CABLE TERMINATION INSPECTION REPORT

COASTAL GUJARAT
PROJECT : COASTAL GUJARAT POWER LIMITED - 4000 MW POWER LIMITED
STERLING & WILSON (800 MW X 5) THERMAL POWER PROJECT, MUNDRA, KUTCH
PVT. LIMITED DOCUMENT NO: SW-CGPL-HVAC-QCP-23
REPORT NO. : S & W ORDER No.: DATE:

PAGE: 1 OF 1
System No.
System Description
Subsystem No.
DRAWING NO. Area / Location
Equipment Tag No.
General Visual Checking
Results
Item No. Description
Accepted N/A Rejected
1 Cable are ready for termination
2 Cable glands are as per hazardous area classifications.
3 Cable stripping method is correct.
4 Cable glands are assembled correctly
5 Glands are tightened as specified.
6 Cable routing inside the panel is correct.

7 Shrouds and earth connections are installed wherever applicable.

8 Crimped lugs are installed correctly and of correct size and type.

9 Cable connections are as per the drawing.


10 Cable connections are tightened as required.

11 Cables are identified as specified and enough slack tail is left.

12 Spare cores are identified and connected to earth.


13 Approved construction material are used.
14 Record resistance of gland body to earth (Maximum 0.1 ohm).
15 Ensure IP sealing washers are fitted to glands where required.

16 All nut bolts are tourqued properly.

Remarks :

EQUIPMENT / SYSTEM MECHANICAL COMPLETION ACCEPTED :

WITNESS S&W CGPL

Signature

Name

Date