TRAINING MANUAL
our buildings,
thereafter
they shape us.”
-Winston Churchill
FIRST EDITION
Published By:
2017
2 3
ACKNOWLEDGMENT
The National Housing Authority (NHA) expresses its gratitude to the following
agencies and individual who in one way or another have contributed in the
compilation and preparation of this TRAINING MANUAL:
Chair
Leoncio B. Evasco, Jr.
Housing and Urban Development Coordinating Council (HUDCC)
Members
Judy F. Sese
DPWH-BRS Representative
Ariel M. Laurente
HGC Representative
Julius H. Tan
HLURB Representative
4 5
Avelino D. Tolentino
Mr. Wilson A Tabuton Technology Proponents
HUDCC Representative
• Permaforms, Inc.
Bureau of Design—Department of Public Works and Highways
• SKS Construction and Development Corporation
Raul C. Asis
Undersecretary for Technical Services, DPWH • SRC Int’l Panel System, Inc.
Josephine P. Isturis
Engineer V, Chief Buildings Division, BOD-DPWH
6 7
FOREWORD
The manual and the hands-on training roll-
Socialized housing, and its desired outcome of community-building, has out recognize the mistakes, gaps and short-cuts of
always had a special significance in every Philippine president’s socio-economic the past. Adopting new housing technologies will
agenda, the current administration included. lessen vulnerabilities of home sites affected by
poor materials, techniques and construction.
The Duterte Administration’s vision of serving the multitude of homeless
Filipino low-income families is guided by the constitution, with its provisions With the production of the manual and the
stating that the prime duty of the government is to serve and protect the roll-out of hands-on training on new housing
people, protect life, liberty and property, and promote the general welfare of technologies, we have set our sight in achieving a
the people. uniform way addressing our need for cost-efficient
housing technologies, processes and concepts,
What better way to abide by the constitutional mandate than to provide roles and functions, and unity of action.
safe, livable and enduring urban and rural housing communities to the greatest
number of people. As much as possible utilizing the latest housing technologies, Indeed, building up our capabilities
and leveraging these and the leadership and people trained in optimizing their through training and adopting standardized
benefits, to produce in massive numbers modern, affordable and climate- approaches should help us go beyond our “silos”,
change resilient housing structures. and make us better builders of society.
It all starts from enhancing and building capabilities in the long, medium
MARCELINO P. ESCALADA, JR.
and short terms. A strong and effective shelter capability will combine the
General Manager
essential ingredients of leadership, regulations, training, innovation, quality and
National Housing Authority
application of technologies and materials development, and ensure that
housing in the 21st century will depart from the rough-shod construction and
squalid appearance of low-cost housing sites in the past.
8 9
MESSAGE
10 11
MESSAGE
12 13
MESSAGE
It is my pleasure to present to you this first edition of the Training Manual We look forward to a continued upgrading of
on the Use of New Technologies for NHA Housing Projects. This manual building systems and materials, the necessary skills,
accompanies the hands-on trainings conducted and will be conducted by evaluation tools, and even our own acceptance to
HTDO with the technology proponent for NHA employees and contractors new ways of doing things. Then, maybe we can see
involved in the construction of projects that utilize such AITECH-accredited that day when housing backlog is just a thing of the
systems or materials for housing, as required under NHA Memorandum Circular past.
No. 2016-120. The training and this manual are essential components towards
achieving the desired benefits of the technologies in housing through teaching Lastly, I would like to thank my HTDO Team for
of their proper installation and methodology of application. making this Training Manual possible.
We encourage users of these technologies to abide by existing
standards and requirements and to conform to prescribed conditions in
applying them, so that we can continue on the track of upgrading the housing
delivery for the public. We acknowledge the proponents for providing the
alternative solutions in this important government mission. While we usually
associate technology with high costs, it may surprise some of us that non-
conventional systems and materials that are better in most physical aspects can
AR. MARIA BENITA O. REGALA, FUAP, ASEAN ARCHITECT
actually be more cost effective. However, it takes due diligence for assessing
Department Manager, HTDO
how any of the features of a technology could bring about more advantage,
Editor-in-Chief
especially for our lower income fellow Filipinos. That is why the AITECH
Committee has devised and continually improves the tools for properly
evaluating proposed technologies from our country and abroad.
14 15
TABLE OF CONTENTS
BACKGROUND OF THE AITECH ———————————————————–—— 18
NATIONAL HOUSING AUTHORITY AITECH PROCESS FLOWCHART —————————————————————--- 22
SUMMARY OF DPWH-APPROVED HOUSING MODELS W/ AITECH ACCREDITED
TECHNOLOGIES —————————————————————————- 23
MEMORANDUM CIRCULAR 2016-020: Guidelines for Construction Using
AITECH Accredited – New Technologies —————————————–– 28
VISION CHECKLIST FOR CONSTRUCTION TEMPLATE ————————————–———- 37
ANNEXES
HANDS-ON TRAINING 1: MAY 11-15, 2015 ———————————————–——–—— 156
HANDS-ON TRAINING 2 (TACLOBAN): JUNE 22-24, 2015 ————–——————–--—- 159
HANDS-ON TRAINING 3 (BACOLOD): NOVEMBER 24-26, 2015 ————–—–——–--—- 162
HANDS-ON TRAINING 4 (ECO KEY SYSTEM): DEC. 16, 2015 & JAN. 8, 2016———–--— 164
HANDS-ON TRAINING 5 (NCR): MARCH 9-11, 2016 ——————————-——–--—— 166
HANDS-ON TRAINING 6 (LEYTE): MARCH 10-12, 2016 ————————–—--—-——— 168
PROPONENT’S DIRECTORY ———————————————————————————— 174
16 17
National Housing Authority
BACKGROUND (NHA)
The AITECH Committee is composed of the following agencies: Housing and Land Use Regulatory Board
(HLURB)
18 19
In the aftermath of Typhoon Yolanda (Haiyan), there was a huge
demand for building materials and labor, due to the devastation on public and
Construction Industry Authority of the Philippines private infrastructure brought on by the typhoon. The NHA had to find ways to
(CIAP) address this concern in order to meet the housing demand. Concurrently, there
was also an influx of offers for new technologies, systems and materials to
AITECH. Most of the offers were wall systems & roofing materials. As an added
measure, the NHA through HTDO was directed to consult the Bureau of Design,
DPWH for reviews of the structural plans using the systems/materials.
