /CUM
101 MISTRY 2.75 DAY 460.00 1265.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
104 COOLIE 18 DAY 350.00 6300.00
105 BLACK SMITH 6 DAY 425.00 2550.00
106 BHISTI 3 DAY 350.00 1050.00
107 CARPENTER 8 DAY 460.00 3680.00
235 BRICKS IST CLASS 4250 1000NO. 7350.00 31237.50
249 COARSE SAND(BADARPUR) 3.6 CUM. 1395.00 5022.00
251 CEMENT 36 BAG 370.00 13320.00
Sundries.. L.S. 1342.04
76316.54
Add for contractor's profit @ 10 % 7631.65
83948.19
1054 20 MM THICK D.P.C. WITH CEMENT & COARSE-SAND 1:2. 233.47 256.82 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.05 DAY 460.00 23.00
102 MASON/STONE MASON 0.25 DAY 425.00 106.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
104 COOLIE 0.25 DAY 350.00 87.50
106 BHISTI 0.25 DAY 350.00 87.50
249 COARSE SAND(BADARPUR) 0.18 CUM. 1395.00 251.10
251 CEMENT 2.6 BAG 370.00 962.00
278 WATER PROOFING COMPOUND 6.5 KG. 105.00 682.50
Sundries.. L.S. 47.35
2334.70
Add for contractor's profit @ 10 % 233.47
2568.17
1055 SAME AS ITEM 1054 BUT 25 MM THICK C.C. WITH CEMENT, COARSE-SAND & 281.85 310.04 /SQM
12 MM STONE GRIT 1:1.5:3.
Details of cost for 10 /SQM
101 MISTRY 0.06 DAY 460.00 27.60
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
106 BHISTI 0.125 DAY 350.00 43.75
247 STONE GRIT 10-12MM 0.22 CUM. 1090.00 239.80
249 COARSE SAND(BADARPUR) 0.11 CUM. 1395.00 153.45
251 CEMENT 2.2 BAG 370.00 814.00
278 WATER PROOFING COMPOUND 3.4 KG. 105.00 357.00
Sundries.. L.S. 20.43
2818.53
Add for contractor's profit @ 10 % 281.85
3100.38
1057 SUPPLY & FIX 40 MM THICK STONE-SLAB IN STEPS & SHELVES WITH 1009.17 1110.09 /SQM
CEMENT & LOCAL-SAND 1:6.
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7.5 DAY 350.00 2625.00
104 COOLIE 6 DAY 350.00 2100.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 0.25 DAY 350.00 87.50
250 LOCAL SAND 0.45 CUM. 860.00 387.00
251 CEMENT 2 BAG 370.00 740.00
260 STONE 40MM THICK 10.5 SQM 350.00 3675.00
Sundries.. L.S. 52.21
10091.71
Add for contractor's profit @ 10 % 1009.17
11100.88
1058 SUPPLY & FIX 40 MM THICK STONE CHAJJAS WITH CEMENT & LOCAL-SAND 1009.17 1110.09 /SQM
1:6.
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7.5 DAY 350.00 2625.00
104 COOLIE 6 DAY 350.00 2100.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
106 BHISTI 0.25 DAY 350.00 87.50
250 LOCAL SAND 0.45 CUM. 860.00 387.00
251 CEMENT 2 BAG 370.00 740.00
260 STONE 40MM THICK 10.5 SQM 350.00 3675.00
Sundries.. L.S. 52.21
10091.71
Add for contractor's profit @ 10 % 1009.17
11100.88
1059 SUPPLY & FIX UPTO 40 MM THICK STONE SUN-SHADE OVER DOORS & 816.69 898.36 /SQM
WINDOWS WITH CEMENT & LOCAL-SAND 1:6.
Details of cost for 2 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
106 BHISTI 0.125 DAY 350.00 43.75
133 STONE DRESSER 1 DAY 400.00 400.00
260 STONE 40MM THICK 2 SQM 350.00 700.00
Sundries.. L.S. 102.13
1633.38
Add for contractor's profit @ 10 % 163.34
1796.72
1061 C.P. TEAK-WOOD WROUGHT, FRAMED & FIXED IN CHAUKHATS. 124173.40 136590.80 /CUM
Details of cost for 0.05 /CUM
101 MISTRY 0.08 DAY 460.00 36.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
107 CARPENTER 0.75 DAY 460.00 345.00
301 TEAK WOOD(C.P.) 0.054 CUM. 101500.00 5481.00
Sundries.. L.S. 170.87
6208.67
Add for contractor's profit @ 10 % 620.87
6829.54
1062 SAME AS ITEM 1061 BUT WITH SHEESHAM-WOOD. 62092.80 68302.00 /CUM
Details of cost for 0.05 /CUM
101 MISTRY 0.08 DAY 460.00 36.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
107 CARPENTER 0.75 DAY 460.00 345.00
302 SHISHAM WOOD 0.054 CUM. 45600.00 2462.40
Sundries.. L.S. 85.44
3104.64
Add for contractor's profit @ 10 % 310.46
3415.10
1063 SAME AS ITEM 1061 BUT WITH INDIAN-SAL-WOOD. 74975.40 82473.00 /CUM
Details of cost for 0.05 /CUM
101 MISTRY 0.08 DAY 460.00 36.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
107 CARPENTER 0.75 DAY 460.00 345.00
303 SAL WOOD 0.054 CUM. 57200.00 3088.80
Sundries.. L.S. 103.17
3748.77
Add for contractor's profit @ 10 % 374.88
4123.65
1064 SAME AS ITEM 1061 BUT WITH DEODAR-WOOD. 90856.40 99942.00 /CUM
Details of cost for 0.05 /CUM
101 MISTRY 0.08 DAY 460.00 36.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
107 CARPENTER 0.75 DAY 460.00 345.00
304 DEODAR WOOD 0.054 CUM. 71500.00 3861.00
Sundries.. L.S. 125.02
4542.82
Add for contractor's profit @ 10 % 454.28
4997.10
1066 SAME AS ITEM 1061 BUT WITH COUNTRY-WOOD. 70089.00 77097.80 /CUM
Details of cost for 0.05 /CUM
101 MISTRY 0.08 DAY 460.00 36.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
107 CARPENTER 0.75 DAY 460.00 345.00
306 COUNTRY WOOD 0.054 CUM. 52800.00 2851.20
Sundries.. L.S. 96.45
3504.45
Add for contractor's profit @ 10 % 350.44
3854.89
1067 SAME AS ITEM 1061 TO 1066 BUT FOR CURVED WORK (EXTRA ON ITEMS 1061 25%
TO 1066).
Details of cost for 0 25%
Sundries.. L.S.
1068 WOOD-WORK WROUGHT, FRAMED & FIX IN ROOF-TRUSSES PURLINS, 188.60 207.46 /CUM
CEILINGS, JOINTS (DEDUCT FROM ITEMS 1061 TO 1066).
Details of cost for 1 /CUM
107 CARPENTER 0.41 DAY 460.00 188.60
1069 SUPPLY & FIX 40 MM THICK C.P. TEAK WOOD PART PANNELLED & PART 5440.96 5985.06 /SQM
GLAZED IN DOOR & WINDOW SHUTTERS.
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.07 CUM. 101500.00 7105.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 60.85
11763.35
Add for contractor's profit @ 10 % 1176.34
12939.69
1071 SAME AS ITEM 1069 BUT FOR C.P. TEAK WOOD FULLY PANELLED (40 MM 5920.93 6513.02 /SQM
THICK).
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.1 CUM. 101500.00 10150.00
Sundries.. L.S. 53.54
12801.04
Add for contractor's profit @ 10 % 1280.10
14081.14
1072 SAME AS ITEM 1069 BUT FOR C.P. TEAK WOOD FULLY GLAZED (40 MM THICK). 6473.29 7120.61 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
301 TEAK WOOD(C.P.) 0.035 CUM. 101500.00 3552.50
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 79.93
9709.93
Add for contractor's profit @ 10 % 970.99
10680.92
1073 SAME AS ITEM 1069 BUT FOR C.P. TEAK WOOD 35 MM THICK. 4971.52 5468.67 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.06 CUM. 101500.00 6090.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 60.92
10748.42
Add for contractor's profit @ 10 % 1074.84
11823.26
1074 SAME AS ITEM 1071 BUT FOR C.P. TEAK WOOD 35 MM THICK. 5451.65 5996.82 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.09 CUM. 101500.00 9135.00
Sundries.. L.S. 53.97
11786.47
Add for contractor's profit @ 10 % 1178.65
12965.12
1076 SAME AS ITEM 1069 BUT FOR C.P. TEAK WOOD 25 MM THICK. 4221.53 4643.68 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.044 CUM. 101500.00 4466.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 63.44
9126.94
Add for contractor's profit @ 10 % 912.69
10039.63
1077 SAME AS ITEM 1071 BUT FOR C.P. TEAK WOOD 25 MM THICK. 4184.07 4602.47 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
301 TEAK WOOD(C.P.) 0.063 CUM. 101500.00 6394.50
Sundries.. L.S. 53.95
9045.95
Add for contractor's profit @ 10 % 904.60
9950.55
1078 SAME AS ITEM 1072 BUT FOR C.P. TEAK WOOD 25 MM THICK. 5599.06 6158.97 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
301 TEAK WOOD(C.P.) 0.022 CUM. 101500.00 2233.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 88.09
8398.59
Add for contractor's profit @ 10 % 839.86
9238.45
1079 SAME AS ITEM 1069 BUT FOR SHEESHAM WOOD 40 MM THICK. 3626.69 3989.36 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
302 SHISHAM WOOD 0.07 CUM. 45600.00 3192.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 51.41
7840.91
Add for contractor's profit @ 10 % 784.09
8625.00
1081 SAME AS ITEM 1072 BUT FOR SHEESHAM WOOD 40 MM THICK. 5167.33 5684.07 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
302 SHISHAM WOOD 0.035 CUM. 45600.00 1596.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 77.50
7751.00
Add for contractor's profit @ 10 % 775.10
8526.10
1082 SAME AS ITEM 1079 BUT FOR SHEESHAM WOOD 35 MM THICK. 3416.76 3758.43 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
302 SHISHAM WOOD 0.06 CUM. 45600.00 2736.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 53.53
7387.03
Add for contractor's profit @ 10 % 738.70
8125.73
1083 SAME AS ITEM 1080 BUT FOR SHEESHAM WOOD 35 MM THICK. 3118.27 3430.10 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
302 SHISHAM WOOD 0.09 CUM. 45600.00 4104.00
Sundries.. L.S. 40.21
6741.71
Add for contractor's profit @ 10 % 674.17
7415.88
1084 SAME AS ITEM 1081 BUT FOR SHEESHAM WOOD 35 MM THICK. 5047.50 5552.25 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
302 SHISHAM WOOD 0.031 CUM. 45600.00 1413.60
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 80.15
7571.25
Add for contractor's profit @ 10 % 757.12
8328.37
1086 SAME AS ITEM 1071 BUT FOR SAL WOOD 40 MM THICK. 3872.91 4260.20 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
303 SAL WOOD 0.1 CUM. 57200.00 5720.00
Sundries.. L.S. 55.73
8373.23
Add for contractor's profit @ 10 % 837.32
9210.55
1087 SAME AS ITEM 1072 BUT FOR SAL WOOD 40 MM THICK. 5447.74 5992.51 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
303 SAL WOOD 0.035 CUM. 57200.00 2002.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 92.11
8171.61
Add for contractor's profit @ 10 % 817.16
8988.77
1088 SAME AS ITEM 1085 BUT FOR SAL WOOD 35 MM THICK. 3744.75 4119.22 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
303 SAL WOOD 0.06 CUM. 57200.00 3432.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 66.64
8096.14
Add for contractor's profit @ 10 % 809.61
8905.75
1089 SAME AS ITEM 1076 BUT FOR SAL WOOD 35 MM THICK. 3608.36 3969.20 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
303 SAL WOOD 0.09 CUM. 57200.00 5148.00
Sundries.. L.S. 55.77
7801.27
Add for contractor's profit @ 10 % 780.13
8581.40
1091 SAME AS ITEM 1069 BUT FOR DEODAR WOOD 40 MM THICK. 4468.58 4915.44 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
304 DEODAR WOOD 0.07 CUM. 71500.00 5005.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 58.58
9661.08
Add for contractor's profit @ 10 % 966.11
10627.19
1092 SAME AS ITEM 1071 BUT FOR DEODAR WOOD 40 MM THICK. 4531.55 4984.70 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
304 DEODAR WOOD 0.1 CUM. 71500.00 7150.00
Sundries.. L.S. 49.71
9797.21
Add for contractor's profit @ 10 % 979.72
10776.93
1093 SAME AS ITEM 1072 BUT FOR DEODAR WOOD 40 MM THICK. 5774.34 6351.77 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 0.035 CUM. 71500.00 2502.50
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 81.51
8661.51
Add for contractor's profit @ 10 % 866.15
9527.66
1094 SAME AS ITEM 1091 BUT FOR DEODAR WOOD 35 MM THICK. 4138.32 4552.15 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
304 DEODAR WOOD 0.06 CUM. 71500.00 4290.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 59.55
8947.05
Add for contractor's profit @ 10 % 894.70
9841.75
1096 SAME AS ITEM 1093 BUT FOR DEODAR WOOD 35 MM THICK. 5578.55 6136.40 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 0.031 CUM. 71500.00 2216.50
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 73.82
8367.82
Add for contractor's profit @ 10 % 836.78
9204.60
1097 SAME AS ITEM 1091 BUT FOR DEODAR WOOD 25 MM THICK. 3610.29 3971.32 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
304 DEODAR WOOD 0.044 CUM. 71500.00 3146.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 61.95
7805.45
Add for contractor's profit @ 10 % 780.54
8585.99
1098 SAME AS ITEM 1092 BUT FOR DEODAR WOOD 25 MM THICK. 3308.24 3639.07 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
304 DEODAR WOOD 0.063 CUM. 71500.00 4504.50
Sundries.. L.S. 50.42
7152.42
Add for contractor's profit @ 10 % 715.24
7867.66
1099 SAME AS ITEM 1093 BUT FOR DEODAR WOOD 25 MM THICK. 5154.91 5670.40 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 0.022 CUM. 71500.00 1573.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 81.86
7732.36
Add for contractor's profit @ 10 % 773.24
8505.60
1101 SAME AS ITEM 1071 BUT FOR CHIR WOOD 40 MM THICK. 3159.28 3475.21 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
307 CHIR WOOD 0.1 CUM. 41800.00 4180.00
Sundries.. L.S. 52.86
6830.36
Add for contractor's profit @ 10 % 683.04
7513.40
1102 SAME AS ITEM 1072 BUT FOR CHIR WOOD 40 MM THICK. 5089.33 5598.27 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
307 CHIR WOOD 0.035 CUM. 41800.00 1463.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 93.50
7634.00
Add for contractor's profit @ 10 % 763.40
8397.40
1103 SAME AS ITEM 1100 BUT FOR CHIR WOOD 35 MM THICK. 3316.78 3648.46 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
307 CHIR WOOD 0.06 CUM. 41800.00 2508.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 65.37
7170.87
Add for contractor's profit @ 10 % 717.09
7887.96
1104 SAME AS ITEM 1101 BUT FOR CHIR WOOD 35 MM THICK. 2965.90 3262.49 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
307 CHIR WOOD 0.09 CUM. 41800.00 3762.00
Sundries.. L.S. 52.78
6412.28
Add for contractor's profit @ 10 % 641.23
7053.51
1106 SAME AS ITEM 1100 BUT FOR CHIR WOOD 25 MM THICK. 3008.76 3309.63 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
307 CHIR WOOD 0.044 CUM. 41800.00 1839.20
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 68.23
6504.93
Add for contractor's profit @ 10 % 650.49
7155.42
1107 SAME AS ITEM 1101 BUT FOR CHIR WOOD 25 MM THICK. 2444.39 2688.83 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
307 CHIR WOOD 0.063 CUM. 41800.00 2633.40
Sundries.. L.S. 53.88
5284.78
Add for contractor's profit @ 10 % 528.48
5813.26
1108 SAME AS ITEM 1102 BUT FOR CHIR WOOD 25 MM THICK. 4714.18 5185.60 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
307 CHIR WOOD 0.022 CUM. 41800.00 919.60
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 74.17
7071.27
Add for contractor's profit @ 10 % 707.13
7778.40
1109 SAME AS ITEM 1069 BUT FOR KAIL WOOD 40 MM THICK. 3999.18 4399.10 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
303 SAL WOOD 0.07 CUM. 57200.00 4004.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 44.73
8646.23
Add for contractor's profit @ 10 % 864.62
9510.85
1111 SAME AS ITEM 1072 BUT FOR KAIL WOOD 40 MM THICK. 5160.33 5676.37 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
305 KAIL WOOD 0.035 CUM. 45000.00 1575.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 88.00
7740.50
Add for contractor's profit @ 10 % 774.05
8514.55
1112 SAME AS ITEM 1109 BUT FOR KAIL WOOD 35 MM THICK. 3403.70 3744.07 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
305 KAIL WOOD 0.06 CUM. 45000.00 2700.00
349 GLASS PANE 24*36CM(2.5MM THICK) 8 NO. 250.00 2000.00
Sundries.. L.S. 61.30
7358.80
Add for contractor's profit @ 10 % 735.88
8094.68
1113 SAME AS ITEM 1110 BUT FOR KAIL WOOD 35 MM THICK. 3097.45 3407.20 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 4 DAY 460.00 1840.00
305 KAIL WOOD 0.09 CUM. 45000.00 4050.00
Sundries.. L.S. 49.19
6696.69
Add for contractor's profit @ 10 % 669.67
7366.36
1114 SAME AS ITEM 1111 BUT FOR KAIL WOOD 35 MM THICK. 5041.95 5546.14 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
305 KAIL WOOD 0.031 CUM. 45000.00 1395.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 90.42
7562.92
Add for contractor's profit @ 10 % 756.29
8319.21
1116 SAME AS ITEM 1110 BUT FOR KAIL WOOD 25 MM THICK. 4147.08 4561.79 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
305 KAIL WOOD 0.063 CUM. 45000.00 2835.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 53.48
8965.98
Add for contractor's profit @ 10 % 896.60
9862.58
1117 SAME AS ITEM 1111 BUT FOR KAIL WOOD 25 MM THICK. 4776.69 5254.35 /SQM
Details of cost for 1.5 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
305 KAIL WOOD 0.022 CUM. 45000.00 990.00
350 GLASS PANE(18*34CM)2.5MM THICK 16 NO. 275.00 4400.00
Sundries.. L.S. 97.53
7165.03
Add for contractor's profit @ 10 % 716.50
7881.53
1118 SUPPLY OF 1 MM THICK SHEET IRON PANNELLED DOOR & WINDOW 2931.57 3224.72 /SQM
SHUTTERS IN 40 MM THICK SALWOOD FRAME.
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
107 CARPENTER 2.5 DAY 460.00 1150.00
303 SAL WOOD 0.063 CUM. 57200.00 3603.60
321 SHEET IRON 1MM THICK 10.03 KG. 65.00 651.95
Sundries.. L.S. 0.00
6338.05
Add for contractor's profit @ 10 % 633.80
6971.85
1120 SAME AS ITEM 1119 BUT IN SHEESHAM WOOD 40 MM THICK. 2517.72 2769.49 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
107 CARPENTER 2.5 DAY 460.00 1150.00
302 SHISHAM WOOD 0.063 CUM. 45600.00 2872.80
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.22 SQM. 400.00 488.00
Sundries.. L.S. 0.00
5443.30
Add for contractor's profit @ 10 % 544.33
5987.63
1121 SAME AS ITEM 1119 BUT IN SAL WOOD 40 MM THICK. 2855.74 3141.31 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
107 CARPENTER 2.5 DAY 460.00 1150.00
303 SAL WOOD 0.063 CUM. 57200.00 3603.60
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.22 SQM. 400.00 488.00
Sundries.. L.S. 0.00
6174.10
Add for contractor's profit @ 10 % 617.41
6791.51
1122 SAME AS ITEM 1119 BUT IN DEODAR WOOD 40 MM THICK. 3272.43 3599.68 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
107 CARPENTER 2.5 DAY 460.00 1150.00
304 DEODAR WOOD 0.063 CUM. 71500.00 4504.50
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.22 SQM. 400.00 488.00
Sundries.. L.S. 0.00
7075.00
Add for contractor's profit @ 10 % 707.50
7782.50
1123 SAME AS ITEM 1119 BUT IN CHIR WOOD 40 MM THICK. 2406.98 2647.68 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
107 CARPENTER 2.5 DAY 460.00 1150.00
307 CHIR WOOD 0.063 CUM. 41800.00 2633.40
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.22 SQM. 400.00 488.00
Sundries.. L.S. 0.00
5203.90
Add for contractor's profit @ 10 % 520.39
5724.29
1125 SUPPLY OF GALVANIZED IRON WIRE OVER WINDOWS AND C.P. TEAK WOOD 976.67 1074.34 /SQM
BATTENS 50 MM X 12 MM.
Details of cost for 1.5 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
107 CARPENTER 0.25 DAY 460.00 115.00
301 TEAK WOOD(C.P.) 0.0044 CUM. 101500.00 446.60
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.65 SQM. 400.00 660.00
Sundries.. L.S. 155.91
1465.01
Add for contractor's profit @ 10 % 146.50
1611.51
1126 SAME AS ITEM 1125 BUT WITH SHEESHAM WOOD BATTENS 50 MM X 12 MM. 802.74 883.01 /SQM
Details of cost for 1.5 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
107 CARPENTER 0.25 DAY 460.00 115.00
302 SHISHAM WOOD 0.0044 CUM. 45600.00 200.64
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.65 SQM. 400.00 660.00
Sundries.. L.S. 140.97
1204.11
Add for contractor's profit @ 10 % 120.41
1324.52
1127 SAME AS ITEM 1125 BUT WITH DEODAR WOOD BATTENS 50 MM X 12 MM. 885.49 974.04 /SQM
Details of cost for 1.5 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
107 CARPENTER 0.25 DAY 460.00 115.00
304 DEODAR WOOD 0.0044 CUM. 71500.00 314.60
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.65 SQM. 400.00 660.00
Sundries.. L.S. 151.14
1328.24
Add for contractor's profit @ 10 % 132.82
1461.06
1128 SAME AS ITEM 1125 BUT WITH SAL WOOD BATTENS 50 MM X 12 MM. 847.30 932.03 /SQM
Details of cost for 1.5 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
107 CARPENTER 0.25 DAY 460.00 115.00
303 SAL WOOD 0.0044 CUM. 57200.00 251.68
343 G.I. WIRE GAUGE 2.5,2 OR 1.5MM MESH 1.65 SQM. 400.00 660.00
Sundries.. L.S. 156.77
1270.95
Add for contractor's profit @ 10 % 127.10
1398.05
1130 SAME AS ITEM 1129 BUT IN SAL WOOD 40 MM THICK. 5065.81 5572.39 /SQM
Details of cost for 1.32 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
303 SAL WOOD 0.092 CUM. 57200.00 5262.40
331 IRON SCREW 65*25MM. 50 100NO. 105.00 52.50
Sundries.. L.S. 99.47
6686.87
Add for contractor's profit @ 10 % 668.69
7355.56
1131 SAME AS ITEM 1129 BUT IN COUNTRY WOOD 40 MM THICK. 4740.93 5215.02 /SQM
Details of cost for 1.32 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
306 COUNTRY WOOD 0.092 CUM. 52800.00 4857.60
331 IRON SCREW 65*25MM. 50 100NO. 105.00 52.50
Sundries.. L.S. 75.43
6258.03
Add for contractor's profit @ 10 % 625.80
6883.83
1132 SAME AS ITEM 1129 BUT IN DEODAR WOOD 40 MM THICK. 6060.17 6666.18 /SQM
Details of cost for 1.32 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
304 DEODAR WOOD 0.092 CUM. 71500.00 6578.00
331 IRON SCREW 65*25MM. 50 100NO. 105.00 52.50
Sundries.. L.S. 96.42
7999.42
Add for contractor's profit @ 10 % 799.94
8799.36
1133 SAME AS ITEM 1129 BUT IN KAIL WOOD 40 MM THICK. 4190.66 4609.73 /SQM
Details of cost for 1.32 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
305 KAIL WOOD 0.092 CUM. 45000.00 4140.00
331 IRON SCREW 65*25MM. 50 100NO. 105.00 52.50
Sundries.. L.S. 66.67
5531.67
Add for contractor's profit @ 10 % 553.17
6084.84
1135 SUPPLY OF 40MM THICK C.P. TEAK WOOD DOOR & WINDOW SHUTTERS 4339.18 4773.10 /SQM
WITH 9MM THICK PLYWOOD OR PRESSED WOOD PANELS AND FIXING C.P.
TEAK WOOD CLEATS, STOPS, HINGES, LOCK, BOLTS, HANDLERS, SPRINGS &
OTHER FITTINGS (EXCLUDING SUPPLY OF FITTINGS).
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
301 TEAK WOOD(C.P.) 0.063 CUM. 101500.00 6394.50
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 103.91
9381.31
Add for contractor's profit @ 10 % 938.13
10319.44
1136 SAME AS ITEM 1135 BUT IN DEODAR WOOD 40 MM THICK. 3463.06 3809.36 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
304 DEODAR WOOD 0.063 CUM. 71500.00 4504.50
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 99.73
7487.13
Add for contractor's profit @ 10 % 748.71
8235.84
1137 SAME AS ITEM 1135 BUT IN SHEESHAM WOOD 40 MM THICK. 2701.35 2971.48 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
302 SHISHAM WOOD 0.063 CUM. 45600.00 2872.80
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 84.61
5840.31
Add for contractor's profit @ 10 % 584.03
6424.34
1139 SAME AS ITEM 1135 BUT IN KAIL WOOD 40 MM THICK. 2691.80 2960.99 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
305 KAIL WOOD 0.063 CUM. 45000.00 2835.00
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 101.78
5819.68
Add for contractor's profit @ 10 % 581.97
6401.65
1140 SAME AS ITEM 1135 BUT IN CHIR WOOD 40 MM THICK. 2602.00 2862.20 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
307 CHIR WOOD 0.063 CUM. 41800.00 2633.40
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 109.22
5625.52
Add for contractor's profit @ 10 % 562.55
6188.07
1141 SAME AS ITEM 1135 BUT IN COUNTRY WOOD 40 MM THICK. 2949.56 3244.52 /SQM
Details of cost for 2.162 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.5 DAY 460.00 690.00
306 COUNTRY WOOD 0.063 CUM. 52800.00 3326.40
308 PLY WOOD 9MM 1.22 SQM. 1320.00 1610.40
Sundries.. L.S. 167.65
6376.95
Add for contractor's profit @ 10 % 637.70
7014.65
Sundries.. L.S.
Sundries.. L.S.
Sundries.. L.S.
Sundries.. L.S.
1146 ROLLED STEEL JOISTS LIGHT SECTION 0.0 - 7.5M HIGH. 1204.52 1324.98 /QTL
Details of cost for 0.5 /QTL
102 MASON/STONE MASON 0.1 DAY 425.00 42.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
104 COOLIE 1 DAY 350.00 350.00
120 PESHRAJ 0.05 DAY 350.00 17.50
Sundries.. L.S. 17.26
602.26
Add for contractor's profit @ 10 % 60.23
662.49
1147 ROLLED STEEL JOISTS HEAVY SECTION 0.0 - 7.5M HIGH. 2363.30 2599.62 /QTL
Details of cost for 0.5 /QTL
102 MASON/STONE MASON 0.1 DAY 425.00 42.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 1.5 DAY 350.00 525.00
120 PESHRAJ 0.05 DAY 350.00 17.50
Sundries.. L.S. 246.65
1181.65
Add for contractor's profit @ 10 % 118.16
1299.81
1148 EXTRA ON ITEMS 1146 & 1147 FOR MORE THAN 7.5M HEIGHT. 746.68 821.34 /QTL
Details of cost for 0.5 /QTL
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
104 COOLIE 0.5 DAY 350.00 175.00
Sundries.. L.S. 23.34
373.34
Add for contractor's profit @ 10 % 37.33
410.67
1150 MILD STEEL OR IRON WORK IN HEAVY SIZES. 6586.73 7245.41 /QTL
Details of cost for 0.5 /QTL
104 COOLIE 1 DAY 350.00 350.00
105 BLACK SMITH 1 DAY 425.00 425.00
108 HAMMER MAN 1 DAY 350.00 350.00
279 STEEL 51.25 KG. 37.50 1921.88
Sundries.. L.S. 246.49
3293.37
Add for contractor's profit @ 10 % 329.34
3622.71
1152 CUTTING ROLLED STEEL JOISTS UPTO 225MM X 100MM. 221.46 243.61 /CUT
Details of cost for 1 /CUT
104 COOLIE 0.25 DAY 350.00 87.50
105 BLACK SMITH 0.25 DAY 425.00 106.25
Sundries.. L.S. 27.71
221.46
Add for contractor's profit @ 10 % 22.15
243.61
1153 CUTTING ROLLED STEEL JOISTS ABOVE 225MM X 100MM. 442.91 487.20 /CUT
Details of cost for 1 /CUT
104 COOLIE 0.5 DAY 350.00 175.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 55.41
442.91
Add for contractor's profit @ 10 % 44.29
487.20
1154 CUTTING OF PLATES & ANGLES UPTO 20MM THICK. 96.88 106.57 /SQM
Details of cost for 1 /SQM
104 COOLIE 0.125 DAY 350.00 43.75
105 BLACK SMITH 0.125 DAY 425.00 53.13
Sundries.. L.S. 0.00
96.88
Add for contractor's profit @ 10 % 9.69
106.57
1156 BORING HOLES IN MILD STEEL OR IRON UPTO 10MM DIA. & UPTO 6 MM THICK 29.99 32.99 /HOLE
PLATE.
Details of cost for 100 /HOLE
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 3 DAY 350.00 1050.00
105 BLACK SMITH 3.5 DAY 425.00 1487.50
Sundries.. L.S. 111.17
2998.67
Add for contractor's profit @ 10 % 299.87
3298.54
1157 SAME AS ITEM 1156 BUT HOLES 10 - 20MM DIA. & 6.0 - 13.0 MM THICK PLATE. 47.53 52.29 /HOLE
Details of cost for 100 /HOLE
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
105 BLACK SMITH 6 DAY 425.00 2550.00
Sundries.. L.S. 103.23
4753.23
Add for contractor's profit @ 10 % 475.32
5228.55
1158 PROVIDE & FIX 100MM DIA. C.I. DOWN PIPE. 564.47 620.92 / RM
Details of cost for 10 / RM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
327 M.S. CLAMP 5 NO. 270.00 1350.00
352 C.I.DOWN PIPE 100MM DIA. 2M LONG 10 RM. 302.50 3025.00
359 ROSE BOWL 1 NO. 115.50 115.50
360 HEAD 1 NO. 110.00 110.00
361 SHOE SPLASH PROOF 1 NO. 110.00 110.00
362 BEND WITH EYE HOLE 1 NO. 82.50 82.50
Sundries.. L.S. 289.20
5644.70
Add for contractor's profit @ 10 % 564.47
6209.17
1161 SAME AS ITEM 1160 BUT FOR DOUBLE ALLAHABAD TILES ROOF. 943.92 1038.31 /SQM
Details of cost for 225 /SQM
101 MISTRY 3.2 DAY 460.00 1472.00
102 MASON/STONE MASON 38.4 DAY 425.00 16320.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 38.4 DAY 350.00 13440.00
104 COOLIE 76.8 DAY 350.00 26880.00
106 BHISTI 1.6 DAY 350.00 560.00
107 CARPENTER 28.8 DAY 460.00 13248.00
253 WHITE LIME(SLAKED) 0.72 CUM 750.00 540.00
256 SURKHI 1.52 CUM 550.00 836.00
264 FLAT TILES 4032 100NOS 385.00 15523.20
265 HALF ROUND TILES 4032 100NOS 594.00 23950.08
266 FLAT RIDGE 204.8 100NOS 594.00 1216.51
280 COAL TARRING 176 SQM. 24.00 4224.00
303 SAL WOOD 1.52 CUM. 57200.00 86944.00
328 NAILS 89.6 KG. 75.00 6720.00
Sundries.. L.S. 508.50
212382.29
Add for contractor's profit @ 10 % 21238.23
233620.52
1162 SUPPLY & FIX LARGE COUNTRY TILES ROOFING ON BAMBOO FRAMES. 887.91 976.70 /SQM
Details of cost for 10 /SQM
104 COOLIE 2 DAY 350.00 700.00
121 TILE LAYER 2 DAY 350.00 700.00
122 THATCHER 1 DAY 350.00 350.00
267 LARGE COUNTRY TILES 120 100NOS 1199.00 1438.80
268 SEGMENTAL TILES 120 100NOS 494.00 592.80
280 COAL TARRING 10 SQM. 24.00 240.00
314 BAMBOOS 25MM DIA. 40 NO. 80.00 3200.00
315 CHATAI 12 SQM. 125.00 1500.00
316 BAN 5 KG. 16.50 82.50
328 NAILS 1 KG. 75.00 75.00
Sundries.. L.S. 0.00
8879.10
Add for contractor's profit @ 10 % 887.91
9767.01
1164 LAYING OF R.B. SLAB WITH 1ST CLASS BRICKS LAID IN CEMENT MORTAR 9410.66 10351.73 /CUM
WITH APPROVED COARSE SAND (1:3).
Details of cost for 1 /CUM
101 MISTRY 0.167 DAY 460.00 76.82
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
104 COOLIE 2.75 DAY 350.00 962.50
105 BLACK SMITH 0.75 DAY 425.00 318.75
106 BHISTI 0.5 DAY 350.00 175.00
107 CARPENTER 0.5 DAY 460.00 230.00
235 BRICKS IST CLASS 425 1000NO. 7350.00 3123.75
249 COARSE SAND(BADARPUR) 0.36 CUM. 1395.00 502.20
251 CEMENT 3.6 BAG 370.00 1332.00
297 SAL BALLIES(EUCALYPTUS)100MM 3 RM. 165.00 495.00
306 COUNTRY WOOD 0.015 CUM. 52800.00 792.00
Sundries.. L.S. 277.64
9410.66
Add for contractor's profit @ 10 % 941.07
10351.73
1165 SUPPLY & FIX GALVANISED CORRUGATED IRON ROOFING 0.63MM THICK. 1011.39 1112.53 /SQM
Details of cost for 225 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 22 DAY 350.00 7700.00
107 CARPENTER 22 DAY 460.00 10120.00
322 G.C. SHEETS 0.63MM 17.5 QTL. 10450.00 182875.00
332 G.I. BOLTS 25*6MM. 650 10NO. 95.00 6175.00
333 G.I. BOLTS 150MM. 480 10NO. 125.00 6000.00
354 LUMPET WASHER 1100 10NO. 104.50 11495.00
355 BITUMEN WASHER 1100 10NO. 12.65 1391.50
Sundries.. L.S. 1806.05
227562.55
Add for contractor's profit @ 10 % 22756.26
250318.81
1167 SUPPLY & LAY 40MM THICK INSULATION LAYER OF SAND & CLAY OVER 42.26 46.48 /SQM
ROOF.
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.25 DAY 425.00 106.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
250 LOCAL SAND 0.22 CUM. 860.00 189.20
258 EARTH 0.22 CUM 180.00 39.60
Sundries.. L.S. 0.00
422.55
Add for contractor's profit @ 10 % 42.26
464.81
1168 SUPPLY & LAY 25MM THICK DEODAR WOOD PLANK CEILING. 2824.53 3106.98 /SQM
Details of cost for 30 /SQM
101 MISTRY 2 DAY 460.00 920.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 1.13 CUM. 71500.00 80795.00
330 SCREW 30/40MM 400 100NO. 95.00 380.00
Sundries.. L.S. 320.78
84735.78
Add for contractor's profit @ 10 % 8473.58
93209.36
1169 SAME AS ITEM 1168 BUT FOR C.P. TEAK WOOD. 3958.82 4354.70 /SQM
Details of cost for 30 /SQM
101 MISTRY 2 DAY 460.00 920.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
107 CARPENTER 2 DAY 460.00 920.00
301 TEAK WOOD(C.P.) 1.13 CUM. 101500.00 114695.00
330 SCREW 30/40MM 400 100NO. 95.00 380.00
Sundries.. L.S. 449.60
118764.60
Add for contractor's profit @ 10 % 11876.46
130641.06
1171 SUPPLY & FIX 6MM THICK A.C. PLANE SHEETS CEILING WITH 25MM X 40MM 249.48 274.43 /SQM
DEODAR WOOD BEADINGS.
Details of cost for 30 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 0.06 CUM. 71500.00 4290.00
330 SCREW 30/40MM 400 100NO. 95.00 380.00
356 A.C.SHEET 6MM THICK 30 SQM. 38.50 1155.00
Sundries.. L.S. 39.46
7484.46
Add for contractor's profit @ 10 % 748.45
8232.91
1172 SAME AS ITEM 1171 BUT WITH C.P. TEAK WOOD BEADING. 309.80 340.78 /SQM
Details of cost for 30 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
301 TEAK WOOD(C.P.) 0.06 CUM. 101500.00 6090.00
330 SCREW 30/40MM 400 100NO. 95.00 380.00
356 A.C.SHEET 6MM THICK 30 SQM. 38.50 1155.00
Sundries.. L.S. 49.00
9294.00
Add for contractor's profit @ 10 % 929.40
10223.40
1173 SAME AS ITEM 1171 BUT OF MASONITE OR CELOTAX WITH DEODAR 707.91 778.70 /SQM
BEADING.
Details of cost for 30 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
107 CARPENTER 2 DAY 460.00 920.00
304 DEODAR WOOD 0.06 CUM. 71500.00 4290.00
324 MASONITE OR CALOTAX 6MM THICK 30 SQM. 495.00 14850.00
330 SCREW 30/40MM 400 100NO. 95.00 380.00
Sundries.. L.S. 97.24
21237.24
Add for contractor's profit @ 10 % 2123.72
23360.96
1175 STRUCK POINTING WITH KANKAR LIME ON BRICK-WORK. 160.50 176.55 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1.75 DAY 425.00 743.75
104 COOLIE 1.75 DAY 350.00 612.50
106 BHISTI 0.35 DAY 350.00 122.50
255 KANKAR LIME 0.05 CUM 2100.00 105.00
Sundries.. L.S. 21.22
1604.97
Add for contractor's profit @ 10 % 160.50
1765.47
1176 SAME AS ITEM 1175 BUT FOR FLUSH POINTING. 130.20 143.22 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
104 COOLIE 1.25 DAY 350.00 437.50
106 BHISTI 0.35 DAY 350.00 122.50
255 KANKAR LIME 0.04 CUM 2100.00 84.00
Sundries.. L.S. 20.50
1302.00
Add for contractor's profit @ 10 % 130.20
1432.20
1177 RUBBING WITH KANKAR LIME OR WITH WHITE LIME & SURKHI ON BRICK- 68.33 75.16 /SQM
WORK.
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
104 COOLIE 0.5 DAY 350.00 175.00
106 BHISTI 0.25 DAY 350.00 87.50
255 KANKAR LIME 0.09 CUM 2100.00 189.00
Sundries.. L.S. 19.26
683.26
Add for contractor's profit @ 10 % 68.33
751.59
1178 SAME AS ITEM 1175 BUT WITH CEMENT & LOCAL SAND (1:2) MORTAR. 179.24 197.17 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1.75 DAY 425.00 743.75
104 COOLIE 1.75 DAY 350.00 612.50
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.04 CUM. 860.00 34.40
251 CEMENT 0.6 BAG 370.00 222.00
Sundries.. L.S. 57.26
1792.41
Add for contractor's profit @ 10 % 179.24
1971.65
1180 SAME AS ITEM 1178 & 1179 BUT IN FLOORS (DEDUCT FROM ITEMS 1178 & 31.20 34.32 /SQM
1179).
