Professional Documents
Culture Documents
How To Create Layout For Operations Flow: Value Chain Competitiveness (VCC)
How To Create Layout For Operations Flow: Value Chain Competitiveness (VCC)
How To Create Layout For Operations Flow: Value Chain Competitiveness (VCC)
Operations Flow
Value Chain Competitiveness (VCC)
Version: 1
December 2019
This information is provided by Rolls-Royce in good faith based upon the latest information
© 2019 Rolls-Royce | Not Subject to Export available to it; no warranty or representation is given; no contractual or other binding
Control commitment is implied.
2
How to Create Layout for Operations BACK Map NEXT
Flow
Scope Objectives & Principles
Prerequisites
2. Define product
1. Define scope Gate Gate
families and
Start and understand Check Check
list degree of process list
facility types
dedication
Gate 3. Determine
Check material flow and
list design the layout
End
© 2019 Rolls-Royce
3
© 2019 Rolls-Royce
4
A world class production/assembly facility (or cell) will draw on Visual Management principles and
techniques to ensure:
• Flow of material and information is easily identified
• Performance and status of output, equipment, quality and delivery status are monitored in real time
and deviation from expectation dealt with in a timely manner
© 2019 Rolls-Royce
5
1. Implement appropriate facility type 2. Focus on products and their 3. Minimise distance
based on volume and variety of value streams, not processes. travelled, eliminate
products. Flexible cells, high volume Group products into families backtracking and cross-
dedicated facilities or a combination. that have similar process traffic of material flow for
flows and takt times. safe, productive
Integrated Programme operations.
Management Cellular Layout Plan Project Manager
Engineering Scheduling
Product Cell A
Production Despatch
August September
13-Aug
20-Aug
27-Aug
10-Sep
17-Sep
24-Sep
Richard Oram
30-Jul
Target Week
6-Aug
3-Sep
1-Oct
Comp Date
Milestone Description
Number
Owner
Process Flow
Stephen McKenzie (SM) 100%
33 PW 3 Material flow process determined Peter Winton (PW) 80% Engineering Scheduling Production Despatch
33 SM 4 Conceptual layout of cells designed within whole facility Rob Poyner (RP) 100%
34 RO 5 Detailed layout of cell A designed Neil Richards (NR) 100%
35 RO 6 Process operator work combination documented Matt Spooner (MS) 30%
37 RO 7 Cell A physical layout completed Paul Cooper (PC) 30% Product Cell C
38 RO 8 Cell A workplace organisation completed Tom Fellows (TF) 30%
Engineering Scheduling Production Despatch
38 RP 9 Line side material storage integrated Simon Chalk (SC) 70%
38 RO 10 RRPS visible standards deployed
Procurement
Maintenance
39 PW 11 Process operators trained Project Sponsor Date
Despatch
Logistics
Royan Anthony
HR
On Schedule Overdue on milestone, recovery plan on schedule, expect to achieve project on time
Off Schedule, expect to complete milestone on time Overdue on milestone, recovery plan behind schedule, expect to achieve project on time
Off Schedule, expect to complete milestone late Overdue on milestone, recovery plan behind schedule, expect to achieve project late
Aligned
Organisation
Optimised Layout
4. Build quality into the process.
High process capability prevents 6. Ensure flexibility of
making a defect, error proofing 5. Separate machine time layout and response to
and over-checking prevents from human work, change of requirements
passing a defect on. balance to takt time and within the layout design.
eliminate waste.