20 21
PROCESS FLOW CHART
ACCREDITATION OF INNOVATIVE TECHNOLOGIES FOR HOUSING
AITECH ACCREDITED TECHNOLOGIES WITH DPWH APPROVAL
(AITECH)
(FOR YOLANDA PROJECTS)
PROPONENT NHA OTHER AGENCIES MODEL PROPONENT/ AGENCY COST PER UNIT
Submits AITECH Accredita- AITECH Secretariat receives
tion Application application and reviews at-
tached documents if complete Proposed 28.60 sq.m. PermaForms Inc. / Realm Php196,244.32
Bungalow Design as Homebuilders Incorporated
If documents are
Another Option for
complete Permanent Housing –
Yolanda Project
Pays fee and returns AITECH Secretariat issues Order 22 sq.m. Rowhouse with PermaForms Inc. / Realm Php195,000.09
copy of receipt V
of Payment for Evaluation Fee
Loft Provision Homebuilders Incorporated
22 23
21 Sq.M. Duplex Housing Jose Cris Builders Php150,127.
Model 98
AITECH ACCREDITED TECHNOLOGIES WITH DPWH APPROVAL
(FOR YOLANDA PROJECTS)
22 Sq.M. Lofted Rowhouse Jose Cris Builders Php
For Typhoon Yolanda Victims 200,000.00
MODEL PROPONENT/ AGENCY COST PER UNIT
26 sq.m Single Storey Paligid Development Php 194,999.30 26 sq.m. Rowhouse Inquina Development Php
Rowhouse Corp. Corporation 194,999.00
24 25
HANDS-ON TRAINING SEMINAR FOR DPWH-APPROVED &
AITECH ACCREDITED TECHNOLOGIES FOR TYPHOON YOLANDA
26 27
NHA MEMORANDUM CIRCULAR 2016-020
-To review the consistency of pertinent documents required for
accreditation before payment of the required fees;
-To refer necessary testing/evaluation to the proper AITECH member
SUBJECT : GUIDELINES FOR CONSTRUCTION USING AITECH ACCREDITED – NEW agencies upon payment of the required fees;
TECHNOLOGIES -To coordinate regular Committee meetings and other for a;
-To perform other administrative functions related to accreditation.
NHA – The National Housing Authority shall act or serve as the AITECH Secretariat DTI-BPS – as the agency tasked with monitoring of quality production; information
for the Committee, and the agency involved with the structural and dissemination on new construction materials as well as the development of
economic evaluation of new technology systems appropriate for socialized, standards.
economic, medium, and high-end housing project with the following
specific functions:
28 29
4. PRE-CONSTRUCTION PHASE
1.2 The Amended Implementing Guidelines on the Accreditation of Innovative
Technologies for Housing dated 27 August 2003 also mandates the AITECH
4.1 There shall be a mandatory coordination meeting among NHA personnel,
to act as a monitoring body to ensure that the accredited technology/
both from HTDO and from Project Implementing Team, AITECH technology
system/building materials is/are being used in accordance to the
proponent or supplier and the contractors who will use the technology prior
proponent’s approved proposal.
to actual construction.
1.3 I n line with the above, two (2) hands-on training workshops and seminars
4.2 A hands-on training seminar and workshop shall be conducted and
were conducted. The first one was held at the NHA Compound, Elliptical
scheduled prior to actual construction.
Road, Diliman, Quezon City, from 11-15 May 2015. The second one was held
in Leyte-Samar Project Office, Calanipawan Road, Sagkahan, Tacloban
The Housing Technology Development Office (HTDO), together with the
City, from 22-25 June 2015. The training included (a) lecture presentation by
accredited technology proponent shall conduct training for the NHA
the technology providers, and (b) on-site demonstration construction to
employees and the contractors before using the new technology.
familiarize the participants on the proper application and construction
methodologies. Participants included NHA technical personnel including
Training shall highlight the proper installation and methodology of the
project team heads, staff, contractors/developers who will be using said
technologies. technology. Certificates shall be awarded to those who completed the
trainings. Contractors who are not issued certificates of training
2. OBJECTIVES completion will not be allowed to implement the new technology.
The guidelines are hereby issued with the following objectives:
The site where the hands-on training will be conducted shall be identified
2.1 To ensure the quality and proper application of new technologies which are by the NHA project team leader.
AITECH accredited in all NHA housing projects;
Participants shall be identified at least two (2) weeks prior to the conduct
2.2 To provide uniform guidelines to NHA project implementors and inspectors on of the training, the list of which must be submitted to HTDO, and
the proper use of the technologies. forwarded to HRMD, and for approval of the General Manager.
2.3 To establish and maintain a reliable AITECH monitoring system. A checklist for construction shall be provided by the technology proponent
to the NHA and the contractor for compliance and to be used as a
3. COVERAGE monitoring and inspection tool by NHA project implementors (see Annex
These guidelines shall cover all current and future NHA housing projects A).
using AITECH accredited technology/system/building materials. These shall also
cover the three-phases of construction. All expenses incurred in the preparation and conduct of the hands-on
training and seminar workshop shall be for the account of the proponent
and contractor as agreed between them.
30 31
6.6 Vertical bars should be tied at the bottom of the panels to ensure non-
5. CONSTRUCTION PHASE movement and also to avoid pilferage.
5.1 The technology proponents/suppliers shall submit to NHA copies of the 6.7 Utilities (electrical piping and plumbing) should be well secured to avoid
certification every quarter for the project made by the contractors/ movement within the panel. Fixed sockets should be included in the
developers to authenticate that the items purchased are from the specifications.
accredited proponents. The contractor/developer shall attach said
purchase orders to the billing documents to be submitted to the NHA 6.8 On-site fabrication of panel technologies (e.g. Plaswall and Permaforms, or
Project Officer in charge of the project. similar) by the contractor/developer shall no longer be allowed. For the
protection of the technology and to ensure right methodology, the supplier
5.2 The construction checklist shall be used by the NHA project implementers should strictly fabricate the panels or strictly supervise fabrication on site by
and which shall likewise include notes observation and findings on the their qualified personnel.
critical points for construction of the technology (see Annex B).
6.9 Material specifications (e.g. thickness of the boards to be used as
5.3 Sanctions shall be set should errors be made in actual installation of the permanentformworks for panels) should be uniform and in accordance to
new technology, in the form of possible revocation of the certificate approved plansand specifications.
awarded to the technology provider or non-payment of the
accomplishment of the contractor by the NHA Project Implementing Team 6.10 A set basis for the concrete mixture where contractors can derive from
(NPIT). shall beestablished. A trial mix should be required from the contractor, to
check the mixture, strength, and slump, prior to pouring.