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.33 DAY 425.00 140.25
104 COOLIE 0.33 DAY 350.00 115.50
106 BHISTI 0.1 DAY 350.00 35.00
Sundries.. L.S. 21.22
311.97
Add for contractor's profit @ 10 % 31.20
343.17
1181 RAISED POINTING WITH CEMENT & LOCAL SAND MORTAR (1:2) ON BRICK 199.53 219.48 /SQM
WORK.
Details of cost for 10 /SQM
102 MASON/STONE MASON 1.75 DAY 425.00 743.75
104 COOLIE 1.75 DAY 350.00 612.50
106 BHISTI 0.6 DAY 350.00 210.00
250 LOCAL SAND 0.05 CUM. 860.00 43.00
251 CEMENT 1 BAG 370.00 370.00
Sundries.. L.S. 16.03
1995.28
Add for contractor's profit @ 10 % 199.53
2194.81
1182 STRUCK CEMENT POINTING IN CEMENT MORTAR (1:2) WITH COLOURING 191.53 210.68 /SQM
MATERIALS.
Details of cost for 10 /SQM
102 MASON/STONE MASON 1.75 DAY 425.00 743.75
104 COOLIE 1.75 DAY 350.00 612.50
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.04 CUM. 860.00 34.40
251 CEMENT 0.6 BAG 370.00 222.00
Sundries.. L.S. 180.11
1915.26
Add for contractor's profit @ 10 % 191.53
2106.79
1183 12MM THICK PLASTER WITH KANKAR LIME OVER BRICK-WORK. 108.29 119.12 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
255 KANKAR LIME 0.18 CUM 2100.00 378.00
Sundries.. L.S. 19.88
1082.88
Add for contractor's profit @ 10 % 108.29
1191.17
1185 SAME AS ITEM 1183 BUT WITH CEMENT & COARSE SAND (1:2) MORTAR. 190.15 209.16 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.475 DAY 350.00 166.25
249 COARSE SAND(BADARPUR) 0.15 CUM. 1395.00 209.25
251 CEMENT 2 BAG 370.00 740.00
Sundries.. L.S. 10.96
1901.46
Add for contractor's profit @ 10 % 190.15
2091.61
1186 SAME AS ITEM 1183 BUT WITH CEMENT & LOCAL SAND (1:3) MORTAR. 157.68 173.44 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.15 CUM. 860.00 129.00
251 CEMENT 1.45 BAG 370.00 536.50
Sundries.. L.S. 13.75
1576.75
Add for contractor's profit @ 10 % 157.68
1734.43
1187 SAME AS ITEM 1183 BUT WITH CEMENT & COARSE-SAND MORTAR (1:3). 165.46 182.01 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
249 COARSE SAND(BADARPUR) 0.15 CUM. 1395.00 209.25
251 CEMENT 1.45 BAG 370.00 536.50
Sundries.. L.S. 11.34
1654.59
Add for contractor's profit @ 10 % 165.46
1820.05
1188 SAME AS ITEM 1183 BUT WITH CEMENT & LOCAL SAND MORTAR (1:4). 149.29 164.22 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.16 CUM. 860.00 137.60
251 CEMENT 1.2 BAG 370.00 444.00
Sundries.. L.S. 13.76
1492.86
Add for contractor's profit @ 10 % 149.29
1642.15
1190 SAME AS ITEM 1183 BUT WITH CEMENT & LOCAL SAND MORTAR (1:6). 140.05 154.06 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.18 CUM. 860.00 154.80
251 CEMENT 0.9 BAG 370.00 333.00
Sundries.. L.S. 15.24
1400.54
Add for contractor's profit @ 10 % 140.05
1540.59
1191 EXTRA ON ALL ITEM OF PLASTER IF DONE ON CEILING. 19.13 21.04 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.25 DAY 425.00 106.25
1192 SAME AS ITEM 1183 BUT WITH CEMENT, WHITE LIME & LOCAL SAND (1:1:6). 142.16 156.38 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.35 DAY 350.00 122.50
250 LOCAL SAND 0.18 CUM. 860.00 154.80
251 CEMENT 0.9 BAG 370.00 333.00
253 WHITE LIME(SLAKED) 0.03 CUM 750.00 22.50
Sundries.. L.S. 13.80
1421.60
Add for contractor's profit @ 10 % 142.16
1563.76
1195 20MM THICK PLASTER ON WALLS, STEPS ETC. FINISHED WITH 5MM THICK 886.82 975.51 /SQM
CEMENT & MARBLE CHIPS (1:2).
Details of cost for 10 /SQM
102 MASON/STONE MASON 3 DAY 425.00 1275.00
104 COOLIE 3.25 DAY 350.00 1137.50
106 BHISTI 0.75 DAY 350.00 262.50
118 SPECIAL MAZDOOR/COOLIE(FOR 9 DAY 400.00 3600.00
RUBBING AND POLISHING)
249 COARSE SAND(BADARPUR) 0.15 CUM. 1395.00 209.25
251 CEMENT 2.9 BAG 370.00 1073.00
262 MARBLE CHIPS 0.06 CUM 3200.00 192.00
Sundries.. L.S. 1118.99
8868.24
Add for contractor's profit @ 10 % 886.82
9755.06
1196 SAME AS ITEM 1195 BUT FINISHED WITH 5MM THICK WHITE CEMENT & 801.73 881.90 /SQM
MARBLE CHIPS.
Details of cost for 10 /SQM
102 MASON/STONE MASON 3 DAY 425.00 1275.00
104 COOLIE 3.25 DAY 350.00 1137.50
106 BHISTI 0.75 DAY 350.00 262.50
118 SPECIAL MAZDOOR/COOLIE(FOR 9 DAY 400.00 3600.00
RUBBING AND POLISHING)
249 COARSE SAND(BADARPUR) 0.15 CUM. 1395.00 209.25
251 CEMENT 2.1 BAG 370.00 777.00
252 WHITE CEMENT 0.8 BAG 665.00 532.00
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
Sundries.. L.S. 0.00
8017.25
Add for contractor's profit @ 10 % 801.72
8818.97
1199 ROUGH CAST FINISH TO PLASTER OF DIFFERENT MORTARS (EXTRA TO 74.29 81.72 /SQM
PLASTER ITEMS).
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
104 COOLIE 0.5 DAY 350.00 175.00
106 BHISTI 0.125 DAY 350.00 43.75
251 CEMENT 0.8 BAG 370.00 296.00
Sundries.. L.S. 15.64
742.89
Add for contractor's profit @ 10 % 74.29
817.18
1200 PLASTER OVER ROUGH FACE OF ONE BRICK WALL (EXTRA TO PLASTER 24.72 27.19 /SQM
ITEMS).
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.125 DAY 425.00 53.13
104 COOLIE 0.125 DAY 350.00 43.75
Sundries.. L.S. 150.32
247.20
Add for contractor's profit @ 10 % 24.72
271.92
1202 25MM THICK 1:2:4 P.C.C. FLOOR WITH CEMENT, COARSE SAND AND 20MM 487.30 536.03 /SQM
GAUGE STONE BALLAST WITH BASE CONCRETE (75MM THICK) 1:4:8
CEMENT, LOCAL SAND & BRICK BALLAST 40MM GAUGE.
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 1.075 DAY 425.00 456.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.4 DAY 350.00 490.00
104 COOLIE 1.4 DAY 350.00 490.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
246 STONE BALLAST 20MM GAUGE 0.24 CUM. 750.00 180.00
249 COARSE SAND(BADARPUR) 0.12 CUM. 1395.00 167.40
250 LOCAL SAND 0.356 CUM. 860.00 306.16
251 CEMENT 4.36 BAG 370.00 1613.20
Sundries.. L.S. 24.24
4872.96
Add for contractor's profit @ 10 % 487.30
5360.26
1203 SAME AS ITEM 1202 BUT WITH BASE CONCRETE CONSISTING OF BRICK 382.62 420.88 /SQM
BALLAST, WHITE LIME & SURKHI 100:16:32.
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 1.075 DAY 425.00 456.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.4 DAY 350.00 490.00
104 COOLIE 1.4 DAY 350.00 490.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
246 STONE BALLAST 20MM GAUGE 0.24 CUM. 750.00 180.00
249 COARSE SAND(BADARPUR) 0.12 CUM. 1395.00 167.40
251 CEMENT 1.81 BAG 370.00 669.70
253 WHITE LIME(SLAKED) 0.113 CUM 750.00 84.75
256 SURKHI 0.225 CUM 550.00 123.75
Sundries.. L.S. 18.66
3826.22
Add for contractor's profit @ 10 % 382.62
4208.84
1205 SAME AS ITEM 1202 BUT WITH 50MM THICK 1:1.5:3 P.C.C. FLOOR. 677.74 745.52 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.153 DAY 460.00 70.38
102 MASON/STONE MASON 1.575 DAY 425.00 669.38
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.15 DAY 350.00 752.50
104 COOLIE 1.9 DAY 350.00 665.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.446 DAY 350.00 156.10
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
246 STONE BALLAST 20MM GAUGE 0.48 CUM. 750.00 360.00
249 COARSE SAND(BADARPUR) 0.24 CUM. 1395.00 334.80
250 LOCAL SAND 0.356 CUM. 860.00 306.16
251 CEMENT 6.8 BAG 370.00 2516.00
Sundries.. L.S. 4.06
6777.43
Add for contractor's profit @ 10 % 677.74
7455.17
1206 SAME AS ITEM 1202 BUT WITH 40MM THICK FLOOR & WITHOUT BASE 290.89 319.98 /SQM
CONCERETE.
Details of cost for 10 /SQM
101 MISTRY 0.125 DAY 460.00 57.50
102 MASON/STONE MASON 1.25 DAY 425.00 531.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 0.75 DAY 350.00 262.50
106 BHISTI 0.25 DAY 350.00 87.50
246 STONE BALLAST 20MM GAUGE 0.38 CUM. 750.00 285.00
249 COARSE SAND(BADARPUR) 0.19 CUM. 1395.00 265.05
251 CEMENT 2.75 BAG 370.00 1017.50
Sundries.. L.S. 52.56
2908.86
Add for contractor's profit @ 10 % 290.89
3199.75
1208 EXTRA ON ITEMS 1202, 1205 & 1206 WHEN COLOURED, POLISHED FLOORS 330.74 363.81 /SQM
ARE LAID.
Details of cost for 10 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
251 CEMENT 0.42 BAG 370.00 155.40
282 COLOUR 4 KG. 88.00 352.00
Sundries.. L.S. 0.00
3307.40
Add for contractor's profit @ 10 % 330.74
3638.14
1209 STONE FLOORS 40MM THICK OF MIRZAPUR OR OTHER APPROVED STONE 1625.28 1787.81 /SQM
FLAGS, SET IN WHITE LIME & SAND.
Details of cost for 10 /SQM
101 MISTRY 0.153 DAY 460.00 70.38
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.9 DAY 350.00 1715.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.238 DAY 350.00 83.30
123 MASON(JUNIOR) 2 DAY 400.00 800.00
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
250 LOCAL SAND 0.345 CUM. 860.00 296.70
253 WHITE LIME(SLAKED) 0.173 CUM 750.00 129.75
272 STONE SLAB STANDARD 40MM THICK 10.5 SQM 1012.00 10626.00
Sundries.. L.S. 391.77
16252.83
Add for contractor's profit @ 10 % 1625.28
17878.11
1210 SAME AS ITEM 1209 BUT STONE FLAGS LAID IN (1:4) CEMENT & LOCAL SAND 1716.60 1888.26 /SQM
MORTAR.
Details of cost for 10 /SQM
101 MISTRY 0.153 DAY 460.00 70.38
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.9 DAY 350.00 1715.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.238 DAY 350.00 83.30
123 MASON(JUNIOR) 2 DAY 400.00 800.00
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
250 LOCAL SAND 0.476 CUM. 860.00 409.36
251 CEMENT 3.55 BAG 370.00 1313.50
272 STONE SLAB STANDARD 40MM THICK 10.5 SQM 1012.00 10626.00
Sundries.. L.S. 8.58
17166.05
Add for contractor's profit @ 10 % 1716.60
18882.65
1212 SAME AS ITEMS 1209, 1210, 1211 BUT UPPER SURFACE & EDGES CHIESEL 1333.22 1466.54 /SQM
DRESSED & JOINT UPTO 6MM THICK IN WHITE LIME & SAND.
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.9 DAY 350.00 1715.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.238 DAY 350.00 83.30
123 MASON(JUNIOR) 2 DAY 400.00 800.00
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
250 LOCAL SAND 0.465 CUM. 860.00 399.90
253 WHITE LIME(SLAKED) 0.233 CUM 750.00 174.75
273 STONE SLAB NON STANDARD 40MM 10.5 SQM 726.00 7623.00
THICK
Sundries.. L.S. 321.37
13332.23
Add for contractor's profit @ 10 % 1333.22
14665.45
1213 SAME AS ITEM 1212 BUT IN CEMENT & SAND. 1463.96 1610.35 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.9 DAY 350.00 1715.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.238 DAY 350.00 83.30
123 MASON(JUNIOR) 2 DAY 400.00 800.00
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
250 LOCAL SAND 0.596 CUM. 860.00 512.56
251 CEMENT 4.55 BAG 370.00 1683.50
273 STONE SLAB NON STANDARD 40MM 10.5 SQM 726.00 7623.00
THICK
Sundries.. L.S. 7.32
14639.59
Add for contractor's profit @ 10 % 1463.96
16103.55
1215 1ST CLASS BRICK FLOOR LAID IN CEMENT & LOCAL SAND MORTAR (1:6) & 918.15 1009.96 /SQM
POINTED WITH (1:2) CEMENT MORTAR OVER 75MM THICK BASE CONCRETE
WITH KANKAR LIME.
Details of cost for 10 /SQM
101 MISTRY 0.138 DAY 460.00 63.48
102 MASON/STONE MASON 2.495 DAY 425.00 1060.38
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.9 DAY 350.00 665.00
104 COOLIE 2.82 DAY 350.00 987.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.588 DAY 350.00 205.80
235 BRICKS IST CLASS 500 1000NO. 7350.00 3675.00
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
250 LOCAL SAND 0.565 CUM. 860.00 485.90
251 CEMENT 1.75 BAG 370.00 647.50
255 KANKAR LIME 0.113 CUM 2100.00 237.30
256 SURKHI 0.225 CUM 550.00 123.75
Sundries.. L.S. 87.30
9181.46
Add for contractor's profit @ 10 % 918.15
10099.61
1216 SAME AS ITEM 1215 BUT WITH 75MM BASE CONCRETE WITH (1:2) WHITE 899.27 989.19 /SQM
LIME & SURKHI.
Details of cost for 10 /SQM
101 MISTRY 0.138 DAY 460.00 63.48
102 MASON/STONE MASON 2.495 DAY 425.00 1060.38
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.9 DAY 350.00 665.00
104 COOLIE 2.82 DAY 350.00 987.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.588 DAY 350.00 205.80
235 BRICKS IST CLASS 500 1000NO. 7350.00 3675.00
244 BRICK BALLAST 40MM GAUGE 0.718 CUM. 1300.00 933.40
250 LOCAL SAND 0.34 CUM. 860.00 292.40
251 CEMENT 1.75 BAG 370.00 647.50
255 KANKAR LIME 0.113 CUM 2100.00 237.30
256 SURKHI 0.225 CUM 550.00 123.75
Sundries.. L.S. 85.51
8992.67
Add for contractor's profit @ 10 % 899.27
9891.94
1218 1ST CLASS BRICKS FLOOR LAID DRY, JOINTS SAND FILLED. 508.38 559.22 /SQM
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
104 COOLIE 0.5 DAY 350.00 175.00
235 BRICKS IST CLASS 500 1000NO. 7350.00 3675.00
250 LOCAL SAND 0.33 CUM. 860.00 283.80
Sundries.. L.S. 0.00
5083.80
Add for contractor's profit @ 10 % 508.38
5592.18
1219 GRANOLYTHIC MARBLE FLOORING 25MM THICK WITH 20MM THICK LAYER OF 1052.36 1157.59 /SQM
CEMENT & COARSE SAND & 12 MM GAUGE STONE CHIPS WITH SURFACE
COAT OF ORDINARY CEMENT INCLUDING 75MM THICK BASE CONCRETE
WITH WHITE LIME & SAND.
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.9 DAY 350.00 6265.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
246 STONE BALLAST 20MM GAUGE 0.09 CUM. 750.00 67.50
247 STONE GRIT 10-12MM 0.18 CUM. 1090.00 196.20
250 LOCAL SAND 0.225 CUM. 860.00 193.50
251 CEMENT 2.4 BAG 370.00 888.00
253 WHITE LIME(SLAKED) 0.113 CUM 750.00 84.75
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
Sundries.. L.S. 262.68
10523.59
Add for contractor's profit @ 10 % 1052.36
11575.95
1221 SAME AS ITEM 1219 BUT WITH COLOURED FLOOR. 1089.99 1198.99 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.153 DAY 460.00 70.38
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.9 DAY 350.00 6265.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
247 STONE GRIT 10-12MM 0.18 CUM. 1090.00 196.20
249 COARSE SAND(BADARPUR) 0.09 CUM. 1395.00 125.55
250 LOCAL SAND 0.225 CUM. 860.00 193.50
251 CEMENT 2.4 BAG 370.00 888.00
253 WHITE LIME(SLAKED) 0.113 CUM 750.00 84.75
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
282 COLOUR 4 KG. 88.00 352.00
Sundries.. L.S. 233.59
10899.95
Add for contractor's profit @ 10 % 1089.99
11989.94
1223 SAME AS ITEM 1220 BUT BASE CONCRETE IN (1:4:8) CEMENT, LOCAL SAND 1184.72 1303.19 /SQM
AND BRICK BALLAST.
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.9 DAY 350.00 6265.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
247 STONE GRIT 10-12MM 0.18 CUM. 1090.00 196.20
249 COARSE SAND(BADARPUR) 0.09 CUM. 1395.00 125.55
250 LOCAL SAND 0.356 CUM. 860.00 306.16
251 CEMENT 3.95 BAG 370.00 1461.50
252 WHITE CEMENT 1 BAG 665.00 665.00
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
Sundries.. L.S. 261.83
11847.20
Add for contractor's profit @ 10 % 1184.72
13031.92
1225 SAME AS ITEM 1219 BUT BASE CONCRETE IN WHITE LIME & SURKHI (1:2) 1050.85 1155.94 /SQM
(EXTRA ON ITEM 1219).
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.9 DAY 350.00 6265.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
247 STONE GRIT 10-12MM 0.18 CUM. 1090.00 196.20
249 COARSE SAND(BADARPUR) 0.09 CUM. 1395.00 125.55
251 CEMENT 2.4 BAG 370.00 888.00
253 WHITE LIME(SLAKED) 0.113 CUM 750.00 84.75
256 SURKHI 0.225 CUM 550.00 123.75
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
Sundries.. L.S. 259.30
10508.51
Add for contractor's profit @ 10 % 1050.85
11559.36
1227 SAME AS ITEM 1221 BUT BASE CONCRETE IN WHITE LIME & SURKHI (1:2) 1077.56 1185.31 /SQM
(EXTRA ON ITEM 1221).
Details of cost for 10 /SQM
101 MISTRY 0.163 DAY 460.00 74.98
102 MASON/STONE MASON 2.075 DAY 425.00 881.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.9 DAY 350.00 6265.00
104 COOLIE 0.9 DAY 350.00 315.00
105 BLACK SMITH 0.038 DAY 425.00 16.15
106 BHISTI 0.363 DAY 350.00 127.05
244 BRICK BALLAST 40MM GAUGE 0.713 CUM. 1300.00 926.90
247 STONE GRIT 10-12MM 0.13 CUM. 1090.00 141.70
249 COARSE SAND(BADARPUR) 0.09 CUM. 1395.00 125.55
251 CEMENT 2.4 BAG 370.00 888.00
253 WHITE LIME(SLAKED) 0.113 CUM 750.00 84.75
256 SURKHI 0.225 CUM 550.00 123.75
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
282 COLOUR 4 KG. 88.00 352.00
Sundries.. L.S. 228.86
10775.57
Add for contractor's profit @ 10 % 1077.56
11853.13
1228 GRANOLYTHIC MARBLE DADO 20MM THICK WITH 14MM THICK LAYER OF 943.96 1038.35 /SQM
CEMENT & COARSE SAND (1:2) WITH 6MM THICK SURFACE COAT OF
ORDINARY CEMENT.
Details of cost for 10 /SQM
101 MISTRY 0.1 DAY 460.00 46.00
102 MASON/STONE MASON 2.75 DAY 425.00 1168.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16.75 DAY 350.00 5862.50
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.6 DAY 350.00 210.00
249 COARSE SAND(BADARPUR) 0.18 CUM. 1395.00 251.10
251 CEMENT 3.22 BAG 370.00 1191.40
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
Sundries.. L.S. 135.83
9439.58
Add for contractor's profit @ 10 % 943.96
10383.54
1230 SAME AS ITEM 1228 BUT WITH COLOURED DADO. 981.98 1080.18 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.1 DAY 460.00 46.00
102 MASON/STONE MASON 2.75 DAY 425.00 1168.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16.75 DAY 350.00 5862.50
104 COOLIE 1 DAY 350.00 350.00
106 BHISTI 0.725 DAY 350.00 253.75
249 COARSE SAND(BADARPUR) 0.18 CUM. 1395.00 251.10
251 CEMENT 3.22 BAG 370.00 1191.40
262 MARBLE CHIPS 0.07 CUM 3200.00 224.00
282 COLOUR 4 KG. 88.00 352.00
Sundries.. L.S. 120.27
9819.77
Add for contractor's profit @ 10 % 981.98
10801.75
1231 SUPPLY AND FIXING OF 15X15CM CHINA WHITE GLAZED TILES 6MM THICK IN 1663.81 1830.19 /SQM
FLOORING OR IN SKIRTING OR DADO LAID WITH (1:3) CEMENT & COARSE
SAND.
Details of cost for 10 /SQM
121 TILE LAYER 4 DAY 350.00 1400.00
124 WOMAN COOLIE 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.32 CUM. 1395.00 446.40
251 CEMENT 3.2 BAG 370.00 1184.00
263 WHITE MARBLE BAGS 1 BAG 665.00 665.00
271 TILES 15*15CM GLAZED 450 NO. 27.00 12150.00
Sundries.. L.S. 92.65
16638.05
Add for contractor's profit @ 10 % 1663.80
18301.85
1232 PAINTING OR VARNISHING ON NEW IRON WORK IN SMALL AREAS OR NEW 91.29 100.42 /SQM
WOOD WORK WITH ONE COAT PRIMING & ONE COAT PAINT OR VARNISH.
Details of cost for 100 /SQM
104 COOLIE 7 DAY 350.00 2450.00
109 PAINTER 7 DAY 460.00 3220.00
283 PRIMER 6 LTR. 182.00 1092.00
284 VARNISH 10 LTR. 225.00 2250.00
Sundries.. L.S. 117.16
9129.16
Add for contractor's profit @ 10 % 912.92
10042.08
1234 SAME AS ITEM 1233 BUT FOR EVERY COAT ON PREVIOUSLY PAINTED 62.81 69.09 /SQM
SURFACE.
Details of cost for 100 /SQM
104 COOLIE 4 DAY 350.00 1400.00
109 PAINTER 4 DAY 460.00 1840.00
285 PAINT(ENAMEL) 10 LTR. 295.00 2950.00
Sundries.. L.S. 90.99
6280.99
Add for contractor's profit @ 10 % 628.10
6909.09
1235 PAINTING ROOF OR OTHER IRON WORK IN LARGE AREA WITH ONE COAT 98.18 108.00 /SQM
PRIMING & ONE COAT PAINT OR VARNISH.
Details of cost for 100 /SQM
104 COOLIE 7 DAY 350.00 2450.00
109 PAINTER 7 DAY 460.00 3220.00
283 PRIMER 6 LTR. 182.00 1092.00
285 PAINT(ENAMEL) 10 LTR. 295.00 2950.00
Sundries.. L.S. 105.86
9817.86
Add for contractor's profit @ 10 % 981.79
10799.65
1236 SAME AS ITEM 1235 BUT FOR EVERY COAT AFTER FIRST COAT. 58.75 64.62 /SQM
Details of cost for 100 /SQM
104 COOLIE 3.5 DAY 350.00 1225.00
109 PAINTER 3.5 DAY 460.00 1610.00
285 PAINT(ENAMEL) 10 LTR. 295.00 2950.00
Sundries.. L.S. 89.67
5874.67
Add for contractor's profit @ 10 % 587.47
6462.14
1237 SAME AS ITEM 1236 BUT FOR EVERY COAT OVER PREVIOUSLY PAINTED 58.75 64.62 /SQM
SURFACE.
Details of cost for 100 /SQM
104 COOLIE 3.5 DAY 350.00 1225.00
109 PAINTER 3.5 DAY 460.00 1610.00
285 PAINT(ENAMEL) 10 LTR. 295.00 2950.00
Sundries.. L.S. 89.67
5874.67
Add for contractor's profit @ 10 % 587.47
6462.14
1239 SAME AS ITEM 1238 BUT FOR EVERY SUBSEQUENT COAT ON PREVIOUSLY 61.88 68.07 /SQM
TREATED SURFACE WITH ENAMEL OR VARNISH.
Details of cost for 100 /SQM
104 COOLIE 5 DAY 350.00 1750.00
109 PAINTER 5 DAY 460.00 2300.00
292 ENAMEL(SYNTHETIC) 9 LTR. 225.00 2025.00
Sundries.. L.S. 112.99
6187.99
Add for contractor's profit @ 10 % 618.80
6806.79
1240 ONE PRIMING & ONE OIL DISTEMPER COAT ON NEW WORK. 62.54 68.79 /SQM
Details of cost for 100 /SQM
104 COOLIE 6 DAY 350.00 2100.00
109 PAINTER 6 DAY 460.00 2760.00
286 WHITING 10 KG. 8.00 80.00
287 DISTEMPER OIL 15 LTR. 80.00 1200.00
Sundries.. L.S. 113.59
6253.59
Add for contractor's profit @ 10 % 625.36
6878.95
1241 SAME AS ITEM 1240 BUT FOR EVERY COAT AFTER 1ST COAT. 35.96 39.55 /SQM
Details of cost for 100 /SQM
104 COOLIE 3.5 DAY 350.00 1225.00
109 PAINTER 3.5 DAY 460.00 1610.00
287 DISTEMPER OIL 9 LTR. 80.00 720.00
Sundries.. L.S. 40.88
3595.88
Add for contractor's profit @ 10 % 359.59
3955.47
1242 SAME AS ITEM 1241 BUT FOR EVERY COAT ON PREVIOUSLY DISTEMPERED 39.84 43.83 /SQM
SURFACE.
Details of cost for 100 /SQM
104 COOLIE 4 DAY 350.00 1400.00
109 PAINTER 4 DAY 460.00 1840.00
287 DISTEMPER OIL 9 LTR. 80.00 720.00
Sundries.. L.S. 24.16
3984.16
Add for contractor's profit @ 10 % 398.42
4382.58
1244 SAME AS ITEM 1243 BUT FOR EVERY COAT AFTER 1ST COAT. 14.25 15.68 /SQM
Details of cost for 100 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
288 COAL TAR 5 LTR. 35.00 175.00
Sundries.. L.S. 25.48
1425.48
Add for contractor's profit @ 10 % 142.55
1568.03
1245 ONE COAT SOLIGNUM OR OTHER PRESERVATIVE ON NEW WOOD WORK. 31.73 34.90 /SQM
Details of cost for 100 /SQM
104 COOLIE 3 DAY 350.00 1050.00
109 PAINTER 3 DAY 460.00 1380.00
289 SOLIGNUM 5 LTR. 125.00 625.00
Sundries.. L.S. 117.62
3172.62
Add for contractor's profit @ 10 % 317.26
3489.88
1246 SAME AS ITEM 1245 BUT FOR EVERY COAT AFTER FIRST COAT ON 20.54 22.59 /SQM
PREVIOUSLY TREATED SURFACE.
Details of cost for 100 /SQM
104 COOLIE 2 DAY 350.00 700.00
109 PAINTER 2 DAY 460.00 920.00
289 SOLIGNUM 3 LTR. 125.00 375.00
Sundries.. L.S. 58.65
2053.65
Add for contractor's profit @ 10 % 205.36
2259.01
1247 OILING WOOD WORK WITH DOUBLE BOILED LINSED OIL. 12.66 13.92 /SQM
Details of cost for 100 /SQM
104 COOLIE 1 DAY 350.00 350.00
109 PAINTER 1 DAY 460.00 460.00
281 LINSEED OIL 3.5 LTR. 115.00 402.50
Sundries.. L.S. 53.35
1265.85
Add for contractor's profit @ 10 % 126.58
1392.43
1248 REMOVING PAINT OR VARNISHING WITH PAINT REMOVER OR CAUSTIC SODA. 28.27 31.10 /SQM
Details of cost for 100 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
104 COOLIE 3.5 DAY 350.00 1225.00
290 CAUSTIC SODA 5 KG. 63.00 315.00
Sundries.. L.S. 62.49
2827.49
Add for contractor's profit @ 10 % 282.75
3110.24
1250 SAME AS ITEM 1249 BUT REPOLISHING WOOD WORK ALREADY WAX 22.70 24.97 /SQM
POLISHED WITH READY MADE WAX POLISH.
Details of cost for 100 /SQM
104 COOLIE 2 DAY 350.00 700.00
109 PAINTER 2 DAY 460.00 920.00
291 WAX POLISH 2.5 KG. 245.00 612.50
Sundries.. L.S. 37.73
2270.23
Add for contractor's profit @ 10 % 227.02
2497.25
1252 SAME AS ITEM 1251 BUT TWO COATS. 10.85 11.93 /SQM
Details of cost for 100 /SQM
104 COOLIE 1 DAY 350.00 350.00
110 WHITE WASHER 1 DAY 300.00 300.00
254 WHITE LIME(UNSLAKED) 0.2 QTL 650.00 130.00
Sundries.. L.S. 304.67
1084.67
Add for contractor's profit @ 10 % 108.47
1193.14
1253 SAME AS ITEM 1251 BUT THREE COATS. 16.95 18.65 /SQM
Details of cost for 100 /SQM
104 COOLIE 1.67 DAY 350.00 584.50
110 WHITE WASHER 1.67 DAY 300.00 501.00
254 WHITE LIME(UNSLAKED) 0.3 QTL 650.00 195.00
Sundries.. L.S. 414.63
1695.13
Add for contractor's profit @ 10 % 169.51
1864.64
1255 SAME AS ITEM 1254 BUT TWO COATS. 13.05 14.35 /SQM
Details of cost for 100 /SQM
104 COOLIE 1 DAY 350.00 350.00
110 WHITE WASHER 1 DAY 300.00 300.00
254 WHITE LIME(UNSLAKED) 0.2 QTL 650.00 130.00
293 COLOURING MATERIAL 5 KG. 55.00 275.00
Sundries.. L.S. 249.61
1304.61
Add for contractor's profit @ 10 % 130.46
1435.07
1256 SAME AS ITEM 1254 BUT USING COLOURING MATERIALS OF PINK, GREEN OR 8.74 9.61 /SQM
YELLOW SHADE.
Details of cost for 100 /SQM
104 COOLIE 0.67 DAY 350.00 234.50
110 WHITE WASHER 0.67 DAY 300.00 201.00
254 WHITE LIME(UNSLAKED) 0.1 QTL 650.00 65.00
293 COLOURING MATERIAL 2.5 KG. 55.00 137.50
Sundries.. L.S. 235.74
873.74
Add for contractor's profit @ 10 % 87.37
961.11
1257 SAME AS ITEM 1256 BUT TWO COATS. 14.71 16.18 /SQM
Details of cost for 100 /SQM
104 COOLIE 1 DAY 350.00 350.00
110 WHITE WASHER 1 DAY 300.00 300.00
254 WHITE LIME(UNSLAKED) 0.2 QTL 650.00 130.00
293 COLOURING MATERIAL 5 KG. 55.00 275.00
Sundries.. L.S. 415.99
1470.99
Add for contractor's profit @ 10 % 147.10
1618.09
1258 COLOUR WASHING ONE COAT USING COPPER OR IRON SULPHATE. 9.05 9.95 /SQM
Details of cost for 100 /SQM
104 COOLIE 0.67 DAY 350.00 234.50
110 WHITE WASHER 0.67 DAY 300.00 201.00
254 WHITE LIME(UNSLAKED) 0.1 QTL 650.00 65.00
293 COLOURING MATERIAL 2.5 KG. 55.00 137.50
Sundries.. L.S. 266.94
904.94
Add for contractor's profit @ 10 % 90.49
995.43
1261 ONE PRIMING COAT & ONE COAT OF DRY DISTEMPER ON NEW WORK. 39.61 43.57 /SQM
Details of cost for 100 /SQM
104 COOLIE 3.5 DAY 350.00 1225.00
109 PAINTER 3.5 DAY 460.00 1610.00
286 WHITING 10 KG. 8.00 80.00
294 DRY DISTEMPER 7.5 KG. 105.00 787.50
Sundries.. L.S. 258.43
3960.93
Add for contractor's profit @ 10 % 396.09
4357.02
1262 SAME AS ITEM 1261 BUT FOR EACH COAT OF DISTEMPER AFTER FIRST 22.93 25.23 /SQM
COAT.
Details of cost for 100 /SQM
104 COOLIE 2 DAY 350.00 700.00
109 PAINTER 2 DAY 460.00 920.00
294 DRY DISTEMPER 6 KG. 105.00 630.00
Sundries.. L.S. 43.20
2293.20
Add for contractor's profit @ 10 % 229.32
2522.52
1265 SAME AS ITEM 1264 BUT IN MUD MORTAR. 280.00 308.00 /CUM
Details of cost for 10 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
104 COOLIE 3 DAY 350.00 1050.00
Sundries.. L.S. 0.00
2800.00
Add for contractor's profit @ 10 % 280.00
3080.00
1267 DISMANTLING JACK ARCHED OR WOODEN BEAM & BARJA ROOFS 490.00 539.00 /CUM
INCLUDING BEAMS & ROOF CONCRETE.
Details of cost for 10 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
104 COOLIE 7 DAY 350.00 2450.00
Sundries.. L.S. 0.00
4900.00
Add for contractor's profit @ 10 % 490.00
5390.00
1268 SAME AS ITEM 1269 BUT ONLY ROOF CONCRETE. 350.00 385.00 /CUM
Details of cost for 10 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
104 COOLIE 5 DAY 350.00 1750.00
Sundries.. L.S. 0.00
3500.00
Add for contractor's profit @ 10 % 350.00
3850.00
1269 DISMANTLING CEMENT CONCRETE OR BRICKS OR GRANOLYTHIC FLOORS 70.00 77.00 /SQM
INCLUDING BASE CONCRETE.
Details of cost for 10 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 1 DAY 350.00 350.00
Sundries.. L.S. 0.00
700.00
Add for contractor's profit @ 10 % 70.00
770.00
1271 DISMANTLING SINGLE TILED ROOF INCLUDING PURLINES & BATTENS. 74.60 82.06 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.1 DAY 460.00 46.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 1 DAY 350.00 350.00
Sundries.. L.S. 0.00
746.00
Add for contractor's profit @ 10 % 74.60
820.60
1272 SAME AS ITEM 1271 BUT DOUBLE TILED ROOF. 127.10 139.81 /SQM
Details of cost for 10 /SQM
101 MISTRY 0.1 DAY 460.00 46.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
104 COOLIE 1.5 DAY 350.00 525.00
Sundries.. L.S. 0.00
1271.00
Add for contractor's profit @ 10 % 127.10
1398.10
1273 DISMANTLING CORRUGATED IRON ROOFS, WALLS OR PARTITIONS 58.13 63.94 /SQM
INCLUDING PURLINS, BATTENS & VERTICAL SUPPORTS.
Details of cost for 10 /SQM
104 COOLIE 0.75 DAY 350.00 262.50
105 BLACK SMITH 0.75 DAY 425.00 318.75
Sundries.. L.S. 0.00
581.25
Add for contractor's profit @ 10 % 58.12
639.37
1274 DISMANTLING OF GIRDERS, TRUSSES & OTHER STEEL WORK. 1749.94 1924.93 /QTL
Details of cost for 1 /QTL
104 COOLIE 3 DAY 350.00 1050.00
105 BLACK SMITH 1.5 DAY 425.00 637.50
Sundries.. L.S. 62.44
1749.94
Add for contractor's profit @ 10 % 174.99
1924.93
1275 DISMANTLING DOORS & WINDOWS INCLUDING CHAUKHATS WITH 62.25 68.48 /SQM
HOLDFASTS.
Details of cost for 10 /SQM
102 MASON/STONE MASON 0.1 DAY 425.00 42.50
104 COOLIE 1 DAY 350.00 350.00
107 CARPENTER 0.5 DAY 460.00 230.00
Sundries.. L.S. 0.00
622.50
Add for contractor's profit @ 10 % 62.25
684.75
1277 DISMANTLING DOORS & WINDOWS INCLUDING CHAUKHATS BUT EXCLUDING 54.69 60.16 /SQM
HOLDFASTS.
Details of cost for 10 /SQM
104 COOLIE 1 DAY 350.00 350.00
107 CARPENTER 0.33 DAY 460.00 151.80
Sundries.. L.S. 45.11
546.91
Add for contractor's profit @ 10 % 54.69
601.60
1279 RACKING OUT JOINTS OF BRICK WORK IN CEMENT & LIME MORTAR TO A 35.00 38.50 /SQM
DEPTH OF 10MM.
Details of cost for 10 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
1281 SUPPLY & FIX BLOCK OF C.P. TEAK WOOD 75X75X120MM IN WALL WITH (1:3) 72.73 80.00 /NO.
(CEMENT & COARSE SAND MORTAR.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.04 DAY 425.00 17.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.04 DAY 350.00 14.00
311 TEAK WOOD BLOCK 75*75*120MM 1 NO. 30.00 30.00
Sundries.. L.S. 11.73
72.73
Add for contractor's profit @ 10 % 7.27
80.00
1283 SAME AS ITEM 1282 BUT WITH OXIDISED IRON CLEATS. 119.37 131.31 /NO.
Details of cost for 1 /NO.
107 CARPENTER 0.042 DAY 460.00 19.32
312 TEAK WOOD PLATE 100*100*10MM 1 NO. 20.00 20.00
329 IRON CLEAT 1 NO. 75.00 75.00
331 IRON SCREW 65*25MM. 1 100NO. 105.00 1.05
345 BRASS SCREW 2 100NO. 35.00 0.70
Sundries.. L.S. 3.30
119.37
Add for contractor's profit @ 10 % 11.94
131.31
1284 SUPPLY & FIX COTTON CORD FOR CLERESTORY WINDOW. 129.94 142.93 /KG
Details of cost for 1 /KG
296 COTTON CORD 1 KG. 115.50 115.50
1285 SUPPLY & FIX C.P. TEAK WOOD CLEATS 100X75X50 MM TO C.P. TEAK DOORS 218.18 240.00 /NO.
& WINDOWS WITH BRASS HINGS 50MM.
