Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

MINUTES OF MEETING

I. Date of Meeting 04 June 2021 Time: 5:25PM-8:00PM Meeting No: 9


ATTENDEES:
NAME FIRM NAME FIRM
Joven Sore BFI-PMG Jerry Carreon Jamvi
Arche Vale Alibiano Jamvi Tj Tugari Jamvi
Robert Jay Villanueva Jamvi Clark Aranas Makima
Jennie john Agoot Jamvi Marvin Castulo Makima
Michael Vincent Calaque Amcoop Leonardo Polido BFI-PMG
Lyka San Gaspar Amcoop Kessil Mae Dedicatoria Makima
Randolph Brana GEIS Febert billones BFI-PMG

II. AGENDA:

1. Review of Week 21 Minutes and New Updates


2. Project Updates and Look ahead Plan for Week 23
3. OTHERS

III. MEETING SUMMARY


S/N Topics Action by Target Date Status &
Remarks
PROGRESS & PROGRAM
GENERAL UPDATE
1. Review of Week 21 Minutes and New Updates

Update on Perimeter Fences


-Staking already done,Manpower already deployed INFO
-Downtime workers are the ones assigned for this

Site Development Updates General


-Excavation between Finisher and Nucleus Ongoing
-Maam Lyca, Sir Clark and Sir Mike will team up
-Kindly observe on the embedded pipes during excavation
INFO
Cistern 1000 cu.m
-Inspection Request for Leak Test, Leak Test will be done on
Monday

ICT POWERHOUSE INFO


- Slab where the Container Van is to be placed is ready, where is
the container van??
-ICT post locations not yet finalized
- INFO

POWERHOUSE SOW SITE


-Lacking post to be installed -to finalize exact locations
INFO

DUCTBANKS
NURSERY 1-4 SOW SITE Sir Marvin
-Washed Sand Availability is the concern- needed for backfilling
- only 2 pull boxes remains along the road side

NUCLEUS UPDATES
1. Powerhouse Nucleus
-Painting and plastering activities also ongoing Sir Marvin ONGOING
-Manpower focuses on Nursery 3 for turnover

SOW SITE UPDATES

1. Breeder Gestation
-Paneling Works done including back gable
-EE room Works done- query on the presence of door near EE
room- to check RFI's Sir John
-Ceiling installation is almost done
-Pavement North side is ongoing- concern is the availability of INFO
dump trucks to directly haul excavated materials

1. Farrowing 1 Sow Site


-Alley Slab Ongoing
-slats installation ongoing- Kindly post to crystal spring group on
whats app on any concerns regarding installation INFO

2. Powerhouse Sow Site (Almost done)


-Start Punch list for Powerhouse Maam Joan Week 22
-Waiting for Panels to be placed inside prior to closing all walls

3.Site Development
-Pending culvert- to be delivered on Monday
-Rainwater collector tank is not located near farrowing culverts will Sir Clark
be installed instead.
-Priority is the finalization of the Access Roads to Nucleus and
Phase 4 B
-Check on slope Protection Works
-CHB Production kindly check efficiency of workers

PROJECT UPDATES

Pre-Assembled Bin-703
Alley slab Backfilling -
CHB Pit walls construction Sir Clark
Plastering works

ICT 2 AND 3-MAY 30 DEALINE


-Excavated- rebars prefabricated
Pedestals- rebars fabrication ongoing
Pipes -laid
Machines-waiting for hdpe machines
Materials -complete
Welding Machines fo HDPE- still used in Slaughter

SLURRY LINE SOW SITE


Lacking Nursery 1- hampered due to heavy rains- canals already
excavated today-
Nursery 3 to ICT pipes- Materials mechanical at back of
powerhouse
PLUMBERS ON SITE
13 pax day shift
13 pax night shift
Evaluate manpower requirement:

POWERHOUSE NUCLEUS
-Clearing activities
-Doors and Windows fabrication- ongoing- request for 2 shift on
fabrication
-Doorways and window ways -ready
-Painting Works on Purlins
-Genset to arrive 6 months away -works must proceed

LAND DEVELOPMENT,STORM DRAIN AND RAINWATER


COLLECTION TANK
-Newly installed rainwater tank destroyed due to heavy rains,
Culverts from Finisher 1 used in Transformer used in Nucleus for
Catch Basin- Farrowing
Rainwater- pending depends on equipment availability
Problems- Equipment concerns

ELECTRICAL UPDATES:
DUCTBANKS NURSERY 1-3
Sow Site- ongoing on nursery 1
Nursery 2- Lights installed okay- temporary to provide lights for
night shift
Inlet for Farrowing and Breeder Gest- done
Cline's flashing is the critical activity on Nucleus nursery 3