6. INSTRUCTIONS FOR COMPLIANCE DURING ACTUAL CONSTRUCTION
6.11 Concrete mixtures that need to be modified according to locally available
6.1 Execution of designs must strictly conform to the plans as approved by the sand or aggregates, or any modifications made in the design mix should
NHA and/or the DPWH as the case may be. first be approved by the field office before implementation. Design mix per
approved specification must be used for the project as agreed during
6.2 Tests like soil compaction tests, compression tests, etc. should strictly be construction meeting.
observed by the contractor and copies of the results duly submitted to the
Project Office. 6.12 Boards for permanent formworks with at least 4.5mm thickness should
beinstalled horizontally to allow pouring at the recommended height. The
6.3 Field density test shall be required per block, and costs shall be included in pouring should only be done at a height of 0.30m. To ensure that there is no
the indirect cost. segregation of aggregates walls should be tapped with a rubber mallet
immediately after concrete pouring.
6.4 Compaction is critical and should be observed prior to actual construction.
6.13 For roofing, proper overlaps should be observed to avoid leaks. For rib-type
6.5 For panel technologies like Plaswall and Permaforms, starter bars should be roofing, rib profile should follow the standard 0.30m (2 ½ corrugations)
aligned with the spacers within the panel. overlaps.
32 33
6.14 A digital micrometer should be used as caliper for roofing sheets. A Vernier
caliper (for bolts) will not be able to yield the same result, thus, shall not be 8.3 The schedule of the AITECH Inspection Team shall be coordinated with the
used to get the thickness of the roofing sheets. CPES Team, if the concerned project is included in the CPES evaluation list.
While the CPES is concerned with the over-all performance of the
contractor, the AITECH Team shall check on the proper use and application
6.15 On random checking, the NHA inspector, supplier and the contractor shall
of the technology.
certify that the correct roofing had been delivered on site. NHA shall not
accept nor use sheets or other materials that are less than the
8.4 All AMOs/Regional Managers shall designate the Project Manager of the
recommended specifications.
concerned project or his/her technical representative to witness the
inspection.
6.16 In the event that a contractor developer decides to change any material
or methodology and shifted to another technology, the contractor/ 8.5 The AITECH Inspection Team shall likewise submit its report supported by
developer must secure prior written approval from the NHA, through the photos and videos to the AITECH Inter-Agency Committee and to the
AMO/Regional Offices. This shall be covered by a variation order. All General Manager for information, within five (5) days after its inspection.
change in technology and plans must likewise be submitted to HTDO for
review, for the final approval by the General Manager. 8.6 Should there be discrepancies/negative findings on the project, a
memorandum shall be issued by the HTDO Department Manager to the
General Manager thru the AMO/Regional Office Head concerned, and
7. POST-CONSTRUCTION PHASE POSSO recommending corrective measures. The contractor/developer may
7.1 An accomplished final report certifying compliance to the checklist for request for another inspection after corrective measures have been made.
construction shall be attached to the billing and final acceptance of the Non-compliance to the recommended corrective measure within the
project (see Annex B). The same must be submitted to the Project specified time frame will result in the revocation of AITECH certificate.
Implementing Team and to the AITECH Secretariat of HTDO.
8.7 The Head of the AITECH Secretariat shall submit to the AITECH Committee a
Summary Report of all NHA housing projects inspected/monitored including
8. AITECH TEAM INSPECTION
its findings/recommendations for proper action.
8.1 An AITECH Inspection Team is hereby created and shall be composed of
architects and engineers from the HTDO as well as members of the AITECH 9. OTHER PROVISIONS
Inter-Agency Committee. It shall conduct inspections on projects with
critical findings on the use of the new technologies. There shall be at least 9.1 The technology proponent and/or the contractor concerned shall shoulder
three (3) members of the Inspection Team, two (2) from HTDO and one (1) the costs of transportation, accommodation, and other incidental expenses
from the AITECH Committee. of the AITECH Inspection and Monitoring Team in the conduct of inspection.
8.2 The AITECH Inspection Team shall be undertaken at least once during pre-
construction phase and during construction phase as may be necessary.
34 35
CHECKLIST FOR CONSTRUCTION TEMPLATE
9.2 Should there be other technologies that will be accredited and 1. PROJECT SITE INFORMATION DETAILS
which shall be adopted in any NHA project, the same procedures
shall be applied. Likewise, a new set of instructions for compliance 1.1 Project Name: __________________________________________________________
during construction shall be issued particular to the said new 1.2 Date Inspected: __________________________________________________________
1.3 Project Location: __________________________________________________________
technology.
1.4 Name of Developer/Contractor: ___________________________________________
1.5 Block / Lot: ________________________________________________________________
1.6 Type of Dwelling
EFFECTIVITY One Storey Loftable Low Rise Building
This Memorandum Circular shall take effect immediately. Row house
Duplex
--
2-Storey
For guidance and strict compliance of all concerned. 3-Storey
36 37
2. FOUNDATION WORKS (use DPWH and NHA certified plans as reference)
1.8 Site Condition
Cut 2.1 Grade Beams and Slab on Fill
Infill
RECOMMENDED MARK REMARKS
Mechanically Compacted
(As Per Manufacturer’s (Correct/
-By how many percent? %
Specification) Incorrect)
1.9 Is the site free from any foreign debris? Sizes of Beams
Yes Thickness of Slab
No Diameter of Bars
Provide description with pictures) Spacing of Bars
38 39
3. WALL PANELS (use DPWH-APPROVED plans as reference) 4. CONCRETE POURING
RECOMMENDED MARK REMARKS 4.1 For manual pouring checklist
(As Per (Correct/
Manufacturer’s Incorrect) 30CM X 30CM X 30CM
Specification) ONE BAGGER MIXER MIXING BOARD MEASURING BOX
Spacer Distances (if applicable)
Frame Distances (if applicable)
Note:
Frame Thk. (if applicable)
4.1.1 Use Rubber mallet during concrete pouring to avoid honeycomb
Cement Mixture 4.1.2 Clean the outer face of the walls right after concrete pouring
Cladding material (if applicable)
Cladding thk. (if applicable) 4.2 Concrete Mixture
Plastering thk. (if applicable) RECOMMENDED MARK (Correct/ REMARKS
Dia. & Spacing of Hor. Bars Incorrect)
Dia. & Spacing of Vert. Bars Approved Mixture
Wire mesh accessories (if app.)