Details of cost for 1 /NO.
107 CARPENTER 0.033 DAY 460.00 15.18
310 C.P. TEAK WOOD CLEAT 1 NO. 18.00 18.00
346 BRASS HINGES 50MM. 1 NO. 185.00 185.00
Sundries.. L.S. 0.00
218.18
Add for contractor's profit @ 10 % 21.82
240.00
1287 SUPPLY & FIX C.P. TEAK WOOD PAG RACK 900X75X25MM WITH THREE 670.93 738.02 /NO.
BRASS PEGS ON 75X75X120MM TEAK WOOD BLOCK.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.83 DAY 350.00 290.50
107 CARPENTER 0.083 DAY 460.00 38.18
311 TEAK WOOD BLOCK 75*75*120MM 1 NO. 30.00 30.00
313 C.P. TEAK WOOD PEG RACK 1 NO. 22.00 22.00
345 BRASS SCREW 6 100NO. 35.00 2.10
347 BRASS HAT PEG 3 NO. 75.00 225.00
Sundries.. L.S. 63.15
670.93
Add for contractor's profit @ 10 % 67.09
738.02
1288 SUPPLY & FIX 40MM THICK C.P. TEAK WOOD PANNELLED PARTITION WITH 6662.76 7329.03 /SQM
TEAK WOOD FRAMES 100X80MM TOP, BOTTOM & SIDE VERTICALS AT 1.5M
APART.
Details of cost for 3 /SQM
101 MISTRY 0.225 DAY 460.00 103.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.1 DAY 350.00 735.00
107 CARPENTER 6.15 DAY 460.00 2829.00
301 TEAK WOOD(C.P.) 0.15 CUM. 101500.00 15225.00
Sundries.. L.S. 1095.77
19988.27
Add for contractor's profit @ 10 % 1998.83
21987.10
1289 SUPPLY & FIX PLAIN ASBESTOS SHEET PARTITION WITH 50X10MM DEODAR 1915.33 2106.86 /SQM
OR SHEESHAM WOOD BEADING, ERECTION & FIXING.
Details of cost for 8 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
107 CARPENTER 1.25 DAY 460.00 575.00
304 DEODAR WOOD 0.173 CUM. 71500.00 12369.50
356 A.C.SHEET 6MM THICK 8.4 SQM. 38.50 323.40
Sundries.. L.S. 1104.73
15322.63
Add for contractor's profit @ 10 % 1532.26
16854.89
1291 CONSOLIDATION OF 30 TO 40MM GUAGE KANKAR BY HAND RAMMER, 484.36 532.80 /CUM
SORTING KANKAR INTO THREE SIZES REPAIRING PATCHES IN EXISTING
ROAD SURFACE WITH KANKAR, PICKING UP OLD SURFACE, SPREADING
KANKAR, MAKING MEDIS TO RETAIN WATER & RAMMING WITH CARRIAGE OF
MATEL
& WATER AND MAINTENANCE OF BARRIERS, CAUTION POSTS, LIGHTS ETC.
(EXCLUDING SUPPLY OF KANKAR).
Details of cost for 30 /CUM
101 MISTRY 10 DAY 460.00 4600.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 23.5 DAY 350.00 8225.00
106 BHISTI 4 DAY 350.00 1400.00
Sundries.. L.S. 305.84
14530.84
Add for contractor's profit @ 10 % 1453.08
15983.92
1292 SAME AS ITEM 1291 BUT FOR CONSOLIDATION BY ROAD ROLLER. 665.89 732.48 /CUM
Details of cost for 30 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 25.5 DAY 350.00 8925.00
106 BHISTI 4 DAY 350.00 1400.00
357 STEAM COAL 2.5 QTL. 440.00 1100.00
363 HIRING OF ROAD ROLLER 1 DAY 8000.00 8000.00
Sundries.. L.S. 551.67
19976.67
Add for contractor's profit @ 10 % 1997.67
21974.34
1293 SAME AS ITEM 1291 BUT FOR 120MM THICK COAT OF BRICK BALLAST. 484.36 532.80 /CUM
Details of cost for 30 /CUM
101 MISTRY 10 DAY 460.00 4600.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 23.5 DAY 350.00 8225.00
106 BHISTI 4 DAY 350.00 1400.00
Sundries.. L.S. 305.84
14530.84
Add for contractor's profit @ 10 % 1453.08
15983.92
1294 SAME AS ITEM 1292 BUT FOR 80MM THICK COAT OF BRICK BALLAST. 665.89 732.48 /CUM
Details of cost for 30 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 25.5 DAY 350.00 8925.00
106 BHISTI 4 DAY 350.00 1400.00
357 STEAM COAL 2.5 QTL. 440.00 1100.00
363 HIRING OF ROAD ROLLER 1 DAY 8000.00 8000.00
Sundries.. L.S. 551.67
19976.67
Add for contractor's profit @ 10 % 1997.67
21974.34
1296 SAME AS ITEM 1292 BUT 80MM THICK STONE BALLAST OVER EXISTING 911.07 1002.18 /CUM
KANKAR ROAD SURFACE.
Details of cost for 20 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
106 BHISTI 6 DAY 350.00 2100.00
357 STEAM COAL 1.7 QTL. 440.00 748.00
363 HIRING OF ROAD ROLLER 1 DAY 8000.00 8000.00
Sundries.. L.S. 1073.46
18221.46
Add for contractor's profit @ 10 % 1822.15
20043.61
1298 DIGGING KANKAR INCLUDING BREAKING, CLEANING & ROLLING AND THE 1140.72 1254.79 /CUM
COST OF BORING TO FIND KANKAR STRATA.
Details of cost for 3 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
104 COOLIE 4 DAY 350.00 1400.00
Sundries.. L.S. 622.16
3422.16
Add for contractor's profit @ 10 % 342.22
3764.38
1299 MAKING MUD TREE GUARDS IM (I.D) & 1M HIGH ABOVE G.L. 657.63 723.39 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.75 DAY 425.00 318.75
104 COOLIE 0.75 DAY 350.00 262.50
Sundries.. L.S. 76.38
657.63
Add for contractor's profit @ 10 % 65.76
723.39
1300 DUG BELLING 150MM DEEP IN ONE LINE ALIGNED WITH FLAGS & JHANDIES. 2285.00 2513.50 /KM
Details of cost for 1 /KM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
119 MATE 0.5 DAY 370.00 185.00
Sundries.. L.S. 0.00
2285.00
Add for contractor's profit @ 10 % 228.50
2513.50
1302 BRICK SOLING WITH STRAIGHT OVER BURNT BRICKS & DRY WITH BRICK 293.26 322.59 /SQM
EDGING LAID VERTICAL ON EITHER SIDE, FILLING THE JOINTS WITH LOCAL
EARTH.
Details of cost for 10 /SQM
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
240 BRICKS OVER BURNT 500 1000NOS 4000.00 2000.00
Sundries.. L.S. 70.13
2932.63
Add for contractor's profit @ 10 % 293.26
3225.89
1303 RENEWING PARTIES 3M WIDE, DRESSING SURFACE, FILLING UP TO 8 CM 51.05 56.16 /RM
DEPTH & MAKING PROFILES OF EVERY 15M APART.
Details of cost for 200 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
104 COOLIE 14 DAY 350.00 4900.00
119 MATE 1 DAY 370.00 370.00
317 BASKETS 4 NO. 100.00 400.00
Sundries.. L.S. 340.52
10210.52
Add for contractor's profit @ 10 % 1021.05
11231.57
1304 BRICK EDGING OF 1ST CLASS BRICKS LAID VERTICAL WITH MUD MORTAR. 188.39 207.23 /RM
Details of cost for 100 /RM
102 MASON/STONE MASON 2.5 DAY 425.00 1062.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
104 COOLIE 6 DAY 350.00 2100.00
235 BRICKS IST CLASS 2000 1000NO. 7350.00 14700.00
Sundries.. L.S. 101.18
18838.68
Add for contractor's profit @ 10 % 1883.87
20722.55
1305 STACKING OF ROAD METAL TO THE REQUIRED TEMPLATE AFTER 126.32 138.95 /CUM
SCREENING AT ROAD SIDE.
Details of cost for 10 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
104 COOLIE 1.5 DAY 350.00 525.00
Sundries.. L.S. 38.22
1263.22
Add for contractor's profit @ 10 % 126.32
1389.54
1307 SAME AS ITEM 1306 BUT SUBSEQUENT COATS OF PAINTING OVER 19.59 21.55 /SQM
PREVIOUSLY PAINTED SURFACE.
Details of cost for 350 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
104 COOLIE 4 DAY 350.00 1400.00
118 SPECIAL MAZDOOR/COOLIE(FOR 2.5 DAY 400.00 1000.00
RUBBING AND POLISHING)
119 MATE 0.5 DAY 370.00 185.00
131 WORK MISTRI 0.5 DAY 475.00 237.50
132 TAR BOILER MAN/FIRE MAN 0.5 DAY 350.00 175.00
Sundries.. L.S. 360.61
6858.11
Add for contractor's profit @ 10 % 685.81
7543.92
1308 SAME AS ITEM 1306 BUT WITH COLD EMULSION IN 2ND COAT. 34.05 37.45 /SQM
Details of cost for 350 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
104 COOLIE 6 DAY 350.00 2100.00
118 SPECIAL MAZDOOR/COOLIE(FOR 1 DAY 400.00 400.00
RUBBING AND POLISHING)
119 MATE 1 DAY 370.00 370.00
Sundries.. L.S. 2747.33
11917.33
Add for contractor's profit @ 10 % 1191.73
13109.06
1309 SAME AS ITEM 1306 BUT WITH TAR IN ONE COAT. 34.37 37.81 /SQM
Details of cost for 350 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
104 COOLIE 8 DAY 350.00 2800.00
118 SPECIAL MAZDOOR/COOLIE(FOR 5 DAY 400.00 2000.00
RUBBING AND POLISHING)
119 MATE 1 DAY 370.00 370.00
131 WORK MISTRI 1 DAY 475.00 475.00
132 TAR BOILER MAN/FIRE MAN 1 DAY 350.00 350.00
Sundries.. L.S. 434.81
12029.81
Add for contractor's profit @ 10 % 1202.98
13232.79
1311 SCRAPPING OF OLD PAINTED SURFACE (ROAD SURFACE). 76.30 83.93 /SQM
Details of cost for 10 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
1312 LAYING C.C. ROAD SLAB 100MM THICK IN (1:2:4) CEMENT, COARSE SAND & 8675.87 9543.46 /CUM
STONE BALLAST OVER PREPARED SURFACE.
Details of cost for 3.5 /CUM
101 MISTRY 0.167 DAY 460.00 76.82
102 MASON/STONE MASON 2.5 DAY 425.00 1062.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17 DAY 350.00 5950.00
104 COOLIE 20 DAY 350.00 7000.00
119 MATE 2 DAY 370.00 740.00
125 CHOWKIDAR 2 DAY 350.00 700.00
126 WORK AGENT 0.33 DAY 350.00 115.50
127 DRIVER FOR CONCRETE MIXER 0.25 DAY 700.00 175.00
128 CLEANER 0.5 DAY 350.00 175.00
245 STONE BALLAST 40MM GAUGE 3.15 CUM. 800.00 2520.00
249 COARSE SAND(BADARPUR) 1.6 CUM. 1395.00 2232.00
251 CEMENT 24 BAG 370.00 8880.00
318 EMPTY BAGS 15 NO. 8.00 120.00
Sundries.. L.S. 618.73
30365.55
Add for contractor's profit @ 10 % 3036.56
33402.11
1314 BLENDING OF WATER BOUND STONE OR KANKAR ROAD SURFACE WITH 12.03 13.24 /RM
LOCAL EARTH OR SAND IN 15MM DEEP LAYERS.
Details of cost for 200 /RM
101 MISTRY 0.04 DAY 460.00 18.40
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.15 DAY 350.00 1102.50
104 COOLIE 3.62 DAY 350.00 1267.00
105 BLACK SMITH 0.04 DAY 425.00 17.00
Sundries.. L.S. 1.92
2406.82
Add for contractor's profit @ 10 % 240.68
2647.50
1315 EARTH WORK IN EDGING OF THE PAINTED OR C.C. ROAD IN A WIDTH OF 22.93 25.22 /RM
0.5M ON EITHER SIDE & 100MM DEEP.
Details of cost for 200 /RM
101 MISTRY 0.075 DAY 460.00 34.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
104 COOLIE 6.9 DAY 350.00 2415.00
105 BLACK SMITH 0.075 DAY 425.00 31.88
Sundries.. L.S. 3.67
4585.05
Add for contractor's profit @ 10 % 458.50
5043.55
1316 JOINT FILLING IN C.C. ROADS & REMOVING THE OLD TAR OR OTHER 1.79 1.97 /RM
MATERIALS (LABOUR ONLY).
Details of cost for 1600 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
104 COOLIE 1 DAY 350.00 350.00
119 MATE 3 DAY 370.00 1110.00
Sundries.. L.S. 0.00
2860.00
Add for contractor's profit @ 10 % 286.00
3146.00
1318 PATCH REPAIR OF SURFACE PAINTED WITH BITUMEN INCLUDING HEATING 3962.50 4358.75 /CUM
THE PAINT ETC. (LABOUR ONLY).
Details of cost for 1 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
104 COOLIE 5 DAY 350.00 1750.00
119 MATE 1.25 DAY 370.00 462.50
Sundries.. L.S. 0.00
3962.50
Add for contractor's profit @ 10 % 396.25
4358.75
1319 CLEANING OF THE EXISTING PAINTED SURFACE & LAYING PREMIX 20MM 47.73 52.50 /SQM
THICK OVER A TACK COAT WITH GRADED GRIT & BITUMEN (LABIUR ONLY).
Details of cost for 350 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 33 DAY 350.00 11550.00
104 COOLIE 9 DAY 350.00 3150.00
119 MATE 2 DAY 370.00 740.00
126 WORK AGENT 1 DAY 350.00 350.00
132 TAR BOILER MAN/FIRE MAN 2 DAY 350.00 700.00
Sundries.. L.S. 214.37
16704.37
Add for contractor's profit @ 10 % 1670.44
18374.81
1321 CLEANING THE PREMIX SURFACE & LAYING SEAL COAT WITH 6MM GRADED 14.08 15.49 /SQM
GRIT & BITUMEN INCLUDING HEATING OF PAINT (LABOUR ONLY).
Details of cost for 350 /SQM
101 MISTRY 0.25 DAY 460.00 115.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
104 COOLIE 2 DAY 350.00 700.00
119 MATE 1 DAY 370.00 370.00
132 TAR BOILER MAN/FIRE MAN 1 DAY 350.00 350.00
Sundries.. L.S. 242.21
4927.21
Add for contractor's profit @ 10 % 492.72
5419.93
1323 PROVIDE ALL MATERIALS, LABOUR,T & P ETC. & CONSTRUCT 100MM THICK 1542.62 1696.89 /SQM
(1:2:4:) CEMENT CONCRETE ROAD FOR REINSTATEMENT OF PATCH &
TRENCH CUTS IN CEMENT CONCRETE ROAD.
Details of cost for 10 /SQM
101 MISTRY 0.048 DAY 460.00 22.08
102 MASON/STONE MASON 1.714 DAY 425.00 728.45
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7.247 DAY 350.00 2536.45
104 COOLIE 5.714 DAY 350.00 1999.90
106 BHISTI 0.16 DAY 350.00 56.00
119 MATE 0.571 DAY 370.00 211.27
125 CHOWKIDAR 0.571 DAY 350.00 199.85
126 WORK AGENT 0.095 DAY 350.00 33.25
127 DRIVER FOR CONCRETE MIXER 0.071 DAY 700.00 49.70
128 CLEANER 0.143 DAY 350.00 50.05
240 BRICKS OVER BURNT 500 1000NOS 4000.00 2000.00
245 STONE BALLAST 40MM GAUGE 2.1 CUM. 800.00 1680.00
249 COARSE SAND(BADARPUR) 0.457 CUM. 1395.00 637.52
251 CEMENT 6.857 BAG 370.00 2537.09
318 EMPTY BAGS 4.286 NO. 8.00 34.29
357 STEAM COAL 0.1 QTL. 440.00 44.00
363 HIRING OF ROAD ROLLER 0.04 DAY 8000.00 320.00
Sundries.. L.S. 2286.34
15426.23
Add for contractor's profit @ 10 % 1542.62
16968.85
1324 SAME AS ITEM 1323 BUT TWO COATS OF BITUMEN PAINTING INSTEAD OF 822.33 904.56 /SQM
100MM THICK CEMENT CONCRETE CONCRETE LAYER.
Details of cost for 10 /SQM
101 MISTRY 0.0429 DAY 460.00 19.73
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.2457 DAY 350.00 1136.00
104 COOLIE 0.3429 DAY 350.00 120.02
106 BHISTI 0.16 DAY 350.00 56.00
113 WATCHMAN 0.2144 DAY 350.00 75.04
119 MATE 0.0429 DAY 370.00 15.87
132 TAR BOILER MAN/FIRE MAN 0.0429 DAY 350.00 15.02
240 BRICKS OVER BURNT 500 1000NOS 4000.00 2000.00
245 STONE BALLAST 40MM GAUGE 1.2 CUM. 800.00 960.00
247 STONE GRIT 10-12MM 0.21 CUM. 1090.00 228.90
357 STEAM COAL 0.1 QTL. 440.00 44.00
363 HIRING OF ROAD ROLLER 0.04 DAY 8000.00 320.00
384 BITUMEN 0.034 TONNE 22500.00 765.00
Sundries.. L.S. 2042.68
8223.25
Add for contractor's profit @ 10 % 822.33
9045.58
1326 MAINTENANCE OF TERRACED ROOFS, FILLING UP CRACKS BEFORE RAINS 80.85 88.94 /SQM
WITH BITUMINOUS FILLER.
Details of cost for 10 /SQM
104 COOLIE 1 DAY 350.00 350.00
Sundries.. L.S.
Sundries.. L.S.
1329 CLEANING OF WELL & THROWING OUT THE SILT TO THE PLACE AS DIRECTD 1379.43 1517.37 /RM
BY THE ENGINEER IN CHARGE.
Details of cost for 1 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
104 COOLIE 2 DAY 350.00 700.00
130 WELL SINKER 0.5 DAY 475.00 237.50
Sundries.. L.S. 91.93
1379.43
Add for contractor's profit @ 10 % 137.94
1517.37
1331 RENEWING PANES OF GLASS 2.5MM THICK WITH PUTTY & BEADS. 465.31 511.84 /SQM
Details of cost for 1 /SQM
351 GLASS PANE 2.5MM THICK 1.05 SQM. 330.00 346.50
1332 CLEANING DOORS & WINDOWS WITH ORDINARY OIL & WATER. 13.16 14.47 /SQM
Details of cost for 10 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
295 MUSTARD OIL 0.125 KG. 200.00 25.00
Sundries.. L.S. 19.07
131.57
Add for contractor's profit @ 10 % 13.16
144.73
1333 FIXING PANES & GLASS INCLUDING PUTTY & BEADS (EXCLUDING COST OF 249.48 274.43 /SQM
GLASS).
Details of cost for 1 /SQM
109 PAINTER 0.333 DAY 460.00 153.18
1334 CLEANING PANES OF GLASS WITH SPRIT OR CAUSTIC SODA. 84.23 92.65 /SQM
Details of cost for 1 /SQM
109 PAINTER 0.167 DAY 460.00 76.82
1335 LABOUR FOR FIXING DOOR BOLTS OR HINGES OR TOWER BOLTS OR HASP & 18.40 20.24 /EACH
STRAPLES OR HANDLES ETC. TO DOORS & WINDOWS.
Details of cost for 1 /EACH
107 CARPENTER 0.04 DAY 460.00 18.40
1337 VARNISHING OR POLISHING FURNITURE WITH HIGH GRADE VARNISH OR 112.45 123.70 /NO.
POLISH AFTER SAND PAPERING.
Details of cost for 7 /NO.
104 COOLIE 0.44 DAY 350.00 154.00
109 PAINTER 0.44 DAY 460.00 202.40
284 VARNISH 1.25 LTR. 225.00 281.25
Sundries.. L.S. 149.53
787.18
Add for contractor's profit @ 10 % 78.72
865.90
2002 SAME AS ITEM 2001 BUT IN SOIL MIXED WITH MOORUM/SHINGLE/KANKAR. 221.26 243.38 /CUM
Details of cost for 100 /CUM
101 MISTRY 0.438 DAY 460.00 201.48
103 BELDAR/MAZDOOR/DIGGER/DRESSER 42 DAY 350.00 14700.00
104 COOLIE 18 DAY 350.00 6300.00
105 BLACK SMITH 0.875 DAY 425.00 371.88
Sundries.. L.S. 552.28
22125.64
Add for contractor's profit @ 10 % 2212.56
24338.20
2003 EXTRA ON ITEMS 2001 AND 2002 FOR ADDITIONAL LEAD AND LIFT. 46.20 50.82 /CUM
Details of cost for 100 /CUM
104 COOLIE 12 DAY 350.00 4200.00
2004 CARTING FROM STORE, LAYING, JOINTING, FIXING & TESTING OF 15MM DIA. 75.79 83.37 /RM
(NOMINAL) M.S. GALVANIZED SCREWED & SOCKETTED PIPES (LIGHT &
MEDIUM QUALITY), SPECIALS & FITTINGS (INSIDE HOUSES).
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 473.76
2273.76
Add for contractor's profit @ 10 % 227.38
2501.14
2005 SAME AS ITEM 2004 BUT FOR 20MM DIA. 83.72 92.09 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 511.60
2511.60
Add for contractor's profit @ 10 % 251.16
2762.76
2007 SAME AS ITEM 2004 BUT FOR 32MM DIA. 128.26 141.08 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
Sundries.. L.S. 947.72
3847.72
Add for contractor's profit @ 10 % 384.77
4232.49
2008 SAME AS ITEM 2004 BUT FOR 40MM DIA. 154.93 170.42 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 2.5 DAY 400.00 1000.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
Sundries.. L.S. 1197.84
4647.84
Add for contractor's profit @ 10 % 464.78
5112.62
2009 CARTING FROM STORE, LAYING, JOINTING, FIXING & TESTING OF 15MM DIA. 19.54 21.50 /RM
(NOMINAL) M.S. GALVANIZED SCREWED & SOCKETTED PIPES (MEDIUM
QUALITY),SPECIALS & FITTINGS (IN TRENCHES OUTSIDE HOUSES).
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
373 CARTAGE OF 0.38 QTL. 41.25 15.68
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 120.61
586.29
Add for contractor's profit @ 10 % 58.63
644.92
2010 SAME AS ITEM 2009 BUT FOR 20MM DIA. 28.27 31.10 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
114 FITTER/PLUMBER 0.375 DAY 400.00 150.00
115 JUNIOR FITTER 0.75 DAY 350.00 262.50
373 CARTAGE OF 0.5 QTL. 41.25 20.63
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 152.55
848.18
Add for contractor's profit @ 10 % 84.82
933.00
2012 SAME AS ITEM 2009 BUT FOR 32MM DIA. 47.19 51.91 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
373 CARTAGE OF 0.99 QTL. 41.25 40.84
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 299.94
1415.78
Add for contractor's profit @ 10 % 141.58
1557.36
2013 SAME AS ITEM 2009 BUT FOR 40MM DIA. 52.47 57.72 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
373 CARTAGE OF 1.14 QTL. 41.25 47.03
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 364.67
1574.20
Add for contractor's profit @ 10 % 157.42
1731.62
2014 SAME AS ITEM 2009 BUT FOR 50MM DIA. 60.80 66.88 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
115 JUNIOR FITTER 1.5 DAY 350.00 525.00
373 CARTAGE OF 1.62 QTL. 41.25 66.83
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 407.20
1824.03
Add for contractor's profit @ 10 % 182.40
2006.43
2016 SAME AS ITEM 2009 BUT FOR 80MM DIA. 88.87 97.76 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
114 FITTER/PLUMBER 1.25 DAY 400.00 500.00
115 JUNIOR FITTER 1.75 DAY 350.00 612.50
373 CARTAGE OF 2.71 QTL. 41.25 111.79
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 566.81
2666.10
Add for contractor's profit @ 10 % 266.61
2932.71
2017 SAME AS ITEM 2009 BUT FOR 100MM DIA. 105.00 115.50 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
373 CARTAGE OF 3.91 QTL. 41.25 161.29
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 638.62
3149.91
Add for contractor's profit @ 10 % 314.99
3464.90
2018 SAME AS ITEM 2009 BUT FOR 125MM DIA. 115.94 127.53 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
373 CARTAGE OF 5.39 QTL. 41.25 222.34
M.S.G.I.SCREWED/SOCKETED PIPE 15-
150MM DIA.
Sundries.. L.S. 730.79
3478.13
Add for contractor's profit @ 10 % 347.81
3825.94
2020 CARTING FROM STORE, LAYING, JOINTING & TESTING 50MM DIA. CLASS I & II 20.44 22.49 /RM
A.C. PRESURE PIPE WITH FITTING ETC.
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 4.1 QTL. 41.26 169.17
300MM DIA.
Sundries.. L.S. 274.93
2044.10
Add for contractor's profit @ 10 % 204.41
2248.51
2023 SAME AS ITEM 2020 BUT 100MM DIA. 32.44 35.69 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 1.125 DAY 400.00 450.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 8.2 QTL. 41.26 338.33
300MM DIA.
Sundries.. L.S. 356.13
3244.46
Add for contractor's profit @ 10 % 324.45
3568.91
2025 SAME AS ITEM 2020 BUT 150MM DIA. 46.68 51.35 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 12.8 QTL. 41.26 528.13
300MM DIA.
Sundries.. L.S. 390.17
4668.30
Add for contractor's profit @ 10 % 466.83
5135.13
2026 SAME AS ITEM 2020 BUT 200MM DIA. 55.83 61.41 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
114 FITTER/PLUMBER 2.25 DAY 400.00 900.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 19.1 QTL. 41.26 788.07
300MM DIA.
Sundries.. L.S. 394.81
5582.88
Add for contractor's profit @ 10 % 558.29
6141.17
2027 SAME AS ITEM 2020 BUT 250MM DIA. 66.65 73.32 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
114 FITTER/PLUMBER 2.75 DAY 400.00 1100.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 24.2 QTL. 41.26 998.49
300MM DIA.
Sundries.. L.S. 366.57
6665.06
Add for contractor's profit @ 10 % 666.51
7331.57
2028 SAME AS ITEM 2020 BUT 300MM DIA. 77.21 84.93 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13 DAY 350.00 4550.00
114 FITTER/PLUMBER 3.75 DAY 400.00 1500.00
371 CARTAGE OF A.C.CLASSI&II PIPE 50- 31.1 QTL. 41.26 1283.19
300MM DIA.
Sundries.. L.S. 387.93
7721.12
Add for contractor's profit @ 10 % 772.11
8493.23
2030 SAME AS ITEM 2020 BUT 400MM DIA. 138.74 152.61 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 21.9 DAY 350.00 7665.00
114 FITTER/PLUMBER 6.3 DAY 400.00 2520.00
372 CARTAGE OF A.C.CLASS I&II PIPE 350- 52.3 QTL. 57.20 2991.56
600MM DIA.
Sundries.. L.S. 697.04
13873.60
Add for contractor's profit @ 10 % 1387.36
15260.96
2031 SAME AS ITEM 2020 BUT 450MM DIA. 166.87 183.56 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 26.3 DAY 350.00 9205.00
114 FITTER/PLUMBER 7.6 DAY 400.00 3040.00
372 CARTAGE OF A.C.CLASS I&II PIPE 350- 63 QTL. 57.20 3603.60
600MM DIA.
Sundries.. L.S. 838.39
16686.99
Add for contractor's profit @ 10 % 1668.70
18355.69
2032 SAME AS ITEM 2020 BUT 500MM DIA. 206.21 226.83 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 32.5 DAY 350.00 11375.00
114 FITTER/PLUMBER 9.4 DAY 400.00 3760.00
372 CARTAGE OF A.C.CLASS I&II PIPE 350- 77.8 QTL. 57.20 4450.16
600MM DIA.
Sundries.. L.S. 1036.05
20621.21
Add for contractor's profit @ 10 % 2062.12
22683.33
2033 SAME AS ITEM 2020 BUT 600MM DIA. 287.88 316.67 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 45.4 DAY 350.00 15890.00
114 FITTER/PLUMBER 13.1 DAY 400.00 5240.00
372 CARTAGE OF A.C.CLASS I&II PIPE 350- 108.6 QTL. 57.20 6211.92
600MM DIA.
Sundries.. L.S. 1446.39
28788.31
Add for contractor's profit @ 10 % 2878.83
31667.14
Sundries.. L.S.
2035 CARTING FROM STORE, LAYING, JOINTING, FIXING & TESTING 15 MM DIA. 6.19 6.81 /RM
(I.D.) P.V.C. PIPES & SPECIALS.
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
114 FITTER/PLUMBER 0.143 DAY 400.00 57.20
Sundries.. L.S. 124.76
619.46
Add for contractor's profit @ 10 % 61.95
681.41
2036 SAME AS ITEM 2035 BUT 20MM DIA. 7.56 8.31 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.167 DAY 400.00 66.80
Sundries.. L.S. 163.93
755.73
Add for contractor's profit @ 10 % 75.57
831.30
2037 SAME AS ITEM 2035 BUT 25MM DIA. 8.25 9.07 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.2 DAY 400.00 80.00
Sundries.. L.S. 219.74
824.74
Add for contractor's profit @ 10 % 82.47
907.21
2038 SAME AS ITEM 2035 BUT 32MM DIA. 9.98 10.97 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.75 DAY 350.00 612.50
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 285.00
997.50
Add for contractor's profit @ 10 % 99.75
1097.25
2039 SAME AS ITEM 2035 BUT 40MM DIA. 11.36 12.50 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 336.00
1136.00
Add for contractor's profit @ 10 % 113.60
1249.60
2041 SAME AS ITEM 2035 BUT 65MM DIA. 23.20 25.52 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 720.00
2320.00
Add for contractor's profit @ 10 % 232.00
2552.00
2042 SAME AS ITEM 2035 BUT 80MM DIA. 28.64 31.50 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
114 FITTER/PLUMBER 0.625 DAY 400.00 250.00
Sundries.. L.S. 864.00
2864.00
Add for contractor's profit @ 10 % 286.40
3150.40
2043 SAME AS ITEM 2035 BUT 100 MM DIA. 31.75 34.92 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.25 DAY 350.00 1837.50
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
Sundries.. L.S. 1037.12
3174.62
Add for contractor's profit @ 10 % 317.46
3492.08
2044 SAME AS ITEM 2035 BUT 125 MM DIA. 34.53 37.99 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 953.25
3453.25
Add for contractor's profit @ 10 % 345.32
3798.57
2045 SAME AS ITEM 2035 BUT 150 MM DIA. 44.44 48.88 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
114 FITTER/PLUMBER 1.125 DAY 400.00 450.00
Sundries.. L.S. 1543.96
4443.96
Add for contractor's profit @ 10 % 444.40
4888.36
2047 SAME AS ITEM 2035 BUT 200 MM DIA. 51.31 56.44 /RM
Details of cost for 100 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
Sundries.. L.S. 1730.94
5130.94
Add for contractor's profit @ 10 % 513.09
5644.03
2048 CARTING FROM STORE P1 QUALITY R.C.C. PRESSURE PIPES & SPECIALS 97.38 107.12 /RM
80MM DIA., LAYING JOINTING, & TESTING WITH (1:1.5) CEMENT & SAND
MORTAR JOINTS.
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.065 CUM. 1395.00 90.68
251 CEMENT 1.22 BAG 370.00 451.40
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 22.75 QTL. 41.93 953.91
300MM DIA.
Sundries.. L.S. 922.15
9738.13
Add for contractor's profit @ 10 % 973.81
10711.94
2049 SAME AS ITEM 2048 BUT 100 MM DIA. 117.43 129.17 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.073 CUM. 1395.00 101.84
251 CEMENT 1.36 BAG 370.00 503.20
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 27 QTL. 41.93 1132.11
300MM DIA.
Sundries.. L.S. 1136.03
11743.18
Add for contractor's profit @ 10 % 1174.32
12917.50
2051 SAME AS ITEM 2048 BUT 250 MM DIA. 180.84 198.92 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.139 CUM. 1395.00 193.91
251 CEMENT 2.6 BAG 370.00 962.00
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 58.7 QTL. 41.93 2461.29
300MM DIA.
Sundries.. L.S. 2146.74
18083.94
Add for contractor's profit @ 10 % 1808.39
19892.33
2052 SAME AS ITEM 2048 BUT 300 MM DIA. 203.88 224.27 /RM
Details of cost for 100 /RM
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
249 COARSE SAND(BADARPUR) 0.178 CUM. 1395.00 248.31
251 CEMENT 3.35 BAG 370.00 1239.50
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 82.45 QTL. 41.93 3457.13
300MM DIA.
Sundries.. L.S. 2367.82
20387.76
Add for contractor's profit @ 10 % 2038.78
22426.54
2054 SAME AS ITEM 2049 BUT P2 QUALITY 100MM DIA. PIPES. 117.47 129.22 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.073 CUM. 1395.00 101.84
251 CEMENT 1.37 BAG 370.00 506.90
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 27 QTL. 41.93 1132.11
300MM DIA.
Sundries.. L.S. 1136.42
11747.27
Add for contractor's profit @ 10 % 1174.73
12922.00
2055 SAME AS ITEM 2050 BUT P2 QUALITY 150MM DIA. PIPES. 143.52 157.87 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.098 CUM. 1395.00 136.71
251 CEMENT 1.85 BAG 370.00 684.50
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 37.35 QTL. 41.93 1566.09
300MM DIA.
Sundries.. L.S. 1544.56
14351.86
Add for contractor's profit @ 10 % 1435.19
15787.05
2057 SAME AS ITEM 2055 BUT P2 QUALITY 300MM DIA. PIPES. 218.39 240.23 /RM
Details of cost for 100 /RM
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
249 COARSE SAND(BADARPUR) 0.232 CUM. 1395.00 323.64
251 CEMENT 4.35 BAG 370.00 1609.50
376 CARTAGE OF R.C.C. P2 PIPE 80-300MM DIA. 114 QTL. 39.93 4552.02
Sundries.. L.S. 2278.76
21838.92
Add for contractor's profit @ 10 % 2183.89
24022.81
2058 SAME AS ITEM 2055 BUT P2 QUALITY 350MM DIA. PIPES. 289.08 317.99 /RM
Details of cost for 100 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.296 CUM. 1395.00 412.92
251 CEMENT 5.56 BAG 370.00 2057.20
377 CARTAGE OF R.C.C.P2 PIPE 350-600MM DIA. 147.4 QTL. 54.06 7968.44
Sundries.. L.S. 2739.85
28908.41
Add for contractor's profit @ 10 % 2890.84
31799.25
2059 SAME AS ITEM 2055 BUT P2 QUALITY 400MM DIA. PIPES. 335.92 369.51 /RM
Details of cost for 100 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 15 DAY 425.00 6375.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 22 DAY 350.00 7700.00
106 BHISTI 1.5 DAY 350.00 525.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.374 CUM. 1395.00 521.73
251 CEMENT 6.98 BAG 370.00 2582.60
377 CARTAGE OF R.C.C.P2 PIPE 350-600MM DIA. 186.5 QTL. 54.06 10082.19
Sundries.. L.S. 3375.19
33591.71
Add for contractor's profit @ 10 % 3359.17
36950.88
2061 SAME AS ITEM 2055 BUT P2 QUALITY 500MM DIA. PIPES. 443.32 487.65 /RM
Details of cost for 100 /RM
101 MISTRY 3.5 DAY 460.00 1610.00
102 MASON/STONE MASON 18 DAY 425.00 7650.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 28 DAY 350.00 9800.00
106 BHISTI 1.5 DAY 350.00 525.00
115 JUNIOR FITTER 3.5 DAY 350.00 1225.00
249 COARSE SAND(BADARPUR) 0.613 CUM. 1395.00 855.14
251 CEMENT 11.44 BAG 370.00 4232.80
377 CARTAGE OF R.C.C.P2 PIPE 350-600MM DIA. 258.4 QTL. 54.06 13969.10
Sundries.. L.S. 4465.11
44332.15
Add for contractor's profit @ 10 % 4433.21
48765.36
2062 SAME AS ITEM 2055 BUT P2 QUALITY 600MM DIA. PIPES. 554.07 609.48 /RM
Details of cost for 100 /RM
101 MISTRY 3.5 DAY 460.00 1610.00
102 MASON/STONE MASON 20 DAY 425.00 8500.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 32 DAY 350.00 11200.00
106 BHISTI 2 DAY 350.00 700.00
115 JUNIOR FITTER 3.5 DAY 350.00 1225.00
249 COARSE SAND(BADARPUR) 0.863 CUM. 1395.00 1203.89
251 CEMENT 16.19 BAG 370.00 5990.30
377 CARTAGE OF R.C.C.P2 PIPE 350-600MM DIA. 366.25 QTL. 54.06 19799.48
Sundries.. L.S. 5178.57
55407.23
Add for contractor's profit @ 10 % 5540.72
60947.95
2064 SAME AS ITEM 2049 BUT P3 QUALITY 100MM DIA. PIPES. 117.43 129.17 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.073 CUM. 1395.00 101.84
251 CEMENT 1.36 BAG 370.00 503.20
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 27 QTL. 41.93 1132.11
300MM DIA.
Sundries.. L.S. 1136.03
11743.18
Add for contractor's profit @ 10 % 1174.32
12917.50
2065 SAME AS ITEM 2050 BUT P3 QUALITY 150MM DIA. PIPES. 143.52 157.87 /RM
Details of cost for 100 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.098 CUM. 1395.00 136.71
251 CEMENT 1.85 BAG 370.00 684.50
375 CARTAGE OF R.C.C. P1 QUALITY PIPE 80- 37.35 QTL. 41.93 1566.09
300MM DIA.