© 2019 Rolls-Royce
6
© 2019 Rolls-Royce
7
Knowledge:
• Understanding of Lean Manufacturing principles
• Understanding of Value Stream Mapping techniques
• Planned products & volumes and bill-of-materials
• Processes, machines, routings and times (manual and auto)
• Planned level of performance required
• Current actual performance, eg. changeovers, quality, machine uptime / reliability
© 2019 Rolls-Royce
8
1. Define scope and understand facility BACK Map NEXT
types
Determine scope for operations layout by selecting the range of products and process span
Upstream
• The range of products is usually
Narrow
process
determined by a product ‘make versus
span buy’ strategy covering all components,
detail parts, sub-assemblies, assemblies
and finished products
Materials
Produc
products
Range of
Sub-
• The scope of the factory or cell to be
ts
Parts Assembly
assembly
designed is also determined by the
process span - i.e. how much of the
value stream will it cover. The span can
Wide process span
be wide or narrow (degree of vertical
integration)
Downstream
© 2019 Rolls-Royce
9
1. Define scope and understand facility BACK Map NEXT
types
Understand appropriate facility types based on product, customer or process
characteristics
‘Simple’ Facility Types • An understanding of what the
PRODUCT / CUSTOMER FOCUS appropriate type of facility may be,
No. guides the type of analysis to determine
Multi-product the layout for operations flow
Customer
products
focus
(families) multi-customer
cells
Product focus • A ‘simple’ facility type is one where the
No. Customers range of products, and/or processes and
PRODUCT / PROCESS FOCUS and/or customers is small and the focus
is easy to determine
No.
Process/batc
products Multi-product
h focus
(families) multi-process
cells • Otherwise, common product or process
Transfer line process
characteristics dictate the type of layout
No. Processes
© 2019 Rolls-Royce
10
1. Define scope and understand facility BACK Map NEXT
types
Understand appropriate facility types based on product, customer or process
characteristics Product - Probable Features
Product-quantity analysis indicates probable facility type Quantity facility type
based on volume:
Matls
Lathe
NC
Matls `
l
Mil - nta
l Process routing or cluster analysis
rizo
can then be used to define the
Manual
o
Grinder
Goods
H
Ops
Fin
families.
Multiple routing cell layout (low volume) • Low-volume items made in an
environment with machines arranged
Screw
holes
NC
Matls
Dr
layout
l l
Mil - nta
rizo
Grinder
Manual
Goods
Ho
Ops
Fin
© 2019 Rolls-Royce
12
Gate checklist 1: Define scope and BACK Map NEXT
understand facility types
Initial span of processes determined for layout
Initial range of products determined for layout
Product volume assumptions determined
Likely facility type determined based on customer, product or processing
characteristics
© 2019 Rolls-Royce
13
2. Define product families and degree of BACK Map NEXT
process dedication
• If a product’s demand is sufficiently
Workload Degree of high, the workload may economically or
Efficiency Facility strategically justify dedicated equipment or
derived process
focus type manufacturing cells that can achieve very
from dedication
high efficiencies (no or few changeovers)
Single /
few high Dedicated Transfer
volume to products
Machine
line • When there is insufficient workload to justify
products dedicated equipment, volume can be
consolidated into product groupings
Families or families to give required resource
of Dedicated
medium to families People Cell utilisation at lower efficiencies
volume of products
products • To determine whether dedicated equipment
or cells is justifiable, a capacity model needs
Many, low Flexible, Machines to be created to establish the workload that
Job-
volume no and demand for products or families of products
shop
products dedication people
place on workstations
© 2019 Rolls-Royce
14
2. Define product families and degree of BACK Map NEXT
process dedication
Product – Work-centre matrix • A product family is a group of
Operation
products that are made in an
Part no. Lathe Grind Broach CMM Erode Weld Blast NDT
identical or very similar way.
ba321 x x x x
ab123 x x x x • This is usually represented by a
cd456 x x x x x x matrix showing the parts that are in
ef789 x x x x x x the scope of the design for the cell
yz987 x x x x x or facility and the machines or work-
wx654 x x x x x
centres that each part goes to. This
…. And so on is the product or work-centre matrix
Process Routing Analysis • A variation on this includes a
Operation
representation of the sequence of
Part no. Lathe Grind Broach CMM Erode Weld Blast NDT
the process in a matrix. This is known
ba321 x
1 2x x
3 x
4
as a Process Routing Analysis
ab123 x
1 x
3 2x x
4
cd456 x
1 x
3 4x 2x x
5 6x • The families defined will be used
ef789 x
1 x
2 x3 x
4 x
5 x
6 throughout the design process,
yz987 1x x
2 x
3 4x x
5 therefore this is a critical output.