4.3 Concrete Testing
Corner Reinforcing Bars
RECOMMENDED RESULT REMARKS
Size
Slump Test
Spacing
Wire mesh accessories (if app.)
Compression Test
Ties
BOND BEAMS
Name of Testing Company ___________________________
Reinf. Bars Installation
Address of Testing Company ___________________________
C-Bars/Stirrups Installation
Name of Representative
ROUGHING INS NHA Representative ___________________________
Electrical Contractor’s Representative ___________________________
Plumbing Date When Test Was Conducted __________________________
Conforme:
___________________________
Contractor/Developer
Concurred by:
___________________________
Project Manager
44 45
One of the most valuable features of this technology is that its installation is 60%
faster than traditional construction methodologies; the single storey NHA Model for 22
and 26 square meter area can be installed within 6 days. Its smooth surface allows it to
be painted without additional preparation work before painting.
In line with creating disaster resilient housing structures for mass housing, the
structure is designed to withstand a wind load of 250 km per hour and has an earthquake
ECO-KEY SYSTEM – FIBER CEMENT EPS BOARD resistance of more than 9 degrees.
2. Safe
3. Easy to Handle
The Eco-Key System is a fiber cement EPS (Expanded Polystyrene) foam Easy assembly; requiring no special tools and assures no construction waste;
board, a fast and green housing technology solution to modern pre-fabricated recyclable
housing. Made of high strength fibers and cement, it is resistant to water and 4. Fast to Build
moisture, corrosion and acid, and pest damage. Fire tests yield that the system is
Easy to move around; time saving with smooth surface with no need to polish before
A-grade and does not produce toxic fumes. painting; most construction work is done in the factory which saves time on site
Manufactured by pulping, shaping, cutting, pressurizing and steam- 5. Affordable price
curing, the material is absolutely free of toxic substances, such as asbestos,
Saves on labor cost with much faster building speed; installation does not require
formaldehyde, benzene, and others. Its strength enables it to be used for single-
complicated procedure and heavy machine operation on-site, and can easily be
storey as well as multi-storey buildings. The Eco-Key System allows for ease in stored; can achieve longer life span due to typhoon and earthquake proof structure
construction and installation, requiring no special tools and minimizes wastage.
46 47
48 49
50 51
52 53
54 55
56 57
58 59
LIGHT GAUGE STEEL FRAMING SYSTEM
ERECTING
Assembly:
For an NHA house of 22 square meters, 400 linear meters of steel coil are
used. 3 men can take 5 hours to frame and erect or 15 man hours total.
22 square meter house with 3 men, it takes 1.5 hours to fabricate the steel
frames, 5 hours or 15 man-hours to assemble frame and erect, 6.5 hours to
60 61
STEP 3: FOUNDATION
STEP 1: FOUNDATION – STAKING & LAYOUT
62 63
STEP 5: FOUNDATION – CONCRETE FLOOR SLAB
STEP 7: STEEL FRAMING - ERECTION
• The proper position of starter bars should be
checked prior to pouring of slab. Starter bars should
be 10mm Ø x 400 mm spaced at 600mm O.C. An RFI • Start at the external corner; place and plumb
(request for inspection) is required to verify that the a wall frame panel. Install the adjoining
embedded items were placed according to plan. frame to make a self-supporting corner.
64 65
STEP 8: ELECTRICAL & PLUMBING STUB-OUTS
• Install removable forms for interior side of walls first. This is to ensure that all
STEP 9: WALL FORMS roughing-ins are in place.
• Install the removable forms for the exterior side of the wall next. Make sure
the boards are placed up to the finished grade line to achieve a monolithic
concrete mix covering the floor line; also to detain possible water seepage
along floor line level.
• Pouring shall be done at 1.2m lifts maximum with the design ration of 1:5,
flow able type using 1 bagger mixer in a direct concrete placement
method.
66 67
STEP 9: CONCRETE WALL IN-FILL
68 69
LIGHT GAUGE STEEL FRAMING SYSTEM ILLUSTRATION
70 71
PANEL FABRICATION
72 73
74 75
PANEL INSTALLATION
76 77
78 79
POURING OF CONCRETE
80 81
CONSTRUCTION MODULES
82 83
PANEL TYPICAL CONNECTION
84 85
86 87
Starter bars or link bars should be clearly
STEP exposed and free from obstacles prior to
3
installation of Plaswall panel. Once con-
PLASWALL crete slabs are cured, installation of Plas-
wall panel shall commence.
METHODOLOGY
1
specification and details of plans.
4
crete slab, to serve as guide for the rest of the
panels to be erected & also to secure Plaswalls
in place & correct alignment.
STEP
2
Concrete slab should be rough
even finished.
88 89
STEP Before installation, cut panels for the door and
5
window openings, and others, as per specifica-
tion in the plan.
7
lines and plumbing wall roughing-ins are slides
into the panels and cut appropriate holes for
connection of:
6
slide into starter bars or link-bars and rest verti-
cally on the slab.
90 91
Use wall angle or scrap plastic spacer
STEP
9
Temporary braces & horizontal struts should be installed & cut as brackets and screw to support
tied up both sides of the panel to keep the plaswall pan- interconnection of plaswall panels t-
STEP el plumb & upright position. also will help prevent panel section and elbow section.
8
from bulging while concrete pouring. mounted @ 0.30m
and 1.2m from the concrete slab. use leveling bar to
check the plumbness of the panel.
10
vertical and horizontal reinforcement. Spac-
ing of rebars will be based on given plan.
92 93
For filling of concrete inside the plaswall panel use fun-
STEP
11
nel and place it in between plastic spacers. compres-
sive strength and the mixture of concrete will be based
on the structural specification.
CONRETE STRENGTH
CLASS PROPORTION CEMENT SAND GRAVEL
PSI Mpa
AA 1:2:3 12 0.6 1 4000 27.5
13
do not remove the screws but instead pound the screws
until the head of it penetrates the panels and flatten the
STEP
12
Pour concrete inside the panel by level @ 0.30m surface even.
gradually until it fills the entire panel.
14
it skim coat. Polish the surface of the plaswall by sand
paper prior for painting.