Sundries.. L.S. 1544.56
14351.86
Add for contractor's profit @ 10 % 1435.19
15787.05
2067 SAME AS ITEM 2065 BUT 300MM DIA. PIPES. 229.05 251.95 /RM
Details of cost for 100 /RM
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
249 COARSE SAND(BADARPUR) 0.265 CUM. 1395.00 369.68
251 CEMENT 4.98 BAG 370.00 1842.60
378 CARTAGE OF R.C.C.P3 PIPE 200-300MM DIA. 129.25 QTL. 41.26 5332.86
Sundries.. L.S. 2284.71
22904.84
Add for contractor's profit @ 10 % 2290.48
25195.32
2068 SAME AS ITEM 2065 BUT 350MM DIA. PIPES. 299.25 329.17 /RM
Details of cost for 100 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
106 BHISTI 1 DAY 350.00 350.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.384 CUM. 1395.00 535.68
251 CEMENT 7.2 BAG 370.00 2664.00
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 184.85 QTL. 45.26 8366.31
Sundries.. L.S. 2628.60
29924.59
Add for contractor's profit @ 10 % 2992.46
32917.05
2069 SAME AS ITEM 2065 BUT 400MM DIA. PIPES. 344.58 379.04 /RM
Details of cost for 100 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 15 DAY 425.00 6375.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 22 DAY 350.00 7700.00
106 BHISTI 1.5 DAY 350.00 525.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.472 CUM. 1395.00 658.44
251 CEMENT 8.86 BAG 370.00 3278.20
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 228.75 QTL. 45.26 10353.23
Sundries.. L.S. 3138.25
34458.12
Add for contractor's profit @ 10 % 3445.81
37903.93
2071 SAME AS 2070 BUT 100MM DIA. PIPES. 35.73 39.30 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.7 DAY 350.00 595.00
114 FITTER/PLUMBER 0.21 DAY 400.00 84.00
115 JUNIOR FITTER 0.21 DAY 350.00 73.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 6.15 QTL. 39.93 245.57
Sundries.. L.S. 73.86
1071.93
Add for contractor's profit @ 10 % 107.19
1179.12
2072 SAME AS 2070 BUT 125MM DIA. PIPES. 46.18 50.80 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.2 DAY 350.00 770.00
114 FITTER/PLUMBER 0.27 DAY 400.00 108.00
115 JUNIOR FITTER 0.27 DAY 350.00 94.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 7.95 QTL. 39.93 317.44
Sundries.. L.S. 95.46
1385.40
Add for contractor's profit @ 10 % 138.54
1523.94
2073 SAME AS 2070 BUT 150MM DIA. PIPES. 57.61 63.37 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.74 DAY 350.00 959.00
114 FITTER/PLUMBER 0.34 DAY 400.00 136.00
115 JUNIOR FITTER 0.34 DAY 350.00 119.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 9.9 QTL. 39.93 395.31
Sundries.. L.S. 119.09
1728.40
Add for contractor's profit @ 10 % 172.84
1901.24
2074 SAME AS 2070 BUT 200MM DIA. PIPES. 84.24 92.67 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 14.48 QTL. 39.93 578.19
Sundries.. L.S. 174.14
2527.33
Add for contractor's profit @ 10 % 252.73
2780.06
2076 SAME AS 2070 BUT 300MM DIA. PIPES. 146.59 161.25 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.96 DAY 350.00 2436.00
114 FITTER/PLUMBER 0.87 DAY 400.00 348.00
115 JUNIOR FITTER 0.87 DAY 350.00 304.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 25.2 QTL. 39.93 1006.24
Sundries.. L.S. 303.01
4397.75
Add for contractor's profit @ 10 % 439.77
4837.52
2077 SAME AS 2070 BUT C.I. SCREWED FLANGED PIPES (CLASS 'A') 80 MM DIA. 31.86 35.04 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.51 DAY 350.00 528.50
114 FITTER/PLUMBER 0.19 DAY 400.00 76.00
115 JUNIOR FITTER 0.19 DAY 350.00 66.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 5.48 QTL. 39.93 218.82
Sundries.. L.S. 65.85
955.67
Add for contractor's profit @ 10 % 95.57
1051.24
2084 C.I. FLANGED PIPES VERTICALLY CAST CLASS (A) - SAME RATES AS FOR /RM
ITEMS 2077 TO 2083.
Details of cost for /RM
Sundries.. L.S.
2086 SAME AS ITEM 2070 BUT 400 MM DIA. 216.68 238.34 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.9 DAY 350.00 3465.00
114 FITTER/PLUMBER 1.24 DAY 400.00 496.00
115 JUNIOR FITTER 1.24 DAY 350.00 434.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 38.55 QTL. 42.60 1642.23
Sundries.. L.S. 463.06
6500.29
Add for contractor's profit @ 10 % 650.03
7150.32
2087 SAME AS ITEM 2070 BUT 450 MM DIA. 261.19 287.30 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.94 DAY 350.00 4179.00
114 FITTER/PLUMBER 1.49 DAY 400.00 596.00
115 JUNIOR FITTER 1.49 DAY 350.00 521.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 46.5 QTL. 42.60 1980.90
Sundries.. L.S. 558.18
7835.58
Add for contractor's profit @ 10 % 783.56
8619.14
2088 SAME AS ITEM 2070 BUT 500 MM DIA. 306.33 336.96 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
114 FITTER/PLUMBER 1.75 DAY 400.00 700.00
115 JUNIOR FITTER 1.75 DAY 350.00 612.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 54.525 QTL. 42.60 2322.77
Sundries.. L.S. 654.65
9189.92
Add for contractor's profit @ 10 % 918.99
10108.91
2089 SAME AS ITEM 2070 BUT 600 MM DIA. 407.86 448.65 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18.64 DAY 350.00 6524.00
114 FITTER/PLUMBER 2.33 DAY 400.00 932.00
115 JUNIOR FITTER 2.33 DAY 350.00 815.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 72.6 QTL. 42.60 3092.76
Sundries.. L.S. 871.64
12235.90
Add for contractor's profit @ 10 % 1223.59
13459.49
2091 SAME AS ITEM 2070 BUT 750 MM DIA. 589.78 648.76 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 26.95 DAY 350.00 9432.50
114 FITTER/PLUMBER 3.37 DAY 400.00 1348.00
115 JUNIOR FITTER 3.37 DAY 350.00 1179.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 105 QTL. 42.60 4473.00
Sundries.. L.S. 1260.41
17693.41
Add for contractor's profit @ 10 % 1769.34
19462.75
2092 SAME AS ITEM 2085 BUT C.I. FLANGED PIPES (VERTICALLY CAST CLASS - A) 198.19 218.01 /RM
350 MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.06 DAY 350.00 3171.00
114 FITTER/PLUMBER 1.13 DAY 400.00 452.00
115 JUNIOR FITTER 1.13 DAY 350.00 395.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 35.3 QTL. 42.60 1503.78
Sundries.. L.S. 423.56
5945.84
Add for contractor's profit @ 10 % 594.58
6540.42
2093 SAME AS ITEM 2085 BUT FOR 400 MM DIA. 243.18 267.49 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.11 DAY 350.00 3888.50
114 FITTER/PLUMBER 1.39 DAY 400.00 556.00
115 JUNIOR FITTER 1.39 DAY 350.00 486.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 43.3 QTL. 42.60 1844.58
Sundries.. L.S. 519.69
7295.27
Add for contractor's profit @ 10 % 729.53
8024.80
2094 SAME AS ITEM 2085 BUT FOR 450 MM DIA. 292.56 321.81 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.37 DAY 350.00 4679.50
114 FITTER/PLUMBER 1.67 DAY 400.00 668.00
115 JUNIOR FITTER 1.67 DAY 350.00 584.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 52.1 QTL. 42.60 2219.46
Sundries.. L.S. 625.22
8776.68
Add for contractor's profit @ 10 % 877.67
9654.35
2096 SAME AS ITEM 2085 BUT FOR 600 MM DIA. 456.18 501.80 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20.84 DAY 350.00 7294.00
114 FITTER/PLUMBER 2.61 DAY 400.00 1044.00
115 JUNIOR FITTER 2.61 DAY 350.00 913.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 81.2 QTL. 42.60 3459.12
Sundries.. L.S. 974.90
13685.52
Add for contractor's profit @ 10 % 1368.55
15054.07
2097 SAME AS ITEM 2085 BUT FOR 700 MM DIA. 592.04 651.25 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 27.06 DAY 350.00 9471.00
114 FITTER/PLUMBER 3.38 DAY 400.00 1352.00
115 JUNIOR FITTER 3.38 DAY 350.00 1183.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 105.4 QTL. 42.60 4490.04
Sundries.. L.S. 1265.25
17761.29
Add for contractor's profit @ 10 % 1776.13
19537.42
2098 SAME AS ITEM 2085 BUT FOR 750 MM DIA. 666.26 732.88 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 30.44 DAY 350.00 10654.00
114 FITTER/PLUMBER 3.81 DAY 400.00 1524.00
115 JUNIOR FITTER 3.81 DAY 350.00 1333.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 118.6 QTL. 42.60 5052.36
Sundries.. L.S. 1423.85
19987.71
Add for contractor's profit @ 10 % 1998.77
21986.48
2099 SAME AS ITEM 2070 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 800 657.17 722.88 /RM
MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24.58 DAY 350.00 8603.00
114 FITTER/PLUMBER 4.92 DAY 400.00 1968.00
115 JUNIOR FITTER 4.92 DAY 350.00 1722.00
369 CARTAGE OF C.I.PIPE 800-1000MM DIA. 125.58 QTL. 50.58 6351.84
Sundries.. L.S. 1070.21
19715.05
Add for contractor's profit @ 10 % 1971.50
21686.55
2101 SAME AS ITEM 2070 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 964.56 1061.01 /RM
1000MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 36.08 DAY 350.00 12628.00
114 FITTER/PLUMBER 7.22 DAY 400.00 2888.00
115 JUNIOR FITTER 7.22 DAY 350.00 2527.00
369 CARTAGE OF C.I.PIPE 800-1000MM DIA. 184.32 QTL. 50.58 9322.91
Sundries.. L.S. 1570.80
28936.71
Add for contractor's profit @ 10 % 2893.67
31830.38
2102 SAME AS ITEM 2099 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 800 695.38 764.92 /RM
MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 26.02 DAY 350.00 9107.00
114 FITTER/PLUMBER 5.2 DAY 400.00 2080.00
115 JUNIOR FITTER 5.2 DAY 350.00 1820.00
369 CARTAGE OF C.I.PIPE 800-1000MM DIA. 132.9 QTL. 50.58 6722.08
Sundries.. L.S. 1132.45
20861.53
Add for contractor's profit @ 10 % 2086.15
22947.68
2103 SAME AS ITEM 2099 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 900 843.52 927.88 /RM
MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 31.56 DAY 350.00 11046.00
114 FITTER/PLUMBER 6.31 DAY 400.00 2524.00
115 JUNIOR FITTER 6.31 DAY 350.00 2208.50
369 CARTAGE OF C.I.PIPE 800-1000MM DIA. 161.2 QTL. 50.58 8153.50
Sundries.. L.S. 1373.70
25305.70
Add for contractor's profit @ 10 % 2530.57
27836.27
2104 SAME AS ITEM 2099 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 1020.34 1122.38 /RM
1000MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 38.18 DAY 350.00 13363.00
114 FITTER/PLUMBER 7.63 DAY 400.00 3052.00
115 JUNIOR FITTER 7.63 DAY 350.00 2670.50
369 CARTAGE OF C.I.PIPE 800-1000MM DIA. 195 QTL. 50.58 9863.10
Sundries.. L.S. 1661.65
30610.25
Add for contractor's profit @ 10 % 3061.02
33671.27
2106 SAME AS ITEM 2070 BUT C.I.S. & S PIPES (VERTICALLY CAST CLASS A) 1255.30 1380.83 /RM
1200MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 43.06 DAY 350.00 15071.00
114 FITTER/PLUMBER 8.61 DAY 400.00 3444.00
115 JUNIOR FITTER 8.61 DAY 350.00 3013.50
370 CARTAGE OF C.I.PIPE 1100-1200MM DIA. 253.74 QTL. 55.90 14184.07
Sundries.. L.S. 1946.33
37658.90
Add for contractor's profit @ 10 % 3765.89
41424.79
2107 CARTING FROM STORE CLASS 'A' C.I. SEREWED FLANGED SPUN PIPES & 112.12 123.33 /RM
CLASS 'A' VERTICALLY CAST PIPES, SPECIALS & FITTINGS, HOISTING &
ERECTING IN VERTICAL POSITION (UPTO 8 M HIGHT) 80 MM DIA.
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.36 DAY 350.00 476.00
114 FITTER/PLUMBER 0.17 DAY 400.00 68.00
115 JUNIOR FITTER 0.17 DAY 350.00 59.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 1.46 QTL. 39.93 58.30
Sundries.. L.S. 235.14
896.94
Add for contractor's profit @ 10 % 89.69
986.63
2108 SAME AS ITEM 2107 BUT 100 DIA. 139.20 153.12 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.69 DAY 350.00 591.50
114 FITTER/PLUMBER 0.21 DAY 400.00 84.00
115 JUNIOR FITTER 0.21 DAY 350.00 73.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 1.82 QTL. 39.93 72.67
Sundries.. L.S. 291.94
1113.61
Add for contractor's profit @ 10 % 111.36
1224.97
2109 SAME AS ITEM 2107 BUT 125 DIA. 182.38 200.62 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.21 DAY 350.00 773.50
114 FITTER/PLUMBER 0.28 DAY 400.00 112.00
115 JUNIOR FITTER 0.28 DAY 350.00 98.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 2.33 QTL. 39.93 93.04
Sundries.. L.S. 382.49
1459.03
Add for contractor's profit @ 10 % 145.90
1604.93
2111 SAME AS IETM 2107 BUT 200 DIA. 329.79 362.77 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 4.3 QTL. 39.93 171.70
Sundries.. L.S. 691.66
2638.36
Add for contractor's profit @ 10 % 263.84
2902.20
2112 SAME AS ITEM 2107 BUT 250 DIA. 443.23 487.56 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.38 DAY 350.00 1883.00
114 FITTER/PLUMBER 0.67 DAY 400.00 268.00
115 JUNIOR FITTER 0.67 DAY 350.00 234.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 5.78 QTL. 39.93 230.80
Sundries.. L.S. 929.57
3545.87
Add for contractor's profit @ 10 % 354.59
3900.46
2113 SAME AS IETM 2107 BUT 300 DIA. 572.51 629.76 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.94 DAY 350.00 2429.00
114 FITTER/PLUMBER 0.87 DAY 400.00 348.00
115 JUNIOR FITTER 0.87 DAY 350.00 304.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 7.46 QTL. 39.93 297.88
Sundries.. L.S. 1200.69
4580.07
Add for contractor's profit @ 10 % 458.01
5038.08
2114 SAME AS IETM 2107 BUT 8.0 - 16.0 HIGH 80 MM DIA. 187.04 205.75 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.04 DAY 350.00 714.00
114 FITTER/PLUMBER 0.34 DAY 400.00 136.00
115 JUNIOR FITTER 0.34 DAY 350.00 119.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 1.46 QTL. 39.93 58.30
Sundries.. L.S. 469.06
1496.36
Add for contractor's profit @ 10 % 149.64
1646.00
2116 SAME AS ITEM 2107 BUT 8.0 - 16.0 HIGH 125MM DIA. 303.98 334.38 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.32 DAY 350.00 1162.00
114 FITTER/PLUMBER 0.55 DAY 400.00 220.00
115 JUNIOR FITTER 0.55 DAY 350.00 192.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 2.38 QTL. 39.93 95.03
Sundries.. L.S. 762.31
2431.84
Add for contractor's profit @ 10 % 243.18
2675.02
2117 SAME AS ITEM 2107 BUT 8.0 - 16.0 HIGH 150MM DIA. 380.99 419.09 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.16 DAY 350.00 1456.00
114 FITTER/PLUMBER 0.69 DAY 400.00 276.00
115 JUNIOR FITTER 0.69 DAY 350.00 241.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 2.98 QTL. 39.93 118.99
Sundries.. L.S. 955.43
3047.92
Add for contractor's profit @ 10 % 304.79
3352.71
2118 SAME AS ITEM 2107 BUT 8.0 - 16.0 HIGH 200MM DIA. 550.18 605.19 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 4.3 QTL. 39.93 171.70
Sundries.. L.S. 1379.71
4401.41
Add for contractor's profit @ 10 % 440.14
4841.55
2119 SAME AS ITEM 2107 BUT 8.0 - 16.0 HIGH 250MM DIA. 738.64 812.50 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8.06 DAY 350.00 2821.00
114 FITTER/PLUMBER 1.34 DAY 400.00 536.00
115 JUNIOR FITTER 1.34 DAY 350.00 469.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 5.78 QTL. 39.93 230.80
Sundries.. L.S. 1852.33
5909.13
Add for contractor's profit @ 10 % 590.91
6500.04
2121 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 80 MM DIA. 298.87 328.76 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.72 DAY 350.00 952.00
114 FITTER/PLUMBER 0.68 DAY 400.00 272.00
115 JUNIOR FITTER 0.68 DAY 350.00 238.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 1.46 QTL. 39.93 58.30
Sundries.. L.S. 870.67
2390.97
Add for contractor's profit @ 10 % 239.10
2630.07
2122 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 100MM DIA. 372.86 410.15 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.39 DAY 350.00 1186.50
114 FITTER/PLUMBER 0.85 DAY 400.00 340.00
115 JUNIOR FITTER 0.85 DAY 350.00 297.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 1.82 QTL. 39.93 72.67
Sundries.. L.S. 1086.22
2982.89
Add for contractor's profit @ 10 % 298.29
3281.18
2123 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 125MM DIA. 487.15 535.87 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.43 DAY 350.00 1550.50
114 FITTER/PLUMBER 1.11 DAY 400.00 444.00
115 JUNIOR FITTER 1.11 DAY 350.00 388.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 2.38 QTL. 39.93 95.03
Sundries.. L.S. 1419.17
3897.20
Add for contractor's profit @ 10 % 389.72
4286.92
2124 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 150MM DIA. 609.52 670.47 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.54 DAY 350.00 1939.00
114 FITTER/PLUMBER 1.39 DAY 400.00 556.00
115 JUNIOR FITTER 1.39 DAY 350.00 486.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 2.98 QTL. 39.93 118.99
Sundries.. L.S. 1775.65
4876.14
Add for contractor's profit @ 10 % 487.61
5363.75
2126 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 250MM DIA. 1181.65 1299.81 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10.75 DAY 350.00 3762.50
114 FITTER/PLUMBER 2.69 DAY 400.00 1076.00
115 JUNIOR FITTER 2.69 DAY 350.00 941.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 5.78 QTL. 39.93 230.80
Sundries.. L.S. 3442.38
9453.18
Add for contractor's profit @ 10 % 945.32
10398.50
2127 SAME AS ITEM 2107 BUT 16.0 - 24.0 HIGH 300MM DIA. 1525.20 1677.72 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.88 DAY 350.00 4858.00
114 FITTER/PLUMBER 3.47 DAY 400.00 1388.00
115 JUNIOR FITTER 3.47 DAY 350.00 1214.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 7.46 QTL. 39.93 297.88
Sundries.. L.S. 4443.22
12201.60
Add for contractor's profit @ 10 % 1220.16
13421.76
2128 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 350 MM DIA. 766.42 843.06 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.97 DAY 350.00 2439.50
114 FITTER/PLUMBER 1.16 DAY 400.00 464.00
115 JUNIOR FITTER 1.16 DAY 350.00 406.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 9.41 QTL. 42.60 400.87
Sundries.. L.S. 2421.01
6131.38
Add for contractor's profit @ 10 % 613.14
6744.52
2129 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 400 MM DIA. 942.04 1036.24 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8.56 DAY 350.00 2996.00
114 FITTER/PLUMBER 1.43 DAY 400.00 572.00
115 JUNIOR FITTER 1.43 DAY 350.00 500.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 11.55 QTL. 42.60 492.03
Sundries.. L.S. 2975.75
7536.28
Add for contractor's profit @ 10 % 753.63
8289.91
2131 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 500 MM DIA. 1319.96 1451.96 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 16.2 QTL. 42.60 690.12
Sundries.. L.S. 4169.55
10559.67
Add for contractor's profit @ 10 % 1055.97
11615.64
2132 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 600 MM DIA. 1763.79 1940.17 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16.04 DAY 350.00 5614.00
114 FITTER/PLUMBER 2.67 DAY 400.00 1068.00
115 JUNIOR FITTER 2.67 DAY 350.00 934.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 21.65 QTL. 42.60 922.29
Sundries.. L.S. 5571.56
14110.35
Add for contractor's profit @ 10 % 1411.04
15521.39
2133 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 700 MM DIA. 2290.16 2519.17 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20.82 DAY 350.00 7287.00
114 FITTER/PLUMBER 3.47 DAY 400.00 1388.00
115 JUNIOR FITTER 3.47 DAY 350.00 1214.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 28.11 QTL. 42.60 1197.49
Sundries.. L.S. 7234.26
18321.25
Add for contractor's profit @ 10 % 1832.12
20153.37
2134 SAME AS ITEM 2107 BUT VERTICALLY CAST PIPES 750 MM DIA. 2577.99 2835.79 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 23.43 DAY 350.00 8200.50
114 FITTER/PLUMBER 3.91 DAY 400.00 1564.00
115 JUNIOR FITTER 3.91 DAY 350.00 1368.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 31.63 QTL. 42.60 1347.44
Sundries.. L.S. 8143.49
20623.93
Add for contractor's profit @ 10 % 2062.39
22686.32
2136 SAME AS ITEM 2128 BUT 8.0 - 16.0 HIGH FOR 400 MM DIA. 1258.54 1384.40 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.41 DAY 350.00 3993.50
114 FITTER/PLUMBER 2.85 DAY 400.00 1140.00
115 JUNIOR FITTER 2.85 DAY 350.00 997.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 11.55 QTL. 42.60 492.03
Sundries.. L.S. 3445.30
10068.33
Add for contractor's profit @ 10 % 1006.83
11075.16
2137 SAME AS ITEM 2128 BUT 8.0 - 16.0 HIGH FOR 450 MM DIA. 1513.78 1665.16 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.72 DAY 350.00 4802.00
114 FITTER/PLUMBER 3.43 DAY 400.00 1372.00
115 JUNIOR FITTER 3.43 DAY 350.00 1200.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 13.89 QTL. 42.60 591.71
Sundries.. L.S. 4144.02
12110.23
Add for contractor's profit @ 10 % 1211.02
13321.25
2138 SAME AS ITEM 2128 BUT 8.0 - 16.0 HIGH FOR 500 MM DIA. 1764.61 1941.07 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15.99 DAY 350.00 5596.50
114 FITTER/PLUMBER 4 DAY 400.00 1600.00
115 JUNIOR FITTER 4 DAY 350.00 1400.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 16.19 QTL. 42.60 689.69
Sundries.. L.S. 4830.68
14116.87
Add for contractor's profit @ 10 % 1411.69
15528.56
2139 SAME AS ITEM 2128 BUT 8.0 - 16.0 HIGH FOR 600 MM DIA. 2359.69 2595.66 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 21.38 DAY 350.00 7483.00
114 FITTER/PLUMBER 5.35 DAY 400.00 2140.00
115 JUNIOR FITTER 5.35 DAY 350.00 1872.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 21.65 QTL. 42.60 922.29
Sundries.. L.S. 6459.73
18877.52
Add for contractor's profit @ 10 % 1887.75
20765.27
2141 SAME AS ITEM 2128 BUT 8.0 - 16.0 HIGH FOR 750 MM DIA. 3446.85 3791.54 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 31.24 DAY 350.00 10934.00
114 FITTER/PLUMBER 7.81 DAY 400.00 3124.00
115 JUNIOR FITTER 7.81 DAY 350.00 2733.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 31.63 QTL. 42.60 1347.44
Sundries.. L.S. 9435.88
27574.82
Add for contractor's profit @ 10 % 2757.48
30332.30
2142 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 350 MM DIA. 1599.48 1759.43 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.69 DAY 350.00 4091.50
114 FITTER/PLUMBER 4.67 DAY 400.00 1868.00
115 JUNIOR FITTER 4.67 DAY 350.00 1634.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 9.47 QTL. 42.60 403.42
Sundries.. L.S. 4798.45
12795.87
Add for contractor's profit @ 10 % 1279.59
14075.46
2143 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 400 MM DIA. 1951.61 2146.77 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14.26 DAY 350.00 4991.00
114 FITTER/PLUMBER 5.7 DAY 400.00 2280.00
115 JUNIOR FITTER 5.7 DAY 350.00 1995.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 11.55 QTL. 42.60 492.03
Sundries.. L.S. 5854.82
15612.85
Add for contractor's profit @ 10 % 1561.28
17174.13
2144 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 450 MM DIA. 2347.84 2582.63 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.15 DAY 350.00 6002.50
114 FITTER/PLUMBER 6.86 DAY 400.00 2744.00
115 JUNIOR FITTER 6.86 DAY 350.00 2401.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 13.89 QTL. 42.60 591.71
Sundries.. L.S. 7043.53
18782.74
Add for contractor's profit @ 10 % 1878.27
20661.01
2146 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 600 MM DIA. 3659.06 4024.96 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 26.73 DAY 350.00 9355.50
114 FITTER/PLUMBER 10.69 DAY 400.00 4276.00
115 JUNIOR FITTER 10.69 DAY 350.00 3741.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 21.65 QTL. 42.60 922.29
Sundries.. L.S. 10977.17
29272.46
Add for contractor's profit @ 10 % 2927.25
32199.71
2147 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 700 MM DIA. 4750.50 5225.55 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 34.7 DAY 350.00 12145.00
114 FITTER/PLUMBER 13.88 DAY 400.00 5552.00
115 JUNIOR FITTER 13.88 DAY 350.00 4858.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 28.11 QTL. 42.60 1197.49
Sundries.. L.S. 14251.49
38003.98
Add for contractor's profit @ 10 % 3800.40
41804.38
2148 SAME AS ITEM 2128 BUT 16.0 - 24.0 HIGH FOR 750 MM DIA. 5345.99 5880.59 /RM
Details of cost for 8 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 39.05 DAY 350.00 13667.50
114 FITTER/PLUMBER 15.62 DAY 400.00 6248.00
115 JUNIOR FITTER 15.62 DAY 350.00 5467.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 31.63 QTL. 42.60 1347.44
Sundries.. L.S. 16037.96
42767.90
Add for contractor's profit @ 10 % 4276.79
47044.69
2149 CARTING, LAYING & TESTING OF STEEL CYLENDER REINFORCED CONCRETE 122.50 134.75 /RM
PIPES CLASS 3 AND SPECIALS 200 MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
114 FITTER/PLUMBER 0.67 DAY 400.00 268.00
115 JUNIOR FITTER 0.67 DAY 350.00 234.50
378 CARTAGE OF R.C.C.P3 PIPE 200-300MM DIA. 29 QTL. 41.26 1196.54
Sundries.. L.S. 225.91
3674.95
Add for contractor's profit @ 10 % 367.50
4042.45
2151 SAME AS ITEM 2149 BUT 300 MM DIA. 184.87 203.36 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
378 CARTAGE OF R.C.C.P3 PIPE 200-300MM DIA. 41 QTL. 41.26 1691.66
Sundries.. L.S. 304.54
5546.20
Add for contractor's profit @ 10 % 554.62
6100.82
2152 SAME AS ITEM 2149 BUT 350 MM DIA. 218.72 240.59 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
114 FITTER/PLUMBER 1.25 DAY 400.00 500.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 47 QTL. 45.26 2127.22
Sundries.. L.S. 346.78
6561.50
Add for contractor's profit @ 10 % 656.15
7217.65
2153 SAME AS ITEM 2149 BUT 400 MM DIA. 253.89 279.27 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
114 FITTER/PLUMBER 1.75 DAY 400.00 700.00
115 JUNIOR FITTER 1.75 DAY 350.00 612.50
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 53 QTL. 45.26 2398.78
Sundries.. L.S. 405.27
7616.55
Add for contractor's profit @ 10 % 761.66
8378.21
2154 SAME AS ITEM 2149 BUT 450 MM DIA. 313.78 345.16 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 71 QTL. 45.26 3213.46
Sundries.. L.S. 500.05
9413.51
Add for contractor's profit @ 10 % 941.35
10354.86
2156 SAME AS ITEM 2149 BUT 600 MM DIA. 436.13 479.74 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 100 QTL. 45.26 4526.00
Sundries.. L.S. 707.91
13083.91
Add for contractor's profit @ 10 % 1308.39
14392.30
2157 SAME AS ITEM 2149 BUT 700 MM DIA. 537.09 590.80 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
114 FITTER/PLUMBER 4 DAY 400.00 1600.00
115 JUNIOR FITTER 4 DAY 350.00 1400.00
379 CARTAGE OF R.C.C.P3 PIPE 350-700MM DIA. 115 QTL. 45.26 5204.90
Sundries.. L.S. 907.73
16112.63
Add for contractor's profit @ 10 % 1611.26
17723.89
2158 SAME AS ITEM 2149 BUT 900 MM DIA. 922.75 1015.03 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 25 DAY 350.00 8750.00
114 FITTER/PLUMBER 5 DAY 400.00 2000.00
115 JUNIOR FITTER 5 DAY 350.00 1750.00
380 CARTAGE OF R.C.C.P3 PIPE 900-1200MM 146 QTL. 95.86 13995.56
DIA.
Sundries.. L.S. 1187.00
27682.56
Add for contractor's profit @ 10 % 2768.26
30450.82
2159 SAME AS ITEM 2149 BUT 1100 MM DIA. 1220.91 1343.00 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 30 DAY 350.00 10500.00
114 FITTER/PLUMBER 6 DAY 400.00 2400.00
115 JUNIOR FITTER 6 DAY 350.00 2100.00
380 CARTAGE OF R.C.C.P3 PIPE 900-1200MM 210 QTL. 95.86 20130.60
DIA.