2. PROJECT UPDATES AND LOOK AHEAD PLAN

NUCLEUS:

1. Nursery 3 Nucleus
- Remaining Work is the leak found on the Gas Line of repair
-Painting Works on Building Sir Arche
- Hopefully to be Turned-Over on May 29,2021

2. Nursery 4 Nucleus
-Ongoing RC Wall Installation on Grid B to complete on May
29,2021
-To proceed directly to securing connections

3. Boar Stud Building and Office


-Partial number of workers have been deployed to at least start
work
-Stiffener Beam Works ongoing

4. Site Development
-Ongoing Excavation Activities on Finisher and Nucleus Phase 1
-Excavated 100/248m at 40% accomplishment Sir Clark

Activities for Week 22:

1.Nursery 4 Nucleus
- Masonry Works on Grid B
- To clearing in between Nursery 3 and 4 ,then to proceed to Sir Arche
Doghouse Works and EE Room
-Start Pavement and Canal Works Between Nursery 3 and 4
- Excavate Foundation Bed on Grid A if the culverts in front of
Nursery 4 is repaired.

2.Boar Stud Building and Office


- Stiffener Beam Works Sir Arche
-Hauling of Steel Structures
-Pedestal Grouting and Correction
-To erect remaining 6 pedestals

3.Site Development
-Priority is the Excavation Works on Finisher and Nucleus 1 Sir Clark
- Benching near Boarstud Building
-Culvert installation at Nucleus Storm Drain near Farrowing

4.Powerhouse Nucleus
-Painting and Plastering Works must be completed including
Roofing Works Sir Marvin
-electrical team must finalized placement and location of all their
panels

5.Plumbing Team
-To excavate at center of Boar stud building Sir Moi

SOW SITE

1. Breeder Gestation
Remaining Works are Penning Installation, Waterline, Feeder Sir John
Line, Electrical Works, Pavement and Canal North side

2. Farrowing Sow site Sir John


-Ongoing Slats installation

3. Surveying
-Done staking sat Boar Stud Ma'am Lyca
-Done confirming Gate Location

ACTIVITIES FOR WEEK 22

1.Site Development Sir Mike


- Priority is the NGl Leveling at Finisher Sow Site
- to check plans on Slope Protection to start Gabion Works near
Breeder Gestation Sir Clark
-Manpower must be allocated, kindly coordinate with the P.E and
P.S for Manpower Distribution

2.Breeder Gestation
- Shutter installation on Front Gable Sir John
-Pavement and Canal Works North side
-Penning Installation
-Log Screw installation- team will try to use ordinary hose filled
with epoxy and then drilled with screw.

4. Farrowing Sow site


-Slats installation Sir John
-Alley slab Backfilling
-EE Room and Pavement Canal

5. Plumbing Team
-Backfilling works on Nursery 1 Sow Site
-Excavate Slurry Line form Nursery 3 to ICT Sir Moi
-connection of slurry from Nucleus is From Finisher 7 down to
Breeder Gest (langkoy). Kindly send RFI regarding the slurry
Flow.
-Finisher 1 Sow site also needs sand to start sand bedding works
-Kindly check existing Electrical post because it's in conflict with
slurry line location

6. CHB Fabrication
-Monitor CHB Production Sir Mike
-2 machines working-1 for each size

7. Canal near Valdez


-Long term solution is to provide deep canals- to check flow and Sir Mike
volume during heavy rain

8. Nursery -
-Bamboo planting- How many must be planted- proper nurturing Sir John
and growing

9. Surveying
-Markings for Finisher Sow site Maam Lyca
-IR Checking
- Get coordinates of all as built
-Site Dev't for Breeder

3 OTHERS
1. FREE Meals on all Workers
- No work no Free Meal Project
-all Staff are advised to get their meal allocations supervisors
2. Documentations will be intensified on new contract- trade test
documents must be submitted on time.
3. All worker will be enrolled to Jeonsofr- All P.S must submit list
of workers
4. There might be a rate change though minimal on workers -
please properly disseminate infos about this.
Biotech Farms, PMG prepared these minutes for recording the information discussed at the meeting. Should anyone object to the statements or
interpretations contained herein, please advise Joyce T. Maglasang (rce.joycemaglasang@gmail.com)

Prepared by:

Joyce T. Maglasang,CE,RMP
AMCOOP

Noted by:
Joven Sore
Planner/Scheduler
Project Management Group
Biotech farms Incorporated

You might also like