94 95
96 97
98 99
100 101
102 103
104 105
106 107
PRE-PAINTED
G.I. ROOFING
Paint Specification
• 0.40 BMT + 0.01mm coating + 0.01mm paint= 0.42mm
• Polyester Paint System
• 2 coat 2 bake process
• Top coat = 10 microns
• Primer = 4 microns
• Black Coat = 5 microns
• Primer = 4 microns
108 109
Steeltech Rib22
Step 1
Canyon Beige
110 111
STEELTECH RIB 22
Installation Visual
Step 2
Install the Steeltech Corrugated Roofing sheets using J-Bolt and lock it
with washer nuts.
STEELTECH CORRUGATED
Installation Visual
ISOMETRIC DETAIL
112 113
PROPER STORAGE
Not following the care and storage instructions may lead to serious product
quality issues such as paint peel off, stains, blistering, corrosion, color changes, etc.
1. Indoor Storage
Storage should be indoors if possible, preferably in a clean, dry area away
from any source of chemical pollution. Since rapid changes in temperature may
cause condensation leading to quality issues, storage should be at an even
temperature. In particular, storage of products on site will be improved by a few
simple precautions:
1). Always stack the Products on metal or wooden skids in tilted position
3). Store away from chemically aggressive substances (e.g. salt, cement,
to keep them from direct contact with the ground, or drainage of water
fertilizer), away from material that could contaminate the surface (e.g.
or moisture and to prevent sagging.
diesel oil, paint, grease) and away from site traffic.
114 115
4) Where possible, do not leave uncovered products stacks lying in the
open. Store them under cover and away from open doorways.
3) Store out of direct sunlight if possible.
2. Outdoor Storage 4) Store away from chemically aggressive substances (e.g. salt, cement,
When storing outdoors in unavoidable, these are the recommendations: fertilizer), away from material that could contaminate the surface (e.g.
1) Always stack the Products on metal or wooden skids in tilted position diesel oil, paint, grease) and away from site traffic.
to keep them from direct contact with the ground, or drainage of water
or moisture and to prevent sagging. 5) The period of outdoor storage should be kept as short as possible.
Particularly during the rainy season because sheets in stack get wet due to
condensation and that the condense water cannot evaporate easily.
116 117
PAINT DELAMINATION
3. When products get wet
Regularly inspect the products during storage preferably at least once a week. If • Soft and pliable paint surface
there is presence of water in the product, please perform the following: • Bubbles underneath the paint surface is present
1) Wipe off the water with clean cloth and allow air circulation to • Paint peeling
complete the drying process.
2) Check presence of water in between sheets, if water is present separate
the wet sheets and place in tilted position so that water will flow until
dry.
118 119
PROPER INSTALLATION GUIDE
120 121
PROPER MAINTENANCE GUIDE
3) Areas not subject to the natural washing action of rainfall, washing of roofing should
be done at least every 6 months and 3 months for coastal areas and in areas near
industrial sites to remove contaminants and prevent accumulation of salty deposits and
WITH REMOVABLE STEEL FORM
industrial debris that may accelerate corrosion.
SPACED AT 900 MM O.C.
4) Remember that accumulation of wind-borne salty deposits in seaside localities can
have a particularly aggressive effect on steel products.
5) Failure of proper maintenance may lead to premature fading and early corrosion of A pre cast, pre stressed concrete product used for floor and roof slab system. It is
the colored roofing. a concrete product with 5,500 psi. and with a pre-tensioned tendons as its
reinforcements. It is basically a concrete joist which supports a suspended
flooring and form part as a slab system.
Widely used on different types of residential and other kinds of buildings. These
are commonly used on mass housing, socialized housing, high end housing,
townhouses and privately owned residences. Also, it is widely used on
commercial buildings, mall buildings, condominiums, walk up buildings, medium
rise and high rise buildings. It is as well applied mostly on government and
private schools, municipal buildings, hospital, churches and other institutional
buildings. Moreover, it is also suitable for light and heavy warehouses, factories,
car parking, stadium and gymnasiums, cockpit arena, amusement park,
agricultural farm buildings and other possible suspended slab construction
122 123
124 125
General Notes
1. Shoring: C-Joist must rest firmly before pouring of concrete slab. Shoring
members must be capable of supporting the dead-weight of C-Joist and
concrete slab. For C-Joist more than five meter (5.0m) span, quarter spacing
of shoring is required. For C-Joist above 3.0 m to 5.0 m span, only midspan
shoring is required. While C-Joist below 3.0 m span, there will be no shoring. C-JOIST with 75 mm thk
CONCRETE SLAB @
2. Removable Steel Forms & Steel Stiffeners can be removed 3 days after the 900 mm SPACING
pouring of concrete slab. However, shoring of C-Joist must remain in place
for not less than seven (7) days.
3. Slab: Concrete slab shall have a minimum fc’ at 28 days = 20.68 Mpa (3000)
psi
Safety
Removable steel forms are temporarily forms to support the concrete during
pouring for safety, it is recommended to walk on C-Joist.
126 127
TYPICAL DETAILS OF CONNECTIONS
128 129
INSTALLATION GUIDE OF C JOIST- RSF
130 131
132 133
MAIN OPERATIONAL STEPS:
1. Anchoring to foundation
2. Assembling the panels
- connecting panels on the rebars
- connecting adjacent panels
EMMEDUE/M2 PANELS - placing of reinforcement meshes
• Used for partitions and claddings, in new building *Value obtained by analytical calculation
construction or renovation; Used for curtain walls and
partitions in large-sized industrial and commercial buildings;
Sound Proofing Index : 45 dB **
• Used for insulating frameworks for roofing and moderate floor span; with or Fire Resistance REI 120 ***
without pre-cast beams. ** Test Carried out on PSM 90 at Santiago del Chile University
134 135
METHOD 2
REBAR SPECIFICATION
1. ANCHORING TO FOUNDATION number, diameter and length accord-
ing to calculations
1. Insert cut rebars on one side first
For example:
The panels are placed over a reinforced concrete foundation slab or strip -diameter 8-10mm
2. Place the panel
foundation beam. The size and characteristics of the foundations should be -interval 30mm(11.8 in)/ 400mm(15.75 in)
determined by specific structural calculations, based on the geotechnical 3. Insert the rebars on the other side -height 400mm (15.75 in)
analysis of the site.