Sundries.. L.S. 1496.56
36627.16
Add for contractor's profit @ 10 % 3662.72
40289.88
2161 MAKING LEAD & SPUN YARN JOINTS OF C.I.S & S PIPES & SPECIALS 80 MM 421.64 463.80 /JNT
DIA.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
274 SPUN YARN 1 KG. 60.50 60.50
275 PIG LEAD 18 KG. 130.00 2340.00
276 FUEL(WOOD) 0.2 QTL. 700.00 140.00
Sundries.. L.S. 225.86
4216.36
Add for contractor's profit @ 10 % 421.64
4638.00
2162 SAME AS ITEM 2161 BUT 100 MM DIA. 528.94 581.83 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
114 FITTER/PLUMBER 1.25 DAY 400.00 500.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
274 SPUN YARN 1.8 KG. 60.50 108.90
275 PIG LEAD 22 KG. 130.00 2860.00
276 FUEL(WOOD) 0.3 QTL. 700.00 210.00
Sundries.. L.S. 297.99
5289.39
Add for contractor's profit @ 10 % 528.94
5818.33
2163 SAME AS ITEM 2161 BUT 125 MM DIA. 620.46 682.51 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
115 JUNIOR FITTER 1.5 DAY 350.00 525.00
274 SPUN YARN 2 KG. 60.50 121.00
275 PIG LEAD 26 KG. 130.00 3380.00
276 FUEL(WOOD) 0.35 QTL. 700.00 245.00
Sundries.. L.S. 283.62
6204.62
Add for contractor's profit @ 10 % 620.46
6825.08
2165 SAME AS ITEM 2161 BUT 200 MM DIA. 1113.63 1224.99 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.5 DAY 350.00 1575.00
114 FITTER/PLUMBER 2.25 DAY 400.00 900.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
274 SPUN YARN 3 KG. 60.50 181.50
275 PIG LEAD 50 KG. 130.00 6500.00
276 FUEL(WOOD) 0.55 QTL. 700.00 385.00
Sundries.. L.S. 719.78
11136.28
Add for contractor's profit @ 10 % 1113.63
12249.91
2166 SAME AS ITEM 2161 BUT 250 MM DIA. 1346.01 1480.61 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.5 DAY 350.00 1925.00
114 FITTER/PLUMBER 2.75 DAY 400.00 1100.00
115 JUNIOR FITTER 2.75 DAY 350.00 962.50
274 SPUN YARN 3.5 KG. 60.50 211.75
275 PIG LEAD 61 KG. 130.00 7930.00
276 FUEL(WOOD) 0.65 QTL. 700.00 455.00
Sundries.. L.S. 875.86
13460.11
Add for contractor's profit @ 10 % 1346.01
14806.12
2167 SAME AS ITEM 2161 BUT 300 MM DIA. 1525.89 1678.48 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
274 SPUN YARN 4.8 KG. 60.50 290.40
275 PIG LEAD 72 KG. 130.00 9360.00
276 FUEL(WOOD) 0.75 QTL. 700.00 525.00
Sundries.. L.S. 733.53
15258.93
Add for contractor's profit @ 10 % 1525.89
16784.82
2169 SAME AS ITEM 2161 BUT 400 MM DIA. 2123.84 2336.22 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
114 FITTER/PLUMBER 4.5 DAY 400.00 1800.00
115 JUNIOR FITTER 4.5 DAY 350.00 1575.00
274 SPUN YARN 7.5 KG. 60.50 453.75
275 PIG LEAD 95 KG. 130.00 12350.00
276 FUEL(WOOD) 1.1 QTL. 700.00 770.00
Sundries.. L.S. 1139.60
21238.35
Add for contractor's profit @ 10 % 2123.84
23362.19
2170 SAME AS ITEM 2161 BUT 450 MM DIA. 2853.20 3138.52 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
114 FITTER/PLUMBER 5 DAY 400.00 2000.00
115 JUNIOR FITTER 5 DAY 350.00 1750.00
274 SPUN YARN 9.5 KG. 60.50 574.75
275 PIG LEAD 140 KG. 130.00 18200.00
276 FUEL(WOOD) 1.3 QTL. 700.00 910.00
Sundries.. L.S. 1597.23
28531.98
Add for contractor's profit @ 10 % 2853.20
31385.18
2171 SAME AS ITEM 2161 BUT 500 MM DIA. 3091.40 3400.54 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11 DAY 350.00 3850.00
114 FITTER/PLUMBER 5.5 DAY 400.00 2200.00
115 JUNIOR FITTER 5.5 DAY 350.00 1925.00
274 SPUN YARN 10 KG. 60.50 605.00
275 PIG LEAD 150 KG. 130.00 19500.00
276 FUEL(WOOD) 1.4 QTL. 700.00 980.00
Sundries.. L.S. 1854.03
30914.03
Add for contractor's profit @ 10 % 3091.40
34005.43
2173 SAME AS ITEM 2161 BUT 700 MM DIA. 4617.61 5079.37 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17 DAY 350.00 5950.00
114 FITTER/PLUMBER 8.5 DAY 400.00 3400.00
115 JUNIOR FITTER 8.5 DAY 350.00 2975.00
274 SPUN YARN 13.5 KG. 60.50 816.75
275 PIG LEAD 220 KG. 130.00 28600.00
276 FUEL(WOOD) 2.1 QTL. 700.00 1470.00
Sundries.. L.S. 2964.33
46176.08
Add for contractor's profit @ 10 % 4617.61
50793.69
2174 SAME AS ITEM 2161 BUT 750 MM DIA. 5306.67 5837.34 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
114 FITTER/PLUMBER 10 DAY 400.00 4000.00
115 JUNIOR FITTER 10 DAY 350.00 3500.00
274 SPUN YARN 14.5 KG. 60.50 877.25
275 PIG LEAD 250 KG. 130.00 32500.00
276 FUEL(WOOD) 2.6 QTL. 700.00 1820.00
Sundries.. L.S. 3369.47
53066.72
Add for contractor's profit @ 10 % 5306.67
58373.39
2175 SAME AS ITEM 2161 BUT 800 MM DIA. 6550.38 7205.42 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24 DAY 350.00 8400.00
114 FITTER/PLUMBER 12 DAY 400.00 4800.00
115 JUNIOR FITTER 12 DAY 350.00 4200.00
274 SPUN YARN 15.3 KG. 60.50 925.65
275 PIG LEAD 315 KG. 130.00 40950.00
276 FUEL(WOOD) 2.8 QTL. 700.00 1960.00
Sundries.. L.S. 4268.12
65503.77
Add for contractor's profit @ 10 % 6550.38
72054.15
2177 SAME AS ITEM 2161 BUT 1000MM DIA. 8499.37 9349.30 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 32 DAY 350.00 11200.00
114 FITTER/PLUMBER 16 DAY 400.00 6400.00
115 JUNIOR FITTER 16 DAY 350.00 5600.00
274 SPUN YARN 20.5 KG. 60.50 1240.25
275 PIG LEAD 410 KG. 130.00 53300.00
276 FUEL(WOOD) 3.5 QTL. 700.00 2450.00
Sundries.. L.S. 4803.40
84993.65
Add for contractor's profit @ 10 % 8499.36
93493.01
2178 SAME AS ITEM 2161 BUT 1100MM DIA. 9557.01 10512.72 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 36 DAY 350.00 12600.00
114 FITTER/PLUMBER 18 DAY 400.00 7200.00
115 JUNIOR FITTER 18 DAY 350.00 6300.00
274 SPUN YARN 24 KG. 60.50 1452.00
275 PIG LEAD 460 KG. 130.00 59800.00
276 FUEL(WOOD) 4 QTL. 700.00 2800.00
Sundries.. L.S. 5418.14
95570.14
Add for contractor's profit @ 10 % 9557.01
105127.15
2179 SAME AS ITEM 2161 BUT 1200MM DIA. 10450.78 11495.86 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 40 DAY 350.00 14000.00
114 FITTER/PLUMBER 20 DAY 400.00 8000.00
115 JUNIOR FITTER 20 DAY 350.00 7000.00
274 SPUN YARN 26 KG. 60.50 1573.00
275 PIG LEAD 500 KG. 130.00 65000.00
276 FUEL(WOOD) 4.3 QTL. 700.00 3010.00
Sundries.. L.S. 5924.84
104507.84
Add for contractor's profit @ 10 % 10450.78
114958.62
2181 SAME AS ITEM 2180 BUT 100 MM DIA. 319.57 351.52 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
115 JUNIOR FITTER 0.75 DAY 350.00 262.50
334 NUT WITH BOLT 16*65MM. 19.7 KG. 92.00 1812.40
358 3MM THICK RUBBER INSERTION 1.1 KG. 99.00 108.90
Sundries.. L.S. 186.85
3195.65
Add for contractor's profit @ 10 % 319.56
3515.21
2182 SAME AS ITEM 2180 BUT 125 MM DIA. 362.34 398.58 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
334 NUT WITH BOLT 16*65MM. 19.7 KG. 92.00 1812.40
358 3MM THICK RUBBER INSERTION 1.4 KG. 99.00 138.60
Sundries.. L.S. 222.43
3623.43
Add for contractor's profit @ 10 % 362.34
3985.77
2183 SAME AS ITEM 2180 BUT 150 MM DIA. 487.66 536.43 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
335 NUT WITH BOLT 20*65MM 32.2 KG. 92.00 2962.40
358 3MM THICK RUBBER INSERTION 1.7 KG. 99.00 168.30
Sundries.. L.S. 295.91
4876.61
Add for contractor's profit @ 10 % 487.66
5364.27
2184 SAME AS ITEM 2180 BUT 200 MM DIA. 551.11 606.22 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
114 FITTER/PLUMBER 1.25 DAY 400.00 500.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
336 NUT WITH BOLT 20*75MM 34.2 KG. 92.00 3146.40
358 3MM THICK RUBBER INSERTION 2.2 KG. 99.00 217.80
Sundries.. L.S. 334.41
5511.11
Add for contractor's profit @ 10 % 551.11
6062.22
2186 SAME AS ITEM 2180 BUT 300 MM DIA. 851.90 937.09 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
336 NUT WITH BOLT 20*75MM 51.4 KG. 92.00 4728.80
358 3MM THICK RUBBER INSERTION 3.1 KG. 99.00 306.90
Sundries.. L.S. 583.27
8518.97
Add for contractor's profit @ 10 % 851.90
9370.87
2187 SAME AS ITEM 2180 BUT 350 MM DIA. 1129.96 1242.96 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
114 FITTER/PLUMBER 2.5 DAY 400.00 1000.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
337 NUT WITH BOLT 20*90MM 70.9 KG. 92.00 6522.80
358 3MM THICK RUBBER INSERTION 3.8 KG. 99.00 376.20
Sundries.. L.S. 775.62
11299.62
Add for contractor's profit @ 10 % 1129.96
12429.58
2188 SAME AS ITEM 2180 BUT 400 MM DIA. 1507.69 1658.46 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
114 FITTER/PLUMBER 2.5 DAY 400.00 1000.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
338 NUT WITH BOLT 24*90MM. 109.8 KG. 92.00 10101.60
358 3MM THICK RUBBER INSERTION 4.6 KG. 99.00 455.40
Sundries.. L.S. 894.88
15076.88
Add for contractor's profit @ 10 % 1507.69
16584.57
2189 SAME AS ITEM 2180 BUT 450 MM DIA. 1876.36 2064.00 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
338 NUT WITH BOLT 24*90MM. 137.2 KG. 92.00 12622.40
358 3MM THICK RUBBER INSERTION 5.1 KG. 99.00 504.90
Sundries.. L.S. 1286.33
18763.63
Add for contractor's profit @ 10 % 1876.36
20639.99
2191 SAME AS ITEM 2180 BUT 600 MM DIA. 2623.88 2886.27 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
114 FITTER/PLUMBER 4.5 DAY 400.00 1800.00
115 JUNIOR FITTER 4.5 DAY 350.00 1575.00
339 NUT WITH BOLT 27*100MM 189 KG. 92.00 17388.00
358 3MM THICK RUBBER INSERTION 7.2 KG. 99.00 712.80
Sundries.. L.S. 1612.99
26238.79
Add for contractor's profit @ 10 % 2623.88
28862.67
2192 SAME AS ITEM 2180 BUT 700 MM DIA. 3198.23 3518.05 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11 DAY 350.00 3850.00
114 FITTER/PLUMBER 5.5 DAY 400.00 2200.00
115 JUNIOR FITTER 5.5 DAY 350.00 1925.00
339 NUT WITH BOLT 27*100MM 226.8 KG. 92.00 20865.60
358 3MM THICK RUBBER INSERTION 9 KG. 99.00 891.00
Sundries.. L.S. 2250.68
31982.28
Add for contractor's profit @ 10 % 3198.23
35180.51
2193 SAME AS ITEM 2180 BUT 750 MM DIA. 3402.47 3742.72 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
114 FITTER/PLUMBER 6 DAY 400.00 2400.00
115 JUNIOR FITTER 6 DAY 350.00 2100.00
340 NUT WITH BOLT 27*110MM 237.7 KG. 92.00 21868.40
358 3MM THICK RUBBER INSERTION 10.4 KG. 99.00 1029.60
Sundries.. L.S. 2426.73
34024.73
Add for contractor's profit @ 10 % 3402.47
37427.20
2194 SAME AS ITEM 2180 BUT 800 MM DIA. 4825.93 5308.52 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13 DAY 350.00 4550.00
114 FITTER/PLUMBER 6.5 DAY 400.00 2600.00
115 JUNIOR FITTER 6.5 DAY 350.00 2275.00
341 NUT WITH BOLT 30*110MM 373.4 KG. 92.00 34352.80
358 3MM THICK RUBBER INSERTION 11.3 KG. 99.00 1118.70
Sundries.. L.S. 3362.75
48259.25
Add for contractor's profit @ 10 % 4825.92
53085.17
2196 SAME AS ITEM 2180 BUT 1000MM DIA. 6568.26 7225.09 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
114 FITTER/PLUMBER 8 DAY 400.00 3200.00
115 JUNIOR FITTER 8 DAY 350.00 2800.00
342 NUT WITH BOLT 33*120MM 517.7 KG. 92.00 47628.40
358 3MM THICK RUBBER INSERTION 14.8 KG. 99.00 1465.20
Sundries.. L.S. 4989.01
65682.61
Add for contractor's profit @ 10 % 6568.26
72250.87
2197 CARTING, LAYING & TESTING OF C.I.S & S CLASS 'LA' TYTON JOINT & LEAD 23.09 25.40 /RM
JOINT PIPES & SPECIALS 80 MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.99 DAY 350.00 346.50
114 FITTER/PLUMBER 0.11 DAY 400.00 44.00
115 JUNIOR FITTER 0.11 DAY 350.00 38.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 4.8 QTL. 39.93 191.66
Sundries.. L.S. 72.18
692.84
Add for contractor's profit @ 10 % 69.28
762.12
2198 SAME AS ITEM 2097 BUT 100 MM DIA. 29.58 32.54 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.27 DAY 350.00 444.50
114 FITTER/PLUMBER 0.14 DAY 400.00 56.00
115 JUNIOR FITTER 0.14 DAY 350.00 49.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 6.15 QTL. 39.93 245.57
Sundries.. L.S. 92.47
887.54
Add for contractor's profit @ 10 % 88.75
976.29
2199 SAME AS ITEM 2097 BUT 125 MM DIA. 38.32 42.16 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.65 DAY 350.00 577.50
114 FITTER/PLUMBER 0.18 DAY 400.00 72.00
115 JUNIOR FITTER 0.18 DAY 350.00 63.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 7.95 QTL. 39.93 317.44
Sundries.. L.S. 119.78
1149.72
Add for contractor's profit @ 10 % 114.97
1264.69
2201 SAME AS ITEM 2097 BUT 200 MM DIA. 69.79 76.77 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 0.33 DAY 400.00 132.00
115 JUNIOR FITTER 0.33 DAY 350.00 115.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 14.48 QTL. 39.93 578.19
Sundries.. L.S. 218.14
2093.83
Add for contractor's profit @ 10 % 209.38
2303.21
2202 SAME AS ITEM 2097 BUT 250 MM DIA. 94.15 103.56 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.04 DAY 350.00 1414.00
114 FITTER/PLUMBER 0.45 DAY 400.00 180.00
115 JUNIOR FITTER 0.45 DAY 350.00 157.50
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 19.5 QTL. 39.93 778.64
Sundries.. L.S. 294.25
2824.39
Add for contractor's profit @ 10 % 282.44
3106.83
2203 SAME AS ITEM 2097 BUT 300 MM DIA. 121.61 133.77 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.22 DAY 350.00 1827.00
114 FITTER/PLUMBER 0.58 DAY 400.00 232.00
115 JUNIOR FITTER 0.58 DAY 350.00 203.00
367 CARTAGE OF C.I.PIPE 80-300MM DIA. 25.2 QTL. 39.93 1006.24
Sundries.. L.S. 380.10
3648.34
Add for contractor's profit @ 10 % 364.83
4013.17
2204 SAME AS ITEM 2097 BUT 350 MM DIA. 140.34 154.37 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.82 DAY 350.00 2037.00
114 FITTER/PLUMBER 0.68 DAY 400.00 272.00
115 JUNIOR FITTER 0.68 DAY 350.00 238.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 31.72 QTL. 42.60 1351.27
Sundries.. L.S. 311.86
4210.13
Add for contractor's profit @ 10 % 421.01
4631.14
2206 SAME AS ITEM 2097 BUT 450 MM DIA. 205.79 226.37 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8.53 DAY 350.00 2985.50
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 46.5 QTL. 42.60 1980.90
Sundries.. L.S. 457.31
6173.71
Add for contractor's profit @ 10 % 617.37
6791.08
2207 SAME AS ITEM 2097 BUT 500 MM DIA. 241.22 265.34 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
114 FITTER/PLUMBER 1.17 DAY 400.00 468.00
115 JUNIOR FITTER 1.17 DAY 350.00 409.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 54.53 QTL. 42.60 2322.98
Sundries.. L.S. 536.04
7236.52
Add for contractor's profit @ 10 % 723.65
7960.17
2208 SAME AS ITEM 2097 BUT 600 MM DIA. 320.90 352.99 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.31 DAY 350.00 4658.50
114 FITTER/PLUMBER 1.55 DAY 400.00 620.00
115 JUNIOR FITTER 1.55 DAY 350.00 542.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 72.6 QTL. 42.60 3092.76
Sundries.. L.S. 713.10
9626.86
Add for contractor's profit @ 10 % 962.69
10589.55
2209 SAME AS ITEM 2097 BUT 700 MM DIA. 414.64 456.10 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.19 DAY 350.00 6016.50
114 FITTER/PLUMBER 2.01 DAY 400.00 804.00
115 JUNIOR FITTER 2.01 DAY 350.00 703.50
368 CARTAGE OF C.I.PIPE 350-750MM DIA. 93.75 QTL. 42.60 3993.75
Sundries.. L.S. 921.42
12439.17
Add for contractor's profit @ 10 % 1243.92
13683.09
2211 MAKE SPECIAL RUBBER GASKET TYTON JOINT C.I.S. & S PIPES & SPECIALS 27.53 30.28 /JNT
ALL CLASSES 80 MM OR 100 MM DIA.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.125 DAY 400.00 50.00
Sundries.. L.S. 50.26
275.26
Add for contractor's profit @ 10 % 27.53
302.79
2212 SAME AS ITEM 2211 BUT 125 OR 150 MM DIA. 38.43 42.28 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.667 DAY 350.00 233.45
114 FITTER/PLUMBER 0.167 DAY 400.00 66.80
Sundries.. L.S. 84.07
384.32
Add for contractor's profit @ 10 % 38.43
422.75
2213 SAME AS ITEM 2211 BUT 200 MM DIA. 46.33 50.96 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 100.78
463.28
Add for contractor's profit @ 10 % 46.33
509.61
2214 SAME AS ITEM 2211 BUT 250 MM DIA. 58.80 64.68 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 138.01
588.01
Add for contractor's profit @ 10 % 58.80
646.81
2215 SAME AS ITEM 2211 BUT 300 MM DIA. 78.57 86.42 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
114 FITTER/PLUMBER 0.375 DAY 400.00 150.00
Sundries.. L.S. 198.16
785.66
Add for contractor's profit @ 10 % 78.57
864.23
2217 SAME AS ITEM 2211 BUT 400 MM DIA. 118.29 130.12 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.75 DAY 350.00 612.50
114 FITTER/PLUMBER 0.625 DAY 400.00 250.00
Sundries.. L.S. 320.42
1182.92
Add for contractor's profit @ 10 % 118.29
1301.21
2218 SAME AS ITEM 2211 BUT 450 MM DIA. 134.55 148.00 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 0.625 DAY 400.00 250.00
Sundries.. L.S. 395.48
1345.48
Add for contractor's profit @ 10 % 134.55
1480.03
2219 SAME AS ITEM 2211 BUT 500 MM DIA. 155.52 171.08 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.25 DAY 350.00 787.50
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
Sundries.. L.S. 467.73
1555.23
Add for contractor's profit @ 10 % 155.52
1710.75
2220 SAME AS ITEM 2211 BUT 600 MM DIA. 170.38 187.41 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
Sundries.. L.S. 528.75
1703.75
Add for contractor's profit @ 10 % 170.38
1874.13
2221 SAME AS ITEM 2211 BUT 700 MM DIA. 206.45 227.09 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.75 DAY 350.00 962.50
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 701.96
2064.46
Add for contractor's profit @ 10 % 206.45
2270.91
2223 MAKING RUBBER RING FLANGED JOINTS (USING C.I. DETACHABLE JOINTS) 27.53 30.28 /JNT
A.C.PRESURE PIPES & C.I. PLAIN ENDED SPECIALS ALL CLASSES 50, 80 OR
100 MM DIA.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.125 DAY 400.00 50.00
Sundries.. L.S. 50.26
275.26
Add for contractor's profit @ 10 % 27.53
302.79
2224 SAME AS ITEM 2223 BUT 125 OR 150 MM DIA. 38.43 42.28 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.667 DAY 350.00 233.45
114 FITTER/PLUMBER 0.167 DAY 400.00 66.80
Sundries.. L.S. 84.07
384.32
Add for contractor's profit @ 10 % 38.43
422.75
2225 SAME AS ITEM 2223 BUT 200 MM DIA. 46.33 50.96 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 100.78
463.28
Add for contractor's profit @ 10 % 46.33
509.61
2226 SAME AS ITEM 2223 BUT 250 MM DIA. 58.80 64.68 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 138.01
588.01
Add for contractor's profit @ 10 % 58.80
646.81
2227 SAME AS ITEM 2223 BUT 300 MM DIA. 78.57 86.42 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
114 FITTER/PLUMBER 0.375 DAY 400.00 150.00
Sundries.. L.S. 198.16
785.66
Add for contractor's profit @ 10 % 78.57
864.23
2229 SAME AS ITEM 2228 BUT 250 MM DIA. 1429.61 1572.57 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 2.25 DAY 425.00 956.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
106 BHISTI 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
247 STONE GRIT 10-12MM 0.195 CUM. 1090.00 212.55
249 COARSE SAND(BADARPUR) 0.104 CUM. 1395.00 145.08
251 CEMENT 1.96 BAG 370.00 725.20
275 PIG LEAD 41.4 KG. 130.00 5382.00
276 FUEL(WOOD) 0.45 QTL. 700.00 315.00
279 STEEL 9.2 KG. 37.50 345.00
Sundries.. L.S. 989.97
14296.05
Add for contractor's profit @ 10 % 1429.60
15725.65
2230 SAME AS ITEM 2228 BUT 300 MM DIA. 1680.16 1848.17 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 3 DAY 425.00 1275.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
106 BHISTI 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
247 STONE GRIT 10-12MM 0.24 CUM. 1090.00 261.60
249 COARSE SAND(BADARPUR) 0.124 CUM. 1395.00 172.98
251 CEMENT 2.26 BAG 370.00 836.20
275 PIG LEAD 51.52 KG. 130.00 6697.60
276 FUEL(WOOD) 0.6 QTL. 700.00 420.00
279 STEEL 10 KG. 37.50 375.00
Sundries.. L.S. 1188.18
16801.56
Add for contractor's profit @ 10 % 1680.16
18481.72
2232 SAME AS ITEM 2228 BUT 400 MM DIA. 2429.56 2672.51 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 4.5 DAY 425.00 1912.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
106 BHISTI 1 DAY 350.00 350.00
114 FITTER/PLUMBER 4.5 DAY 400.00 1800.00
115 JUNIOR FITTER 4.5 DAY 350.00 1575.00
247 STONE GRIT 10-12MM 0.3 CUM. 1090.00 327.00
249 COARSE SAND(BADARPUR) 0.156 CUM. 1395.00 217.62
251 CEMENT 2.89 BAG 370.00 1069.30
275 PIG LEAD 72.32 KG. 130.00 9401.60
276 FUEL(WOOD) 0.8 QTL. 700.00 560.00
279 STEEL 13 KG. 37.50 487.50
Sundries.. L.S. 1695.04
24295.56
Add for contractor's profit @ 10 % 2429.56
26725.12
2233 SAME AS ITEM 2228 BUT 450 MM DIA. 2894.36 3183.79 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 5 DAY 425.00 2125.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
106 BHISTI 1 DAY 350.00 350.00
114 FITTER/PLUMBER 5 DAY 400.00 2000.00
115 JUNIOR FITTER 5 DAY 350.00 1750.00
247 STONE GRIT 10-12MM 0.32 CUM. 1090.00 348.80
249 COARSE SAND(BADARPUR) 0.167 CUM. 1395.00 232.97
251 CEMENT 3.24 BAG 370.00 1198.80
275 PIG LEAD 95.49 KG. 130.00 12413.70
276 FUEL(WOOD) 1 QTL. 700.00 700.00
279 STEEL 15 KG. 37.50 562.50
Sundries.. L.S. 2011.80
28943.57
Add for contractor's profit @ 10 % 2894.36
31837.93
2235 SAME AS ITEM 2228 BUT 600 MM DIA. 3803.88 4184.27 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 19 DAY 350.00 6650.00
106 BHISTI 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 6.5 DAY 400.00 2600.00
115 JUNIOR FITTER 6.5 DAY 350.00 2275.00
247 STONE GRIT 10-12MM 0.4 CUM. 1090.00 436.00
249 COARSE SAND(BADARPUR) 0.21 CUM. 1395.00 292.95
251 CEMENT 4.08 BAG 370.00 1509.60
275 PIG LEAD 130 KG. 130.00 16900.00
276 FUEL(WOOD) 1.4 QTL. 700.00 980.00
279 STEEL 19 KG. 37.50 712.50
Sundries.. L.S. 2607.73
38038.78
Add for contractor's profit @ 10 % 3803.88
41842.66
2236 SAME AS ITEM 2228 BUT 700 MM DIA. 4767.18 5243.89 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 7 DAY 425.00 2975.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 27 DAY 350.00 9450.00
106 BHISTI 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 10 DAY 400.00 4000.00
115 JUNIOR FITTER 10 DAY 350.00 3500.00
247 STONE GRIT 10-12MM 0.46 CUM. 1090.00 501.40
249 COARSE SAND(BADARPUR) 0.242 CUM. 1395.00 337.59
251 CEMENT 4.63 BAG 370.00 1713.10
275 PIG LEAD 149.7 KG. 130.00 19461.00
276 FUEL(WOOD) 1.6 QTL. 700.00 1120.00
279 STEEL 21 KG. 37.50 787.50
Sundries.. L.S. 3301.17
47671.76
Add for contractor's profit @ 10 % 4767.18
52438.94
2238 SAME AS ITEM 2228 BUT 1100MM DIA. 7342.98 8077.27 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 38 DAY 350.00 13300.00
106 BHISTI 2.25 DAY 350.00 787.50
114 FITTER/PLUMBER 15 DAY 400.00 6000.00
115 JUNIOR FITTER 15 DAY 350.00 5250.00
247 STONE GRIT 10-12MM 0.68 CUM. 1090.00 741.20
249 COARSE SAND(BADARPUR) 0.359 CUM. 1395.00 500.81
251 CEMENT 6.86 BAG 370.00 2538.20
275 PIG LEAD 250.29 KG. 130.00 32537.70
276 FUEL(WOOD) 2.65 QTL. 700.00 1855.00
279 STEEL 31 KG. 37.50 1162.50
Sundries.. L.S. 4931.85
73429.76
Add for contractor's profit @ 10 % 7342.98
80772.74
2239 SAME AS ITEM 2228 BUT 1200MM DIA. 8440.14 9284.16 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 40 DAY 350.00 14000.00
106 BHISTI 2.5 DAY 350.00 875.00
114 FITTER/PLUMBER 16 DAY 400.00 6400.00
115 JUNIOR FITTER 16 DAY 350.00 5600.00
247 STONE GRIT 10-12MM 0.92 CUM. 1090.00 1002.80
249 COARSE SAND(BADARPUR) 0.483 CUM. 1395.00 673.79
251 CEMENT 9.25 BAG 370.00 3422.50
275 PIG LEAD 296.66 KG. 130.00 38565.80
276 FUEL(WOOD) 3.1 QTL. 700.00 2170.00
279 STEEL 42 KG. 37.50 1575.00
Sundries.. L.S. 5866.56
84401.45
Add for contractor's profit @ 10 % 8440.14
92841.59
2241 SAME AS ITEM 2240 BUT FOR 100 MM DIA. 136.89 150.58 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.076 CUM. 1395.00 106.02
251 CEMENT 1.42 BAG 370.00 525.40
Sundries.. L.S. 843.20
6844.62
Add for contractor's profit @ 10 % 684.46
7529.08
2242 SAME AS ITEM 2240 BUT FOR 150 MM DIA. 155.61 171.17 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.1012 CUM. 1395.00 141.17
251 CEMENT 1.9 BAG 370.00 703.00
Sundries.. L.S. 1141.27
7780.44
Add for contractor's profit @ 10 % 778.04
8558.48
2243 SAME AS ITEM 2240 BUT FOR 250 MM DIA. 181.02 199.12 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.145 CUM. 1395.00 202.28
251 CEMENT 2.71 BAG 370.00 1002.70
Sundries.. L.S. 1626.07
9051.05
Add for contractor's profit @ 10 % 905.10
9956.15
2245 SAME AS ITEM 2240 BUT P2 QUALITY PIPES 80 MM DIA. 115.45 127.00 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.068 CUM. 1395.00 94.86
251 CEMENT 1.27 BAG 370.00 469.90
Sundries.. L.S. 687.97
5772.73
Add for contractor's profit @ 10 % 577.27
6350.00
2246 SAME AS ITEM 2241 BUT P2 QUALITY PIPES 100 MM DIA. 136.89 150.58 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.076 CUM. 1395.00 106.02
251 CEMENT 1.42 BAG 370.00 525.40
Sundries.. L.S. 843.20
6844.62
Add for contractor's profit @ 10 % 684.46
7529.08
2247 SAME AS ITEM 2242 BUT P2 QUALITY PIPES 150 MM DIA. 155.61 171.17 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.1012 CUM. 1395.00 141.17
251 CEMENT 1.9 BAG 370.00 703.00
Sundries.. L.S. 1141.27
7780.44
Add for contractor's profit @ 10 % 778.04
8558.48
2249 SAME AS ITEM 2247 BUT 300 MM DIA. 249.71 274.69 /JNT
Details of cost for 40 /JNT
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.241 CUM. 1395.00 336.20
251 CEMENT 4.57 BAG 370.00 1690.90
Sundries.. L.S. 1511.47
9988.57
Add for contractor's profit @ 10 % 998.86
10987.43
2250 SAME AS ITEM 2247 BUT 350 MM DIA. 286.11 314.72 /JNT
Details of cost for 40 /JNT
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 11 DAY 425.00 4675.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.31 CUM. 1395.00 432.45
251 CEMENT 5.85 BAG 370.00 2164.50
Sundries.. L.S. 1742.47
11444.42
Add for contractor's profit @ 10 % 1144.44
12588.86
2251 SAME AS ITEM 2247 BUT 400 MM DIA. 326.94 359.64 /JNT
Details of cost for 40 /JNT
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1.5 DAY 350.00 525.00
249 COARSE SAND(BADARPUR) 0.39 CUM. 1395.00 544.05
251 CEMENT 7.33 BAG 370.00 2712.10
Sundries.. L.S. 2116.60
13077.75
Add for contractor's profit @ 10 % 1307.78
14385.53
2253 SAME AS ITEM 2247 BUT 500 MM DIA. 431.33 474.47 /JNT
Details of cost for 40 /JNT
101 MISTRY 3.5 DAY 460.00 1610.00
102 MASON/STONE MASON 13 DAY 425.00 5525.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
106 BHISTI 1.5 DAY 350.00 525.00
249 COARSE SAND(BADARPUR) 0.645 CUM. 1395.00 899.78
251 CEMENT 12.09 BAG 370.00 4473.30
Sundries.. L.S. 2820.22
17253.30
Add for contractor's profit @ 10 % 1725.33
18978.63
2254 SAME AS ITEM 2247 BUT 600 MM DIA. 511.12 562.24 /JNT
Details of cost for 40 /JNT
101 MISTRY 3.5 DAY 460.00 1610.00
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
106 BHISTI 2 DAY 350.00 700.00
249 COARSE SAND(BADARPUR) 0.91 CUM. 1395.00 1269.45
251 CEMENT 17.04 BAG 370.00 6304.80
Sundries.. L.S. 3210.74
20444.99
Add for contractor's profit @ 10 % 2044.50
22489.49
2255 SAME AS ITEM 2240 BUT FOR P3 QUALITY PIPES 80 MM DIA. 115.45 127.00 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.068 CUM. 1395.00 94.86
251 CEMENT 1.27 BAG 370.00 469.90
Sundries.. L.S. 687.97
5772.73
Add for contractor's profit @ 10 % 577.27
6350.00
2257 SAME AS ITEM 2242 BUT FOR P3 QUALITY PIPES 150MM DIA. 155.61 171.17 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.1012 CUM. 1395.00 141.17
251 CEMENT 1.9 BAG 370.00 703.00
Sundries.. L.S. 1141.27
7780.44
Add for contractor's profit @ 10 % 778.04
8558.48
2258 SAME AS ITEM 2257 BUT FOR 250 MM DIA. 188.02 206.83 /JNT
Details of cost for 50 /JNT
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.196 CUM. 1395.00 273.42
251 CEMENT 3.67 BAG 370.00 1357.90
Sundries.. L.S. 1549.85
9401.17
Add for contractor's profit @ 10 % 940.12
10341.29
2259 SAME AS ITEM 2257 BUT FOR 300 MM DIA. 256.27 281.90 /JNT
Details of cost for 40 /JNT
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.279 CUM. 1395.00 389.21
251 CEMENT 5.24 BAG 370.00 1938.80
Sundries.. L.S. 1472.95
10250.96
Add for contractor's profit @ 10 % 1025.10
11276.06
2261 SAME AS ITEM 2257 BUT FOR 400 MM DIA. 346.63 381.30 /JNT
Details of cost for 40 /JNT
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
106 BHISTI 1.5 DAY 350.00 525.00
249 COARSE SAND(BADARPUR) 0.497 CUM. 1395.00 693.32
251 CEMENT 9.32 BAG 370.00 3448.40
Sundries.. L.S. 2018.68
13865.40
Add for contractor's profit @ 10 % 1386.54
15251.94
2262 RATE TO REGULATE PAYMENT FOR MAKING LEAD & SPUN YARN JOINTS IN 548.13 602.94 /JNT
R.C.C. P1 QUALITY PIPES 80 MM DIA.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.6 DAY 350.00 910.00
114 FITTER/PLUMBER 1.3 DAY 400.00 520.00
115 JUNIOR FITTER 1.3 DAY 350.00 455.00
274 SPUN YARN 1.3 KG. 60.50 78.65
275 PIG LEAD 23.4 KG. 130.00 3042.00
276 FUEL(WOOD) 0.26 QTL. 700.00 182.00
Sundries.. L.S. 293.62
5481.27
Add for contractor's profit @ 10 % 548.13
6029.40
2263 SAME AS ITEM 2262 BUT 100 MM DIA. 661.21 727.33 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.125 DAY 350.00 1093.75
114 FITTER/PLUMBER 1.563 DAY 400.00 625.20
115 JUNIOR FITTER 1.563 DAY 350.00 547.05
274 SPUN YARN 2.25 KG. 60.50 136.13
275 PIG LEAD 27.5 KG. 130.00 3575.00
276 FUEL(WOOD) 0.375 QTL. 700.00 262.50
Sundries.. L.S. 372.51
6612.14
Add for contractor's profit @ 10 % 661.21
7273.35
2265 SAME AS ITEM 2262 BUT 250 MM DIA. 1507.53 1658.29 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.16 DAY 350.00 2156.00
114 FITTER/PLUMBER 3.08 DAY 400.00 1232.00
115 JUNIOR FITTER 3.08 DAY 350.00 1078.00
274 SPUN YARN 3.92 KG. 60.50 237.16
275 PIG LEAD 68.32 KG. 130.00 8881.60
276 FUEL(WOOD) 0.728 QTL. 700.00 509.60
Sundries.. L.S. 980.97
15075.33
Add for contractor's profit @ 10 % 1507.53
16582.86
2266 SAME AS ITEM 2262 BUT 300 MM DIA. 1678.48 1846.33 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.6 DAY 350.00 2310.00
114 FITTER/PLUMBER 3.3 DAY 400.00 1320.00
115 JUNIOR FITTER 3.3 DAY 350.00 1155.00
274 SPUN YARN 5.28 KG. 60.50 319.44
275 PIG LEAD 79.2 KG. 130.00 10296.00
276 FUEL(WOOD) 0.825 QTL. 700.00 577.50
Sundries.. L.S. 806.89
16784.83
Add for contractor's profit @ 10 % 1678.48
18463.31
2267 SAME AS ITEM 2262 BUT PC QUALITY PIPES 80 MM DIA. 548.13 602.94 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.6 DAY 350.00 910.00
114 FITTER/PLUMBER 1.3 DAY 400.00 520.00
115 JUNIOR FITTER 1.3 DAY 350.00 455.00
274 SPUN YARN 1.3 KG. 60.50 78.65
275 PIG LEAD 23.4 KG. 130.00 3042.00
276 FUEL(WOOD) 0.26 QTL. 700.00 182.00
Sundries.. L.S. 293.62
5481.27
Add for contractor's profit @ 10 % 548.13
6029.40
2269 SAME AS ITEM 2264 BUT 150 MM DIA. 910.13 1001.14 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.095 DAY 350.00 1433.25
114 FITTER/PLUMBER 2.05 DAY 400.00 820.00
115 JUNIOR FITTER 2.05 DAY 350.00 717.50
274 SPUN YARN 2.34 KG. 60.50 141.57
275 PIG LEAD 39.78 KG. 130.00 5171.40
276 FUEL(WOOD) 0.468 QTL. 700.00 327.60
Sundries.. L.S. 489.98
9101.30
Add for contractor's profit @ 10 % 910.13
10011.43
2270 SAME AS ITEM 2264 BUT 250 MM DIA. 1521.07 1673.18 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.215 DAY 350.00 2175.25
114 FITTER/PLUMBER 3.108 DAY 400.00 1243.20
115 JUNIOR FITTER 3.108 DAY 350.00 1087.80
274 SPUN YARN 3.955 KG. 60.50 239.28
275 PIG LEAD 68.93 KG. 130.00 8960.90
276 FUEL(WOOD) 0.735 QTL. 700.00 514.50
Sundries.. L.S. 989.78
15210.71
Add for contractor's profit @ 10 % 1521.07
16731.78
2271 SAME AS ITEM 2264 BUT 300 MM DIA. 1770.04 1947.04 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.96 DAY 350.00 2436.00
114 FITTER/PLUMBER 3.48 DAY 400.00 1392.00
115 JUNIOR FITTER 3.48 DAY 350.00 1218.00
274 SPUN YARN 5.568 KG. 60.50 336.86
275 PIG LEAD 83.52 KG. 130.00 10857.60
276 FUEL(WOOD) 0.87 QTL. 700.00 609.00
Sundries.. L.S. 850.90
17700.36
Add for contractor's profit @ 10 % 1770.04
19470.40
2273 SAME AS ITEM 2264 BUT 400 MM DIA. 2463.65 2710.01 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10.44 DAY 350.00 3654.00
114 FITTER/PLUMBER 5.22 DAY 400.00 2088.00
115 JUNIOR FITTER 5.22 DAY 350.00 1827.00
274 SPUN YARN 8.7 KG. 60.50 526.35
275 PIG LEAD 110.2 KG. 130.00 14326.00
276 FUEL(WOOD) 1.276 QTL. 700.00 893.20
Sundries.. L.S. 1321.93
24636.48
Add for contractor's profit @ 10 % 2463.65
27100.13
2274 SAME AS ITEM 2264 BUT 450 MM DIA. 3252.97 3578.26 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.4 DAY 350.00 3990.00
114 FITTER/PLUMBER 5.7 DAY 400.00 2280.00
115 JUNIOR FITTER 5.7 DAY 350.00 1995.00
274 SPUN YARN 10.88 KG. 60.50 658.24
275 PIG LEAD 159.6 KG. 130.00 20748.00
276 FUEL(WOOD) 1.482 QTL. 700.00 1037.40
Sundries.. L.S. 1821.02
32529.66
Add for contractor's profit @ 10 % 3252.97
35782.63
2275 SAME AS ITEM 2264 BUT 500 MM DIA. 3524.31 3876.74 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12.543 DAY 350.00 4390.05
114 FITTER/PLUMBER 6.27 DAY 400.00 2508.00
115 JUNIOR FITTER 6.27 DAY 350.00 2194.50
274 SPUN YARN 11.4 KG. 60.50 689.70
275 PIG LEAD 171 KG. 130.00 22230.00
276 FUEL(WOOD) 1.596 QTL. 700.00 1117.20
Sundries.. L.S. 2113.66
35243.11
Add for contractor's profit @ 10 % 3524.31
38767.42
2277 SAME AS ITEM 2262 BUT P3 QUALITY PIPES 80 MM DIA. 548.13 602.94 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.6 DAY 350.00 910.00
114 FITTER/PLUMBER 1.3 DAY 400.00 520.00
115 JUNIOR FITTER 1.3 DAY 350.00 455.00
274 SPUN YARN 1.3 KG. 60.50 78.65
275 PIG LEAD 23.4 KG. 130.00 3042.00
276 FUEL(WOOD) 0.26 QTL. 700.00 182.00
Sundries.. L.S. 293.62
5481.27
Add for contractor's profit @ 10 % 548.13
6029.40
2278 SAME AS ITEM 2263 BUT 100 MM DIA. 661.21 727.33 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.125 DAY 350.00 1093.75
114 FITTER/PLUMBER 1.563 DAY 400.00 625.20
115 JUNIOR FITTER 1.563 DAY 350.00 547.05
274 SPUN YARN 2.25 KG. 60.50 136.13
275 PIG LEAD 27.5 KG. 130.00 3575.00
276 FUEL(WOOD) 0.375 QTL. 700.00 262.50
Sundries.. L.S. 372.51
6612.14
Add for contractor's profit @ 10 % 661.21
7273.35
2279 SAME AS ITEM 2264 BUT 150 MM DIA. 910.13 1001.14 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.095 DAY 350.00 1433.25
114 FITTER/PLUMBER 2.05 DAY 400.00 820.00
115 JUNIOR FITTER 2.05 DAY 350.00 717.50
274 SPUN YARN 2.34 KG. 60.50 141.57
275 PIG LEAD 39.78 KG. 130.00 5171.40
276 FUEL(WOOD) 0.468 QTL. 700.00 327.60
Sundries.. L.S. 489.98
9101.30
Add for contractor's profit @ 10 % 910.13
10011.43
2281 SAME AS ITEM 2264 BUT 300 MM DIA. 1831.07 2014.18 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7.2 DAY 350.00 2520.00
114 FITTER/PLUMBER 3.6 DAY 400.00 1440.00
115 JUNIOR FITTER 3.6 DAY 350.00 1260.00
274 SPUN YARN 5.76 KG. 60.50 348.48
275 PIG LEAD 86.4 KG. 130.00 11232.00
276 FUEL(WOOD) 0.9 QTL. 700.00 630.00
Sundries.. L.S. 880.24
18310.72
Add for contractor's profit @ 10 % 1831.07
20141.79
2282 SAME AS ITEM 2264 BUT 350 MM DIA. 2173.73 2391.10 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8.47 DAY 350.00 2964.50
114 FITTER/PLUMBER 4.235 DAY 400.00 1694.00
115 JUNIOR FITTER 4.235 DAY 350.00 1482.25
274 SPUN YARN 7.26 KG. 60.50 439.23
275 PIG LEAD 101.64 KG. 130.00 13213.20
276 FUEL(WOOD) 1.15 QTL. 700.00 805.00
Sundries.. L.S. 1139.08
21737.26
Add for contractor's profit @ 10 % 2173.73
23910.99
2283 SAME AS ITEM 2264 BUT 400 MM DIA. 2612.32 2873.55 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.07 DAY 350.00 3874.50
114 FITTER/PLUMBER 5.535 DAY 400.00 2214.00
115 JUNIOR FITTER 5.535 DAY 350.00 1937.25
274 SPUN YARN 9.225 KG. 60.50 558.11
275 PIG LEAD 116.85 KG. 130.00 15190.50
276 FUEL(WOOD) 1.353 QTL. 700.00 947.10
Sundries.. L.S. 1401.71
26123.17
Add for contractor's profit @ 10 % 2612.32
28735.49
2287 SAME AS ITEM 2284 BUT 100 TO 150 MM DIA. 75.00 82.50 /CUT
Details of cost for 10 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
Sundries.. L.S. 49.98
749.98
Add for contractor's profit @ 10 % 75.00
824.98
2288 CUTTING 50-100 MM DIA A.C. PIPE INCLUDING SHAPING & FINISHING THE 60.05 66.06 /CUT
ENDS.
Details of cost for 10 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
Sundries.. L.S. 38.02
600.52
Add for contractor's profit @ 10 % 60.05
660.57
2289 SAME AS ITEM 2288 BUT 125 OR 150 MM DIA. 80.00 88.00 /CUT
Details of cost for 10 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 50.02
800.02
Add for contractor's profit @ 10 % 80.00
880.02
2291 SAME AS ITEM 2288 BUT 300 MM DIA. 160.01 176.01 /CUT
Details of cost for 10 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
Sundries.. L.S. 100.05
1600.05
Add for contractor's profit @ 10 % 160.00
1760.05
2292 CUTTING C.I. (SPUN) PIPES (CLASS LA AND A) OR SPECIALS INCLUDING 200.40 220.44 /CUT
SHAPING & FINISHING THE ENDS 80 TO 300 MM DIA.
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.167 DAY 350.00 58.45
114 FITTER/PLUMBER 0.167 DAY 400.00 66.80
Sundries.. L.S. 75.15
200.40
Add for contractor's profit @ 10 % 20.04
220.44
2293 SAME AS ITEM 2292 BUT 350 TO 750 MM DIA. 660.00 726.00 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 110.00
660.00
Add for contractor's profit @ 10 % 66.00
726.00
2294 SAME AS ITEM 2292 BUT 800 TO 1000 MM DIA. 1533.00 1686.30 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
108 HAMMER MAN 0.625 DAY 350.00 218.75
114 FITTER/PLUMBER 1.125 DAY 400.00 450.00
Sundries.. L.S. 164.25
1533.00
Add for contractor's profit @ 10 % 153.30
1686.30
2295 SAME AS ITEM 2292 BUT 1100 TO 1200 MM DIA. 2468.40 2715.24 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
108 HAMMER MAN 1 DAY 350.00 350.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
Sundries.. L.S. 268.40
2468.40
Add for contractor's profit @ 10 % 246.84
2715.24
2297 SAME AS 2296 BUT 450 TO 600 MM DIA. 1149.98 1264.98 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 399.98
1149.98
Add for contractor's profit @ 10 % 115.00
1264.98
2298 SAME AS 2296 BUT 700 TO 900 MM DIA. 2350.05 2585.05 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 2 DAY 400.00 800.00
Sundries.. L.S. 850.05
2350.05
Add for contractor's profit @ 10 % 235.00
2585.05
2299 SAME AS 2296 BUT 1100 TO 1200 MM DIA. 3499.88 3849.87 /CUT
Details of cost for 1 /CUT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
Sundries.. L.S. 1249.88
3499.88
Add for contractor's profit @ 10 % 349.99
3849.87
2300 MAKING CONNECTION WITH EXISTING M.S. GALVANISED MAINS UPTO 25 MM 600.00 660.00 /CONN
DIA.
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 225.00
600.00
Add for contractor's profit @ 10 % 60.00
660.00
2303 SAME AS ITEM 2300 BUT 100 TO 150 MM DIA. 1949.96 2144.96 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
Sundries.. L.S. 824.96
1949.96
Add for contractor's profit @ 10 % 195.00
2144.96
2304 CUTTING EXISTING A.C. MAINS 50 TO 125 MM DIA., MAKING CONNECTION, 1649.96 1814.96 /CONN
BAILING OUT OF WATER ETC.
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
Sundries.. L.S. 199.96
1649.96
Add for contractor's profit @ 10 % 165.00
1814.96
2305 SAME AS ITEM 2304 BUT 150 TO 300 MM DIA. 2729.25 3002.17 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 229.25
2729.25
Add for contractor's profit @ 10 % 272.92
3002.17
2306 CUTTING OF EXISTING 80 TO 150 MM DIA. S & S OR FLANGED C.I. RUNNING 1320.00 1452.00 /CONN
MAINS, MAKING CONNECTION, BAILING OUT OF WATER ETC.