wx654 2x 1
x x x x
•
3 4 5
…. And so on Some iteration throughout is likely
© 2019 Rolls-Royce however
15
2. Define product families and degree of BACK Map NEXT
process dedication – Cluster Analysis
Routing data
Cluster analysis (or ‘rank-order-clustering’) is
used where large amounts of data have to be
reviewed
Products Work-centres • The purpose of cluster analysis is to place
products into groups, suggested by the
Cluster
Analysis routing data, such that product families are
defined and process/work-centre
Work-centres dedication can take place
• The analysis can be carried out across
Cluster 1 different scenarios, in an attempt to better
Products
group and simplify product families
Cluster 2 enabling simpler layouts and better product
flow
Two separate clusters indicates two product
families (dedicated manufacturing cells)
Use ‘How to: Value Stream Mapping’ to map the current state and opportunities
© 2019 Rolls-Royce
18
2. Define product families and degree of BACK Map NEXT
process dedication
Collect additional information to get a full picture of the current state
A detailed floor plan of facility gives the
Example of a 'Spaghetti physical boundaries of the factory, the size
Chart' flow diagram of facilities and cells
A flow diagram analysis (Spaghetti Chart) assesses work
movement and distance travelled, indicating
transportation waste
An equipment survey (type, capability, component,
condition, space envelope) establishes the availability
Finished
Goods out Raw
of equipment
Material In Determine constraints that exist to establish what cannot
be done or moved (challenge later)
Service Cell
Skills matrices assess the readiness of the workforce to
move to a multi skilled work team
Existing infrastructure requirements (services, craneage,
IT) to establish what layout options are possible
© 2019 Rolls-Royce
19
2. Define product families and degree of BACK Map NEXT
process dedication
Create a rough capacity model
• Creating a rough capacity model helps to determine the
Product products and machines allocation in cells and the rough
Machines loading of those cells
volumes
effectiveness
TO DEFINE • Machine allocation
Process
routings
Product
© 2019 Rolls-Royce
21
3. Determine material flow and design the BACK Map NEXT
layout
The Future State VSM
For each Product Family, complete value stream maps to determine the future state
Use ‘How to: Value Stream Mapping’ to map the future state
© 2019 Rolls-Royce
22
3. Determine material flow and design the BACK Map NEXT
layout
Work Centres and material space
• Estimate cell floor space required for the
work stations, considering the working
envelope
• Estimate addition space for material handling in
the cell
• Estimate cell floor space required for stock
• The future state VSM gives stock required
• Estimate space required for bought out parts
• Stores and line-side material
© 2019 Rolls-Royce
24
3. Determine material flow and design the BACK Map NEXT
layout
Simulate the design concept options
Simulation is a method of analysing and verifying concepts and running different scenarios quickly. It is a
visualisation of the shop floor layout, looking at production flow, control and aspects of industrial
engineering. For example:
Computer based
3D CAD model
simulation
© 2019 Rolls-Royce
25
3. Determine material flow and design the BACK Map NEXT
layout
Analyse operator work in relation to the layout
Determining operator work combinations will ensure that the layout design supports
the future state operation.
© 2019 Rolls-Royce
26
3. Determine material flow and design the BACK Map NEXT
layout
Create standard design pack
Cell layout
18m
GLASS
COAT
BLAST HEAT
PRESS
C
Finance requirements
O SOLN
O TREAT
L
25 m C
O
MULTI- O
FORGE L
HEAT Operator
GLASS BLAST
standard work
COAT
IN LAY OVEN
POOL
PREP
© 2019 Rolls-Royce
27
Gate checklist 3: Determine material flow BACK Map
and design the layout
The future state value stream has been determined for each product family
Machines and equipment have been allocated to meet the future state
Space requirements for machines, materials and materials management processes
have been estimated
Layout relationships have been determined
Options for concept design of layout created and modelled. Optimal solution selected
considering business objectives
Operator work has been analysed in relation to the layout
Standard packs have been created for the layout design
© 2019 Rolls-Royce