FIX REBARS US-
ING STRUCTURAL
EPOXY; MAKE
THE REBARS ARE TO
SURE THAT BE PLACED ON BOTH
METHOD 1 DRILLED HOLE IS SIDES OF THE PANEL
FOLLOWING A ZIGZAG
PLACING THE REBARS BEFORE CASTING THE DUST FREE
LINE
CONCRETE
136 137
PLACING REINFORCEMENT MESHES
CONNECTING PANELS ON
THE REBARS
ANGULAR MESH FOR WALLS CONNECTION
138 139
3. PLUMBING AND SHORING OF WALLS 4. PLACING REINFORCEMENT ON DOORS AND WINDOWS
DOORS
ANCHORING
140 141
5. ROUGHING-IN INSTALLATION 6. STRUCTURAL SHOTCRETE APPLICATION
Roughing-in can be
installed by melting the polystyrene
using a blow torch or a heat gun;
142 143
SRC PANEL
Use Steel Reinforced Concrete (SRC) Panel System for Walls, Roofs and
Floors as a modern alternative to CHB (Concrete Hollow Blocks)
Today, SRC Panel System has paved the way to a new generation of
building construction material which is more economical, faster, and allows for a
much safer structure.
144 145
Build beautiful homes that are structurally superior. TECHNICAL SPECIFICATIONS
Every panel goes through a unique and special process that guarantees
The Steel Reinforced Concrete (SRC) Panel System is a wall board that is made
superior quality. up of styrofoam, welded wire mesh, slant wire, and mortar plaster, used to build
Plus, the EPS core’s acoustic and thermal insulation properties will reduce noise walls, roofs and floors, each performing a solid structural formation.
and will keep the cool air inside even after the air-conditioning has been turned
Styro Thickness
off.
1.50”, 2.00”, 2.50”, 3.00”, 3.50”, 4.00”
SRC Panel System will make your house a BETTER investment.
Length of Panel
2.40 m up to four (4) meters
Economical Flexible Core
Fire Resistant Lightweight Expanded Polystyrene (EPS), Fire retardant grade
ERECTION 1. 2.
ALIGNMENT: Once the SRC PANELS are installed, they are aligned and
plumbed, using rigging bars and wood as shoring. They may be placed on the
exterior or interior of the structure, depending on the building strategy adopted.
148 149
5. 6.
9. 10.
7. 8.
11. 12.
150 151
a. Inspect vertical installation
SRC PANEL SYSTEM METHODOLOGY b. Ensure PANEL Alignment
c. Check reinforcement/bracing of structure
SRC PANELS USED AS FLOOR SLAB AND ROOFING: d. Restore wire mesh that were previously cut during rough-in installation
Basically, the same instructions as for the installation of vertical panels e. Apply 1st plaster coat on external side of the wall, let this plaster settle for a
apply. The panels should be joined together, anchored to the walls with GI tie day before applying the 2nd coat or final plaster.
wires and temperature bars as additional reinforcement at the bottom of the
slabs and roofs. These temperature bars give additional strength on bending. 2. SLABS: Prior to plastering, the following checklist should be in order:
The spacing of these bars depends on the type of usage/occupancy for the a. Inspect horizontal installation leveling
building. These PANELS work as unidirectional slabs with the longitudinal panel b. Ensure all connectors/reinforcement in place
running along the shorter span of the area to be covered. For floor PANELS, c. Restore wire mesh that previously cut during rough-in installation
interior beams/support should be constructed around the perimeter of the d. Check the shoring for a correct positioning to avoid sagging of SRC PANEL
structure and in specific cases, including partition areas. Concrete casting for slabs
slabs/roof requires shoring to limit PANEL deflection. e. Apply 1st coat on the bottom portion of the slabs, let this settle for day
before applying the 2nd coat or final plaster
ROUGHING-INS: Installation of electrical, plumbing, heating, telephone and f. Pour concrete on top slabs using a 3/8” crush gravel with the design
other systems are done by melting/cutting the polystyrene using a hot air or any thickness
simple cutting tools. This is done after the complete erection of the PANELS and
before the plastering phase. In case of rigid pipes, the mesh can be cut open, 3. ROOFING: Prior to plastering the following checklist should be in order:
the pipe then fitted in the polystyrene. It is important for the affected area to be a. Inspect the slope of the roof level
restored by means of a reinforcement mesh. b. Ensure all connectors/reinforcement in place
c. Restore wire mesh that were previously cut during rough-in installation
PLASTERING: d. Check the shoring for a correct positioning to avoid sagging of SRC PANEL
1. WALL PLASTERING: Characteristic of the structural plaster has a grain size from roofings
0 to 5mm. Once cured, its resistance has been gauged to be approximately 200 e. Apply 1st coat on the bottom portion of the roof, let this settle for a day
kg/sq.cm or about 2,844psi. Prior to plastering the following checklist should be in before applying the 2nd coat or finishing
order: f. Apply 1st coat plaster on top portion of the roof with a 0.5 bag of sahara
mixed with a bag of cement to prevent leak
152 153
g. After this coat has settled, apply a black cortal asphalt to the entire surface of
the roof for water proofing purposes
h. Apply the final coat plaster with a 1:1 mixed of sahara for leak prevention
i. Final application/coating of waterproofing paint.
ANNEX
SUMMARY OF ERECTION PROCESS
• Construct wall foundation
• Install SRC PANELS
• Install connectors reinforcement to required areas
Hands-on Training Seminars for the Proper Construction
• Prop, secure, align and plumb wall panels Methodologies of DPWH Approved and AITECH
• Install window sills and door jambs with proper form for concrete application; Accredited Technologies
this may be done at a later stage provided that the openings are not totally
finished plaster
• Install all roughing-ins
• Apply 1st plaster coat on external side of the wall
• Simultaneously install SRC PANEL roof and all roughing-ins
• Secure roof PANELS with tie wires and reinforcement completed
• Prop up roof PANELS with shoring materials
• Pour concrete mix to roof area with water proofing materials
• Install electrical, plumbing and other accessories
• Apply necessary coverings such as paint, tiles, etc.
154 155
HANDS-ON TRAINING FOR DPWH-APPROVED AND AITECH ACCREDITED
TECHNOLOGIES
MAY 11-15, 2015; HTREX BUILDING, NHA COMPOUND, DILIMAN, QUEZON CITY Day 2: Actual Demonstration by Ecostrong Builders Corp. & Permaforms Inc.