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 220.00
1320.00
Add for contractor's profit @ 10 % 132.00
1452.00
2307 SAME AS ITEM 2306 BUT 200 TO 300 MM DIA. 3146.41 3461.05 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 1.125 DAY 400.00 450.00
115 JUNIOR FITTER 1.125 DAY 350.00 393.75
Sundries.. L.S. 902.66
3146.41
Add for contractor's profit @ 10 % 314.64
3461.05
2309 SAME AS ITEM 2306 BUT 500 TO 600 MM DIA. 6636.43 7300.07 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 3 DAY 400.00 1200.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
Sundries.. L.S. 2986.43
6636.43
Add for contractor's profit @ 10 % 663.64
7300.07
2310 SAME AS ITEM 2306 BUT 700 TO 750 MM DIA. 8880.88 9768.97 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 4.25 DAY 400.00 1700.00
115 JUNIOR FITTER 4.25 DAY 350.00 1487.50
Sundries.. L.S. 3593.38
8880.88
Add for contractor's profit @ 10 % 888.09
9768.97
2311 SAME AS ITEM 2306 BUT 800 TO 1000 MM DIA. 13101.38 14411.52 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
114 FITTER/PLUMBER 7 DAY 400.00 2800.00
115 JUNIOR FITTER 7 DAY 350.00 2450.00
Sundries.. L.S. 4351.38
13101.38
Add for contractor's profit @ 10 % 1310.14
14411.52
2312 SAME AS ITEM 2306 BUT 1100 TO 12000 MM DIA. 15405.71 16946.28 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
114 FITTER/PLUMBER 10 DAY 400.00 4000.00
115 JUNIOR FITTER 10 DAY 350.00 3500.00
Sundries.. L.S. 5105.71
15405.71
Add for contractor's profit @ 10 % 1540.57
16946.28
2313 DISMANTLING 15 MM DIA. SCREWED & SOCKETED M.S. GALVANISED PIPES, 42.57 46.83 /RM
SPECIALS & FITTINGS INCLUDING TAKEN OUT FROM INTERNAL WORKS.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
115 JUNIOR FITTER 1.5 DAY 350.00 525.00
Sundries.. L.S. 52.06
1277.06
Add for contractor's profit @ 10 % 127.71
1404.77
2318 SAME AS ITEM 2313 BUT TAKEN OUT FROM TRENCHES 15 MM DIA. 15.54 17.09 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
Sundries.. L.S. 28.61
466.11
Add for contractor's profit @ 10 % 46.61
512.72
2327 SAME AS ITEM 2318 BUT 125 MM DIA. 151.55 166.71 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9 DAY 350.00 3150.00
115 JUNIOR FITTER 3.5 DAY 350.00 1225.00
Sundries.. L.S. 171.50
4546.50
Add for contractor's profit @ 10 % 454.65
5001.15
2328 SAME AS ITEM 2318 BUT 150 MM DIA. 180.78 198.85 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11 DAY 350.00 3850.00
115 JUNIOR FITTER 4 DAY 350.00 1400.00
Sundries.. L.S. 173.25
5423.25
Add for contractor's profit @ 10 % 542.32
5965.57
2329 TAKING OUT 50 OR 80 MM DIA. A.C. PR. PIPES, SPECIALS & FITTINGS 16.62 18.28 /RM
(EXCLUDING DISMANTLING & REMOVAL OF DETACHABLE JOINTS.)
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
115 JUNIOR FITTER 0.063 DAY 350.00 22.05
Sundries.. L.S. 39.06
498.61
Add for contractor's profit @ 10 % 49.86
548.47
2330 SAME AS ITEM 2329 BUT 100 MM DIA. 20.23 22.26 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
115 JUNIOR FITTER 0.125 DAY 350.00 43.75
Sundries.. L.S. 38.28
607.03
Add for contractor's profit @ 10 % 60.70
667.73
2331 SAME AS ITEM 2329 BUT 125 MM DIA. 23.91 26.30 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.75 DAY 350.00 612.50
115 JUNIOR FITTER 0.125 DAY 350.00 43.75
Sundries.. L.S. 61.10
717.35
Add for contractor's profit @ 10 % 71.74
789.09
2333 SAME AS ITEM 2329 BUT 200 MM DIA. 32.19 35.41 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.25 DAY 350.00 787.50
115 JUNIOR FITTER 0.25 DAY 350.00 87.50
Sundries.. L.S. 90.74
965.74
Add for contractor's profit @ 10 % 96.57
1062.31
2334 SAME AS ITEM 2329 BUT 250 MM DIA. 40.14 44.15 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.75 DAY 350.00 962.50
115 JUNIOR FITTER 0.313 DAY 350.00 109.55
Sundries.. L.S. 132.08
1204.13
Add for contractor's profit @ 10 % 120.41
1324.54
2335 SAME AS ITEM 2329 BUT 300 MM DIA. 48.26 53.08 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.25 DAY 350.00 1137.50
115 JUNIOR FITTER 0.429 DAY 350.00 150.15
Sundries.. L.S. 160.05
1447.70
Add for contractor's profit @ 10 % 144.77
1592.47
2336 DISANMTLING OF LEAD CAULKED JOINTS OF 80 - 300 MM DIA. C.I. PIPES, 403.65 444.01 /JNT
SPECIALS AND FITTINGS.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
276 FUEL(WOOD) 2.8 QTL. 700.00 1960.00
Sundries.. L.S. 326.48
4036.48
Add for contractor's profit @ 10 % 403.65
4440.13
2337 SAME AS ITEM 2336 BUT 350 - 600 MM DIA. 920.43 1012.47 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
276 FUEL(WOOD) 8.4 QTL. 700.00 5880.00
Sundries.. L.S. 524.27
9204.27
Add for contractor's profit @ 10 % 920.43
10124.70
2339 SAME AS ITEM 2336 BUT 1000 - 1200 MM DIA. 2892.19 3181.41 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
115 JUNIOR FITTER 7 DAY 350.00 2450.00
276 FUEL(WOOD) 27.6 QTL. 700.00 19320.00
Sundries.. L.S. 1551.88
28921.88
Add for contractor's profit @ 10 % 2892.19
31814.07
2340 DISMANTLING FLANGED JOINTS OF 80 MM DIA. C.I. PIPES, SPECIALS & 118.69 130.56 /JNT
FITTINGS.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 136.92
1186.92
Add for contractor's profit @ 10 % 118.69
1305.61
2341 SAME AS ITEM 2340 BUT 100 - 200 MM DIA. 232.83 256.11 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
115 JUNIOR FITTER 4 DAY 350.00 1400.00
Sundries.. L.S. 228.27
2328.27
Add for contractor's profit @ 10 % 232.83
2561.10
2342 SAME AS ITEM 2340 BUT 250 - 300 MM DIA. 342.41 376.65 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
115 JUNIOR FITTER 6 DAY 350.00 2100.00
Sundries.. L.S. 274.05
3424.05
Add for contractor's profit @ 10 % 342.40
3766.45
2343 SAME AS ITEM 2340 BUT 350 - 400 MM DIA. 451.96 497.16 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
115 JUNIOR FITTER 8 DAY 350.00 2800.00
Sundries.. L.S. 319.62
4519.62
Add for contractor's profit @ 10 % 451.96
4971.58
2345 SAME AS ITEM 2340 BUT 700 - 800 MM DIA. 680.21 748.23 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
115 JUNIOR FITTER 12 DAY 350.00 4200.00
Sundries.. L.S. 502.11
6802.11
Add for contractor's profit @ 10 % 680.21
7482.32
2346 SAME AS ITEM 2340 BUT 900 - 1000 MM DIA. 798.95 878.84 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
115 JUNIOR FITTER 14 DAY 350.00 4900.00
Sundries.. L.S. 639.45
7989.45
Add for contractor's profit @ 10 % 798.94
8788.39
2347 DISMANTLING OF CEMENT & LEAD CAULKED JOINTS OF 200 MM DIA. STEEL 411.33 452.46 /JNT
CYLINDER R.C.C. PIPES & SPECIALS.
Details of cost for 10 /JNT
102 MASON/STONE MASON 2.25 DAY 425.00 956.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
115 JUNIOR FITTER 0.875 DAY 350.00 306.25
276 FUEL(WOOD) 1.7 QTL. 700.00 1190.00
Sundries.. L.S. 260.81
4113.31
Add for contractor's profit @ 10 % 411.33
4524.64
2348 SAME AS ITEM 2347 BUT 250 MM DIA. 494.80 544.28 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 2.75 DAY 425.00 1168.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
115 JUNIOR FITTER 1.125 DAY 350.00 393.75
276 FUEL(WOOD) 2.4 QTL. 700.00 1680.00
Sundries.. L.S. 305.48
4947.98
Add for contractor's profit @ 10 % 494.80
5442.78
2350 SAME AS ITEM 2347 BUT 350 MM DIA. 680.01 748.02 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 4 DAY 425.00 1700.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
276 FUEL(WOOD) 3.5 QTL. 700.00 2450.00
Sundries.. L.S. 462.64
6800.14
Add for contractor's profit @ 10 % 680.01
7480.15
2351 SAME AS ITEM 2347 BUT 400 MM DIA. 713.86 785.25 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 4 DAY 425.00 1700.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
115 JUNIOR FITTER 1.5 DAY 350.00 525.00
276 FUEL(WOOD) 3.8 QTL. 700.00 2660.00
Sundries.. L.S. 503.60
7138.60
Add for contractor's profit @ 10 % 713.86
7852.46
2352 SAME AS ITEM 2347 BUT 450 MM DIA. 887.99 976.79 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 5 DAY 425.00 2125.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
276 FUEL(WOOD) 5.3 QTL. 700.00 3710.00
Sundries.. L.S. 594.86
8879.86
Add for contractor's profit @ 10 % 887.99
9767.85
2353 SAME AS ITEM 2347 BUT 500 MM DIA. 1020.77 1122.85 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
276 FUEL(WOOD) 5.7 QTL. 700.00 3990.00
Sundries.. L.S. 692.69
10207.69
Add for contractor's profit @ 10 % 1020.77
11228.46
2355 SAME AS ITEM 2347 BUT 700 MM DIA. 1488.55 1637.41 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
115 JUNIOR FITTER 4 DAY 350.00 1400.00
276 FUEL(WOOD) 9 QTL. 700.00 6300.00
Sundries.. L.S. 985.51
14885.51
Add for contractor's profit @ 10 % 1488.55
16374.06
2356 SAME AS ITEM 2347 BUT 900 MM DIA. 1993.13 2192.44 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 10 DAY 425.00 4250.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
115 JUNIOR FITTER 6 DAY 350.00 2100.00
276 FUEL(WOOD) 12.3 QTL. 700.00 8610.00
Sundries.. L.S. 1471.26
19931.26
Add for contractor's profit @ 10 % 1993.13
21924.39
2357 SAME AS ITEM 2347 BUT 1100 MM DIA. 2455.72 2701.29 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
115 JUNIOR FITTER 8 DAY 350.00 2800.00
276 FUEL(WOOD) 15 QTL. 700.00 10500.00
Sundries.. L.S. 1957.16
24557.16
Add for contractor's profit @ 10 % 2455.72
27012.88
2358 SAME AS ITEM 2347 BUT 1200 MM DIA. 2834.81 3118.30 /JNT
Details of cost for 10 /JNT
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
115 JUNIOR FITTER 9 DAY 350.00 3150.00
276 FUEL(WOOD) 17.7 QTL. 700.00 12390.00
Sundries.. L.S. 1958.14
28348.14
Add for contractor's profit @ 10 % 2834.81
31182.95
2360 SAME AS ITEM 2359 BUT 100 MM DIA. 25.92 28.51 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.7 DAY 350.00 595.00
115 JUNIOR FITTER 0.21 DAY 350.00 73.50
Sundries.. L.S. 109.17
777.67
Add for contractor's profit @ 10 % 77.77
855.44
2361 SAME AS ITEM 2359 BUT 125 MM DIA. 33.52 36.87 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.2 DAY 350.00 770.00
115 JUNIOR FITTER 0.27 DAY 350.00 94.50
Sundries.. L.S. 141.17
1005.67
Add for contractor's profit @ 10 % 100.57
1106.24
2362 SAME AS ITEM 2359 BUT 150 MM DIA. 41.80 45.98 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.74 DAY 350.00 959.00
115 JUNIOR FITTER 0.34 DAY 350.00 119.00
Sundries.. L.S. 176.04
1254.04
Add for contractor's profit @ 10 % 125.40
1379.44
2363 SAME AS ITEM 2359 BUT 200 MM DIA. 61.07 67.18 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
Sundries.. L.S. 257.20
1832.20
Add for contractor's profit @ 10 % 183.22
2015.42
2364 SAME AS ITEM 2359 BUT 250 MM DIA. 82.25 90.47 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5.39 DAY 350.00 1886.50
115 JUNIOR FITTER 0.67 DAY 350.00 234.50
Sundries.. L.S. 346.36
2467.36
Add for contractor's profit @ 10 % 246.74
2714.10
2366 SAME AS ITEM 2359 BUT C.I. FLANGED PIPE (CLASS A) 80 MM DIA. 23.07 25.38 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.51 DAY 350.00 528.50
115 JUNIOR FITTER 0.19 DAY 350.00 66.50
Sundries.. L.S. 97.16
692.16
Add for contractor's profit @ 10 % 69.22
761.38
2367 SAME AS ITEM 2366 BUT 100 MM DIA. 29.18 32.10 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.91 DAY 350.00 668.50
115 JUNIOR FITTER 0.24 DAY 350.00 84.00
Sundries.. L.S. 122.88
875.38
Add for contractor's profit @ 10 % 87.54
962.92
2368 SAME AS ITEM 2366 BUT 125 MM DIA. 37.73 41.50 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.47 DAY 350.00 864.50
115 JUNIOR FITTER 0.31 DAY 350.00 108.50
Sundries.. L.S. 158.89
1131.89
Add for contractor's profit @ 10 % 113.19
1245.08
2369 SAME AS ITEM 2366 BUT 150 MM DIA. 47.23 51.95 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.09 DAY 350.00 1081.50
115 JUNIOR FITTER 0.39 DAY 350.00 136.50
Sundries.. L.S. 198.90
1416.90
Add for contractor's profit @ 10 % 141.69
1558.59
2370 SAME AS ITEM 2366 BUT 200 MM DIA. 68.13 74.94 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4.46 DAY 350.00 1561.00
115 JUNIOR FITTER 0.56 DAY 350.00 196.00
Sundries.. L.S. 286.92
2043.92
Add for contractor's profit @ 10 % 204.39
2248.31
2372 SAME AS ITEM 2366 BUT 300 MM DIA. 118.08 129.88 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7.73 DAY 350.00 2705.50
115 JUNIOR FITTER 0.97 DAY 350.00 339.50
Sundries.. L.S. 497.25
3542.25
Add for contractor's profit @ 10 % 354.22
3896.47
2373 SAME AS ITEM 2359 BUT STEEL CYLINDER R.C.C. PIPES (CLASS III) 200 MM 97.45 107.19 /RM
DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.38 DAY 350.00 2233.00
115 JUNIOR FITTER 0.8 DAY 350.00 280.00
Sundries.. L.S. 410.37
2923.37
Add for contractor's profit @ 10 % 292.34
3215.71
2374 SAME AS ITEM 2373 BUT 250 MM DIA. 148.07 162.88 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.7 DAY 350.00 3395.00
115 JUNIOR FITTER 1.21 DAY 350.00 423.50
Sundries.. L.S. 623.56
4442.06
Add for contractor's profit @ 10 % 444.21
4886.27
2375 SAME AS ITEM 2373 BUT 300 MM DIA. 173.45 190.79 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11.36 DAY 350.00 3976.00
115 JUNIOR FITTER 1.42 DAY 350.00 497.00
Sundries.. L.S. 730.44
5203.44
Add for contractor's profit @ 10 % 520.34
5723.78
2376 SAME AS ITEM 2359 BUT C.I. S & S PIPES (SPUN CLASS LA LEAD YARN 137.79 151.56 /RM
JOINTED OR RUBBER RING GASKET TYTON JOINTED) 350 MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.31 DAY 350.00 3258.50
115 JUNIOR FITTER 1.45 DAY 350.00 507.50
Sundries.. L.S. 367.56
4133.56
Add for contractor's profit @ 10 % 413.36
4546.92
2378 SAME AS ITEM 2376 BUT 450 MM DIA. 201.94 222.13 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.64 DAY 350.00 4774.00
115 JUNIOR FITTER 2.13 DAY 350.00 745.50
Sundries.. L.S. 538.70
6058.20
Add for contractor's profit @ 10 % 605.82
6664.02
2379 SAME AS ITEM 2376 BUT 500 MM DIA. 236.90 260.59 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
115 JUNIOR FITTER 2.5 DAY 350.00 875.00
Sundries.. L.S. 631.96
7106.96
Add for contractor's profit @ 10 % 710.70
7817.66
2380 SAME AS ITEM 2376 BUT 600 MM DIA. 315.40 346.94 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 21.3 DAY 350.00 7455.00
115 JUNIOR FITTER 3.33 DAY 350.00 1165.50
Sundries.. L.S. 841.36
9461.86
Add for contractor's profit @ 10 % 946.19
10408.05
2381 SAME AS ITEM 2376 BUT 700 MM DIA. 407.34 448.07 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 27.51 DAY 350.00 9628.50
115 JUNIOR FITTER 4.3 DAY 350.00 1505.00
Sundries.. L.S. 1086.63
12220.13
Add for contractor's profit @ 10 % 1222.01
13442.14
2382 SAME AS ITEM 2376 BUT 750 MM DIA. 456.13 501.74 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 30.81 DAY 350.00 10783.50
115 JUNIOR FITTER 4.81 DAY 350.00 1683.50
Sundries.. L.S. 1216.78
13683.78
Add for contractor's profit @ 10 % 1368.38
15052.16
2384 SAME AS ITEM 2383 BUT 400 MM DIA. 188.24 207.06 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12.71 DAY 350.00 4448.50
115 JUNIOR FITTER 1.99 DAY 350.00 696.50
Sundries.. L.S. 502.15
5647.15
Add for contractor's profit @ 10 % 564.72
6211.87
2385 SAME AS ITEM 2383 BUT 450 MM DIA. 226.40 249.04 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15.29 DAY 350.00 5351.50
115 JUNIOR FITTER 2.39 DAY 350.00 836.50
Sundries.. L.S. 603.95
6791.95
Add for contractor's profit @ 10 % 679.20
7471.15
2386 SAME AS ITEM 2383 BUT 500 MM DIA. 263.66 290.03 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 17.81 DAY 350.00 6233.50
115 JUNIOR FITTER 2.78 DAY 350.00 973.00
Sundries.. L.S. 703.35
7909.85
Add for contractor's profit @ 10 % 790.98
8700.83
2387 SAME AS ITEM 2383 BUT 600 MM DIA. 352.79 388.07 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 23.83 DAY 350.00 8340.50
115 JUNIOR FITTER 3.72 DAY 350.00 1302.00
Sundries.. L.S. 941.11
10583.61
Add for contractor's profit @ 10 % 1058.36
11641.97
2388 SAME AS ITEM 2383 BUT 700 MM DIA. 458.56 504.42 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 30.93 DAY 350.00 10825.50
115 JUNIOR FITTER 4.88 DAY 350.00 1708.00
Sundries.. L.S. 1223.27
13756.77
Add for contractor's profit @ 10 % 1375.68
15132.45
2390 SAME AS ITEM 2376 BUT STEEL CYLINDER REINFORCED PIPE (CLAS III) 350 204.63 225.09 /RM
MM DIA.
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13.82 DAY 350.00 4837.00
115 JUNIOR FITTER 2.16 DAY 350.00 756.00
Sundries.. L.S. 545.88
6138.88
Add for contractor's profit @ 10 % 613.89
6752.77
2391 SAME AS ITEM 2390 BUT 400 MM DIA. 230.62 253.69 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15.58 DAY 350.00 5453.00
115 JUNIOR FITTER 2.43 DAY 350.00 850.50
Sundries.. L.S. 615.22
6918.72
Add for contractor's profit @ 10 % 691.87
7610.59
2392 SAME AS ITEM 2390 BUT 450 MM DIA. 308.86 339.75 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20.86 DAY 350.00 7301.00
115 JUNIOR FITTER 3.26 DAY 350.00 1141.00
Sundries.. L.S. 823.94
9265.94
Add for contractor's profit @ 10 % 926.59
10192.53
2393 SAME AS ITEM 2390 BUT 500 MM DIA. 368.79 405.67 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24.91 DAY 350.00 8718.50
115 JUNIOR FITTER 3.89 DAY 350.00 1361.50
Sundries.. L.S. 983.81
11063.81
Add for contractor's profit @ 10 % 1106.38
12170.19
2394 SAME AS ITEM 2390 BUT 600 MM DIA. 433.33 476.67 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 29.31 DAY 350.00 10258.50
115 JUNIOR FITTER 4.53 DAY 350.00 1585.50
Sundries.. L.S. 1155.97
12999.97
Add for contractor's profit @ 10 % 1300.00
14299.97
2396 SAME AS ITEM 2376 BUT 800 MM DIA. 565.97 622.56 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 36.04 DAY 350.00 12614.00
115 JUNIOR FITTER 8.19 DAY 350.00 2866.50
Sundries.. L.S. 1498.51
16979.01
Add for contractor's profit @ 10 % 1697.90
18676.91
2397 SAME AS ITEM 2376 BUT 900 MM DIA. 690.98 760.08 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 44 DAY 350.00 15400.00
115 JUNIOR FITTER 10 DAY 350.00 3500.00
Sundries.. L.S. 1829.52
20729.52
Add for contractor's profit @ 10 % 2072.95
22802.47
2398 SAME AS ITEM 2376 BUT 1000 MM DIA. 831.23 914.35 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 52.93 DAY 350.00 18525.50
115 JUNIOR FITTER 12.03 DAY 350.00 4210.50
Sundries.. L.S. 2200.84
24936.84
Add for contractor's profit @ 10 % 2493.68
27430.52
2399 SAME AS ITEM 2383 BUT 800 MM DIA. 598.60 658.46 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 38.11 DAY 350.00 13338.50
115 JUNIOR FITTER 8.67 DAY 350.00 3034.50
Sundries.. L.S. 1584.91
17957.91
Add for contractor's profit @ 10 % 1795.79
19753.70
2400 SAME AS ITEM 2383 BUT 900 MM DIA. 726.56 799.21 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 46.26 DAY 350.00 16191.00
115 JUNIOR FITTER 10.52 DAY 350.00 3682.00
Sundries.. L.S. 1923.71
21796.71
Add for contractor's profit @ 10 % 2179.67
23976.38
2402 SAME AS ITEM 2390 BUT 900 MM DIA. 658.48 724.33 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 41.93 DAY 350.00 14675.50
115 JUNIOR FITTER 9.53 DAY 350.00 3335.50
Sundries.. L.S. 1743.46
19754.46
Add for contractor's profit @ 10 % 1975.45
21729.91
2403 SAME AS ITEM 2376 BUT 1100 MM DIA. 1038.62 1142.48 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 64.65 DAY 350.00 22627.50
115 JUNIOR FITTER 14.73 DAY 350.00 5155.50
Sundries.. L.S. 3375.63
31158.63
Add for contractor's profit @ 10 % 3115.86
34274.49
2404 SAME AS ITEM 2376 BUT 1200 MM DIA. 1211.20 1332.32 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 75.35 DAY 350.00 26372.50
115 JUNIOR FITTER 17.22 DAY 350.00 6027.00
Sundries.. L.S. 3936.54
36336.04
Add for contractor's profit @ 10 % 3633.60
39969.64
2405 SAME AS ITEM 2390 BUT 1100 MM DIA. 1002.38 1102.62 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 62.36 DAY 350.00 21826.00
115 JUNIOR FITTER 14.25 DAY 350.00 4987.50
Sundries.. L.S. 3257.84
30071.34
Add for contractor's profit @ 10 % 3007.13
33078.47
2406 SAME AS ITEM 2390 BUT 1200 MM DIA. 1288.92 1417.81 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 80.18 DAY 350.00 28063.00
115 JUNIOR FITTER 18.33 DAY 350.00 6415.50
Sundries.. L.S. 4189.14
38667.64
Add for contractor's profit @ 10 % 3866.76
42534.40
2408 SAME AS ITEM 2407 BUT 125 - 150 MM DIA. 42.22 46.44 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.667 DAY 350.00 233.45
115 JUNIOR FITTER 0.167 DAY 350.00 58.45
Sundries.. L.S. 130.27
422.17
Add for contractor's profit @ 10 % 42.22
464.39
2409 SAME AS ITEM 2407 BUT 200 MM DIA. 52.50 57.75 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
115 JUNIOR FITTER 0.25 DAY 350.00 87.50
Sundries.. L.S. 175.00
525.00
Add for contractor's profit @ 10 % 52.50
577.50
2410 SAME AS ITEM 2407 BUT 250 MM DIA. 61.64 67.80 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
115 JUNIOR FITTER 0.25 DAY 350.00 87.50
Sundries.. L.S. 178.85
616.35
Add for contractor's profit @ 10 % 61.64
677.99
2411 SAME AS ITEM 2407 BUT 300 MM DIA. 74.34 81.78 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
115 JUNIOR FITTER 0.375 DAY 350.00 131.25
Sundries.. L.S. 174.66
743.41
Add for contractor's profit @ 10 % 74.34
817.75
2412 SAME AS ITEM 2407 BUT 350 MM DIA. 90.42 99.46 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
115 JUNIOR FITTER 0.5 DAY 350.00 175.00
Sundries.. L.S. 204.19
904.19
Add for contractor's profit @ 10 % 90.42
994.61
2414 SAME AS ITEM 2407 BUT 450 MM DIA. 116.46 128.11 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
115 JUNIOR FITTER 0.625 DAY 350.00 218.75
Sundries.. L.S. 245.86
1164.61
Add for contractor's profit @ 10 % 116.46
1281.07
2415 SAME AS ITEM 2407 BUT 500 MM DIA. 135.19 148.71 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.25 DAY 350.00 787.50
115 JUNIOR FITTER 0.75 DAY 350.00 262.50
Sundries.. L.S. 301.88
1351.88
Add for contractor's profit @ 10 % 135.19
1487.07
2416 SAME AS ITEM 2407 BUT 600 MM DIA. 150.01 165.02 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.5 DAY 350.00 875.00
115 JUNIOR FITTER 0.75 DAY 350.00 262.50
Sundries.. L.S. 362.64
1500.14
Add for contractor's profit @ 10 % 150.01
1650.15
2417 SAME AS ITEM 2407 BUT 700 MM DIA. 166.08 182.69 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.75 DAY 350.00 962.50
115 JUNIOR FITTER 1 DAY 350.00 350.00
Sundries.. L.S. 348.34
1660.84
Add for contractor's profit @ 10 % 166.08
1826.92
2418 SAME AS ITEM 2407 BUT 750 MM DIA. 180.84 198.92 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
Sundries.. L.S. 408.38
1808.38
Add for contractor's profit @ 10 % 180.84
1989.22
2420 SAME AS ITEM 2419 BUT 125 - 150 MM DIA. 42.22 46.44 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.667 DAY 350.00 233.45
115 JUNIOR FITTER 0.167 DAY 350.00 58.45
Sundries.. L.S. 130.27
422.17
Add for contractor's profit @ 10 % 42.22
464.39
2421 SAME AS ITEM 2419 BUT 200 MM DIA. 52.50 57.75 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
115 JUNIOR FITTER 0.25 DAY 350.00 87.50
Sundries.. L.S. 175.00
525.00
Add for contractor's profit @ 10 % 52.50
577.50
2422 SAME AS ITEM 2419 BUT 250 MM DIA. 61.64 67.80 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
115 JUNIOR FITTER 0.25 DAY 350.00 87.50
Sundries.. L.S. 178.85
616.35
Add for contractor's profit @ 10 % 61.64
677.99
2423 SAME AS ITEM 2419 BUT 300 MM DIA. 74.34 81.78 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.25 DAY 350.00 437.50
115 JUNIOR FITTER 0.375 DAY 350.00 131.25
Sundries.. L.S. 174.66
743.41
Add for contractor's profit @ 10 % 74.34
817.75
2424 DISMANTLING OF C.I. M.H. COVER WITH FRAMES 455 - 610 MM CLEAR SIZE. 826.69 909.36 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
Sundries.. L.S. 51.69
826.69
Add for contractor's profit @ 10 % 82.67
909.36
2426 SAME AS ITEM 2425 BUT UPTO 150 MM SIZE. 144.96 159.46 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.167 DAY 425.00 70.98
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.167 DAY 350.00 58.45
Sundries.. L.S. 15.53
144.96
Add for contractor's profit @ 10 % 14.50
159.46
2428 MAKING FERRULE CONNECTION IN 50 - 300 MM DIA. A.C. EXISTING MAINS 715.00 786.50 /CONN
WITH 10 OR 15 MM SIZE FERRULE.
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 165.00
715.00
Add for contractor's profit @ 10 % 71.50
786.50
2429 INSERTING & FIXING WATER METER OR FITTING SUCH AS STOP COCKS, 490.01 539.01 /CONN
WHEEL VALVE ETC. UPTO 25 MM DIA. IN EXISTING M.S. GALVANISED PIPES.
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 115.01
490.01
Add for contractor's profit @ 10 % 49.00
539.01
2432 SAME AS ITEM 2429 BUT 100-150 MM DIA. 1800.00 1980.00 /CONN
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 1.5 DAY 400.00 600.00
Sundries.. L.S. 675.00
1800.00
Add for contractor's profit @ 10 % 180.00
1980.00
2433 FIXING OF 10 - 15 MM SIZE BRASS FERRULE IN EXISTING C.I. OR M.S. 600.00 660.00 /CONN
GALVANISED PIPE (50 MM & ABOVE).
Details of cost for 1 /CONN
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 225.00
600.00
Add for contractor's profit @ 10 % 60.00
660.00
2436 CARTING & PLACING OF C.I. M.H. HEAVY DUTTY 500 - 560 MM (CLEAR 730.00 803.00 /NO.
OPENING) SIZE.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.25 DAY 425.00 106.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
Sundries.. L.S. 273.75
730.00
Add for contractor's profit @ 10 % 73.00
803.00
2438 SAME AS ITEM 2346 BUT LIGHT DUTTY RECTANGULAR. 297.37 327.11 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.2 DAY 425.00 85.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.333 DAY 350.00 116.55
Sundries.. L.S. 95.82
297.37
Add for contractor's profit @ 10 % 29.74
327.11
2439 SAME AS ITEM 2436 BUT MEDIUM OR LIGHT DUTY FOR STANDARD SIZE (250 - 250.70 275.77 /NO.
455 MM).
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.166 DAY 425.00 70.55
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
Sundries.. L.S. 92.65
250.70
Add for contractor's profit @ 10 % 25.07
275.77
2440 CARTAGE & FIXING OF C.I. OR M.S. SURFACE BOX UPTO 200 MM DIA. 184.48 202.93 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.125 DAY 425.00 53.13
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.125 DAY 350.00 43.75
Sundries.. L.S. 87.60
184.48
Add for contractor's profit @ 10 % 18.45
202.93
2441 MAKING I.S.S. THREADS IN 15 - 25 MM DIA. GALVANISED M.S. PIPES. 27.95 30.74 /END
Details of cost for 10 /END
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.375 DAY 350.00 131.25
115 JUNIOR FITTER 0.375 DAY 350.00 131.25
Sundries.. L.S. 16.96
279.46
Add for contractor's profit @ 10 % 27.95
307.41
2444 SAME AS ITEM 2441 BUT 100 - 150 MM DIA. 147.00 161.70 /END
Details of cost for 10 /END
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 70.00
1470.00
Add for contractor's profit @ 10 % 147.00
1617.00
2445 CARTAGE & FIXING OF SLUICE VALVE OR REFLUX VALVE 50 - 125 MM DIA. 325.88 358.47 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 138.38
325.88
Add for contractor's profit @ 10 % 32.59
358.47
2446 SAME AS ITEM BUT 150 - 200 MM DIA. 529.99 582.99 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 154.99
529.99
Add for contractor's profit @ 10 % 53.00
582.99
2447 SAME AS ITEM BUT 250 - 300 MM DIA. 1044.94 1149.43 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.5 DAY 350.00 525.00
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
Sundries.. L.S. 219.94
1044.94
Add for contractor's profit @ 10 % 104.49
1149.43
2448 SAME AS ITEM BUT 350 - 400 MM DIA. 1430.00 1573.00 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 330.00
1430.00
Add for contractor's profit @ 10 % 143.00
1573.00
2450 CARTING & FIXING OF 20 - 25 SCREWED DOWN AIR VALVE IN C.I. MAINS. 550.01 605.01 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
Sundries.. L.S. 175.01
550.01
Add for contractor's profit @ 10 % 55.00
605.01
2451 SAME AS ITEM 2450 BUT 65 - 80 MM DIA. FLANGED AIR VALVE OR FIRE 264.17 290.59 /NO.
HYDRANT OVER EXISTING FLANGED TEE.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.125 DAY 350.00 43.75
114 FITTER/PLUMBER 0.125 DAY 400.00 50.00
334 NUT WITH BOLT 16*65MM. 0.4 KG. 92.00 36.80
358 3MM THICK RUBBER INSERTION 0.1 KG. 99.00 9.90
Sundries.. L.S. 123.72
264.17
Add for contractor's profit @ 10 % 26.42
290.59
2452 BORING OF 150 MM DIA. BY PALM & PRESSURE METHOD 0-30 M. DEEP. 426.67 469.33 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24 DAY 350.00 8400.00
106 BHISTI 4 DAY 350.00 1400.00
134 BORER(BORING MECHANIC) 4 DAY 400.00 1600.00
137 ASSISTANT BORER 4 DAY 350.00 1400.00
Sundries.. L.S. 0.00
12800.00
Add for contractor's profit @ 10 % 1280.00
14080.00
2453 SAME AS ITEM 2452 BUT 31-50 M. DEEP. 473.33 520.67 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 28 DAY 350.00 9800.00
106 BHISTI 4 DAY 350.00 1400.00
134 BORER(BORING MECHANIC) 4 DAY 400.00 1600.00
137 ASSISTANT BORER 4 DAY 350.00 1400.00
Sundries.. L.S. 0.00
14200.00
Add for contractor's profit @ 10 % 1420.00
15620.00
2455 SAME AS ITEM 2454 BUT 31-50 M. DEEP. 710.00 781.00 /RM
Details of cost for 30 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 42 DAY 350.00 14700.00
106 BHISTI 6 DAY 350.00 2100.00
134 BORER(BORING MECHANIC) 6 DAY 400.00 2400.00
137 ASSISTANT BORER 6 DAY 350.00 2100.00
Sundries.. L.S. 0.00
21300.00
Add for contractor's profit @ 10 % 2130.00
23430.00
2456 LOWERING OF HAND PUMP ASSEMBLY 0-45 M. DEEP. 15.93 17.52 /RM
Details of cost for 45 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.3333 DAY 350.00 466.66
134 BORER(BORING MECHANIC) 0.3333 DAY 400.00 133.32
137 ASSISTANT BORER 0.3333 DAY 350.00 116.66
Sundries.. L.S. 0.00
716.63
Add for contractor's profit @ 10 % 71.66
788.29
2458 HIRE CHARGES OF BORING T & P AND CARTAGE OF HAND PUMP MATERIAL /L.S.
BY TRACTOR TROLLEY.
Details of cost for 0 /L.S.
Sundries.. L.S.
3002 EXCAVATION 1.5 - 3.0M DEEP IN ORDINARY SOIL. 252.06 277.27 /CUM
Details of cost for 100 /CUM
101 MISTRY 0.75 DAY 460.00 345.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 46 DAY 350.00 16100.00
104 COOLIE 21 DAY 350.00 7350.00
105 BLACK SMITH 0.75 DAY 425.00 318.75
Sundries.. L.S. 1092.35
25206.10
Add for contractor's profit @ 10 % 2520.61
27726.71
3003 EXCAVATION 3.0 - 4.5M DEEP IN ORDINARY SOIL. 316.74 348.42 /CUM
Details of cost for 100 /CUM
101 MISTRY 1 DAY 460.00 460.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 54 DAY 350.00 18900.00
104 COOLIE 28 DAY 350.00 9800.00
105 BLACK SMITH 1 DAY 425.00 425.00
106 BHISTI 1 DAY 350.00 350.00
Sundries.. L.S. 1739.22
31674.22
Add for contractor's profit @ 10 % 3167.42
34841.64
3004 EXCAVATION 4.5 - 6.0M DEEP IN ORDINARY SOIL. 369.65 406.61 /CUM
Details of cost for 100 /CUM
101 MISTRY 2.5 DAY 460.00 1150.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 56 DAY 350.00 19600.00
104 COOLIE 35 DAY 350.00 12250.00
105 BLACK SMITH 1 DAY 425.00 425.00
106 BHISTI 1.75 DAY 350.00 612.50
Sundries.. L.S. 2927.22
36964.72
Add for contractor's profit @ 10 % 3696.47
40661.19
3005 EXCAVATION 6.0 - 7.5M DEEP IN ORDINARY SOIL. 483.45 531.79 /CUM
Details of cost for 100 /CUM
101 MISTRY 3 DAY 460.00 1380.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 70 DAY 350.00 24500.00
104 COOLIE 50 DAY 350.00 17500.00
105 BLACK SMITH 1.5 DAY 425.00 637.50
106 BHISTI 2.5 DAY 350.00 875.00
Sundries.. L.S. 3452.23
48344.73
Add for contractor's profit @ 10 % 4834.47
53179.20
3007 EXCAVATION 0.0 - 1.5M DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, 29.95 32.95 /CUM
KANKAR ETC.(EXTRA OVER ITEM 3001).
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 332.81
2995.31
Add for contractor's profit @ 10 % 299.53
3294.84
3008 EXCAVATION 1.5 - 3.0M DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, 48.75 53.63 /CUM
KANKAR ETC.(EXTRA OVER ITEM 3002).
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 11 DAY 350.00 3850.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 812.50
4875.00
Add for contractor's profit @ 10 % 487.50
5362.50
3009 EXCAVATION 3.0 - 4.5M DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, 68.28 75.11 /CUM
KANKAR ETC.(EXTRA OVER ITEM 3003).
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 1365.62
6828.12
Add for contractor's profit @ 10 % 682.81
7510.93
3010 EXCAVATION 4.5 - 6.0M DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, 87.06 95.77 /CUM
KANKAR ETC.(EXTRA OVER ITEM 3004).
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 2193.41
8705.91
Add for contractor's profit @ 10 % 870.59
9576.50
3011 EXCAVATION 6.0 - 7.5M DEEP IN SOIL MIXED WITH MOORUM, SHINGLE, 105.88 116.46 /CUM
KANKAR ETC.(EXTRA OVER ITEM 3005).
