MOM - Engineers Alignment Meeting - 04 June 2021
MOM - Engineers Alignment Meeting - 04 June 2021
II. AGENDA:
DUCTBANKS
NURSERY 1-4 SOW SITE Sir Marvin
-Washed Sand Availability is the concern- needed for backfilling
- only 2 pull boxes remains along the road side
NUCLEUS UPDATES
1. Powerhouse Nucleus
-Painting and plastering activities also ongoing Sir Marvin ONGOING
-Manpower focuses on Nursery 3 for turnover
1. Breeder Gestation
-Paneling Works done including back gable
-EE room Works done- query on the presence of door near EE
room- to check RFI's Sir John
-Ceiling installation is almost done
-Pavement North side is ongoing- concern is the availability of INFO
dump trucks to directly haul excavated materials
3.Site Development
-Pending culvert- to be delivered on Monday
-Rainwater collector tank is not located near farrowing culverts will Sir Clark
be installed instead.
-Priority is the finalization of the Access Roads to Nucleus and
Phase 4 B
-Check on slope Protection Works
-CHB Production kindly check efficiency of workers
PROJECT UPDATES
Pre-Assembled Bin-703
Alley slab Backfilling -
CHB Pit walls construction Sir Clark
Plastering works
POWERHOUSE NUCLEUS
-Clearing activities
-Doors and Windows fabrication- ongoing- request for 2 shift on
fabrication
-Doorways and window ways -ready
-Painting Works on Purlins
-Genset to arrive 6 months away -works must proceed
ELECTRICAL UPDATES:
DUCTBANKS NURSERY 1-3
Sow Site- ongoing on nursery 1
Nursery 2- Lights installed okay- temporary to provide lights for
night shift
Inlet for Farrowing and Breeder Gest- done
Cline's flashing is the critical activity on Nucleus nursery 3
NUCLEUS:
1. Nursery 3 Nucleus
- Remaining Work is the leak found on the Gas Line of repair
-Painting Works on Building Sir Arche
- Hopefully to be Turned-Over on May 29,2021
2. Nursery 4 Nucleus
-Ongoing RC Wall Installation on Grid B to complete on May
29,2021
-To proceed directly to securing connections
4. Site Development
-Ongoing Excavation Activities on Finisher and Nucleus Phase 1
-Excavated 100/248m at 40% accomplishment Sir Clark
1.Nursery 4 Nucleus
- Masonry Works on Grid B
- To clearing in between Nursery 3 and 4 ,then to proceed to Sir Arche
Doghouse Works and EE Room
-Start Pavement and Canal Works Between Nursery 3 and 4
- Excavate Foundation Bed on Grid A if the culverts in front of
Nursery 4 is repaired.
3.Site Development
-Priority is the Excavation Works on Finisher and Nucleus 1 Sir Clark
- Benching near Boarstud Building
-Culvert installation at Nucleus Storm Drain near Farrowing
4.Powerhouse Nucleus
-Painting and Plastering Works must be completed including
Roofing Works Sir Marvin
-electrical team must finalized placement and location of all their
panels
5.Plumbing Team
-To excavate at center of Boar stud building Sir Moi
SOW SITE
1. Breeder Gestation
Remaining Works are Penning Installation, Waterline, Feeder Sir John
Line, Electrical Works, Pavement and Canal North side
3. Surveying
-Done staking sat Boar Stud Ma'am Lyca
-Done confirming Gate Location
2.Breeder Gestation
- Shutter installation on Front Gable Sir John
-Pavement and Canal Works North side
-Penning Installation
-Log Screw installation- team will try to use ordinary hose filled
with epoxy and then drilled with screw.
5. Plumbing Team
-Backfilling works on Nursery 1 Sow Site
-Excavate Slurry Line form Nursery 3 to ICT Sir Moi
-connection of slurry from Nucleus is From Finisher 7 down to
Breeder Gest (langkoy). Kindly send RFI regarding the slurry
Flow.
-Finisher 1 Sow site also needs sand to start sand bedding works
-Kindly check existing Electrical post because it's in conflict with
slurry line location
6. CHB Fabrication
-Monitor CHB Production Sir Mike
-2 machines working-1 for each size
8. Nursery -
-Bamboo planting- How many must be planted- proper nurturing Sir John
and growing
9. Surveying
-Markings for Finisher Sow site Maam Lyca
-IR Checking
- Get coordinates of all as built
-Site Dev't for Breeder
3 OTHERS
1. FREE Meals on all Workers
- No work no Free Meal Project
-all Staff are advised to get their meal allocations supervisors
2. Documentations will be intensified on new contract- trade test
documents must be submitted on time.
3. All worker will be enrolled to Jeonsofr- All P.S must submit list
of workers
4. There might be a rate change though minimal on workers -
please properly disseminate infos about this.
Biotech Farms, PMG prepared these minutes for recording the information discussed at the meeting. Should anyone object to the statements or
interpretations contained herein, please advise Joyce T. Maglasang (rce.joycemaglasang@gmail.com)
Prepared by:
Joyce T. Maglasang,CE,RMP
AMCOOP
Noted by:
Joven Sore
Planner/Scheduler
Project Management Group
Biotech farms Incorporated