The Hands-On Training had resumed on the second day with Ecostrong
These are the proceedings of the Hands-On Training for DPWH-Approved Builders Corporation’s and Permaforms Incorporated’s actual board-up demo
and AITECH Accredited Technologies held at the Housing Technology Resource on the front and side walls of the prepared module. Their technologies are
and Exhibit Center Building, NHA Main Compound, Elliptical Road, Diliman, panels that incorporate plastic spacers for the rebars, finished on each side with
Quezon City. The training for NHA staff was conducted last May 11 – 15, 2015. fiber-cement boards that are attached by special glue on the spacers,
Participants were technical staff from the Visayas Management Office, fabricated off-site and assembled easily on site before pouring.
Mindanao Management Office, Southern Luzon-Bicol Office, Project Operations
Support Service Office, Housing Technology Development Office and the Day 3: Actual Demonstration by Nedsteel Construction and Development Corp.
General Services Department. The third day opened with the demonstration of Nedsteel Construction
and Development Corporation installing their Light Steel Framing System for the
The technology providers involved in the training, namely Ecostrong rear wall of the mock-up. The Light Steel Frames were clad with fiber-cement
Builders Corporation, Permaforms Incorporated, Nedsteel Construction and boards that were screwed and secured in place with C-channels before
Development Corporation, Noellouise Custom Furniture and Fitouts Corporation, pouring. In the afternoon, concrete pouring for the in-fill began. Concerns were
and United Steel Technology Corporation, submitted housing design models addressed regarding the correct pouring technique to avoid segregation of
using their AITECH-accredited technologies for review and approval by both the aggregates.
NHA and the DPWH.
Day 4: Roofing Frame Installation and Presentation for the Doors and Windows
The following is an overview of the five days training and the highlights of the The proponents finished the concrete pouring for their walls, and NCDC
program: simultaneously installed the roof framing. In this case, Nedsteel has already pre-
assembled the rafters and trusses prior to the actual installation. The door and
Day 0: Preparation of Foundation and Slab On-Fill window assemblies are provided by Noellouise Custom Furniture and Fit-Outs
Prior to the training, Permaforms Incorporated had already prepared the Corporation, together with its partner, Titan Doors.
foundation and slab for actual construction. A 4.00m x 4.00m module was
prepared in the area between the NCL Office and the HTREX Building where the
proponents held a construction demonstration as part of the training.
158 159
Likewise, Permaforms Inc. addressed concerns on the reports of
Day 2: Actual Construction Demonstration by Permaforms Incorporated segregation of aggregates in the said technology, and thus a recommendation
The participants headed to the project site in Babatngon, Leyte, where of laying the boards horizontally to enable pouring at the proper height was
the site of Phase 2 of the Channel Ridge View project is located. The said made. The company agreed to do a study on the possible implications of this on
project is already implementing the DPWH-approved 28.6 square meter housing the cutting list and the cost. It was also agreed upon that fabrication of the
design model by Permaforms Inc. The presenters from Permaforms gave notes panels by the contractors will no longer be allowed to ensure that the quality of
on the precautionary measures for installing the panels and concrete pouring, the materials will not be compromised.
which are crucial to the technology.
The training concluded on a general discussion on the approved plans
Day 3: Actual Construction Demo by Nedsteel Construction & Dev’t. and the processes should contractors decide to change from using
Corporation, Steeltech and Greenway conventional materials to new technologies.
The second mock-up unit based on Nedsteel’s 26 square meter housing
design model was done within the compound of the NHA Office in Tacloban,
where Nedsteel demonstrated the installation of the framing and the rafters for
the roof. Steeltech also had a small mock-up of their own, where they showed
how the J-Bolts are installed and demonstrated how to check the thickness of
the roofing sheets. Greenway Toilet Solutions also demonstrated the installation
of the water recycling unit for the toilet and bath of the 26 square-meter mock
up.
160 161
HANDS-ON TRAINING FOR DPWH-APPROVED AND AITECH ACCREDITED
TECHNOLOGIES
JUNE 22 – 24, 2015; NHA LEYTE – SAMAR PROJECT OFFICE, TACLOBAN CITY Day 3: Wrap up and Awarding of Certificates
Day 1: March 10, 2016, NGC Project, Holy Spirit, Quezon City; and Camarin Certificates were awarded after the workshop for the participants who
Residences, Camarin, Caloocan City successfully completed the three-day
The participants of the training proceeded to the NGC site in Brgy. Holy
Spirit, Quezon City, for the actual demonstration of the installation for SRC Panels
and Steeltech Steel Decking. The concerns expressed during the previous day
were addressed here, as the contractor of NGC performed the installation at
SRC and Steeltech representatives’ careful attention and guidance. Then the
groups proceed to the Camarin site, where Next Century’s M2 Panels and
Concrete Ventures’ C-Joist are already installed. The actual demo allowed for a
better understanding of the technologies as installed on site. Because the
contractor has already finished installing the C-Joist and concrete pouring,
Concrete Ventures brought a mock-up for the participants to view as the
technical providers explained the technology.
164 165
HANDS-ON TRAINING FOR ECO-KEY SYSTEM BY PALIGID DEVELOPMENT
CORPORATION
DECEMBER 16, 2015 AND JANUARY 08, 2016; NHA MAIN COMPOUND, ELLIPTICAL RD.,
DILIMAN, QUEZON CITY One of the most valuable features of this technology is that its installation
is 60% faster than traditional construction methodologies; the single storey NHA
Model for 22 and 26 square meter area can be installed within 6 days. Its smooth
surface allows it to be painted without additional preparation work before
painting.
On December 16, 2015, the National Housing Authority facilitated its
fourth Hands-On Training for the new technology, Eco-Key System.
Spearheaded by the Housing Technology Development Office, and in
partnership with Paligid Development Corporation, thirty-five of NHA’s technical
staff participated in the lecture presentation and the ensuing actual
demonstration that showed its unique construction methodology. A model
house had been constructed in the Main Compound adopting the NHA 26 sq.
m. house model to showcase the adaptability of the technology to the
Agency’s housing design.
166 167
HANDS-ON TRAINING FOR AITECH ACCREDITED TECHNOLOGIES FOR NCR
PROJECTS Below are the proceedings of the Hands-On Training Seminar:
MARCH 9 TO 11, 2016; NHA MAIN COMPOUND, ELLIPTICAL RD., DILIMAN,
QUEZON CITY Day 1: March 9, 2016, HTREX Lobby
The Seminar began with a word of prayer and the singing of the
Philippine National Anthem. Ar. Maria Benita O. Regala, Department Manager
The three day training held March 9 to 11, 2016, had been attended by of HTDO, opened the Seminar with a few insightful words on the need to train
more than 50 NHA technical personnel from the NCR Program and Project NHA staff as well as our partner companies and contractors to ensure the
Offices, HTDO, and contractors’ representatives and foremen. This is the second excellent quality of work for the Agency’s beneficiaries. A review of the past
Hands-On Training Seminar for the year 2016, and puts the focus on the Hands-On Training Seminars and their outputs were mentioned to further
technical education on the installation of AITECH Accredited technologies for In emphasize the importance and the expected results from the Training.