Details of cost for 100 /CUM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 21 DAY 350.00 7350.00
105 BLACK SMITH 0.5 DAY 425.00 212.50
Sundries.. L.S. 3025.00
10587.50
Add for contractor's profit @ 10 % 1058.75
11646.25
3013 EXCAVATION 0.0 - 1.5M DEEP IN HARD ROCK BY CHISELLING. 1199.25 1319.18 /CUM
Details of cost for 100 /CUM
101 MISTRY 6 DAY 460.00 2760.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 160 DAY 350.00 56000.00
104 COOLIE 65 DAY 350.00 22750.00
105 BLACK SMITH 6 DAY 425.00 2550.00
116 SPECIAL LABOUR FOR ROCK CUTTING 60 DAY 400.00 24000.00
117 CHISELLERS 25 DAY 400.00 10000.00
Sundries.. L.S. 1865.35
119925.35
Add for contractor's profit @ 10 % 11992.54
131917.89
3014 EXCAVATION 1.5 - 3.0M DEEP IN HARD ROCK BY CHISELLING. 1316.04 1447.65 /CUM
Details of cost for 100 /CUM
101 MISTRY 7.75 DAY 460.00 3565.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 160 DAY 350.00 56000.00
104 COOLIE 65 DAY 350.00 22750.00
105 BLACK SMITH 7.75 DAY 425.00 3293.75
116 SPECIAL LABOUR FOR ROCK CUTTING 72 DAY 400.00 28800.00
117 CHISELLERS 30 DAY 400.00 12000.00
Sundries.. L.S. 5195.40
131604.15
Add for contractor's profit @ 10 % 13160.42
144764.57
3015 EXCAVATION 3.0 - 4.5M DEEP IN HARD ROCK BY CHISELLING. 1453.71 1599.08 /CUM
Details of cost for 100 /CUM
101 MISTRY 9.5 DAY 460.00 4370.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 167 DAY 350.00 58450.00
104 COOLIE 65 DAY 350.00 22750.00
105 BLACK SMITH 9.5 DAY 425.00 4037.50
116 SPECIAL LABOUR FOR ROCK CUTTING 84 DAY 400.00 33600.00
117 CHISELLERS 35 DAY 400.00 14000.00
Sundries.. L.S. 8163.85
145371.35
Add for contractor's profit @ 10 % 14537.14
159908.49
3017 EXCAVATION 6.0 - 7.5M DEEP IN HARD ROCK BY CHISELLING. 1829.45 2012.40 /CUM
Details of cost for 100 /CUM
101 MISTRY 14 DAY 460.00 6440.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 190 DAY 350.00 66500.00
104 COOLIE 65 DAY 350.00 22750.00
105 BLACK SMITH 11 DAY 425.00 4675.00
116 SPECIAL LABOUR FOR ROCK CUTTING 120 DAY 400.00 48000.00
117 CHISELLERS 50 DAY 400.00 20000.00
Sundries.. L.S. 14580.41
182945.41
Add for contractor's profit @ 10 % 18294.54
201239.95
3018 EXCAVATION 7.5 - 9.0M DEEP IN HARD ROCK BY CHISELLING. 2057.36 2263.10 /CUM
Details of cost for 100 /CUM
101 MISTRY 16 DAY 460.00 7360.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 210 DAY 350.00 73500.00
104 COOLIE 65 DAY 350.00 22750.00
105 BLACK SMITH 13 DAY 425.00 5525.00
116 SPECIAL LABOUR FOR ROCK CUTTING 140 DAY 400.00 56000.00
117 CHISELLERS 55 DAY 400.00 22000.00
Sundries.. L.S. 18601.22
205736.22
Add for contractor's profit @ 10 % 20573.62
226309.84
3019 EXCAVATION 0.0 - 1.5 DEEP IN MEDIUM ROCK BY CHISELLING OR BY MILD 971.07 1068.17 /CUM
BLASTING.
Details of cost for 100 /CUM
101 MISTRY 5 DAY 460.00 2300.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 140 DAY 350.00 49000.00
104 COOLIE 60 DAY 350.00 21000.00
105 BLACK SMITH 5 DAY 425.00 2125.00
116 SPECIAL LABOUR FOR ROCK CUTTING 35 DAY 400.00 14000.00
117 CHISELLERS 15 DAY 400.00 6000.00
Sundries.. L.S. 2681.67
97106.67
Add for contractor's profit @ 10 % 9710.67
106817.34
3021 EXCAVATION 3.0 - 4.5M DEEP IN MEDIUM ROCK BY CHISELLING OR BY MILD 1177.04 1294.74 /CUM
BLASTING.
Details of cost for 100 /CUM
101 MISTRY 8 DAY 460.00 3680.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 147 DAY 350.00 51450.00
104 COOLIE 60 DAY 350.00 21000.00
105 BLACK SMITH 6.75 DAY 425.00 2868.75
116 SPECIAL LABOUR FOR ROCK CUTTING 60 DAY 400.00 24000.00
117 CHISELLERS 21 DAY 400.00 8400.00
Sundries.. L.S. 6305.17
117703.92
Add for contractor's profit @ 10 % 11770.39
129474.31
3022 EXCAVATION 4.5 - 6.0M DEEP IN MEDIUM ROCK BY CHISELLING OR BY MILD 1307.32 1438.05 /CUM
BLASTING.
Details of cost for 100 /CUM
101 MISTRY 10 DAY 460.00 4600.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 155 DAY 350.00 54250.00
104 COOLIE 60 DAY 350.00 21000.00
105 BLACK SMITH 7.5 DAY 425.00 3187.50
116 SPECIAL LABOUR FOR ROCK CUTTING 73 DAY 400.00 29200.00
117 CHISELLERS 24 DAY 400.00 9600.00
Sundries.. L.S. 8894.14
130731.64
Add for contractor's profit @ 10 % 13073.16
143804.80
3023 EXCAVATION 6.0 - 7.5M DEEP IN MEDIUM ROCK BY CHISELLING OR BY MILD 1434.42 1577.86 /CUM
BLASTING.
Details of cost for 100 /CUM
101 MISTRY 11 DAY 460.00 5060.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 165 DAY 350.00 57750.00
104 COOLIE 60 DAY 350.00 21000.00
105 BLACK SMITH 8 DAY 425.00 3400.00
116 SPECIAL LABOUR FOR ROCK CUTTING 85 DAY 400.00 34000.00
117 CHISELLERS 27 DAY 400.00 10800.00
Sundries.. L.S. 11432.07
143442.07
Add for contractor's profit @ 10 % 14344.21
157786.28
3025 EXCAVATION 0.0 - 1.5M DEEP IN DECOMPOSED OR SOFT ROCK BY 888.02 976.82 /CUM
CHISELLING.
Details of cost for 100 /CUM
101 MISTRY 3 DAY 460.00 1380.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 130 DAY 350.00 45500.00
104 COOLIE 60 DAY 350.00 21000.00
105 BLACK SMITH 3 DAY 425.00 1275.00
116 SPECIAL LABOUR FOR ROCK CUTTING 30 DAY 400.00 12000.00
117 CHISELLERS 15 DAY 400.00 6000.00
Sundries.. L.S. 1647.23
88802.23
Add for contractor's profit @ 10 % 8880.22
97682.45
3026 EXCAVATION 1.5 - 3.0M DEEP IN DECOMPOSED OR SOFT ROCK BY 1022.91 1125.20 /CUM
CHISELLING.
Details of cost for 100 /CUM
101 MISTRY 3 DAY 460.00 1380.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 138 DAY 350.00 48300.00
104 COOLIE 75 DAY 350.00 26250.00
105 BLACK SMITH 3.75 DAY 425.00 1593.75
116 SPECIAL LABOUR FOR ROCK CUTTING 36 DAY 400.00 14400.00
117 CHISELLERS 19 DAY 400.00 7600.00
Sundries.. L.S. 2766.76
102290.51
Add for contractor's profit @ 10 % 10229.05
112519.56
3027 EXCAVATION 3.0 - 4.5M DEEP IN DECOMPOSED OR SOFT ROCK BY 1174.60 1292.05 /CUM
CHISELLING.
Details of cost for 100 /CUM
101 MISTRY 3.75 DAY 460.00 1725.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 155 DAY 350.00 54250.00
104 COOLIE 84 DAY 350.00 29400.00
105 BLACK SMITH 4.25 DAY 425.00 1806.25
116 SPECIAL LABOUR FOR ROCK CUTTING 45 DAY 400.00 18000.00
117 CHISELLERS 20 DAY 400.00 8000.00
Sundries.. L.S. 4278.25
117459.50
Add for contractor's profit @ 10 % 11745.95
129205.45
3029 EXCAVATION 6.0 - 7.5M DEEP IN DECOMPOSED OR SOFT ROCK BY 1653.58 1818.93 /CUM
CHISELLING.
Details of cost for 100 /CUM
101 MISTRY 6 DAY 460.00 2760.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 195 DAY 350.00 68250.00
104 COOLIE 120 DAY 350.00 42000.00
105 BLACK SMITH 8 DAY 425.00 3400.00
116 SPECIAL LABOUR FOR ROCK CUTTING 70 DAY 400.00 28000.00
117 CHISELLERS 25 DAY 400.00 10000.00
Sundries.. L.S. 10947.67
165357.67
Add for contractor's profit @ 10 % 16535.77
181893.44
3030 EXCAVATION 7.5 - 9.0M DEEP IN DECOMPOSED OR SOFT ROCK BY 2038.44 2242.28 /CUM
CHISELLING.
Details of cost for 100 /CUM
101 MISTRY 8 DAY 460.00 3680.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 218 DAY 350.00 76300.00
104 COOLIE 160 DAY 350.00 56000.00
105 BLACK SMITH 9 DAY 425.00 3825.00
116 SPECIAL LABOUR FOR ROCK CUTTING 90 DAY 400.00 36000.00
117 CHISELLERS 30 DAY 400.00 12000.00
Sundries.. L.S. 16038.55
203843.55
Add for contractor's profit @ 10 % 20384.36
224227.91
3031 BAILING OUT OR PUMPING OUT SUBSOIL WATER. 93.23 102.55 /CUM
Details of cost for 100 /CUM
111 MECHANIC 3.5 DAY 425.00 1487.50
112 HELPER 3.5 DAY 350.00 1225.00
Sundries.. L.S. 6610.36
9322.86
Add for contractor's profit @ 10 % 932.29
10255.15
3033 CLOSE TIMBERING IN TRENCHES 3.0 - 6.0M DEEP. 617.51 679.27 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 22.5 DAY 350.00 7875.00
107 CARPENTER 11.25 DAY 460.00 5175.00
298 SAL BALLIES(EUCALYPTUS)125MM 10.8 RM. 192.50 2079.00
300 SAL WOOD WALLERS 0.304 CUM. 57200.00 17388.80
309 PLANKS(COUNTRY WOOD) 1.35 CUM. 16500.00 22275.00
Sundries.. L.S. 783.54
55576.34
Add for contractor's profit @ 10 % 5557.63
61133.97
3034 CLOSE TIMBERING IN TRENCHES 6.0 - 9.0M DEEP. 736.88 810.57 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 30 DAY 350.00 10500.00
107 CARPENTER 15 DAY 460.00 6900.00
299 SAL BALLIES(EUCALYPTUS)150MM 10.8 RM. 220.00 2376.00
300 SAL WOOD WALLERS 0.405 CUM. 57200.00 23166.00
309 PLANKS(COUNTRY WOOD) 1.35 CUM. 16500.00 22275.00
Sundries.. L.S. 1102.17
66319.17
Add for contractor's profit @ 10 % 6631.92
72951.09
3035 CLOSE TIMBERING LEFT IN TRENCHES (UNUSED TIMBERING) 0.0 - 3.0M DEEP. 2594.68 2854.15 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
107 CARPENTER 5 DAY 460.00 2300.00
297 SAL BALLIES(EUCALYPTUS)100MM 72 RM. 165.00 11880.00
300 SAL WOOD WALLERS 1.69 CUM. 57200.00 96668.00
309 PLANKS(COUNTRY WOOD) 7.2 CUM. 16500.00 118800.00
Sundries.. L.S. 373.04
233521.04
Add for contractor's profit @ 10 % 23352.10
256873.14
3036 CLOSE TIMBERING LEFT IN TRENCHES (UNUSED TIMBERING) 3.0 - 6.0M DEEP. 3193.72 3513.10 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
107 CARPENTER 7.5 DAY 460.00 3450.00
298 SAL BALLIES(EUCALYPTUS)125MM 72 RM. 192.50 13860.00
300 SAL WOOD WALLERS 2.025 CUM. 57200.00 115830.00
309 PLANKS(COUNTRY WOOD) 9 CUM. 16500.00 148500.00
Sundries.. L.S. 545.09
287435.09
Add for contractor's profit @ 10 % 28743.51
316178.60
3038 CLOSE TIMBERING LEFT IN TRENCHES (USED TIMBERING) 0.0 - 3.0M DEEP. 1078.96 1186.86 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
107 CARPENTER 5 DAY 460.00 2300.00
297 SAL BALLIES(EUCALYPTUS)100MM 28.8 RM. 165.00 4752.00
300 SAL WOOD WALLERS 0.676 CUM. 57200.00 38667.20
309 PLANKS(COUNTRY WOOD) 2.88 CUM. 16500.00 47520.00
Sundries.. L.S. 367.61
97106.81
Add for contractor's profit @ 10 % 9710.68
106817.49
3039 CLOSE TIMBERING LEFT IN TRENCHES (USED TIMBERING) 3.0 - 6.0M DEEP. 1339.07 1472.97 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
107 CARPENTER 7.5 DAY 460.00 3450.00
298 SAL BALLIES(EUCALYPTUS)125MM 28.8 RM. 192.50 5544.00
300 SAL WOOD WALLERS 0.81 CUM. 57200.00 46332.00
309 PLANKS(COUNTRY WOOD) 3.6 CUM. 16500.00 59400.00
Sundries.. L.S. 539.89
120515.89
Add for contractor's profit @ 10 % 12051.59
132567.48
3040 CLOSE TIMBERING LEFT IN TRENCHES (USED TIMBERING) 6.0 - 9.0M DEEP. 1553.57 1708.93 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
107 CARPENTER 10 DAY 460.00 4600.00
299 SAL BALLIES(EUCALYPTUS)150MM 28.8 RM. 220.00 6336.00
300 SAL WOOD WALLERS 1.08 CUM. 57200.00 61776.00
309 PLANKS(COUNTRY WOOD) 3.6 CUM. 16500.00 59400.00
Sundries.. L.S. 709.47
139821.47
Add for contractor's profit @ 10 % 13982.15
153803.62
3041 OPEN TIMBERING IN TRENCHES 0.0 - 3.0M DEEP. 328.72 361.59 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
107 CARPENTER 6 DAY 460.00 2760.00
297 SAL BALLIES(EUCALYPTUS)100MM 10.8 RM. 165.00 1782.00
300 SAL WOOD WALLERS 0.254 CUM. 57200.00 14528.80
309 PLANKS(COUNTRY WOOD) 0.36 CUM. 16500.00 5940.00
Sundries.. L.S. 373.90
29584.70
Add for contractor's profit @ 10 % 2958.47
32543.17
3043 OPEN TIMBERING IN TRENCHES 6.0 - 9.0M DEEP. 529.93 582.92 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24 DAY 350.00 8400.00
107 CARPENTER 12 DAY 460.00 5520.00
299 SAL BALLIES(EUCALYPTUS)150MM 10.8 RM. 220.00 2376.00
300 SAL WOOD WALLERS 0.405 CUM. 57200.00 23166.00
309 PLANKS(COUNTRY WOOD) 0.45 CUM. 16500.00 7425.00
Sundries.. L.S. 806.46
47693.46
Add for contractor's profit @ 10 % 4769.35
52462.81
3044 OPEN TIMBERING LEFT IN TRENCHES (UNUSED TIMBERING) 0.0 - 3.0M DEEP. 1700.19 1870.21 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
107 CARPENTER 4 DAY 460.00 1840.00
297 SAL BALLIES(EUCALYPTUS)100MM 72 RM. 165.00 11880.00
300 SAL WOOD WALLERS 1.69 CUM. 57200.00 96668.00
309 PLANKS(COUNTRY WOOD) 2.4 CUM. 16500.00 39600.00
Sundries.. L.S. 229.18
153017.18
Add for contractor's profit @ 10 % 15301.72
168318.90
3045 OPEN TIMBERING LEFT IN TRENCHES (UNUSED TIMBERING) 3.0 - 6.0M DEEP. 2072.26 2279.49 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
107 CARPENTER 6 DAY 460.00 2760.00
298 SAL BALLIES(EUCALYPTUS)125MM 72 RM. 192.50 13860.00
300 SAL WOOD WALLERS 2.025 CUM. 57200.00 115830.00
309 PLANKS(COUNTRY WOOD) 3 CUM. 16500.00 49500.00
Sundries.. L.S. 353.68
186503.68
Add for contractor's profit @ 10 % 18650.37
205154.05
3046 OPEN TIMBERING LEFT IN TRENCHES (UNUSED TIMBERING) 6.0 - 9.0M DEEP. 2549.95 2804.94 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
107 CARPENTER 8 DAY 460.00 3680.00
299 SAL BALLIES(EUCALYPTUS)150MM 72 RM. 220.00 15840.00
300 SAL WOOD WALLERS 2.7 CUM. 57200.00 154440.00
309 PLANKS(COUNTRY WOOD) 3 CUM. 16500.00 49500.00
Sundries.. L.S. 435.21
229495.21
Add for contractor's profit @ 10 % 22949.52
252444.73
3048 OPEN TIMBERING LEFT IN TRENCHES (USED TIMBERING) 3.0 - 6.0M DEEP. 877.75 965.53 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
107 CARPENTER 6 DAY 460.00 2760.00
298 SAL BALLIES(EUCALYPTUS)125MM 28.8 RM. 192.50 5544.00
300 SAL WOOD WALLERS 0.81 CUM. 57200.00 46332.00
309 PLANKS(COUNTRY WOOD) 1.2 CUM. 16500.00 19800.00
Sundries.. L.S. 361.73
78997.73
Add for contractor's profit @ 10 % 7899.77
86897.50
3049 OPEN TIMBERING LEFT IN TRENCHES (USED TIMBERING) 6.0 - 9.0M DEEP. 1084.88 1193.37 /SQM
Details of cost for 90 /SQM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 16 DAY 350.00 5600.00
107 CARPENTER 8 DAY 460.00 3680.00
299 SAL BALLIES(EUCALYPTUS)150MM 28.8 RM. 220.00 6336.00
300 SAL WOOD WALLERS 1.08 CUM. 57200.00 61776.00
309 PLANKS(COUNTRY WOOD) 1.2 CUM. 16500.00 19800.00
Sundries.. L.S. 447.08
97639.08
Add for contractor's profit @ 10 % 9763.91
107402.99
3050 SHEET PILING IN TRENCHES 0.0 - 3.0M DEEP (SCRAP VALUE OF SHEETS & 1948.35 2143.19 /SQM
ANGLES & SALVAGE VALUE OF TIMBER WILL BE DEDUCTED).
Details of cost for 5.969 /SQM
101 MISTRY 2 DAY 460.00 920.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
105 BLACK SMITH 0.25 DAY 425.00 106.25
107 CARPENTER 0.75 DAY 460.00 345.00
108 HAMMER MAN 0.25 DAY 350.00 87.50
299 SAL BALLIES(EUCALYPTUS)150MM 1.44 RM. 220.00 316.80
319 M.S.SHEETS 0.24 QTL. 3760.00 902.40
320 ANGLE IRON 0.109 QTL. 3700.00 403.30
Sundries.. L.S. 1548.48
11629.73
Add for contractor's profit @ 10 % 1162.97
12792.70
3052 SHEET PILING IN TRENCHES 6.0 - 9.0M DEEP (SCRAP VALUE OF SHEETS & 3541.08 3895.19 /SQM
ANGLES & SALVAGE VALUE OF TIMBER WILL BE DEDUCTED).
Details of cost for 5.969 /SQM
101 MISTRY 4 DAY 460.00 1840.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 40 DAY 350.00 14000.00
105 BLACK SMITH 0.25 DAY 425.00 106.25
107 CARPENTER 1.5 DAY 460.00 690.00
108 HAMMER MAN 0.25 DAY 350.00 87.50
299 SAL BALLIES(EUCALYPTUS)150MM 1.44 RM. 220.00 316.80
319 M.S.SHEETS 0.24 QTL. 3760.00 902.40
320 ANGLE IRON 0.109 QTL. 3700.00 403.30
Sundries.. L.S. 2790.46
21136.71
Add for contractor's profit @ 10 % 2113.67
23250.38
3053 LAYING, JOINTING 100MM DIA. STONE WARE GLAZED PIPE 0.0 - 1.5M DEEP. 252.26 277.49 /RM
Details of cost for 30 /RM
101 MISTRY 1 DAY 460.00 460.00
102 MASON/STONE MASON 4 DAY 425.00 1700.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 5 DAY 350.00 1750.00
106 BHISTI 1.5 DAY 350.00 525.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.105 CUM. 1395.00 146.48
251 CEMENT 0.35 BAG 370.00 129.50
274 SPUN YARN 2.05 KG. 60.50 124.03
374 CARTAGE OF STONEWARE GLAZED PIPE 4.23 QTL. 46.58 197.03
40-400MM DIA.
Sundries.. L.S. 1485.84
7567.87
Add for contractor's profit @ 10 % 756.79
8324.66
3055 LAYING, JOINTING 200MM DIA. STONE WARE GLAZED PIPE 0.0 - 1.5M DEEP. 380.61 418.68 /RM
Details of cost for 30 /RM
101 MISTRY 1.25 DAY 460.00 575.00
102 MASON/STONE MASON 7 DAY 425.00 2975.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
106 BHISTI 1.75 DAY 350.00 612.50
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.3 CUM. 1395.00 418.50
251 CEMENT 0.9 BAG 370.00 333.00
274 SPUN YARN 6.6 KG. 60.50 399.30
374 CARTAGE OF STONEWARE GLAZED PIPE 9.9 QTL. 46.58 461.14
40-400MM DIA.
Sundries.. L.S. 1794.00
11418.44
Add for contractor's profit @ 10 % 1141.84
12560.28
3056 LAYING, JOINTING 250MM DIA. STONE WARE GLAZED PIPE 0.0 - 1.5M DEEP. 454.56 500.02 /RM
Details of cost for 30 /RM
101 MISTRY 1.5 DAY 460.00 690.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.5 DAY 350.00 3325.00
106 BHISTI 2 DAY 350.00 700.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.6 CUM. 1395.00 837.00
251 CEMENT 1.7 BAG 370.00 629.00
274 SPUN YARN 8.17 KG. 60.50 494.29
374 CARTAGE OF STONEWARE GLAZED PIPE 15.6 QTL. 46.58 726.65
40-400MM DIA.
Sundries.. L.S. 1784.90
13636.83
Add for contractor's profit @ 10 % 1363.68
15000.51
3058 LAYING, JOINTING 350MM DIA. STONE WARE GLAZED PIPE 0.0 - 1.5M DEEP. 635.40 698.94 /RM
Details of cost for 30 /RM
101 MISTRY 2.25 DAY 460.00 1035.00
102 MASON/STONE MASON 11 DAY 425.00 4675.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 13 DAY 350.00 4550.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.8 CUM. 1395.00 1116.00
251 CEMENT 2.5 BAG 370.00 925.00
274 SPUN YARN 15.2 KG. 60.50 919.60
374 CARTAGE OF STONEWARE GLAZED PIPE 30 QTL. 46.58 1397.40
40-400MM DIA.
Sundries.. L.S. 2343.86
19061.86
Add for contractor's profit @ 10 % 1906.19
20968.05
3059 LAYING, JOINTING 400MM DIA. STONE WARE GLAZED PIPE 0.0 - 1.5M DEEP. 710.91 782.00 /RM
Details of cost for 30 /RM
101 MISTRY 2.5 DAY 460.00 1150.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 15 DAY 350.00 5250.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.9 CUM. 1395.00 1255.50
251 CEMENT 2.85 BAG 370.00 1054.50
274 SPUN YARN 18.35 KG. 60.50 1110.18
374 CARTAGE OF STONEWARE GLAZED PIPE 38.4 QTL. 46.58 1788.67
40-400MM DIA.
Sundries.. L.S. 2518.50
21327.35
Add for contractor's profit @ 10 % 2132.73
23460.08
3061 LAYING, JOINTING 250MM DIA. SEV PIPE 0.0 - 1.5M DEEP. 384.79 423.27 /RM
Details of cost for 30 /RM
101 MISTRY 1.25 DAY 460.00 575.00
102 MASON/STONE MASON 6.5 DAY 425.00 2762.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
106 BHISTI 1.5 DAY 350.00 525.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.48 CUM. 1395.00 669.60
251 CEMENT 1.36 BAG 370.00 503.20
274 SPUN YARN 6.54 KG. 60.50 395.67
374 CARTAGE OF STONEWARE GLAZED PIPE 15.6 QTL. 46.58 726.65
40-400MM DIA.
Sundries.. L.S. 1536.17
11543.79
Add for contractor's profit @ 10 % 1154.38
12698.17
3062 LAYING, JOINTING 300MM DIA. SEV PIPE 0.0 - 1.5M DEEP. 471.20 518.32 /RM
Details of cost for 30 /RM
101 MISTRY 1.5 DAY 460.00 690.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
106 BHISTI 2 DAY 350.00 700.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.52 CUM. 1395.00 725.40
251 CEMENT 1.6 BAG 370.00 592.00
274 SPUN YARN 9.36 KG. 60.50 566.28
374 CARTAGE OF STONEWARE GLAZED PIPE 23.7 QTL. 46.58 1103.95
40-400MM DIA.
Sundries.. L.S. 1808.46
14136.09
Add for contractor's profit @ 10 % 1413.61
15549.70
3063 LAYING, JOINTING OF STONE WARE OR SEV PIPE 1.5 - 3.0M DEEP (EXTRA 5.85%
OVER ITEMS 3053 TO 3062).
Details of cost for 0 5.85%
Sundries.. L.S.
Sundries.. L.S.
3065 LAYING, JOINTING OF STONE WARE OR SEV PIPE 4.5 - 6.0M DEEP (EXTRA 21.3%
OVER ITEMS 3053 TO 3062).
Details of cost for 0 21.3%
Sundries.. L.S.
3066 LAYING, JOINTING OF STONE WARE OR SEV PIPE 6.0 - 7.5M DEEP (EXTRA 30.6%
OVER ITEMS 3053 TO 3062).
Details of cost for 0 30.6%
Sundries.. L.S.
3067 LAYING, JOINTING OF STONE WARE OR SEV PIPE 7.5 - 9.0M DEEP (EXTRA 41.4%
OVER ITEMS 3053 TO 3062).
Details of cost for 0 41.4%
Sundries.. L.S.
3068 LAYING, JOINTING 100MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 181.09 199.20 /RM
Details of cost for 32 /RM
101 MISTRY 1 DAY 460.00 460.00
102 MASON/STONE MASON 2 DAY 425.00 850.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
106 BHISTI 1 DAY 350.00 350.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.05 CUM. 1395.00 69.75
251 CEMENT 0.69 BAG 370.00 255.30
274 SPUN YARN 1.17 KG. 60.50 70.79
381 CARTAGE OF R.C.C.NP2 PIPE 100-300MM 8.58 QTL. 20.62 176.92
DIA.
Sundries.. L.S. 1112.15
5794.90
Add for contractor's profit @ 10 % 579.49
6374.39
3070 LAYING, JOINTING 250MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 303.88 334.27 /RM
Details of cost for 32 /RM
101 MISTRY 1.5 DAY 460.00 690.00
102 MASON/STONE MASON 4 DAY 425.00 1700.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
106 BHISTI 2 DAY 350.00 700.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.08 CUM. 1395.00 111.60
251 CEMENT 1.04 BAG 370.00 384.80
274 SPUN YARN 2.42 KG. 60.50 146.41
381 CARTAGE OF R.C.C.NP2 PIPE 100-300MM 18.21 QTL. 20.62 375.49
DIA.
Sundries.. L.S. 1765.95
9724.25
Add for contractor's profit @ 10 % 972.43
10696.68
3071 LAYING, JOINTING 300MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 373.75 411.12 /RM
Details of cost for 32 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 5 DAY 425.00 2125.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
106 BHISTI 2 DAY 350.00 700.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.13 CUM. 1395.00 181.35
251 CEMENT 1.66 BAG 370.00 614.20
274 SPUN YARN 3.63 KG. 60.50 219.62
381 CARTAGE OF R.C.C.NP2 PIPE 100-300MM 26.26 QTL. 20.62 541.48
DIA.
Sundries.. L.S. 2108.25
11959.90
Add for contractor's profit @ 10 % 1195.99
13155.89
3073 LAYING, JOINTING 400MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 457.40 503.14 /RM
Details of cost for 32 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 12 DAY 350.00 4200.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.16 CUM. 1395.00 223.20
251 CEMENT 2.21 BAG 370.00 817.70
274 SPUN YARN 4.35 KG. 60.50 263.18
382 CARTAGE OF R.C.C. NP2 PIPE 350-700MM 36.3 QTL. 30.02 1089.73
DIA.
Sundries.. L.S. 2472.90
14636.70
Add for contractor's profit @ 10 % 1463.67
16100.37
3074 LAYING, JOINTING 450MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 539.76 593.74 /RM
Details of cost for 30 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 14 DAY 350.00 4900.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.19 CUM. 1395.00 265.05
251 CEMENT 2.6 BAG 370.00 962.00
274 SPUN YARN 4.63 KG. 60.50 280.12
382 CARTAGE OF R.C.C. NP2 PIPE 350-700MM 42.11 QTL. 30.02 1264.14
DIA.
Sundries.. L.S. 2951.49
16192.80
Add for contractor's profit @ 10 % 1619.28
17812.08
3076 LAYING, JOINTING 600MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 675.51 743.06 /RM
Details of cost for 30 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.28 CUM. 1395.00 390.60
251 CEMENT 3.7 BAG 370.00 1369.00
274 SPUN YARN 6.26 KG. 60.50 378.73
382 CARTAGE OF R.C.C. NP2 PIPE 350-700MM 63.32 QTL. 30.02 1900.87
DIA.
Sundries.. L.S. 3506.02
20265.22
Add for contractor's profit @ 10 % 2026.52
22291.74
3077 LAYING, JOINTING 700MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 745.41 819.95 /RM
Details of cost for 30 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.31 CUM. 1395.00 432.45
251 CEMENT 4.2 BAG 370.00 1554.00
274 SPUN YARN 7.08 KG. 60.50 428.34
382 CARTAGE OF R.C.C. NP2 PIPE 350-700MM 73.03 QTL. 30.02 2192.36
DIA.
Sundries.. L.S. 3910.01
22362.16
Add for contractor's profit @ 10 % 2236.22
24598.38
3079 LAYING, JOINTING 900MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 1069.03 1175.93 /RM
Details of cost for 30 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 26 DAY 350.00 9100.00
106 BHISTI 4 DAY 350.00 1400.00
113 WATCHMAN 4 DAY 350.00 1400.00
249 COARSE SAND(BADARPUR) 0.47 CUM. 1395.00 655.65
251 CEMENT 6.32 BAG 370.00 2338.40
274 SPUN YARN 8.99 KG. 60.50 543.90
383 CARTAGE OF R.C.C.NP2 PIPE 800-1800MM 117.13 QTL. 36.08 4226.05
DIA.
Sundries.. L.S. 5926.84
32070.84
Add for contractor's profit @ 10 % 3207.08
35277.92
3080 LAYING, JOINTING 1000MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 1189.99 1308.99 /RM
Details of cost for 30 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 28 DAY 350.00 9800.00
106 BHISTI 4 DAY 350.00 1400.00
113 WATCHMAN 4 DAY 350.00 1400.00
249 COARSE SAND(BADARPUR) 0.56 CUM. 1395.00 781.20
251 CEMENT 7.58 BAG 370.00 2804.60
274 SPUN YARN 9.8 KG. 60.50 592.90
383 CARTAGE OF R.C.C.NP2 PIPE 800-1800MM 143.23 QTL. 36.08 5167.74
DIA.
Sundries.. L.S. 6423.25
35699.69
Add for contractor's profit @ 10 % 3569.97
39269.66
3082 LAYING, JOINTING 1200MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 1566.10 1722.71 /RM
Details of cost for 30 /RM
101 MISTRY 4 DAY 460.00 1840.00
102 MASON/STONE MASON 18 DAY 425.00 7650.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 36 DAY 350.00 12600.00
106 BHISTI 5 DAY 350.00 1750.00
113 WATCHMAN 5 DAY 350.00 1750.00
249 COARSE SAND(BADARPUR) 0.78 CUM. 1395.00 1088.10
251 CEMENT 10.64 BAG 370.00 3936.80
274 SPUN YARN 11.71 KG. 60.50 708.46
383 CARTAGE OF R.C.C.NP2 PIPE 800-1800MM 202.63 QTL. 36.08 7310.89
DIA.
Sundries.. L.S. 8348.86
46983.11
Add for contractor's profit @ 10 % 4698.31
51681.42
3083 LAYING, JOINTING 1400MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 1881.08 2069.19 /RM
Details of cost for 30 /RM
101 MISTRY 5 DAY 460.00 2300.00
102 MASON/STONE MASON 20 DAY 425.00 8500.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 40 DAY 350.00 14000.00
106 BHISTI 6 DAY 350.00 2100.00
113 WATCHMAN 6 DAY 350.00 2100.00
249 COARSE SAND(BADARPUR) 1.07 CUM. 1395.00 1492.65
251 CEMENT 14.45 BAG 370.00 5346.50
274 SPUN YARN 14.4 KG. 60.50 871.20
383 CARTAGE OF R.C.C.NP2 PIPE 800-1800MM 272.5 QTL. 36.08 9831.80
DIA.
Sundries.. L.S. 9890.21
56432.36
Add for contractor's profit @ 10 % 5643.24
62075.60
3085 LAYING, JOINTING 1800MM DIA. RCC NP2 HUME PIPE 0.0 - 1.5M DEEP. 2873.48 3160.83 /RM
Details of cost for 30 /RM
101 MISTRY 8 DAY 460.00 3680.00
102 MASON/STONE MASON 30 DAY 425.00 12750.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 60 DAY 350.00 21000.00
106 BHISTI 10 DAY 350.00 3500.00
113 WATCHMAN 10 DAY 350.00 3500.00
249 COARSE SAND(BADARPUR) 1.62 CUM. 1395.00 2259.90
251 CEMENT 22.09 BAG 370.00 8173.30
274 SPUN YARN 21 KG. 60.50 1270.50
383 CARTAGE OF R.C.C.NP2 PIPE 800-1800MM 418.78 QTL. 36.08 15109.58
DIA.
Sundries.. L.S. 14961.09
86204.37
Add for contractor's profit @ 10 % 8620.44
94824.81
3086 LAYING, JOINTING RCC NP2 HUME PIPE 1.5 - 3.0M DEEP (EXTRA OVER ITEMS 6.45%
3068 TO 3085).
Details of cost for 0 6.45%
Sundries.. L.S.
3087 LAYING, JOINTING RCC NP2 HUME PIPE 3.0 - 4.5M DEEP (EXTRA OVER ITEMS 13.05%
3068 TO 3085).
Details of cost for 0 13.05%
Sundries.. L.S.
Sundries.. L.S.
3089 LAYING, JOINTING RCC NP2 HUME PIPE 6.0 - 7.5M DEEP (EXTRA OVER ITEMS 31.55%
3068 TO 3085).
Details of cost for 0 31.55%
Sundries.. L.S.
3090 LAYING, JOINTING RCC NP2 HUME PIPE 7.5 - 9.0M DEEP (EXTRA OVER ITEMS 46.15%
3068 TO 3085).
Details of cost for 0 46.15%
Sundries.. L.S.
3091 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 100MM DIA. HUME PIPE. 92.78 102.06 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0005 DAY 460.00 0.23
102 MASON/STONE MASON 0.043 DAY 425.00 18.28
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.055 DAY 350.00 19.25
104 COOLIE 0.013 DAY 350.00 4.55
105 BLACK SMITH 0.0005 DAY 425.00 0.21
106 BHISTI 0.006 DAY 350.00 2.10
244 BRICK BALLAST 40MM GAUGE 0.009 CUM. 1300.00 11.70
249 COARSE SAND(BADARPUR) 0.004 CUM. 1395.00 5.58
251 CEMENT 0.04 BAG 370.00 14.80
Sundries.. L.S. 16.08
92.78
Add for contractor's profit @ 10 % 9.28
102.06
3092 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 150MM DIA. HUME PIPE. 135.15 148.67 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0003 DAY 460.00 0.14
102 MASON/STONE MASON 0.048 DAY 425.00 20.40
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.068 DAY 350.00 23.80
104 COOLIE 0.023 DAY 350.00 8.05
105 BLACK SMITH 0.0008 DAY 425.00 0.34
106 BHISTI 0.011 DAY 350.00 3.85
244 BRICK BALLAST 40MM GAUGE 0.015 CUM. 1300.00 19.50
249 COARSE SAND(BADARPUR) 0.0075 CUM. 1395.00 10.46
251 CEMENT 0.07 BAG 370.00 25.90
Sundries.. L.S. 22.71
135.15
Add for contractor's profit @ 10 % 13.52
148.67
3094 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 300MM DIA. HUME PIPE. 299.66 329.63 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0023 DAY 460.00 1.06
102 MASON/STONE MASON 0.063 DAY 425.00 26.78
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.119 DAY 350.00 41.65
104 COOLIE 0.063 DAY 350.00 22.05
105 BLACK SMITH 0.0023 DAY 425.00 0.98
106 BHISTI 0.032 DAY 350.00 11.20
244 BRICK BALLAST 40MM GAUGE 0.042 CUM. 1300.00 54.60
249 COARSE SAND(BADARPUR) 0.021 CUM. 1395.00 29.30
251 CEMENT 0.19 BAG 370.00 70.30
Sundries.. L.S. 41.75
299.66
Add for contractor's profit @ 10 % 29.97
329.63
3095 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 350MM DIA. HUME PIPE. 338.53 372.38 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0026 DAY 460.00 1.20
102 MASON/STONE MASON 0.067 DAY 425.00 28.48
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.13 DAY 350.00 45.50
104 COOLIE 0.072 DAY 350.00 25.20
105 BLACK SMITH 0.0026 DAY 425.00 1.11
106 BHISTI 0.036 DAY 350.00 12.60
244 BRICK BALLAST 40MM GAUGE 0.048 CUM. 1300.00 62.40
249 COARSE SAND(BADARPUR) 0.024 CUM. 1395.00 33.48
251 CEMENT 0.22 BAG 370.00 81.40
Sundries.. L.S. 47.17
338.53
Add for contractor's profit @ 10 % 33.85
372.38
3097 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 450MM DIA. HUME PIPE. 410.75 451.83 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0031 DAY 460.00 1.43
102 MASON/STONE MASON 0.08 DAY 425.00 34.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.157 DAY 350.00 54.95
104 COOLIE 0.086 DAY 350.00 30.10
105 BLACK SMITH 0.0031 DAY 425.00 1.32
106 BHISTI 0.043 DAY 350.00 15.05
244 BRICK BALLAST 40MM GAUGE 0.058 CUM. 1300.00 75.40
249 COARSE SAND(BADARPUR) 0.028 CUM. 1395.00 39.06
251 CEMENT 0.26 BAG 370.00 96.20
Sundries.. L.S. 63.25
410.75
Add for contractor's profit @ 10 % 41.08
451.83
3098 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 500MM DIA. HUME PIPE. 542.93 597.22 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.004 DAY 460.00 1.84
102 MASON/STONE MASON 0.096 DAY 425.00 40.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.203 DAY 350.00 71.05
104 COOLIE 0.119 DAY 350.00 41.65
105 BLACK SMITH 0.004 DAY 425.00 1.70
106 BHISTI 0.06 DAY 350.00 21.00
244 BRICK BALLAST 40MM GAUGE 0.08 CUM. 1300.00 104.00
249 COARSE SAND(BADARPUR) 0.039 CUM. 1395.00 54.41
251 CEMENT 0.37 BAG 370.00 136.90
Sundries.. L.S. 69.58
542.93
Add for contractor's profit @ 10 % 54.29
597.22
3100 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 700MM DIA. HUME PIPE. 732.89 806.18 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0056 DAY 460.00 2.58
102 MASON/STONE MASON 0.142 DAY 425.00 60.35
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.286 DAY 350.00 100.10
104 COOLIE 0.16 DAY 350.00 56.00
105 BLACK SMITH 0.0056 DAY 425.00 2.38
106 BHISTI 0.08 DAY 350.00 28.00
244 BRICK BALLAST 40MM GAUGE 0.108 CUM. 1300.00 140.40
249 COARSE SAND(BADARPUR) 0.053 CUM. 1395.00 73.94
251 CEMENT 0.49 BAG 370.00 181.30
Sundries.. L.S. 87.85
732.89
Add for contractor's profit @ 10 % 73.29
806.18
3101 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 800MM DIA. HUME PIPE. 1118.10 1229.91 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.008 DAY 460.00 3.68
102 MASON/STONE MASON 0.275 DAY 425.00 116.88
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.486 DAY 350.00 170.10
104 COOLIE 0.24 DAY 350.00 84.00
105 BLACK SMITH 0.008 DAY 425.00 3.40
106 BHISTI 0.12 DAY 350.00 42.00
244 BRICK BALLAST 40MM GAUGE 0.159 CUM. 1300.00 206.70
249 COARSE SAND(BADARPUR) 0.078 CUM. 1395.00 108.81
251 CEMENT 0.73 BAG 370.00 270.10
Sundries.. L.S. 112.43
1118.10
Add for contractor's profit @ 10 % 111.81
1229.91
3103 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 1000MM DIA. HUME PIPE. 1724.65 1897.11 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.01 DAY 460.00 4.60
102 MASON/STONE MASON 0.781 DAY 425.00 331.93
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.041 DAY 350.00 364.35
104 COOLIE 0.29 DAY 350.00 101.50
105 BLACK SMITH 0.01 DAY 425.00 4.25
106 BHISTI 0.15 DAY 350.00 52.50
244 BRICK BALLAST 40MM GAUGE 0.196 CUM. 1300.00 254.80
249 COARSE SAND(BADARPUR) 0.096 CUM. 1395.00 133.92
251 CEMENT 0.894 BAG 370.00 330.78
Sundries.. L.S. 146.02
1724.65
Add for contractor's profit @ 10 % 172.46
1897.11
3104 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 1100MM DIA. HUME PIPE. 2262.07 2488.28 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.014 DAY 460.00 6.44
102 MASON/STONE MASON 1.04 DAY 425.00 442.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1.39 DAY 350.00 486.50
104 COOLIE 0.39 DAY 350.00 136.50
105 BLACK SMITH 0.014 DAY 425.00 5.95
106 BHISTI 0.19 DAY 350.00 66.50
244 BRICK BALLAST 40MM GAUGE 0.26 CUM. 1300.00 338.00
249 COARSE SAND(BADARPUR) 0.128 CUM. 1395.00 178.56
251 CEMENT 1.2 BAG 370.00 444.00
Sundries.. L.S. 157.62
2262.07
Add for contractor's profit @ 10 % 226.21
2488.28
3106 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 1400MM DIA. HUME PIPE. 3343.21 3677.53 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.0186 DAY 460.00 8.56
102 MASON/STONE MASON 1.805 DAY 425.00 767.13
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.267 DAY 350.00 793.45
104 COOLIE 0.517 DAY 350.00 180.95
105 BLACK SMITH 0.0186 DAY 425.00 7.91
106 BHISTI 0.258 DAY 350.00 90.30
244 BRICK BALLAST 40MM GAUGE 0.35 CUM. 1300.00 455.00
249 COARSE SAND(BADARPUR) 0.17 CUM. 1395.00 237.15
251 CEMENT 1.588 BAG 370.00 587.56
Sundries.. L.S. 215.21
3343.21
Add for contractor's profit @ 10 % 334.32
3677.53
3107 PRECAST CEMENT CONCRETE (1:3:6) SADDLE FOR 1600MM DIA. HUME PIPE. 3880.13 4268.14 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.022 DAY 460.00 10.12
102 MASON/STONE MASON 2.065 DAY 425.00 877.63
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.608 DAY 350.00 912.80
104 COOLIE 0.608 DAY 350.00 212.80
105 BLACK SMITH 0.022 DAY 425.00 9.35
106 BHISTI 0.3 DAY 350.00 105.00
244 BRICK BALLAST 40MM GAUGE 0.408 CUM. 1300.00 530.40
249 COARSE SAND(BADARPUR) 0.2 CUM. 1395.00 279.00
251 CEMENT 1.87 BAG 370.00 691.90
Sundries.. L.S. 251.13
3880.13
Add for contractor's profit @ 10 % 388.01
4268.14
3109 DISMANTLING 100MM DIA. OLD S.W. PIPE SEWERS. 58.50 64.35 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 1.5 DAY 425.00 637.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
Sundries.. L.S. 67.50
1755.00
Add for contractor's profit @ 10 % 175.50
1930.50
3110 DISMANTLING 150MM DIA. OLD S.W. PIPE SEWERS. 79.50 87.45 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 2 DAY 425.00 850.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
Sundries.. L.S. 135.00
2385.00
Add for contractor's profit @ 10 % 238.50
2623.50
3111 DISMANTLING 200MM DIA. OLD S.W. PIPE SEWERS. 110.01 121.01 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 2.5 DAY 425.00 1062.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
Sundries.. L.S. 137.88
3300.38
Add for contractor's profit @ 10 % 330.04
3630.42
3112 DISMANTLING 250MM DIA. OLD S.W. PIPE SEWERS. 140.25 154.28 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 3.5 DAY 425.00 1487.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 7 DAY 350.00 2450.00
Sundries.. L.S. 270.11
4207.61
Add for contractor's profit @ 10 % 420.76
4628.37
3114 DISMANTLING 400MM DIA. OLD S.W. PIPE SEWERS. 210.00 231.00 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 5 DAY 425.00 2125.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 10 DAY 350.00 3500.00
Sundries.. L.S. 675.00
6300.00
Add for contractor's profit @ 10 % 630.00
6930.00
3115 DISMANTLING 100MM DIA. RCC NP2 HUME PIPE SEWERS. 65.61 72.18 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 1.33 DAY 425.00 565.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.67 DAY 350.00 934.50
Sundries.. L.S. 468.67
1968.42
Add for contractor's profit @ 10 % 196.84
2165.26
3116 DISMANTLING 150MM DIA. RCC NP2 HUME PIPE SEWERS. 98.44 108.28 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 2 DAY 425.00 850.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
Sundries.. L.S. 703.12
2953.12
Add for contractor's profit @ 10 % 295.31
3248.43
3117 DISMANTLING 250MM DIA. RCC NP2 HUME PIPE SEWERS. 164.05 180.46 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 3.33 DAY 425.00 1415.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6.67 DAY 350.00 2334.50
Sundries.. L.S. 1171.80
4921.55
Add for contractor's profit @ 10 % 492.16
5413.71
3118 DISMANTLING 300MM DIA. RCC NP2 HUME PIPE SEWERS. 196.88 216.56 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 4 DAY 425.00 1700.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 8 DAY 350.00 2800.00
Sundries.. L.S. 1406.25
5906.25
Add for contractor's profit @ 10 % 590.62
6496.87
3120 DISMANTLING 450MM DIA. RCC NP2 HUME PIPE SEWERS. 342.20 376.42 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 6 DAY 425.00 2550.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
Sundries.. L.S. 1416.00
10266.00
Add for contractor's profit @ 10 % 1026.60
11292.60
3121 DISMANTLING 500MM DIA. RCC NP2 HUME PIPE SEWERS. 380.28 418.30 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 6.67 DAY 425.00 2834.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
Sundries.. L.S. 1573.56
11408.31
Add for contractor's profit @ 10 % 1140.83
12549.14
3122 DISMANTLING 600MM DIA. RCC NP2 HUME PIPE SEWERS. 456.27 501.89 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24 DAY 350.00 8400.00
Sundries.. L.S. 1888.00
13688.00
Add for contractor's profit @ 10 % 1368.80
15056.80
3123 DISMANTLING 700MM DIA. RCC NP2 HUME PIPE SEWERS. 684.40 752.84 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 12 DAY 425.00 5100.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 36 DAY 350.00 12600.00
Sundries.. L.S. 2832.00
20532.00
Add for contractor's profit @ 10 % 2053.20
22585.20
3124 DISMANTLING 800MM DIA. RCC NP2 HUME PIPE SEWERS. 782.06 860.27 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 13.71 DAY 425.00 5826.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 41.14 DAY 350.00 14399.00
Sundries.. L.S. 3236.12
23461.87
Add for contractor's profit @ 10 % 2346.19
25808.06
3126 DISMANTLING 1000MM DIA. RCC NP2 HUME PIPE SEWERS. 933.20 1026.52 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 16.36 DAY 425.00 6953.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 49.09 DAY 350.00 17181.50
Sundries.. L.S. 3861.52
27996.02
Add for contractor's profit @ 10 % 2799.60
30795.62
3127 DISMANTLING 1100MM DIA. RCC NP2 HUME PIPE SEWERS. 1026.60 1129.26 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 18 DAY 425.00 7650.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 54 DAY 350.00 18900.00
Sundries.. L.S. 4248.00
30798.00
Add for contractor's profit @ 10 % 3079.80
33877.80
3128 DISMANTLING 1200MM DIA. RCC NP2 HUME PIPE SEWERS. 1120.00 1232.00 /RM
Details of cost for 30 /RM
102 MASON/STONE MASON 19.64 DAY 425.00 8347.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 58.91 DAY 350.00 20618.50
Sundries.. L.S. 4634.48
33599.98
Add for contractor's profit @ 10 % 3360.00
36959.98
3129 FIXING IND. TYPE WHITE GLAZED EARTHENWARE CLOSET & FOOTRESTS. 1134.20 1247.62 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.75 DAY 425.00 318.75
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
Sundries.. L.S. 465.45
1134.20
Add for contractor's profit @ 10 % 113.42
1247.62
3130 FIXING EUR. TYPE WHITE GLAZED EARTHENWARE CLOSET & FOOTRESTS. 984.38 1082.82 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 1 DAY 350.00 350.00
Sundries.. L.S. 421.88
984.38
Add for contractor's profit @ 10 % 98.44
1082.82
3135 FIXING WHITE GLAZED EARTHENWARE URINALS & WASTE PIPE. 892.52 981.77 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.75 DAY 350.00 262.50
Sundries.. L.S. 417.52
892.52
Add for contractor's profit @ 10 % 89.25
981.77
3136 FIXING IND. URINAL SQUATTING OF WHITE GLAZED FIRECLAY. 2160.47 2376.52 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 1 DAY 425.00 425.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
Sundries.. L.S. 635.47
2160.47
Add for contractor's profit @ 10 % 216.05
2376.52
3138 FIXING 450X300 MM OR 550X400 MM SIZE WASH BASIN OF WHITE GLAZED 816.20 897.82 /NO.
EARTHENWARE.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.375 DAY 425.00 159.38
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 381.82
816.20
Add for contractor's profit @ 10 % 81.62
897.82
3139 FIXING 600X480 MM OR 630X450 MM SIZE WASH BASIN OF WHITE GLAZED 950.62 1045.68 /NO.
EARTHENWARE.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.5 DAY 425.00 212.50
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 463.12
950.62
Add for contractor's profit @ 10 % 95.06
1045.68
3141 FIXING 400X250X150 MM OR 450X300X150 MM OR 500X350X150 MM SIZE SINK. 721.82 794.00 /NO.
Details of cost for 1 /NO.
102 MASON/STONE MASON 0.25 DAY 425.00 106.25
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.25 DAY 400.00 100.00
Sundries.. L.S. 340.57
721.82
Add for contractor's profit @ 10 % 72.18
794.00
Sundries.. L.S.
3145 FIXING BRASS CHAIN AND RUBBER PLUG FOR SINK OR LAVATORY BASIN. /L.S.
Details of cost for 0 /L.S.
Sundries.. L.S.
3146 FIXING 750X450X40 MM THICK WOOD DRAINING BOARD WITH SKIRTING AND /L.S.
HEADING.
Details of cost for 0 /L.S.
Sundries.. L.S.
3147 FIXING 550X450 MM OR 450X300 MM SIZE BEVELLED ON PLAIN EDGE MIRROR. 475.80 523.38 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.5 DAY 350.00 175.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
310 C.P. TEAK WOOD CLEAT 4 NO. 18.00 72.00
345 BRASS SCREW 4 100NO. 35.00 1.40
Sundries.. L.S. 27.40
475.80
Add for contractor's profit @ 10 % 47.58
523.38
3149 FIXING 750X20 MM OR 600X20 MM OR 450X20 MM SIZE BRASS TOWEL RAIL. 190.57 209.63 /NO.
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.17 DAY 350.00 59.50
114 FITTER/PLUMBER 0.17 DAY 400.00 68.00
310 C.P. TEAK WOOD CLEAT 2 NO. 18.00 36.00
345 BRASS SCREW 6 100NO. 35.00 2.10
Sundries.. L.S. 24.97
190.57
Add for contractor's profit @ 10 % 19.06
209.63
3150 FIXING C.P. BRASS WOODEN OR GLAZED OR VITROUS CHINA "TOILET PAPER 299.01 328.91 /NO.
HOLDER".
Details of cost for 1 /NO.
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.25 DAY 350.00 87.50
114 FITTER/PLUMBER 0.125 DAY 400.00 50.00
Sundries.. L.S. 161.51
299.01
Add for contractor's profit @ 10 % 29.90
328.91
3151 FIXING 80 MM DIA. H.C.I. SOIL OR VENT PIPE AND SPECIALS. 361.73 397.90 /RM
Details of cost for 18 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
327 M.S. CLAMP 10 NO. 270.00 2700.00
Sundries.. L.S. 1661.13
6511.13
Add for contractor's profit @ 10 % 651.11
7162.24
3152 FIXING 100 MM DIA. H.C.I. SOIL OR VENT PIPE AND SPECIALS. 403.52 443.87 /RM
Details of cost for 18 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
327 M.S. CLAMP 10 NO. 270.00 2700.00
Sundries.. L.S. 1713.28
7263.28
Add for contractor's profit @ 10 % 726.33
7989.61
3154 MAKING LEAD JOINTS OF 80 MM DIA. H.C.I. PIPES AND SPECIALS. 244.11 268.52 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
274 SPUN YARN 0.95 KG. 60.50 57.48
275 PIG LEAD 6.5 KG. 130.00 845.00
276 FUEL(WOOD) 0.1 QTL. 700.00 70.00
Sundries.. L.S. 18.65
2441.13
Add for contractor's profit @ 10 % 244.11
2685.24
3155 MAKING LEAD JOINTS OF 100 MM DIA. H.C.I. PIPES AND SPECIALS. 320.46 352.51 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2.25 DAY 350.00 787.50
114 FITTER/PLUMBER 1.25 DAY 400.00 500.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
274 SPUN YARN 1.15 KG. 60.50 69.58
275 PIG LEAD 9.65 KG. 130.00 1254.50
276 FUEL(WOOD) 0.18 QTL. 700.00 126.00
Sundries.. L.S. 29.53
3204.61
Add for contractor's profit @ 10 % 320.46
3525.07
3156 MAKING LEAD JOINTS OF 150 MM DIA. H.C.I. PIPES AND SPECIALS. 473.80 521.18 /JNT
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3.5 DAY 350.00 1225.00
114 FITTER/PLUMBER 1.75 DAY 400.00 700.00
115 JUNIOR FITTER 1.75 DAY 350.00 612.50
274 SPUN YARN 2 KG. 60.50 121.00
275 PIG LEAD 13.7 KG. 130.00 1781.00
276 FUEL(WOOD) 0.37 QTL. 700.00 259.00
Sundries.. L.S. 39.47
4737.97
Add for contractor's profit @ 10 % 473.80
5211.77
3157 FIXING 50 MM DIA. A.C. SOIL OR VENT PIPE WITH SPECIALS. 196.13 215.74 /RM
Details of cost for 18 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 2 DAY 350.00 700.00
Sundries.. L.S. 1230.27
3530.27
Add for contractor's profit @ 10 % 353.03
3883.30
3159 FIXING 100 MM DIA. A.C. SOIL OR VENT PIPE WITH SPECIALS. 285.54 314.09 /RM
Details of cost for 18 /RM
103 BELDAR/MAZDOOR/DIGGER/DRESSER 6 DAY 350.00 2100.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 3 DAY 350.00 1050.00
Sundries.. L.S. 1589.69
5139.69
Add for contractor's profit @ 10 % 513.97
5653.66
3160 MAKING 1:1 CEMENT AND COARSE SAND JOINT OF 50MM DIA. A.C. SOIL OR 131.00 144.10 /JNT
VENT PIPE & SPECIALS.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 2 DAY 350.00 700.00
114 FITTER/PLUMBER 0.5 DAY 400.00 200.00
115 JUNIOR FITTER 1 DAY 350.00 350.00
249 COARSE SAND(BADARPUR) 0.0008 CUM. 1395.00 1.12
251 CEMENT 0.02 BAG 370.00 7.40
Sundries.. L.S. 51.47
1309.99
Add for contractor's profit @ 10 % 131.00
1440.99
3161 MAKING 1:1 CEMENT AND COARSE SAND JOINT OF 80MM DIA. A.C. SOIL OR 185.18 203.69 /JNT
VENT PIPE & SPECIALS.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 3 DAY 350.00 1050.00
114 FITTER/PLUMBER 0.75 DAY 400.00 300.00
115 JUNIOR FITTER 1.25 DAY 350.00 437.50
249 COARSE SAND(BADARPUR) 0.0011 CUM. 1395.00 1.53
251 CEMENT 0.028 BAG 370.00 10.36
Sundries.. L.S. 52.36
1851.75
Add for contractor's profit @ 10 % 185.18
2036.93
3162 MAKING 1:1 CEMENT AND COARSE SAND JOINT OF 100MM DIA. A.C. SOIL OR 239.28 263.21 /JNT
VENT PIPE & SPECIALS.
Details of cost for 10 /JNT
103 BELDAR/MAZDOOR/DIGGER/DRESSER 4 DAY 350.00 1400.00
114 FITTER/PLUMBER 1 DAY 400.00 400.00
115 JUNIOR FITTER 1.5 DAY 350.00 525.00
249 COARSE SAND(BADARPUR) 0.0014 CUM. 1395.00 1.95
251 CEMENT 0.035 BAG 370.00 12.95
Sundries.. L.S. 52.88
2392.78
Add for contractor's profit @ 10 % 239.28
2632.06
3164 SINKING OF WELL 2.5M DIA. (EXTERNAL) IN ORDINARY SOIL 1.5 - 3.0M DEEP. 11609.42 12770.36 /RM
Details of cost for 1 /RM
104 COOLIE 16.404 DAY 350.00 5741.40
118 SPECIAL MAZDOOR/COOLIE(FOR 4.9212 DAY 400.00 1968.48
RUBBING AND POLISHING)
130 WELL SINKER 3.2808 DAY 475.00 1558.38
Sundries.. L.S. 2341.16
11609.42
Add for contractor's profit @ 10 % 1160.94
12770.36
3165 SINKING OF WELL 2.5M DIA. (EXTERNAL) IN ORDINARY SOIL 3.0 - 6.0M DEEP. 15827.39 17410.13 /RM
Details of cost for 1 /RM
104 COOLIE 22.9656 DAY 350.00 8037.96
118 SPECIAL MAZDOOR/COOLIE(FOR 6.5616 DAY 400.00 2624.64
RUBBING AND POLISHING)
130 WELL SINKER 3.2808 DAY 475.00 1558.38
Sundries.. L.S. 3606.41
15827.39
Add for contractor's profit @ 10 % 1582.74
17410.13
3166 SINKING OF WELL 2.5M DIA. (EXTERNAL) IN ORDINARY SOIL 6.0 - 9.0M DEEP. 21921.24 24113.36 /RM
Details of cost for 1 /RM
104 COOLIE 32.808 DAY 350.00 11482.80
118 SPECIAL MAZDOOR/COOLIE(FOR 6.5616 DAY 400.00 2624.64
RUBBING AND POLISHING)
130 WELL SINKER 6.5616 DAY 475.00 3116.76
Sundries.. L.S. 4697.04
21921.24
Add for contractor's profit @ 10 % 2192.12
24113.36
3167 SINKING OF WELL 2.5M DIA. (EXTERNAL) IN ORDINARY SOIL 9.0 - 12.0M DEEP. 26671.26 29338.39 /RM
Details of cost for 1 /RM
104 COOLIE 32.808 DAY 350.00 11482.80
118 SPECIAL MAZDOOR/COOLIE(FOR 6.5616 DAY 400.00 2624.64
RUBBING AND POLISHING)
130 WELL SINKER 9.8424 DAY 475.00 4675.14
Sundries.. L.S. 7888.68
26671.26
Add for contractor's profit @ 10 % 2667.13
29338.39
3169 SAME AS ITEM 3163 TO 3168 BUT FOR OTHER DIAMETERS (THE RATES /RM
SHALL BE PROPORTIONAL TO THEIR AREAS).
Details of cost for 0 /RM
Sundries.. L.S.
3170 SAME AS ITEM 3163 TO 3169 BUT FOR SOFT CLAY (EXTRA OVER ITEMS 3163 25%
TO 3169).
Details of cost for 0 25%
Sundries.. L.S.
3171 SAME AS ITEM 3163 TO 3169 BUT FOR HARD CLAY (EXTRA OVER ITEMS 3163 50%
TO 3169).
Details of cost for 0 50%
Sundries.. L.S.
3172 SAME AS ITEM 3163 TO 3169 BUT FOR KANKAR, SHINGLES (EXTRA OVER 75%
ITEMS 3163 TO 3169).
Details of cost for 0 75%
Sundries.. L.S.
3174 KERB & CHANNEL (K&C) DRAINS (ORDINARY) NO. II. 405.86 446.45 /RM
Details of cost for 100 /RM
101 MISTRY 0.3755 DAY 460.00 172.73
102 MASON/STONE MASON 10.076 DAY 425.00 4282.30
103 BELDAR/MAZDOOR/DIGGER/DRESSER 19.508 DAY 350.00 6827.80
104 COOLIE 10.9355 DAY 350.00 3827.43
105 BLACK SMITH 0.3755 DAY 425.00 159.59
106 BHISTI 2.569 DAY 350.00 899.15
247 STONE GRIT 10-12MM 1.8 CUM. 1090.00 1962.00
249 COARSE SAND(BADARPUR) 0.9 CUM. 1395.00 1255.50
250 LOCAL SAND 2.456 CUM. 860.00 2112.16
251 CEMENT 32.969 BAG 370.00 12198.53
385 BRICK BALLAST 25MM GAUGE 4.522 CUM. 1350.00 6104.70
Sundries.. L.S. 784.10
40585.98
Add for contractor's profit @ 10 % 4058.60
44644.58
3175 KERB & CHANNEL (K&C) DRAINS (ORDINARY) NO. III. 454.73 500.21 /RM
Details of cost for 100 /RM
101 MISTRY 0.4125 DAY 460.00 189.75
102 MASON/STONE MASON 12.1535 DAY 425.00 5165.24
103 BELDAR/MAZDOOR/DIGGER/DRESSER 22.698 DAY 350.00 7944.30
104 COOLIE 11.9005 DAY 350.00 4165.18
105 BLACK SMITH 0.4125 DAY 425.00 175.31
106 BHISTI 2.804 DAY 350.00 981.40
247 STONE GRIT 10-12MM 2.025 CUM. 1090.00 2207.25
249 COARSE SAND(BADARPUR) 1.0125 CUM. 1395.00 1412.44
250 LOCAL SAND 2.646 CUM. 860.00 2275.56
251 CEMENT 36.1915 BAG 370.00 13390.86
385 BRICK BALLAST 25MM GAUGE 4.902 CUM. 1350.00 6617.70
Sundries.. L.S. 948.38
45473.36
Add for contractor's profit @ 10 % 4547.34
50020.70
3177 100MM DIA. C.C. SEMI CIRCULAR DRAIN. 846.47 931.12 /RM
Details of cost for 100 /RM
101 MISTRY 0.759 DAY 460.00 349.14
102 MASON/STONE MASON 25.747 DAY 425.00 10942.48
103 BELDAR/MAZDOOR/DIGGER/DRESSER 31.052 DAY 350.00 10868.20
104 COOLIE 25.822 DAY 350.00 9037.70
105 BLACK SMITH 0.559 DAY 425.00 237.58
106 BHISTI 5.001 DAY 350.00 1750.35
235 BRICKS IST CLASS 2000 1000NO. 7350.00 14700.00
247 STONE GRIT 10-12MM 1.062 CUM. 1090.00 1157.58
249 COARSE SAND(BADARPUR) 0.771 CUM. 1395.00 1075.55
250 LOCAL SAND 4.9975 CUM. 860.00 4297.85
251 CEMENT 49.061 BAG 370.00 18152.57
385 BRICK BALLAST 25MM GAUGE 8.075 CUM. 1350.00 10901.25
Sundries.. L.S. 1176.93
84647.17
Add for contractor's profit @ 10 % 8464.72
93111.89
3178 150MM DIA. C.C. SEMI CIRCULAR DRAIN. 915.72 1007.29 /RM
Details of cost for 100 /RM
101 MISTRY 0.8639 DAY 460.00 397.39
102 MASON/STONE MASON 27.9475 DAY 425.00 11877.69
103 BELDAR/MAZDOOR/DIGGER/DRESSER 29.702 DAY 350.00 10395.70
104 COOLIE 25.972 DAY 350.00 9090.20
105 BLACK SMITH 0.6639 DAY 425.00 282.16
106 BHISTI 5.487 DAY 350.00 1920.45
235 BRICKS IST CLASS 2000 1000NO. 7350.00 14700.00
247 STONE GRIT 10-12MM 1.413 CUM. 1090.00 1540.17
249 COARSE SAND(BADARPUR) 0.9465 CUM. 1395.00 1320.37
250 LOCAL SAND 5.672 CUM. 860.00 4877.92
251 CEMENT 57.1545 BAG 370.00 21147.17
385 BRICK BALLAST 25MM GAUGE 9.424 CUM. 1350.00 12722.40
Sundries.. L.S. 1299.91
91571.52
Add for contractor's profit @ 10 % 9157.15
100728.67
3180 300MM DIA. C.C. SEMI CIRCULAR DRAIN. 1257.98 1383.77 /RM
Details of cost for 100 /RM
101 MISTRY 1.214 DAY 460.00 558.44
102 MASON/STONE MASON 31.606 DAY 425.00 13432.55
103 BELDAR/MAZDOOR/DIGGER/DRESSER 50.928 DAY 350.00 17824.80
104 COOLIE 37.448 DAY 350.00 13106.80
105 BLACK SMITH 1.014 DAY 425.00 430.95
106 BHISTI 7.04 DAY 350.00 2464.00
235 BRICKS IST CLASS 2000 1000NO. 7350.00 14700.00
247 STONE GRIT 10-12MM 2.484 CUM. 1090.00 2707.56
249 COARSE SAND(BADARPUR) 1.482 CUM. 1395.00 2067.39
250 LOCAL SAND 7.952 CUM. 860.00 6838.72
251 CEMENT 82.9 BAG 370.00 30673.00
385 BRICK BALLAST 25MM GAUGE 13.984 CUM. 1350.00 18878.40
Sundries.. L.S. 2114.97
125797.58
Add for contractor's profit @ 10 % 12579.76
138377.34
3181 400MM DIA. C.C. SEMI CIRCULAR DRAIN. 1468.81 1615.69 /RM
Details of cost for 100 /RM
101 MISTRY 1.4655 DAY 460.00 674.13
102 MASON/STONE MASON 34.0675 DAY 425.00 14478.69
103 BELDAR/MAZDOOR/DIGGER/DRESSER 60.358 DAY 350.00 21125.30
104 COOLIE 43.878 DAY 350.00 15357.30
105 BLACK SMITH 1.2655 DAY 425.00 537.84
106 BHISTI 8.098 DAY 350.00 2834.30
235 BRICKS IST CLASS 2000 1000NO. 7350.00 14700.00
247 STONE GRIT 10-12MM 3.177 CUM. 1090.00 3462.93
249 COARSE SAND(BADARPUR) 1.8285 CUM. 1395.00 2550.76
250 LOCAL SAND 9.5955 CUM. 860.00 8252.13
251 CEMENT 100.3305 BAG 370.00 37122.29
385 BRICK BALLAST 25MM GAUGE 17.271 CUM. 1350.00 23315.85
Sundries.. L.S. 2469.44
146880.95
Add for contractor's profit @ 10 % 14688.09
161569.04
3183 DISMANTLING & MAKING CONNECTION OF 100MM OR 150MM DIA. DRAIN PIPE 318.51 350.36 /CONN
WITH C.C. 1:2:4.
Details of cost for 1 /CONN
101 MISTRY 0.001 DAY 460.00 0.46
102 MASON/STONE MASON 0.176 DAY 425.00 74.80
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.195 DAY 350.00 68.25
104 COOLIE 0.034 DAY 350.00 11.90
105 BLACK SMITH 0.001 DAY 425.00 0.43
106 BHISTI 0.0161 DAY 350.00 5.64
247 STONE GRIT 10-12MM 0.018 CUM. 1090.00 19.62
249 COARSE SAND(BADARPUR) 0.009 CUM. 1395.00 12.56
250 LOCAL SAND 0.0009 CUM. 860.00 0.77
251 CEMENT 0.1377 BAG 370.00 50.95
Sundries.. L.S. 73.14
318.51
Add for contractor's profit @ 10 % 31.85
350.36
3184 DISMANTLING & MAKING CONNECTION OF 200,250 & 300MM DIA. DRAIN PIPE 520.85 572.94 /CONN
WITH C.C. 1:2:4.
Details of cost for 1 /CONN
101 MISTRY 0.0015 DAY 460.00 0.69
102 MASON/STONE MASON 0.2625 DAY 425.00 111.56
103 BELDAR/MAZDOOR/DIGGER/DRESSER 0.292 DAY 350.00 102.20
104 COOLIE 0.05 DAY 350.00 17.50
105 BLACK SMITH 0.0015 DAY 425.00 0.64
106 BHISTI 0.0238 DAY 350.00 8.33
247 STONE GRIT 10-12MM 0.027 CUM. 1090.00 29.43
249 COARSE SAND(BADARPUR) 0.0135 CUM. 1395.00 18.83
250 LOCAL SAND 0.0012 CUM. 860.00 1.03
251 CEMENT 0.2051 BAG 370.00 75.89
Sundries.. L.S. 154.75
520.85
Add for contractor's profit @ 10 % 52.09
572.94
3186 FIXING R.C.C. SPUN VENTILATING COLUMN 9.0M LONG. 9399.93 10339.92 /NO.
Details of cost for 1 /NO.
101 MISTRY 0.5629 DAY 460.00 258.93
102 MASON/STONE MASON 1.1186 DAY 425.00 475.41
103 BELDAR/MAZDOOR/DIGGER/DRESSER 9.8764 DAY 350.00 3456.74
104 COOLIE 1.5672 DAY 350.00 548.52
105 BLACK SMITH 0.0629 DAY 425.00 26.73
106 BHISTI 0.2273 DAY 350.00 79.56
244 BRICK BALLAST 40MM GAUGE 0.9785 CUM. 1300.00 1272.05
246 STONE BALLAST 20MM GAUGE 0.0936 CUM. 750.00 70.20
249 COARSE SAND(BADARPUR) 0.0468 CUM. 1395.00 65.29
250 LOCAL SAND 0.4893 CUM. 860.00 420.80
251 CEMENT 4.1728 BAG 370.00 1543.94
Sundries.. L.S. 1181.77
9399.93
Add for contractor's profit @ 10 % 939.99
10339.92
Sundries.. L.S.
Sundries.. L.S.
3191 EXTRA OVER ITEMS OF CONCRETE, BRICK WORK, D.P.C., PLASTER, 12%
POINTING, FLOORING, DEMOLITION & DISMANTLING WORKS OF SCHEDULE
OF RATES FOR BUILDING, ROADS & W/S IF EXECUTED FROM 4.5 - 6.0M DEEP.
Details of cost for 0 12%
Sundries.. L.S.
3192 EXTRA OVER ITEMS OF CONCRETE, BRICK WORK, D.P.C., PLASTER, 20%
POINTING, FLOORING, DEMOLITION & DISMANTLING WORKS OF SCHEDULE
OF RATES FOR BUILDING, ROADS & W/S IF EXECUTED FROM 6.0 - 7.5M DEEP.
Details of cost for 0 20%
Sundries.. L.S.
Sundries.. L.S.
3194 LAYING, JOINTING 350MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 686.91 755.60 /RM
Details of cost for 30 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 8 DAY 425.00 3400.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 18 DAY 350.00 6300.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.192 CUM. 1395.00 267.84
251 CEMENT 2.604 BAG 370.00 963.48
274 SPUN YARN 4.632 KG. 60.50 280.24
387 CARTAGE OF R.C.C.NP3 PIPE 350-700MM 78.28 QTL. 35.94 2813.38
DIA.
Sundries.. L.S. 3562.39
20607.33
Add for contractor's profit @ 10 % 2060.73
22668.06
3195 LAYING, JOINTING 400MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 749.11 824.02 /RM
Details of cost for 30 /RM
101 MISTRY 2 DAY 460.00 920.00
102 MASON/STONE MASON 9 DAY 425.00 3825.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 20 DAY 350.00 7000.00
106 BHISTI 3 DAY 350.00 1050.00
113 WATCHMAN 3 DAY 350.00 1050.00
249 COARSE SAND(BADARPUR) 0.22 CUM. 1395.00 306.90
251 CEMENT 2.86 BAG 370.00 1058.20
274 SPUN YARN 5.45 KG. 60.50 329.73
387 CARTAGE OF R.C.C.NP3 PIPE 350-700MM 87.27 QTL. 35.94 3136.48
DIA.
Sundries.. L.S. 3796.89
22473.20
Add for contractor's profit @ 10 % 2247.32
24720.52
3196 LAYING, JOINTING 450MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 935.19 1028.71 /RM
Details of cost for 30 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 11 DAY 425.00 4675.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 24 DAY 350.00 8400.00
106 BHISTI 4 DAY 350.00 1400.00
113 WATCHMAN 4 DAY 350.00 1400.00
249 COARSE SAND(BADARPUR) 0.28 CUM. 1395.00 390.60
251 CEMENT 3.7 BAG 370.00 1369.00
274 SPUN YARN 6.26 KG. 60.50 378.73
387 CARTAGE OF R.C.C.NP3 PIPE 350-700MM 98.74 QTL. 35.94 3548.72
DIA.
Sundries.. L.S. 5113.78
28055.83
Add for contractor's profit @ 10 % 2805.58
30861.41
3198 LAYING, JOINTING 600MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 1097.31 1207.04 /RM
Details of cost for 30 /RM
101 MISTRY 3 DAY 460.00 1380.00
102 MASON/STONE MASON 14 DAY 425.00 5950.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 28 DAY 350.00 9800.00
106 BHISTI 4 DAY 350.00 1400.00
113 WATCHMAN 4 DAY 350.00 1400.00
249 COARSE SAND(BADARPUR) 0.31 CUM. 1395.00 432.45
251 CEMENT 4.2 BAG 370.00 1554.00
274 SPUN YARN 7.08 KG. 60.50 428.34
387 CARTAGE OF R.C.C.NP3 PIPE 350-700MM 135.76 QTL. 35.94 4879.21
DIA.
Sundries.. L.S. 5695.26
32919.26
Add for contractor's profit @ 10 % 3291.93
36211.19
3199 LAYING, JOINTING 700MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 1295.32 1424.85 /RM
Details of cost for 30 /RM
101 MISTRY 4 DAY 460.00 1840.00
102 MASON/STONE MASON 16 DAY 425.00 6800.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 32 DAY 350.00 11200.00
106 BHISTI 5 DAY 350.00 1750.00
113 WATCHMAN 5 DAY 350.00 1750.00
249 COARSE SAND(BADARPUR) 0.38 CUM. 1395.00 530.10
251 CEMENT 5.18 BAG 370.00 1916.60
274 SPUN YARN 8.17 KG. 60.50 494.29
387 CARTAGE OF R.C.C.NP3 PIPE 350-700MM 155.3 QTL. 35.94 5581.48
DIA.
Sundries.. L.S. 6997.00
38859.47
Add for contractor's profit @ 10 % 3885.95
42745.42
3201 LAYING, JOINTING 900MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 2002.11 2202.32 /RM
Details of cost for 30 /RM
101 MISTRY 5 DAY 460.00 2300.00
102 MASON/STONE MASON 20 DAY 425.00 8500.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 40 DAY 350.00 14000.00
106 BHISTI 6 DAY 350.00 2100.00
113 WATCHMAN 6 DAY 350.00 2100.00
249 COARSE SAND(BADARPUR) 0.56 CUM. 1395.00 781.20
251 CEMENT 7.58 BAG 370.00 2804.60
274 SPUN YARN 9.8 KG. 60.50 592.90
388 CARTAGE OF R.C.C.NP3 PIPE 800-1200MM 248.6 QTL. 63.43 15768.70
DIA.
Sundries.. L.S. 11115.95
60063.35
Add for contractor's profit @ 10 % 6006.33
66069.68
3202 LAYING, JOINTING 1000MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 2385.73 2624.30 /RM
Details of cost for 30 /RM
101 MISTRY 6 DAY 460.00 2760.00
102 MASON/STONE MASON 25 DAY 425.00 10625.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 50 DAY 350.00 17500.00
106 BHISTI 8 DAY 350.00 2800.00
113 WATCHMAN 8 DAY 350.00 2800.00
249 COARSE SAND(BADARPUR) 0.66 CUM. 1395.00 920.70
251 CEMENT 9.04 BAG 370.00 3344.80
274 SPUN YARN 10.34 KG. 60.50 625.57
388 CARTAGE OF R.C.C.NP3 PIPE 800-1200MM 273.03 QTL. 63.43 17318.29
DIA.
Sundries.. L.S. 12877.54
71571.90
Add for contractor's profit @ 10 % 7157.19
78729.09
3204 LAYING, JOINTING 1200MM DIA. R.C.C. NP3 HUME PIPE 0.0 - 1.5M DEEP. 3321.04 3653.14 /RM
Details of cost for 30 /RM
101 MISTRY 10 DAY 460.00 4600.00
102 MASON/STONE MASON 35 DAY 425.00 14875.00
103 BELDAR/MAZDOOR/DIGGER/DRESSER 70 DAY 350.00 24500.00
106 BHISTI 12 DAY 350.00 4200.00
113 WATCHMAN 12 DAY 350.00 4200.00
249 COARSE SAND(BADARPUR) 0.94 CUM. 1395.00 1311.30
251 CEMENT 12.8 BAG 370.00 4736.00
274 SPUN YARN 13.5 KG. 60.50 816.75
388 CARTAGE OF R.C.C.NP3 PIPE 800-1200MM 375.01 QTL. 63.43 23786.88
DIA.
Sundries.. L.S. 16605.19
99631.12
Add for contractor's profit @ 10 % 9963.11
109594.23
3205 LAYING, JOINTING R.C.C. NP3 HUME PIPE 1.5 - 3.0M DEEP (EXTRA OVER 6.45%
ITEMS 3194 TO 3204).
Details of cost for 0 6.45%
Sundries.. L.S.
3206 LAYING, JOINTING R.C.C. NP3 HUME PIPE 3.0 - 4.5M DEEP (EXTRA OVER 13.05%
ITEMS 3194 TO 3204).
Details of cost for 0 13.05%
Sundries.. L.S.
Sundries.. L.S.
3208 LAYING, JOINTING R.C.C. NP3 HUME PIPE 6.0 - 7.5M DEEP (EXTRA OVER 31.55%
ITEMS 3194 TO 3204).
Details of cost for 0 31.55%
Sundries.. L.S.
3209 LAYING, JOINTING R.C.C. NP3 HUME PIPE 7.5 - 9.0M DEEP (EXTRA OVER 46.15%
ITEMS 3194 TO 3204).
Details of cost for 0 46.15%
Sundries.. L.S.