The presentation began with SRC International Panel System Incorporated’s SRC
-City Resettlement Projects, particularly the 5-Storey Medium-Rise Building Panels, with a short glimpse of the company’s history in the construction industry
Models by the NHA. and a detailed technical lecture on the right installation methods and
construction look-outs. Next, United Steel Technology International Corporation
This Hands-On Training Seminar featured the following technologies, to wit: showed their step-by-step installation methods for Steeltech Steel Decking. The
•Concrete Ventures, Incorporated, C-Joist representatives also shared their dos and don’ts on site, crucial points and
practices that ensure the quality of the said technology is kept.
•Next Century Building Systems, Inc., M2 Panels
•SRC Int’l Panel System, Inc., SRC Panel In the afternoon, Next Century Building Systems Incorporated opened
•United Steel Technology International Corporation, Steeltech Steel Decking the lectures. Due to the similarity between SRC Panels and M2 Panels, the
representatives showed the unique lookout points for their technology and the
The four technologies were presently being used in the NGC Projects in differences in the methodology and accessories as applied in their technology.
Concrete Ventures’ C-Joist was the last to present, and gave a detailed
Brgy. Holy Spirit, Quezon City and the Camarin Residences in Caloocan City.
installation method with drawings of the sequencing of work in installation.
168 169
HANDS-ON TRAINING FOR AITECH ACCREDITED TECHNOLOGIES FOR SAMAR/
LEYTE PROJECTS
MARCH 10 TO 12, 2016; HOTEL ALEJANDRO, PATERNO STREET, DOWNTOWN, TACLOBAN Below are the proceedings of the Hands-On Training Seminar:
CITY, LEYTE
Day 1: May 10, 2016, Alejandro Hotel
The seminar began with a word of prayer and the singing of the
The three day training held May 10 to 12, 2016, had been attended by Philippine National Anthem. Engr. Jovita G. Panopio welcomes all the
more than 50 NHA technical personnel from the Region 8 Project Offices, HTDO, participants and urged them to listen very carefully on the presentations to be
and developers. This Hands-On Training aims to provide technical staffs the right discussed. SKS Construction and Development Corporation was the first
installation of DPWH-Approved and AITECH-Accredited Technologies, presenter. The talk started with a brief discussion of the company’s history
particularly for Rowhouse Projects under the Yolanda Program. followed by the technology’s detail and method of installation.
This Hands-On Training Seminar featured the following technologies, to wit: After the presentation of SKS, POSSO’s Department Manager, Engr.
•SKS Construction and Development Corp., SKS Steel Framing System Eclavea discussed about the MC 2775 on the Guidelines and Procedures on the
•United Steel Technology Int’l Corp., Steeltech Roofing Issuance and Approval of Work Suspension Order, Work Resumption Order and
•Permaforms Inc., Permaforms Contract Time Extension. It was clarified in the discussion that no Work
Suspension Order be given for rainy days but a monthly time suspension report
The three technologies were presently being used in the Basey Pointe, be filled up for a month which will be accumulated and be subject for time
Basey Samar and Guadalupe Heights 3, San Isidro, Tacloban City. extension.
170 171
HANDS-ON TRAINING FOR AITECH ACCREDITED TECHNOLOGIES FOR SAMAR/
LEYTE PROJECTS
MARCH 10 TO 12, 2016; HOTEL ALEJANDRO, PATERNO STREET, DOWNTOWN, TACLOBAN The proper installation of walls and concrete pouring were also shown.
CITY, LEYTE Series of questions and observations during the actual demo were noted and
are included in Annex ‘A’ attached with this Memorandum.
Then, United Steel Technology proceeded with their presentation. They
discussed the company’s profile, projects using their technology and the
description of the roofing sheets they are using in their projects, mainly the Day 2: May 11, 2016, Afternoon Session, Hotel Alejandro
915mm and 1120mm effective width. Lastly, the Permaforms, Inc. presented a The Hands-on Training concluded on May 11, 2016 in the afternoon. At
video on the installation methodology of their technology and discussed it one
by one. The video comprised of the fabrication of the panels, the cutting of the start of the program, the participants were given time to ask questions
panels to size according to layout plan, and the foundation layout, installation regarding their observation in the site using the technologies and are included in
of walls, connection of panel to panel, the setting up of reinforcement and Annex ‘A’ attached in this Memorandum.
concrete pouring.
The Hands-on Training ended with the awarding of certificates to the
In the afternoon, the participants proceeded to Basey Pointe, Basey, participants who successfully completed the training. This signified that the
Samar, for the actual demonstration of the installation of the SKS Steel Framing recipients are certified to install and check technologies on site.
System. The presenter prepared the stages of construction of the technology
from foundation to roof installation to better understand the earlier presentation.
The speaker gave emphasis on the crucial part of the system such as the
connection of wall to purlin, purlin to rafter connection and the correct
orientation of the steel frames which is a crucial look-out point.
Day 1: May 11, 2016, Morning Session, Guadalupe Heights 3, San Isidro, Tacloban
City
172 173
PROPONENT’S DIRECTORY Next Century Building System, Inc.
1011 The Infinity Tower, 26th St., BGC Taguig City
Concrete Ventures Group, Inc. 207, Carolina Mall, Sta. Rosa—Tagaytay Rd., Silang
36 1st Avenue, Cubao, Quezon City Cavite
Paula Dulalia The HTDO is also in charge of the development of the master plan and the
Marketing Manager supervision of construction of new structures in the NHA Main Compound per Office
Josephine Castillo Order No. 9545 dated June 10, 2010. It coordinates with other government agencies and
other organizations on matters pertinent to housing and planning (e.g., disaster risk
Business Development Officer
reduction, climate change adaptation, green building, gender sensitivity) to enhance
567-3668 to 79 / 0917-510-0918 / 0917-671-1746 the NHA’s capacity in carrying out its mandate. Moreover, HTDO aims to encourage the
castillo.marie@steeltech.com.ph use of innovative housing technologies, materials and building systems as an alternative
dulalia.paula@steeltech.com.ph to the traditional housing construction system.
176 177